CN202209056U - Underground safety shield of manual hole digging pile - Google Patents
Underground safety shield of manual hole digging pile Download PDFInfo
- Publication number
- CN202209056U CN202209056U CN2011203324061U CN201120332406U CN202209056U CN 202209056 U CN202209056 U CN 202209056U CN 2011203324061 U CN2011203324061 U CN 2011203324061U CN 201120332406 U CN201120332406 U CN 201120332406U CN 202209056 U CN202209056 U CN 202209056U
- Authority
- CN
- China
- Prior art keywords
- cover plate
- support frame
- protective cover
- bar support
- reinforced bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The utility model relates to a special protective tool used for guaranteeing the safety of underground operating personnel during the construction process of a manual hole digging concrete pile, in particular to an underground safety shield of a manual hole digging pile, which comprises a reinforced support frame and a protective cover plate. The cross section of the reinforced support frame is round and the round protective cover plate is mounted on an upper port of the reinforced support frame. The round protective cover plate comprises a fixed cover plate and a movable cover plate. The fixed cover plate is fixed on the upper port of the reinforced support frame, and the fixed cover plate and the movable cover plate are connected by a flange. The fixed cover plate and the movable cover plate are half round, made of wood plates with thickness of 50mm, and have light weight and good protection performance. The underground safety shield of the manual hole digging pile has a simple structure, is easy to process, is lower in cost, can be used for completely and effectively preventing people from being hurt by falling objects during the manual hole digging pile construction process and preventing events such as object falling and local collapsing during the well pile construction from hurting underground workers.
Description
Technical field
The utility model relates to a kind of special protection apparatus of in the manually digging hole filling pile work progress, guaranteeing the underground operators life security, specifically a kind of hand excavated pile downhole safety protective cover.
Background technology
Hand excavated pile is modal a kind of foundation structure type, and its degree of depth confirms that according to geological conditions shallow has only several meters, and dark reaches tens of meters.According to geological condition, generally can adopt concrete or steel retaining wall that supporting is carried out in the well stake, prevent to produce cave-in accident.But for the another one potential safety hazard---object hits does not but have the reliable precautionary measures.In present manual digging pile construction, generally all can build the walling crib more than the height 200mm by laying bricks or stones at well head, tumble in the well with the foreign material that prevent well head; Require underground operators to wear safety helmet simultaneously, prevent to be injured by a crashing object by foreign material.These ways are feasible in more shallow well pile driving construction; But work as the well stake degree of depth above ten meters; Its protective action is almost lost, and when malfunctioning or diameter drops greater than the stone of 50mm when the elevator facility that soil occurs hanging, must cause the injures and deaths of underground operators.
The utility model content
The technical problem that the utility model will solve provides a kind of simple, safety, is suitable for, reliable and be convenient to the hand excavated pile downhole safety protective cover of underground labour's constructing operation, protect operating personnel when underground work, can not injured by the object that falls in the high-altitude.
For solving the problems of the technologies described above, the technical scheme that the utility model adopts is: a kind of hand excavated pile downhole safety protective cover comprises the reinforced bar support frame, protective cover plate; The cross section of reinforced bar support frame is circular, and the port of reinforced bar support frame is installed circular protective cover plate, and circular protective cover plate comprises securing cover plate and removable cover, and securing cover plate is fixed in the port of reinforced bar support frame, and hinge is connected securing cover plate with removable cover.
The operating principle of the utility model is that the reinforced bar support frame is supported on the well stake substratum, freely descends with digging depth.When the operator drop to fill sand in the hopper of down-hole after, the operator opened removable cover conveniently when hand steered hopper slowly rose to the height of protection cage; Pass through the reinforced bar support frame position of upper of hopper this moment after removable cover is opened; Stretch out one's hand the removable cover that closes subsequently.When hopper descended, the personnel in the pit opened the removable cover hopper of leaving behind and then closes again.Operating personnel are in the safe space from start to finish.
The utility model is simple in structure, handling ease, and cost is low, can avoid the junk in the manual digging pile construction process to hurt sb.'s feelings fully effectively, can reach the set goal.
The utility model special protection apparatus can be resisted incidents such as the object that takes place in the well pile driving construction falls, partial collapse the underground labour is damaged; The reinforced bar support frame has certain intensity, rigidity and bearing capacity, ensures for stranded workman provides security protection and the time of implementing rescue.
Description of drawings
Fig. 1 is the structural representation of the utility model,
Fig. 2 is the vertical view of Fig. 1.
Among the figure: 1-reinforced bar support frame, 2-lateral loops muscle, 3-circular protective cover plate, 301-removable cover, 302-securing cover plate, 4-arc handle, 5-hinge, 6-Protective small mesh net.
The specific embodiment
As shown in the figure: a kind of hand excavated pile downhole safety protective cover comprises reinforced bar support frame 1, circular protective cover plate 3; The cross section of reinforced bar support frame 1 is circular; The port of reinforced bar support frame 1 is installed circular protective cover plate 3; Circular protective cover plate 3 comprises securing cover plate 302 and removable cover 301, and securing cover plate 302 is fixed in the port of reinforced bar support frame 1, and hinge 5 is connected securing cover plate 302 with removable cover 301.Securing cover plate 302 is a large semi-circular, and removable cover 301 is that smaller part is circular, make with the plank that 50 mm are thick, and light weight, barrier propterty is good; Also can securing cover plate 302 and removable cover 301 all be made into semicircle; The stable circular support body that reinforced bar support frame 1 is made up of the reinforcing bar of four φ 22.Reinforced bar support frame 1 highly is 2 meters to 2.2 meters.Generally the height than the operator exceeds 300 to 500mm.
For enough assurance support strengths, reinforced bar support frame 1 top is established in four road φ, 18 reinforcing bars and is bound round as lateral loops muscle 2, and lateral loops muscle 2 spacings are 100mm; For making things convenient for digging, do not establish the lateral loops muscle in lateral loops muscle about 1.5m scope below 2.
Reinforced bar support frame 1 upper side is provided with highly roughly 500mm Protective small mesh net 6, and Protective small mesh net 6 can be wrapped in reinforced bar support frame 1 upper side with colour bar cloth; Can prevent that so the trickle sand and dust that drop from getting into operator's intraocular.
Arc handle 4 is housed below the removable cover 301; Before the workman goes into the well the utility model is put into well, the operating personnel opens removable cover 301 entering shaft bottoms, shuts removable cover 301 conveniently.After underground operators is filled hanging basket to soil, give signal of top operating personnel, and removable cover 301, treat to cover removable cover 301 more conveniently after hanging basket rises.
In work progress, because underground operators is under this protective frame with protective effect always,, also can be kept out by circular protective cover plate even there are foreign material such as stone to fall down, can not cause bottom operating personnel's actual bodily harm.
Claims (7)
1. hand excavated pile downhole safety protective cover, it is characterized in that: it comprises reinforced bar support frame (1), circular protective cover plate (3); The cross section of said reinforced bar support frame (1) is circular; The port of said reinforced bar support frame (1) is installed said circular protective cover plate (3); Said circular protective cover plate (3) comprises securing cover plate (302) and removable cover (301); Said securing cover plate (302) is fixed in the port of said reinforced bar support frame (1), and hinge (5) is connected said securing cover plate (302) with said removable cover (301).
2. a kind of hand excavated pile downhole safety protective cover as claimed in claim 1; It is characterized in that: four road lateral loops muscle (2) are established on said reinforced bar support frame (1) top; Said lateral loops muscle (2) spacing is 100mm, and said lateral loops muscle (2) is by φ 18 reinforcement fabrications.
3. a kind of hand excavated pile downhole safety protective cover as claimed in claim 1 is characterized in that: said securing cover plate (302) is a large semi-circular, and said removable cover (301) is that smaller part is circular, makes with the plank that 50 mm are thick.
4. a kind of hand excavated pile downhole safety protective cover as claimed in claim 1 is characterized in that: said securing cover plate (302) is semicircle with said removable cover (301).
5. like any described a kind of hand excavated pile downhole safety protective cover of claim 1 to 4, it is characterized in that: said reinforced bar support frame (1) upper side is provided with Protective small mesh net (6), and said Protective small mesh net (6) highly is 500mm.
6. a kind of hand excavated pile downhole safety protective cover as claimed in claim 5, it is characterized in that: said reinforced bar support frame (1) is processed by the reinforcing bar of four φ 22; Said reinforced bar support frame (1) highly is 2 meters to 2.2 meters.
7. a kind of hand excavated pile downhole safety protective cover as claimed in claim 6 is characterized in that: arc handle 4 is housed below the said removable cover (301).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011203324061U CN202209056U (en) | 2011-09-06 | 2011-09-06 | Underground safety shield of manual hole digging pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011203324061U CN202209056U (en) | 2011-09-06 | 2011-09-06 | Underground safety shield of manual hole digging pile |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202209056U true CN202209056U (en) | 2012-05-02 |
Family
ID=45988608
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011203324061U Expired - Lifetime CN202209056U (en) | 2011-09-06 | 2011-09-06 | Underground safety shield of manual hole digging pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202209056U (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102864942A (en) * | 2012-08-13 | 2013-01-09 | 云南建工水利水电建设有限公司 | Manufacturing method for security protective cover |
CN104473349A (en) * | 2015-01-06 | 2015-04-01 | 何军 | Safety frame |
CN107063020A (en) * | 2017-04-17 | 2017-08-18 | 贵州新联爆破工程集团有限公司 | A kind of hole stake Excavation blasting flyrock protection device |
CN107620482A (en) * | 2017-05-06 | 2018-01-23 | 山东中迈建筑工程有限公司合肥分公司 | A kind of artificial digging pile protective baffle plate |
CN110130669A (en) * | 2019-06-20 | 2019-08-16 | 中建新疆建工集团第五建筑工程有限公司 | A kind of manually digging hole operation safety protection cover |
CN110258622A (en) * | 2019-04-30 | 2019-09-20 | 安徽省公路桥梁工程有限公司 | Peg board formula barricade and its construction method |
CN110258477A (en) * | 2019-06-28 | 2019-09-20 | 中国电建集团成都勘测设计研究院有限公司 | Water power surge shaft keeps off stone structure |
CN110374346A (en) * | 2019-08-19 | 2019-10-25 | 贵州黔航交通工程有限公司 | Hole stake excavation safety device |
CN110905591A (en) * | 2019-12-19 | 2020-03-24 | 何洪彬 | Underground single small-sized operation protection frame |
-
2011
- 2011-09-06 CN CN2011203324061U patent/CN202209056U/en not_active Expired - Lifetime
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102864942A (en) * | 2012-08-13 | 2013-01-09 | 云南建工水利水电建设有限公司 | Manufacturing method for security protective cover |
CN102864942B (en) * | 2012-08-13 | 2015-06-03 | 云南建工第二建设有限公司 | Manufacturing method for security protective cover |
CN104473349A (en) * | 2015-01-06 | 2015-04-01 | 何军 | Safety frame |
CN107063020A (en) * | 2017-04-17 | 2017-08-18 | 贵州新联爆破工程集团有限公司 | A kind of hole stake Excavation blasting flyrock protection device |
CN107063020B (en) * | 2017-04-17 | 2018-09-18 | 贵州新联爆破工程集团有限公司 | A kind of hole stake Excavation blasting flyrock protection device |
CN107620482A (en) * | 2017-05-06 | 2018-01-23 | 山东中迈建筑工程有限公司合肥分公司 | A kind of artificial digging pile protective baffle plate |
CN107620482B (en) * | 2017-05-06 | 2020-01-07 | 重庆市巴岳建筑安装工程有限公司 | Manual hole digging pile protective baffle |
CN110258622A (en) * | 2019-04-30 | 2019-09-20 | 安徽省公路桥梁工程有限公司 | Peg board formula barricade and its construction method |
CN110130669A (en) * | 2019-06-20 | 2019-08-16 | 中建新疆建工集团第五建筑工程有限公司 | A kind of manually digging hole operation safety protection cover |
CN110258477A (en) * | 2019-06-28 | 2019-09-20 | 中国电建集团成都勘测设计研究院有限公司 | Water power surge shaft keeps off stone structure |
CN110374346A (en) * | 2019-08-19 | 2019-10-25 | 贵州黔航交通工程有限公司 | Hole stake excavation safety device |
CN110905591A (en) * | 2019-12-19 | 2020-03-24 | 何洪彬 | Underground single small-sized operation protection frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202209056U (en) | Underground safety shield of manual hole digging pile | |
EP1431463A1 (en) | Ground treatment | |
CN112681342B (en) | Deep foundation pit supporting structure and deep foundation pit construction method | |
KR101224693B1 (en) | Appratus for preventing dust-scattering of auger machine | |
CN203822367U (en) | Casting and filling machine for roadway | |
CN208542367U (en) | The crusher of safe feeding | |
CN102864942B (en) | Manufacturing method for security protective cover | |
JP6971170B2 (en) | How to build an underground structure | |
CN112857157A (en) | Foundation pit excavation blasting method | |
KR101358622B1 (en) | Apparatus for constructing stone column by adding vertical impact with a cycle and method for constructing stone column by the apparatus | |
CN211448690U (en) | Working platform for shield tunnel segment removal | |
CN106567686B (en) | Device for reducing falling soil by auger hole forming | |
CN107288640A (en) | A kind of steady rope self-supporting modularization vertical shaft driving and masonry construction device of nothing | |
CN202755679U (en) | Safety protective cover | |
GB2366819A (en) | Monitoring the degree of compaction during ground treatment | |
CN201495548U (en) | Manual hole digging filling pile protective wall concrete material receiving platform | |
JP6684314B2 (en) | Bridge pier removal method | |
CN207525752U (en) | Antiskid pile concreting protective device | |
CN204355603U (en) | The upset material-receiving device of vertical trash transhipment station | |
CN220539684U (en) | Suspended frame gabion for rapidly plugging surrounding rock surge mouth of tunnel face | |
CN204266257U (en) | A kind of suspension device of stress relief hole | |
CN114922557B (en) | Protection device and hole digging method for underground operation of manual hole digging pile | |
CN214034872U (en) | Downthehole protector of manual hole digging pile | |
CN105350980B (en) | A kind of mine crushes region laneway support method | |
CN219825255U (en) | Slag discharging safety protection device for manual hole digging pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20120502 |
|
CX01 | Expiry of patent term |