CN107620482A - A kind of artificial digging pile protective baffle plate - Google Patents

A kind of artificial digging pile protective baffle plate Download PDF

Info

Publication number
CN107620482A
CN107620482A CN201710314358.5A CN201710314358A CN107620482A CN 107620482 A CN107620482 A CN 107620482A CN 201710314358 A CN201710314358 A CN 201710314358A CN 107620482 A CN107620482 A CN 107620482A
Authority
CN
China
Prior art keywords
baffle plate
motor
supporter
quarter moon
directive wheel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710314358.5A
Other languages
Chinese (zh)
Other versions
CN107620482B (en
Inventor
王燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Bayue Construction And Installation Engineering Co ltd
Original Assignee
Shandong Sinomark Construction Engineering Co Ltd Hefei Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Sinomark Construction Engineering Co Ltd Hefei Branch filed Critical Shandong Sinomark Construction Engineering Co Ltd Hefei Branch
Priority to CN201710314358.5A priority Critical patent/CN107620482B/en
Publication of CN107620482A publication Critical patent/CN107620482A/en
Application granted granted Critical
Publication of CN107620482B publication Critical patent/CN107620482B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a kind of artificial digging pile protective baffle plate, including the first semicircle baffle plate and the second semicircle baffle plate, the straightway top of the first semicircle baffle plate and the straight line pars infrasegmentalis of the second first quarter moon baffle plate offer the second guide groove, top one end of the first first quarter moon baffle plate is provided with the first motor, the top other end of the first first quarter moon baffle plate is provided with the second motor, lower section one end of the second first quarter moon baffle plate is provided with the 3rd motor, the lower section other end of the second first quarter moon baffle plate is provided with the 4th motor, first motor, second motor, the outboard end of 3rd motor and the 4th motor is provided with jacking screw mandrel, the arc pars infrasegmentalis of the first first quarter moon baffle plate segmental arc top and the second first quarter moon baffle plate is provided with the first guide groove, first guide groove is internally provided with movable pulley.This artificial digging pile protective baffle plate greatly saves labor intensity, preferably protects the life security of worker.

Description

A kind of artificial digging pile protective baffle plate
Technical field
The present invention relates to construction safety protection technology field, specially a kind of artificial digging pile protective baffle plate.
Background technology
In the quick epoch that current construction industry is flourishing, either urban house building trade or means of transportation building row Industry, because job site is often large scale equipment and building, the safety problem of job site becomes work progress In the most important thing, among many buildings, the quality problems of the construction quality relation of pile foundation to whole building thing, although existing It is very advanced in the piling machine equipment of technicalization, but it is unable to reach the pile foundation of aperture requirement in complicated landform either piling machine Position, machine can not normal operation, can only rely on it is artificial carry out borehole, but in manually digging hole operation, operating personnel are in stake Basal part carries out digging base operation, and top may drop debris at any time, influences construction operation or even jeopardizes the life of operating personnel Safety, so occurring a kind of protective baffle plate currently on the market, such a protective baffle plate is a kind of simple semi-circular sheet steel, will Baffle plate actuated position rides upon the top of pile foundation breast wall, and operating personnel carry out digging base operation below baffle plate, but existing Protective baffle plate is very thick and heavy, and when shifting to another scope of operation, by lifting machine with manually operating simultaneously, baffle plate is shifted into another work Industry face, is not only taken time and effort, and personnel may be damaged because hole man is narrow and small in moving process;Using biography During system protective baffle plate operation, because pile foundation breast wall concrete is interim retaining wall, in supporting baffle, baffle plate is to be directly placed at shield The upper end of wall concrete, it is easy to fall, operating personnel are damaged.
The content of the invention
It is an object of the invention to provide a kind of artificial digging pile protective baffle plate, to solve what is proposed in above-mentioned background technology Problem.
To achieve the above object, the present invention provides following technical scheme:A kind of artificial digging pile protective baffle plate, including first Semicircle baffle plate and the second semicircle baffle plate, are hinged between the first semicircle baffle plate and the second semicircle baffle plate by flap, and described The straightway top of one semicircle baffle plate and the straight line pars infrasegmentalis of the second first quarter moon baffle plate offer the second guide groove, and described second leads The second directive wheel supporter is internally provided with to groove, the bottom both ends of the second directive wheel supporter are rotatably connected to second Directive wheel, top one end of the first first quarter moon baffle plate is provided with the first motor, and the first motor is fixedly mounted on the second guiding The top of supporter is taken turns, the top other end of the first first quarter moon baffle plate is provided with the second motor, and the second motor is fixedly mounted In the top of the second directive wheel supporter, lower section one end of the second first quarter moon baffle plate is provided with the 3rd motor, and the 3rd motor The lower section of the second directive wheel supporter is fixedly mounted on, the lower section other end of the second first quarter moon baffle plate is provided with the 4th motor, And the 4th motor be fixedly mounted on the lower section of the second directive wheel supporter, first motor, the second motor, the 3rd motor and The outboard end of four motors is provided with jacking screw mandrel, first motor, the second motor, the outside of the 3rd motor and the 4th motor End is installed with manual adjustment disk on the lateral wall of jacking screw mandrel, first motor, the second motor, the 3rd motor and The medial extremity of 4th motor is mounted on controlling switch, and first motor on the jacking screw mandrel on the outside of the second motor with being respectively provided with There is the first guide pad, the side of first guide pad is provided with the second guide pad, the 3rd motor and the 4th the motor outside Jacking screw mandrel on be provided with the 3rd guide pad, the side of the 3rd guide pad is provided with the 4th guide pad, described first The segmental arc surface layer of first quarter moon baffle plate and the second first quarter moon baffle plate is installed with handle, the first first quarter moon baffle plate segmental arc top The first guide groove is provided with the arc pars infrasegmentalis of the second first quarter moon baffle plate, first guide groove is internally provided with movement Wheel, the movable pulley is by the first directive wheel supporter, resistance to compression buffer spring, wheel shaft, wheel body, race, wheel body supporter, spring Groove, tension buffer spring and the first directive wheel are formed, and first directive wheel is rotatably connected on the upper of the first directive wheel supporter Both sides are held, the wheel body supporter is arranged on the lower section of the first directive wheel supporter, and the tension buffer spring is fixedly connected on Between wheel body supporter and the first directive wheel supporter, the resistance to compression buffer spring is arranged in spring groove, and the wheel body passes through Wheel shaft is rotatably connected on the lower end of wheel body supporter, and the upper surface of the first semicircle baffle plate and the second semicircle baffle plate offers Observation window.
Preferably, the movable pulley installed on the first semicircle baffle plate and the second semicircle baffle plate is no less than five.
Preferably, the quantity of the flap is three.
Preferably, the height of the movable pulley is more than the width of motor.
Preferably, be provided with screw mandrel external screw thread on the outside of the jacking screw mandrel, first guide pad, the second guide pad, Guide pad internal thread is provided with the inside of 3rd guide pad and the 4th guide pad.
Compared with prior art, the beneficial effects of the invention are as follows:This artificial digging pile protective baffle plate, will by jacking screw mandrel Protective baffle plate is firmly fastened on concrete guard wall very much, by the rotation of movable pulley, easily changes very much working region, Labor intensity is greatly saved, preferably protects the life security of worker.
Brief description of the drawings
Fig. 1 is schematic structural view of the invention;
Fig. 2 is the first semicircle baffle plate and the second semicircle baffle plate folded state schematic diagram of the invention;
Fig. 3 is the first semicircle baffle plate and the second semicircle baffle plate its flat presentation schematic diagram of the invention;
Fig. 4 is movable pulley schematic diagram of the present invention;
Fig. 5 is the second directive wheel schematic diagram of the invention;
Fig. 6 is jacking screw mandrel schematic diagram of the present invention.
In figure:1 jacking screw mandrel, 2 first guide pads, 3 flaps, 4 second guide pads, 5 manual adjustment disks, 6 first motors, 7 Controlling switch, 8 first semicircle baffle plates, 9 handles, 10 second semicircle baffle plates, 11 second motors, 12 the 3rd motors, 13 the 4th motors, 14 the 3rd guide pads, 15 the 4th guide pads, 16 screw mandrel external screw threads, 17 guide pad internal threads, 18 observation windows, 19 movable pulleys, 191 One directive wheel supporter, 192 first guide grooves, 193 resistance to compression buffer springs, 194 wheel shafts, 195 wheel bodys, 196 races, 197 wheel bodys Supporter, 198 spring grooves, 199 tension buffer springs, 1,910 first directive wheels, 20 second directive wheels, the support of 21 second directive wheels Body, 22 second guide grooves.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of creative work is not made Embodiment, belong to the scope of protection of the invention.
, it is necessary to explanation in description of the invention, the orientation of instruction such as term " vertical ", " on ", " under ", " level " or Person's position relationship is based on orientation shown in the drawings or position relationship, is for only for ease of the description present invention and simplifies description, Rather than instruction either implies that signified device or element must have specific orientation, with specific azimuth configuration and behaviour Make, therefore be not considered as limiting the invention.
In description of the invention, it is also necessary to explanation, unless otherwise clear and definite regulation and limitation, term " setting ", " peace Dress ", " connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected or be detachably connected, or integratedly Connection, can be mechanical connection or electrical connection, can be directly connected to or be connected by intermediary, can To be the connection of two element internals.For the ordinary skill in the art, can understand as the case may be above-mentioned The concrete meaning of term in the present invention.
Fig. 1-6 are referred to, the present invention provides a kind of technical scheme:A kind of artificial digging pile protective baffle plate, including the first half The circle semicircle baffle plate 10 of baffle plate 8 and second, be hinged by flap 3 between the first semicircle baffle plate 8 and the second semicircle baffle plate 10, institute The quantity for stating flap 3 is three, the straightway top of the first semicircle baffle plate 8 and the straight line pars infrasegmentalis of the second first quarter moon baffle plate 10 The second guide groove 22 is offered, second guide groove 22 is internally provided with the second directive wheel supporter 21, and described second leads The second directive wheel 20, top one end peace of the first first quarter moon baffle plate 8 are rotatably connected to the bottom both ends of wheel supporter 21 Equipped with the first motor 6, and the first motor 6 is fixedly mounted on the top of the second directive wheel supporter 21, the first first quarter moon baffle plate 8 The top other end the second motor 11 is installed, and the second motor 11 is fixedly mounted on the top of the second directive wheel supporter 21, Lower section one end of the second first quarter moon baffle plate 8 is provided with the 3rd motor 12, and the 3rd motor 12 is fixedly mounted on the second directive wheel The lower section of supporter 21, the lower section other end of the second first quarter moon baffle plate 10 is provided with the 4th motor 13, and the 4th motor 13 is solid Dingan County is mounted in the lower section of the second directive wheel supporter 21, first motor 6, the second motor 11, the 3rd motor 12 and the 4th electricity The outboard end of machine 13 is provided with jacking screw mandrel 1, and the outside of the jacking screw mandrel 1 is provided with screw mandrel external screw thread 16, and described first Guide pad 2, the second guide pad 4, the inner side of the 3rd guide pad 14 and the 4th guide pad 15 are provided with guide pad internal thread 17, institute The outboard end for stating the first motor 6, the second motor 11, the 3rd motor 12 and the 4th motor 13 is equal on the lateral wall of jacking screw mandrel 1 It is installed with manual adjustment disk 5, first motor 6, the second motor 11, the medial extremity of the 3rd motor 12 and the 4th motor 13 Controlling switch 7 is mounted on, the first guiding is provided with the jacking screw mandrel 1 in the outside of 6 and second motor of the first motor 11 Block 2, the side of first guide pad 2 are provided with the second guide pad 4, the top in the outside of the 3rd motor 12 and the 4th motor 13 Enter on screw mandrel 1 to be provided with the 3rd guide pad 14, the side of the 3rd guide pad 14 is provided with the 4th guide pad 15, and described The segmental arc surface layer of one first quarter moon baffle plate 8 and the second first quarter moon baffle plate 10 is installed with handle 9, the arc of the first first quarter moon baffle plate 8 The arc pars infrasegmentalis of shape section top and the second first quarter moon baffle plate 10 is provided with the first guide groove 192, first guide groove 192 Movable pulley 19 is internally provided with, the first semicircle baffle plate 8 is no less than with the movable pulley 19 installed on the second semicircle baffle plate 10 Five, the height of the movable pulley 19 is more than the width of motor, and the movable pulley 19 is by the first directive wheel supporter 191, resisted Press buffer spring 193, wheel shaft 194, wheel body 195, race 196, wheel body supporter 197, spring groove 198, tension buffer spring 199 Formed with the first directive wheel 1910, first directive wheel 1910 is rotatably connected on the upper end two of the first directive wheel supporter 191 Side, the wheel body supporter 197 are arranged on the lower section of the first directive wheel supporter 191, and the tension buffer spring 199, which is fixed, to be connected It is connected between the directive wheel supporter 191 of wheel body supporter 197 and first, the resistance to compression buffer spring 193 is arranged on spring groove 198 Interior, the wheel body 195 is rotatably connected on the lower end of wheel body supporter 197, the first semicircle baffle plate 8 and by wheel shaft 194 The upper surface of two semicircle baffle plates 10 offers observation window 18.
Operation principle:When in use, the first first quarter moon baffle plate 8 and the second first quarter moon are kept off 10 plate doublings by operator, by second First quarter moon baffle plate 10 is erected at the upper end of pile foundation breast wall concrete by movable pulley 19, passes through the first motor 6, the second motor 11, Three motors 12 and the 4th motor 13 think both sides extension jacking screw mandrel 1, and jacking screw mandrel 1 is withstood on concrete guard wall, when replacing work When making region, jacking screw mandrel 1 is withdrawn, is rotated the first first quarter moon baffle plate 8 and the second first quarter moon baffle plate 10 to another by movable pulley 19 Side.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of changes, modification can be carried out to these embodiments, replace without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (5)

1. a kind of artificial digging pile protective baffle plate, including the first semicircle baffle plate (8) and the second semicircle baffle plate (10), its feature exist In:It is be hinged by flap (3) between the first semicircle baffle plate (8) and the second semicircle baffle plate (10), the first semicircle baffle plate (8) the straight line pars infrasegmentalis of straightway top and the second first quarter moon baffle plate (10) offers the second guide groove (22), and described second Guide groove (22) is internally provided with the second directive wheel supporter (21), and the bottom both ends of the second directive wheel supporter (21) are equal The second directive wheel (20) is rotatably connected to, top one end of the first first quarter moon baffle plate (8) is provided with the first motor (6), and One motor (6) is fixedly mounted on the top of the second directive wheel supporter (21), the top other end of the first first quarter moon baffle plate (8) Second motor (11) is installed, and the second motor (11) is fixedly mounted on the top of the second directive wheel supporter (21), described Lower section one end of two first quarter moon baffle plates (8) is provided with the 3rd motor (12), and the 3rd motor (12) is fixedly mounted on the second directive wheel The lower section of supporter (21), the lower section other end of the second first quarter moon baffle plate (10) are provided with the 4th motor (13), and the 4th electricity Machine (13) is fixedly mounted on the lower section of the second directive wheel supporter (21), first motor (6), the second motor (11), the 3rd The outboard end of motor (12) and the 4th motor (13) is provided with jacking screw mandrel (1), first motor (6), the second motor (11), the outboard end of the 3rd motor (12) and the 4th motor (13) is installed with hand on the lateral wall of jacking screw mandrel (1) Dynamic adjustment disk (5), first motor (6), the second motor (11), the medial extremity of the 3rd motor (12) and the 4th motor (13) are equal Controlling switch (7) is installed, first motor (6) is with being provided with the on the jacking screw mandrel (1) on the outside of the second motor (11) One guide pad (2), the side of first guide pad (2) are provided with the second guide pad (4), the 3rd motor (12) and the 4th The 3rd guide pad (14) is provided with jacking screw mandrel (1) on the outside of motor (13), the side of the 3rd guide pad (14) is set It is equipped with the 4th guide pad (15), the fixed peace of segmental arc surface layer of the first first quarter moon baffle plate (8) and the second first quarter moon baffle plate (10) Equipped with handle (9), the arc pars infrasegmentalis of the first first quarter moon baffle plate (8) segmental arc top and the second first quarter moon baffle plate (10) is respectively provided with There is the first guide groove (192), first guide groove (192) is internally provided with movable pulley (19), and the movable pulley (19) is By the first directive wheel supporter (191), resistance to compression buffer spring (193), wheel shaft (194), wheel body (195), race (196), wheel body Supporter (197), spring groove (198), tension buffer spring (199) and the first directive wheel (1910) are formed, and described first is oriented to Wheel (1910) is rotatably connected on the upper end both sides of the first directive wheel supporter (191), and the wheel body supporter (197) is arranged on the The lower section of one directive wheel supporter (191), the tension buffer spring (199) are fixedly connected on wheel body supporter (197) and the Between one directive wheel supporter (191), the resistance to compression buffer spring (193) is arranged in spring groove (198), the wheel body (195) it is rotatably connected on the lower end of wheel body supporter (197) by wheel shaft (194), the first semicircle baffle plate (8) and the second half The upper surface of circle baffle plate (10) offers observation window (18).
A kind of 2. artificial digging pile protective baffle plate according to claim 1, it is characterised in that:The first semicircle baffle plate (8) movable pulley (19) with being installed on the second semicircle baffle plate (10) is no less than five.
A kind of 3. artificial digging pile protective baffle plate according to claim 1, it is characterised in that:The quantity of the flap (3) For three.
A kind of 4. artificial digging pile protective baffle plate according to claim 1, it is characterised in that:The height of the movable pulley (19) Width of the degree more than motor.
A kind of 5. artificial digging pile protective baffle plate according to claim 1, it is characterised in that:The jacking screw mandrel (1) Outside is provided with screw mandrel external screw thread (16), first guide pad (2), the second guide pad (4), the 3rd guide pad (14) and the 4th Guide pad internal thread (17) is provided with the inside of guide pad (15).
CN201710314358.5A 2017-05-06 2017-05-06 Manual hole digging pile protective baffle Expired - Fee Related CN107620482B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710314358.5A CN107620482B (en) 2017-05-06 2017-05-06 Manual hole digging pile protective baffle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710314358.5A CN107620482B (en) 2017-05-06 2017-05-06 Manual hole digging pile protective baffle

Publications (2)

Publication Number Publication Date
CN107620482A true CN107620482A (en) 2018-01-23
CN107620482B CN107620482B (en) 2020-01-07

Family

ID=61086813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710314358.5A Expired - Fee Related CN107620482B (en) 2017-05-06 2017-05-06 Manual hole digging pile protective baffle

Country Status (1)

Country Link
CN (1) CN107620482B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108018857A (en) * 2017-12-19 2018-05-11 吴保康 A kind of artificial digging pile steelframe structure protective baffle plate
CN114922557A (en) * 2022-05-26 2022-08-19 中国电建集团成都勘测设计研究院有限公司 Protection device for underground operation of manual hole digging pile and hole digging method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1060894A (en) * 1996-08-19 1998-03-03 Shinko Kigyo Kk Earth retaining temporary device of excavated hole for manhole
CN202194123U (en) * 2011-08-16 2012-04-18 中国十九冶集团有限公司 Protection system for pile hole excavated by manual work
CN202209056U (en) * 2011-09-06 2012-05-02 甘肃第一建设集团有限责任公司 Underground safety shield of manual hole digging pile
CN202430722U (en) * 2012-01-20 2012-09-12 华铁工程咨询有限责任公司 Assembled-type manpower hole digging protection device
CN205000661U (en) * 2015-08-18 2016-01-27 五冶集团上海有限公司 Stake hole overlay
CN205012341U (en) * 2015-08-17 2016-02-03 中建五局第三建设有限公司 Horizontal protector in interim entrance to a cave drives piles
CN205171498U (en) * 2015-11-27 2016-04-20 中建四局第三建筑工程有限公司 Novel manual hole digging pile protection network
CN205369963U (en) * 2016-01-14 2016-07-06 中建四局第一建筑工程有限公司 Vertical safety protection reinforcing bar of manual hole digging pile net piece
CN205776221U (en) * 2016-06-23 2016-12-07 中铁十二局集团有限公司 The portable protective baffle plate of artificial digging pile

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1060894A (en) * 1996-08-19 1998-03-03 Shinko Kigyo Kk Earth retaining temporary device of excavated hole for manhole
CN202194123U (en) * 2011-08-16 2012-04-18 中国十九冶集团有限公司 Protection system for pile hole excavated by manual work
CN202209056U (en) * 2011-09-06 2012-05-02 甘肃第一建设集团有限责任公司 Underground safety shield of manual hole digging pile
CN202430722U (en) * 2012-01-20 2012-09-12 华铁工程咨询有限责任公司 Assembled-type manpower hole digging protection device
CN205012341U (en) * 2015-08-17 2016-02-03 中建五局第三建设有限公司 Horizontal protector in interim entrance to a cave drives piles
CN205000661U (en) * 2015-08-18 2016-01-27 五冶集团上海有限公司 Stake hole overlay
CN205171498U (en) * 2015-11-27 2016-04-20 中建四局第三建筑工程有限公司 Novel manual hole digging pile protection network
CN205369963U (en) * 2016-01-14 2016-07-06 中建四局第一建筑工程有限公司 Vertical safety protection reinforcing bar of manual hole digging pile net piece
CN205776221U (en) * 2016-06-23 2016-12-07 中铁十二局集团有限公司 The portable protective baffle plate of artificial digging pile

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王宏杰等: "超深、超大直径人工挖孔桩施工实践", 《西部探矿工程》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108018857A (en) * 2017-12-19 2018-05-11 吴保康 A kind of artificial digging pile steelframe structure protective baffle plate
CN114922557A (en) * 2022-05-26 2022-08-19 中国电建集团成都勘测设计研究院有限公司 Protection device for underground operation of manual hole digging pile and hole digging method
CN114922557B (en) * 2022-05-26 2023-10-20 中国电建集团成都勘测设计研究院有限公司 Protection device and hole digging method for underground operation of manual hole digging pile

Also Published As

Publication number Publication date
CN107620482B (en) 2020-01-07

Similar Documents

Publication Publication Date Title
CN107620482A (en) A kind of artificial digging pile protective baffle plate
CN111017834A (en) High-safety lifting platform for building construction
CN110303341A (en) A kind of multi-function steel structure cutting drilling device
CN113294138B (en) Full-sleeve full-rotary drilling machine device
CN212459241U (en) Bridge tunnel foundation bearing capacity detection device
CN109653263A (en) A kind of foundation pile detection device
CN207277858U (en) A kind of external wall hanging apparatus
CN207684755U (en) Auxiliary lifting equipment
CN207002026U (en) A kind of harbour machinery crane anchoring device
CN206511869U (en) A kind of high counterweight test self-powered platform of stability
CN108018857A (en) A kind of artificial digging pile steelframe structure protective baffle plate
CN108824423A (en) A kind of bored pile construction alarm device
CN206233235U (en) A kind of architectural engineering pile driving equipment
CN203653147U (en) Hand-operated type lifting winching machine
CN206289630U (en) A kind of hydraulic engineering pile-drawing machine
CN206667047U (en) Bridge inspection vehicle
CN112482375B (en) Piling device for building construction
CN107884025A (en) Drill underground water level measurement meter
CN105000406B (en) Cloth loosening machine with automatic edge aligning device
CN106289355A (en) A kind of building site detector carrying rotation support device
CN210885083U (en) Cable trench cover carrying device
CN206707722U (en) A kind of Geotechnical Engineering support safety protection device
CN107815946A (en) A kind of intelligent road construction device and its method of work
CN206225850U (en) A kind of switch cubicle installs mobile utensil
CN219239068U (en) Bridge crane with deviation correcting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20191204

Address after: 402560 No.1, Northwest Road, Luofeng Town, Tongliang District, Chongqing

Applicant after: Chongqing Bayue construction and Installation Engineering Co.,Ltd.

Address before: Huizhou Avenue in Baohe District of Hefei city in Anhui province 230000 No. 5158 Binhu Century City foreshore garden C room 902

Applicant before: HEFEI BRANCH OF SHANDONG ZHONGMAI BUILDING ENGINEERING CO.,LTD.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200107

CF01 Termination of patent right due to non-payment of annual fee