CN202194686U - 一种隧道底部井点降水装置 - Google Patents

一种隧道底部井点降水装置 Download PDF

Info

Publication number
CN202194686U
CN202194686U CN2011202799383U CN201120279938U CN202194686U CN 202194686 U CN202194686 U CN 202194686U CN 2011202799383 U CN2011202799383 U CN 2011202799383U CN 201120279938 U CN201120279938 U CN 201120279938U CN 202194686 U CN202194686 U CN 202194686U
Authority
CN
China
Prior art keywords
tunnel
pipe
large diameter
water
diameter pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011202799383U
Other languages
English (en)
Inventor
林福地
韩文军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN2011202799383U priority Critical patent/CN202194686U/zh
Application granted granted Critical
Publication of CN202194686U publication Critical patent/CN202194686U/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

本实用新型公开了一种隧道底部井点降水装置。在隧道全风化富水花岗岩隧底上采用高压水射流冲出深度不小于大直径管长度的孔,将大直径管放入孔中,大直径管外径上包裹滤网,将底盖安装在大直径管底端,大直径管另一端与变径接头连接,通过变径接头向大直径管内腔插入小直径抽水芯管,小直径抽水芯管外端与自吸水泵连接,自吸水泵出水口与小直径排水管连接,自吸水泵在大直径管内腔产生负压,地下水在负压汇集到大直径管内腔后由水泵抽出。具有结构简单,成本低,省时省力,施工速度快、效率高,增强花岗岩自稳性特点,功效提高5倍以上,提高了隧底在施工混凝土时模板不跨塌,节省超前预注浆工序和成本,广泛用于隧道富水花岗岩隧底混凝土施工。

Description

一种隧道底部井点降水装置
技术领域
本实用新型涉及隧道工程,具体涉及一种隧道底部井点降水装置。 
背景技术
隧道全风化富水花岗岩隧底在施工混凝土时,经常遭遇因隧底全风化富水花岗岩失稳而导致模板跨塌,因此,在全风化富水花岗岩隧底进行模板安装时,首先要对隧底全风化富水花岗岩采取一定的加固措施,使其具备一定的自稳性后方可进行后续的工序施工。通常采取的加固措施是分段超前预注浆。超前预注浆一般要先进行封堵墙的施工,再布设注浆孔进行逐孔注浆。作为隧底混凝土施工的辅助措施,超前预注浆存在占用的时间长,消耗大量的人力物力,同时先前施工的封堵墙在后续的施工中也要作为临时措施给予拆除,增加了施工成本等缺陷。 
发明内容
本实用新型的目的是提供一种结构简单,成本低,省时省力,施工速度快、效率高,快速降低隧底全风化富水花岗岩中地下水的水位,增强隧底全风化富水花岗岩自稳性的一种隧道底部井点降水装置。 
为了克服现有技术造成的增强隧底自稳性差的不足,本实用新型的技术方案是这样解决的:一种隧道底部井点降水装置,该装置包括一个底盖,一个变径接头,大直径管、滤网、小直径抽水芯管、自吸水泵、小直径排水管、隧底;本实用新型的特殊之处在于所述在隧道全风化富水花岗岩隧底上采用高压水射流冲出深度不小于大直径管长度的孔,将大直径管放入孔中,所述大直径管的外径上包裹滤网,将底盖安装在大直径管一端外侧底部,大直径管另一端与变径接头连接,变径接头、大直径管内腔插入小直径抽水芯管,小直径抽水芯管另一端依次分别与自吸水泵、小直径排水管连接。 
所述小直径抽水芯管、自吸水泵、小直径排水管的连接均为密封连接。 
所述大直径管的管壁上开有至少直径1~5毫米的20个进水孔。 
所述大直径管、小直径抽水芯管、小直径排水管为PVC管。 
本实用新型与现有技术相比,具有结构简单,成本低,省时省力,施工速度快、效率高,排除隧底全风化富水花岗岩中地下水的功能能够增强隧底全风化富水花岗岩自稳性的特点,在某铁路客运专线隧道全风化富水花岗岩隧底混凝土施工中,没有采用隧底井点降水装置的施工效率为1班组10天施工3m,采用隧底井点降水装置的施工效率为1班组2天施工3m,功效提高5倍以上,同时节约了材料成本,广泛用于隧道全风化富水花岗岩隧底的混凝土施工中。 
附图说明
图1为本实用新型结构示意图; 
图2为图1的集水装置图;
图3为图2的Ⅰ-Ⅰ剖面视图。
具体实施方式
附图为本实用新型的实施例。 
下面结合附图对发明内容作进一步说明: 
参照图1至图3所示,一种隧道底部井点降水装置,该装置包括一个底盖1,一个变径接头2,大直径管3、滤网4、小直径抽水芯管5、自吸水泵6、小直径排水管7、隧底8,所述在隧道全风化富水花岗岩隧底8上采用高压水射流冲出深度不小于大直径管3长度的孔,将大直径管3放入孔中,所述大直径管3的外径上包裹滤网4,将底盖1安装在大直径管3底端,大直径管3另一端与变径接头2连接,变径接头2、大直径管3内腔插入小直径抽水芯管5,小直径抽水芯管5另一端依次分别与自吸水泵6、小直径排水管7连接。
所述小直径抽水芯管5、自吸水泵6、小直径排水管7的连接均为密封连接。 
所述大直径管3的管壁上开有至少直径1~5毫米的20个进水孔。 
所述大直径管3、小直径抽水芯管5、小直径排水管7为PVC管。 
综上所述,本实用新型的使用方法简述如下: 
1、在隧道全风化富水花岗岩隧底8上采用高压水射流冲出深度不小于大直径的PVC管3长度的孔;
2、将细铁丝滤网4裹在大直径的PVC管3的外侧,将底盖1安装在大直径的PVC管3的外侧底部,将变径接头2、小直径PVC抽水芯管5与大直径的PVC管3密封连接,组成图2所示的集水装置;
3、集水装置安装在隧道全风化富水花岗岩隧底8上的水流冲孔中,将集水装置顶部周围的土体压实;
4、将小直径PVC抽水芯管5、自吸水泵6、小直径PVC排水管7依次密封连接;
5、由于本装置能快速降低全风化富水花岗岩隧底8上的水位,提高了隧底在施工混凝土时模板不跨塌,节省了超前预注浆的工序和成本。

Claims (4)

1.一种隧道底部井点降水装置,该装置包括一个底盖(1),一个变径接头(2),大直径管(3)、滤网(4)、小直径抽水芯管(5)、自吸水泵(6)、小直径排水管(7)、隧底(8),其特征在于隧道全风化富水花岗岩隧底(8)上采用高压水射流冲出深度不小于大直径管(3)长度的孔,将大直径管(3)放入孔中,所述大直径管(3)的外径上包裹滤网(4),将底盖(1)安装在大直径管(3)一端底部,大直径管(3)另一端与变径接头(2)连接,变径接头(2)、大直径管(3)内腔插入小直径抽水芯管(5),小直径抽水芯管(5)另一端依次分别与自吸水泵(6)、小直径排水管(7)连接。
2.根据权利要求1所述的一种隧道底部井点降水装置,其特征在于所述小直径抽水芯管(5)、自吸水泵(6)、小直径排水管(7)的连接均为密封连接。
3.根据权利要求1所述的一种隧道底部井点降水装置,其特征在于所述大直径管(3)的管壁上开有至少直径1~5毫米的20个进水孔。
4.根据权利要求1所述的一种隧道底部井点降水装置,其特征在于所述大直径管(3)、小直径抽水芯管(5)、小直径排水管(7)为PVC管。
CN2011202799383U 2011-08-03 2011-08-03 一种隧道底部井点降水装置 Expired - Lifetime CN202194686U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011202799383U CN202194686U (zh) 2011-08-03 2011-08-03 一种隧道底部井点降水装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011202799383U CN202194686U (zh) 2011-08-03 2011-08-03 一种隧道底部井点降水装置

Publications (1)

Publication Number Publication Date
CN202194686U true CN202194686U (zh) 2012-04-18

Family

ID=45949603

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011202799383U Expired - Lifetime CN202194686U (zh) 2011-08-03 2011-08-03 一种隧道底部井点降水装置

Country Status (1)

Country Link
CN (1) CN202194686U (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102705006A (zh) * 2012-06-07 2012-10-03 中铁十一局集团第四工程有限公司 采用井点降水法治理营运隧道水患的方法
CN105443141A (zh) * 2015-11-30 2016-03-30 中国神华能源股份有限公司 隧道基底补强方法
CN105735330A (zh) * 2015-03-13 2016-07-06 陈卓杰 一种井点降水的施工方法
CN105804104A (zh) * 2015-03-13 2016-07-27 陈卓杰 一种井点降水的施工方法
CN107964971A (zh) * 2017-11-23 2018-04-27 北京地矿工程建设有限责任公司 一种采用pba工法施工的地铁车站的降水方法
CN109736340A (zh) * 2019-02-22 2019-05-10 宁蔚蔚 一种基础底板预留降水井保证垫层完整性的降水装置与方法
CN110057741A (zh) * 2019-04-29 2019-07-26 华北水利水电大学 一种含水层底部疏放水井渗流试验模型装置
CN111058482A (zh) * 2020-02-26 2020-04-24 福州市规划设计研究院 一种适用于明挖隧道拱底快速降水的施工方法

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102705006A (zh) * 2012-06-07 2012-10-03 中铁十一局集团第四工程有限公司 采用井点降水法治理营运隧道水患的方法
CN105735330A (zh) * 2015-03-13 2016-07-06 陈卓杰 一种井点降水的施工方法
CN105804104A (zh) * 2015-03-13 2016-07-27 陈卓杰 一种井点降水的施工方法
CN105804104B (zh) * 2015-03-13 2017-08-15 河北建设集团卓诚路桥工程有限公司 一种井点降水的施工方法
CN105735330B (zh) * 2015-03-13 2017-11-14 苏建林 一种井点降水的施工方法
CN105443141A (zh) * 2015-11-30 2016-03-30 中国神华能源股份有限公司 隧道基底补强方法
CN107964971A (zh) * 2017-11-23 2018-04-27 北京地矿工程建设有限责任公司 一种采用pba工法施工的地铁车站的降水方法
CN107964971B (zh) * 2017-11-23 2019-11-22 北京地矿工程建设有限责任公司 一种采用pba工法施工的地铁车站的降水方法
CN109736340A (zh) * 2019-02-22 2019-05-10 宁蔚蔚 一种基础底板预留降水井保证垫层完整性的降水装置与方法
CN110057741A (zh) * 2019-04-29 2019-07-26 华北水利水电大学 一种含水层底部疏放水井渗流试验模型装置
CN110057741B (zh) * 2019-04-29 2021-09-21 华北水利水电大学 一种含水层底部疏放水井渗流试验模型装置
CN111058482A (zh) * 2020-02-26 2020-04-24 福州市规划设计研究院 一种适用于明挖隧道拱底快速降水的施工方法
CN111058482B (zh) * 2020-02-26 2022-03-08 福州市规划设计研究院集团有限公司 一种适用于明挖隧道拱底快速降水的施工方法

Similar Documents

Publication Publication Date Title
CN202194686U (zh) 一种隧道底部井点降水装置
CN102704871B (zh) 水源热泵系统中进一步洗井的方法及洗井装置
CN203430473U (zh) 煤矿井下水力压裂钻孔封孔装置
CN202450537U (zh) 一种真空管井复合降水装置
CN207583345U (zh) 矿用钻孔抽排注浆封孔器
CN204185844U (zh) 排水注浆结构
CN202391115U (zh) 一种气囊作基础预留孔施工装置
CN106049518A (zh) 一种改进的真空降水系统及其控制方法
CN104790381A (zh) 基于uea微膨胀剂的内衬墙混凝土浇注逆作方法
CN103615014B (zh) 一种软土基坑的降水装置及其使用方法
CN100557145C (zh) Phc桩内冲内排辅助沉桩施工方法
CN205000321U (zh) 一种尾矿坝联合排渗装置
CN203430466U (zh) 煤矿瓦斯抽采钻孔封孔装置
CN103437338A (zh) 疏干井结合气压劈裂加固吹填土地基施工方法
CN206495205U (zh) 一种预制phc管桩
CN209923909U (zh) 电渗复合地基
CN204326061U (zh) 一种易拔出的管桩
CN109899024B (zh) 注水加压水胀密封花管注浆施工方法
CN210737544U (zh) 清桩装置
CN203879548U (zh) 一种用于矿井巷道堵水的密闭墙
CN204627525U (zh) 封堵装置
CN205999884U (zh) 一种气液两相注入管
CN206338181U (zh) 一种水泵引水装置
CN205276294U (zh) 水冲气动反循环洗井装置
CN205259355U (zh) 钢管柱混凝土顶升连接装置

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA RAILWAY 12TH BUREAU GROUP CO., LTD. CHINA RA

Free format text: FORMER OWNER: CHINA RAILWAY 12TH BUREAU GROUP CO., LTD.

Effective date: 20130712

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Lin Fudi

Inventor after: Han Wenjun

Inventor after: Wang Baoqing

Inventor after: Lin Bentao

Inventor after: You Xu

Inventor before: Lin Fudi

Inventor before: Han Wenjun

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LIN FUDI HAN WENJUN TO: LIN FUDI HAN WENJUN WANG BAOQING LIN BENTAO YOU XU

TR01 Transfer of patent right

Effective date of registration: 20130712

Address after: 710021 Shaanxi province xujiawan Xi'an Weiyang Hongqi Road No. 3

Patentee after: THE 4TH ENGINEERING CO., LTD. OF CHINA RAILWAY 12TH BUREAU Group

Patentee after: CHINA RAILWAY 12TH BUREAU GROUP Co.,Ltd.

Patentee after: CHINA RAILWAY ERYUAN ENGINEERING GROUP Co.,Ltd.

Address before: 710021 Shaanxi province xujiawan Xi'an Weiyang Hongqi Road No. 3

Patentee before: THE 4TH ENGINEERING CO., LTD. OF CHINA RAILWAY 12TH BUREAU Group

Patentee before: CHINA RAILWAY 12TH BUREAU GROUP Co.,Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120418