CN202194394U - Rapid hoisting, positioning and adjusting piece for prefabricated wall board - Google Patents

Rapid hoisting, positioning and adjusting piece for prefabricated wall board Download PDF

Info

Publication number
CN202194394U
CN202194394U CN2011202708628U CN201120270862U CN202194394U CN 202194394 U CN202194394 U CN 202194394U CN 2011202708628 U CN2011202708628 U CN 2011202708628U CN 201120270862 U CN201120270862 U CN 201120270862U CN 202194394 U CN202194394 U CN 202194394U
Authority
CN
China
Prior art keywords
horizontal base
vertical positioning
prefabricated
wall board
positioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011202708628U
Other languages
Chinese (zh)
Inventor
李�浩
李永敢
孔祥忠
余鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
China Construction First Group Construction and Development Co Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN2011202708628U priority Critical patent/CN202194394U/en
Application granted granted Critical
Publication of CN202194394U publication Critical patent/CN202194394U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

A rapid hoisting, positioning and adjusting piece for a prefabricated wall board comprises a horizontal base, a vertical positioning base welded at one end of the horizontal base, and a connecting plate welded at the connection corner of the horizontal base with the vertical positioning base, wherein the horizontal base is provided with an oval hole corresponding to a pre-embedded bolt which is pre-embedded in a lower layer concrete floor slab; the upper part of the vertical positioning base is provided with a guiding groove corresponding to a positioning bolt on a prefabricated steel bar concrete wall board; and the lower part of the vertical positioning base is provided with a grouting opening corresponding to a grouting hole in the prefabricated steel bar concrete wall board. The rapid hoisting, positioning and adjusting piece solves the problem of low hoisting efficiency due to the invisibility of a steel bar sleeve and a lower layer pre-embedded steel bar, overcomes the defect of slow hoisting speed of the traditional prefabricated steel bar concrete wall board and can realize rapid hoisting and positioning of the prefabricated steel bar concrete wall board.

Description

Prefabricated panel fast hoisting location regulating part
Technical field
The utility model relates to a kind of positioner that the prefabricated reinforced concrete wallboard is used of installing.
Background technology
Fabricated construction prefabricated reinforced concrete wallboard is in hoisting process; The prefabricated reinforced concrete wallboard is in place to be that the lower floor's embedded bar on the lower-layer concrete floor is inserted in the reinforced bar sleeve that is reserved in the prefabricated reinforced concrete wallboard, connects through the grouting reinforced bar sleeve then.In reality lifting operating process; Because reinforced bar sleeve is positioned at prefabricated reinforced concrete wallboard bottom recess; Can't observe directly the relative position relation of reinforced bar sleeve and lower floor's embedded bar; Operating personnel need bend to go for the relative position of lower floor's embedded bar and reinforced bar sleeve, could accomplish lifting operation then, have therefore caused prefabricated reinforced concrete wallboard hoisted in position process shortcoming slowly.
The utility model content
The purpose of the utility model provides a kind of prefabricated panel fast hoisting location regulating part, solve traditional prefabricated reinforced concrete wallboard hoisting process technical problem slowly.
For realizing above-mentioned purpose; The utility model adopts following technical scheme: a kind of prefabricated panel fast hoisting location regulating part; It is characterized in that: by horizontal base, be welded on horizontal base a wherein end vertical positioning seat and be welded on horizontal base and form with the junction plate that is connected corner of vertical positioning seat; Have and be embedded in the corresponding elliptical aperture of pre-embedded bolt in the lower-layer concrete floor on the said horizontal base; The top of said vertical positioning seat have with the prefabricated reinforced concrete wallboard on the corresponding guide channel of positioning bolt, the bottom of vertical positioning seat have with the prefabricated reinforced concrete wallboard on the corresponding grouting mouth of grout hole.
Said horizontal base can be channel-section steel, and said vertical positioning seat can be made of welded connection by two channel-section steel openings relatively.
The width of said guide channel from top to bottom diminishes gradually.
The length of prefabricated panel fast hoisting location regulating part can be 400mm~900mm, highly can be 400mm~900mm, and thickness can be 60mm~100mm.
Compared with prior art the utlity model has following characteristics and beneficial effect: the utility model has been avoided owing to reinforced bar sleeve and the invisible low problem of lifting effect that causes of lower floor's embedded bar; Solve traditional prefabricated reinforced concrete wallboard hoisting process shortcoming slowly, can realize the fast hoisting location of prefabricated reinforced concrete wallboard.In addition, the utility model can also doublely be done temporary fixed support member use.
Description of drawings
Below in conjunction with accompanying drawing the utility model is done further detailed explanation.
Fig. 1 is that the master of the utility model looks sketch map.
Fig. 2 is the schematic top plan view of Fig. 1.
Fig. 3 is that sketch map is looked on the right side of Fig. 1.
Fig. 4 is that sketch map is looked on the left side of Fig. 1.
Fig. 5 is the user mode sketch map of the utility model.
Reference numeral: 1-horizontal base, 2-junction plate, the vertical positioning seat of 3-, 4-elliptical aperture, 5-guide channel, 6-pre-embedded bolt, 7-grout hole, 8-positioning bolt, 9-lower-layer concrete floor, 10-prefabricated reinforced concrete wallboard.
The specific embodiment
Embodiment is referring to shown in Fig. 1-5; This prefabricated panel fast hoisting location regulating part; By horizontal base 1, be welded on horizontal base 1 a wherein end vertical positioning seat 3 and be welded on horizontal base 1 and form with the junction plate that is connected corner 2 of vertical positioning seat 3; Have and be embedded in the pre-embedded bolt 6 corresponding elliptical apertures 4 in the lower-layer concrete floor 9 on the said horizontal base 1, horizontal base 1 is connected through elliptical aperture 4 and the pre-embedded bolt 6 that is embedded in the lower-layer concrete floor 12.The top of said vertical positioning seat 3 have with prefabricated reinforced concrete wallboard 10 on positioning bolt 8 corresponding guide channels 5, and the width of guide channel 5 from top to bottom diminish gradually (convenient cooperate) with positioning bolt 8.The bottom of vertical positioning seat 3 have with prefabricated reinforced concrete wallboard 10 on the corresponding grouting mouth 7 (make things convenient for the reinforced bar sleeve in the prefabricated reinforced concrete wallboard 10 is carried out grouting construction) of grout hole.
In the present embodiment, said horizontal base 1 is a channel-section steel, and said vertical positioning seat 3 is made of welded connection by two channel-section steel openings relatively.In other embodiments, said horizontal base 1 also can be processed by other shaped steel with vertical positioning seat 3.
The length a of prefabricated panel fast hoisting location regulating part is 400mm~900mm, and height c is 400mm~900mm, and thickness b is 60mm~100mm.
The course of work of the utility model: in the whole process of using the utility model; Only need earlier horizontal base 1 to be regulated through pre-embedded bolt 6 to be fixed on the lower-layer concrete floor 9; Utilize the inboard control border of vertical positioning seat 3 then, promptly can be used as the foundation of prefabricated reinforced concrete wallboard 10 front and back control in place as prefabricated reinforced concrete wallboard 10; And the guide channel 5 on the vertical positioning seat 3 can use with positioning bolt 8 combinations in the reservation stripper bolt hole on the prefabricated reinforced concrete wallboard 10; Benchmark as control prefabricated reinforced concrete wallboard about 10 location; So once positioning bolt 8 gets into guide channel 5; And the inboard of prefabricated reinforced concrete wallboard 10 closely contacts with vertical positioning seat 3, and then accomplish prefabricated reinforced concrete wallboard about 10, location, front and back.After accomplish prefabricated reinforced concrete wallboard about 10, location, front and back; Just can then carry out prefabricated reinforced concrete wallboard 10 and break off relations in place (being about to corresponding the connecting of lower floor's embedded bar on reinforced bar sleeve and the lower-layer concrete floor 9 on the prefabricated reinforced concrete wallboard 10), whole process need not the relative position that operating personnel directly go for reinforced bar sleeve and lower floor's embedded bar.
In addition, after prefabricated reinforced concrete wallboard 10 lifting is accomplished, can prefabricated reinforced concrete wallboard 10 be carried out through positive left-hand thread bearing diagonal temporary fixed, the verticality through positive left-hand thread bearing diagonal adjusting prefabricated reinforced concrete wallboard 10 etc. then.

Claims (4)

1. a prefabricated panel fast hoisting is located regulating part; It is characterized in that: by horizontal base (1), be welded on horizontal base (1) a wherein end vertical positioning seat (3) and be welded on horizontal base (1) and form with the junction plate that is connected corner (2) of vertical positioning seat (3); Have and be embedded in the corresponding elliptical aperture of pre-embedded bolt (6) (4) in the lower-layer concrete floor (9) on the said horizontal base (1); The top of said vertical positioning seat (3) have with prefabricated reinforced concrete wallboard (10) on the corresponding guide channel of positioning bolt (8) (5), the bottom of vertical positioning seat (3) have with prefabricated reinforced concrete wallboard (10) on the corresponding grouting mouth (7) of grout hole.
2. prefabricated panel fast hoisting according to claim 1 location regulating part, it is characterized in that: said horizontal base (1) is a channel-section steel, and said vertical positioning seat (3) is made of welded connection by two channel-section steel openings relatively.
3. prefabricated panel fast hoisting according to claim 1 location regulating part, it is characterized in that: the width of said guide channel (5) from top to bottom diminishes gradually.
4. prefabricated panel fast hoisting according to claim 1 and 2 location regulating part, it is characterized in that: its length (a) is 400mm~900mm, and highly (c) is 400mm~900mm, and thickness (b) is 60mm~100mm.
CN2011202708628U 2011-07-28 2011-07-28 Rapid hoisting, positioning and adjusting piece for prefabricated wall board Expired - Lifetime CN202194394U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011202708628U CN202194394U (en) 2011-07-28 2011-07-28 Rapid hoisting, positioning and adjusting piece for prefabricated wall board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011202708628U CN202194394U (en) 2011-07-28 2011-07-28 Rapid hoisting, positioning and adjusting piece for prefabricated wall board

Publications (1)

Publication Number Publication Date
CN202194394U true CN202194394U (en) 2012-04-18

Family

ID=45949311

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011202708628U Expired - Lifetime CN202194394U (en) 2011-07-28 2011-07-28 Rapid hoisting, positioning and adjusting piece for prefabricated wall board

Country Status (1)

Country Link
CN (1) CN202194394U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102912903A (en) * 2012-09-26 2013-02-06 苏州金螳螂幕墙有限公司 Fixing part of connecting bolt of open type stone curtain wall sealing layer
CN104314318A (en) * 2014-11-12 2015-01-28 山东三箭建设工程股份有限公司 High-precision positioning guide device and use method thereof
CN104878942A (en) * 2015-05-28 2015-09-02 中国十七冶集团有限公司 High-precision in-place assisting device and method for hoisting prefabricated structural elements
CN105587127A (en) * 2015-06-17 2016-05-18 深圳建业工程集团股份有限公司 Method for locating outer wall prefabricated hanging plate based on laser line marking instrument
CN107842205A (en) * 2017-12-15 2018-03-27 承德绿建建筑节能科技有限公司 A kind of positioning for precast wall body structure adjusts tool part and precast wall body structure
CN110388067A (en) * 2019-07-19 2019-10-29 湖南城市学院 A kind of PC assembled architecture supporting module mounting and positioning device
CN111119495A (en) * 2020-01-20 2020-05-08 中铁十二局集团建筑安装工程有限公司 PCF plate construction method for fabricated building

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102912903A (en) * 2012-09-26 2013-02-06 苏州金螳螂幕墙有限公司 Fixing part of connecting bolt of open type stone curtain wall sealing layer
CN102912903B (en) * 2012-09-26 2014-03-12 苏州金螳螂幕墙有限公司 Fixing part of connecting bolt of open type stone curtain wall sealing layer
CN104314318A (en) * 2014-11-12 2015-01-28 山东三箭建设工程股份有限公司 High-precision positioning guide device and use method thereof
CN104878942A (en) * 2015-05-28 2015-09-02 中国十七冶集团有限公司 High-precision in-place assisting device and method for hoisting prefabricated structural elements
CN105587127A (en) * 2015-06-17 2016-05-18 深圳建业工程集团股份有限公司 Method for locating outer wall prefabricated hanging plate based on laser line marking instrument
CN105587127B (en) * 2015-06-17 2017-10-10 深圳建业工程集团股份有限公司 The exterior wall prefabricated concrete board localization method realized by means of Laser Line Marker
CN107842205A (en) * 2017-12-15 2018-03-27 承德绿建建筑节能科技有限公司 A kind of positioning for precast wall body structure adjusts tool part and precast wall body structure
CN107842205B (en) * 2017-12-15 2023-06-23 承德绿建建筑节能科技有限公司 Positioning adjustment tool piece for prefabricated wall structure and prefabricated wall structure
CN110388067A (en) * 2019-07-19 2019-10-29 湖南城市学院 A kind of PC assembled architecture supporting module mounting and positioning device
CN111119495A (en) * 2020-01-20 2020-05-08 中铁十二局集团建筑安装工程有限公司 PCF plate construction method for fabricated building

Similar Documents

Publication Publication Date Title
CN202194394U (en) Rapid hoisting, positioning and adjusting piece for prefabricated wall board
CN201818051U (en) Supporting frame for overhanging mold plate
CN204252555U (en) Precast facade plate positioning device
CN202090932U (en) Universal template device for tunnel construction
CN202247894U (en) Double-strut cantilever template
CN203998536U (en) Home lift girder assembly
CN103967332B (en) The construction method of a kind of building site enclosing
CN202882376U (en) Elevator shaft template support platform
CN202689491U (en) Lower supporting type overhanging scaffold
CN102425271B (en) Split head used for building floor
CN202157308U (en) Flat gate guiding device
CN207109598U (en) A kind of bridge pier shaft model sheetinstallat positioner
CN201605589U (en) Fixed end
CN202449171U (en) Construction device based on sectioned pull-in method
CN202338070U (en) Cushion block for installation of wallboards
CN205839740U (en) The building enclosure that a kind of vertical cross section-variable underground continuous wall is combined with agent structure
CN201786360U (en) Supporting structure improving load-carrying property of loess tunnel arch springing
CN201771112U (en) Multipurpose reinforcement mat frame
CN206512958U (en) A kind of U-shaped component suitable for splicing installation between brick plate
CN202369932U (en) Bridge curtain board installation trolley
CN202012079U (en) Pile anchor for cable crane
CN203129579U (en) Slip form rail locking device
CN201296609Y (en) A cable crane rear anchor mobile ridge device
CN201794258U (en) Moving floor board for machine room
CN205051201U (en) Prefabricated cabin of transformer substation's delivery formula

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120418