CN202171065U CN2011202668902U CN201120266890U CN202171065U CN 202171065 U CN202171065 U CN 202171065U CN 2011202668902 U CN2011202668902 U CN 2011202668902U CN 201120266890 U CN201120266890 U CN 201120266890U CN 202171065 U CN202171065 U CN 202171065U
Authority
CN
China
Prior art keywords
crane span
span structure
bridge
trapezoidal
testing bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011202668902U
Other languages
Chinese (zh)
Inventor
张光明
王文莉
李颖瑾
蒙家彬
王军飞
曲娟娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Electric Power Engineering Consulting Institute Corp Ltd
Original Assignee
Shandong Electric Power Engineering Consulting Institute Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Electric Power Engineering Consulting Institute Corp Ltd filed Critical Shandong Electric Power Engineering Consulting Institute Corp Ltd
Priority to CN2011202668902U priority Critical patent/CN202171065U/en
Application granted granted Critical
Publication of CN202171065U publication Critical patent/CN202171065U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model relates to an arched cable bridge, wherein the centre of the bridge is an upward arched or trapezoidal bridge section; two ends of the arched or trapezoidal bridge section are provided with a suspending lazy arm or a column support arm. The utility model has the advantages of beautiful and simple cable installation without affecting the path of the cable installation, increases the space on the lower part of the bridge by using the arched bridge and improves the detection environment of the inspector.

Description

Arch formula cable testing bridge
Technical field
The utility model relates to a kind of cable testing bridge device, relates in particular to a kind of arch formula cable testing bridge.
Background technique
Cable testing bridge is widely used in the power industry at present.Particularly electric substation's inner cable quantity is various, and direction of routing is complicated, and cable testing bridge uses to solve and much lays problem, makes cable laying more clear.
But the layout of cable testing bridge has certain restriction again; Be that cable testing bridge generally is installed in the cable half storey; The height of cable half storey is generally all lower, and personnel are just smaller in the space itself of installing, overhauling and making an inspection tour, and secondary crane span structure layer distance when arranging has the requirement of rules standard again.When in the cable half storey, laying like this, bottom crane span structure does not often meet the demands apart from the distance on ground, and personnel are very difficult when tour is passed through.
Summary of the invention
The purpose of the utility model is exactly in order to address the above problem, and a kind of arch formula cable testing bridge is provided, and this kind crane span structure has simple in structure, and is easy to use, can effectively improve cable testing bridge below personnel and make an inspection tour the problem through difficulty.
For realizing above-mentioned purpose, the utility model adopts following technological scheme:
A kind of arch formula cable testing bridge, arc or the trapezoidal crane span structure section of the centre of crane span structure for upwards arching upward, suspension arm or upright supports arm are established in the two ends of arc or trapezoidal crane span structure section.
Described arc or trapezoidal crane span structure section are provided with the wire earthed system.
Described suspension arm or upright supports arm link to each other with crane span structure through the pallet fixing device.
The pallet fixing device is that bolt, anchor such as buckle at the support fixed system of forming, and is used for supports such as support brachium pontis or arm and is connected with the direct of crane span structure.
The arch formula cable testing bridge personnel of being installed on of the utility model make an inspection tour the passage place, and when personnel maked an inspection tour, personnel were through convenient.
The beneficial effect of the utility model is: cable laying is attractive in appearance, succinct, does not influence the path of cable laying, and adopts the space of arch formula crane span structure rear axle stand below to increase, and has improved the personnel's that make an inspection tour maintenance environment.Under the constant basically situation of cost, as the user of service convenience is provided after using this crane span structure, embodied the theory that people-oriented, enlarged the Applicable scope that crane span structure lays.
Description of drawings
Fig. 1 is the structural representation of the utility model;
Wherein, 1. arc or trapezoidal crane span structure section 2. hang arm or upright supports arm, 3. pallet fixing device, 4. crane span structure connection set and fixed block, 5. earthed system.
Embodiment
Below in conjunction with accompanying drawing and embodiment the utility model is further specified.
A kind of arch formula cable testing bridge, arc or the trapezoidal crane span structure section 1 of the centre of crane span structure for upwards arching upward, suspension arm or upright supports arm 2 are established in the two ends of arc or trapezoidal crane span structure section 1.
Described arc or trapezoidal crane span structure section 1 are provided with wire earthed system 5.
Described suspension arm or upright supports arm 2 link to each other with crane span structure through pallet fixing device 3.
Among Fig. 1, slot type or ladder type crane span structure directly link to each other with former crane span structure, use equivalent material.Make an inspection tour through the place personnel, crane span structure upwards arches upward on former level height basis, and to be angle be the oblique top of straight line or be arc.Arching upward is parallel to former crane span structure or maintenance arc again to the appropriate location, about 1000mm of length or radius are about 500mm, are angle again and are oblique below of straight line or arc, until former crane span structure level height.
Crane span structure uses trailing arm or column arm supports, uses fixed block such as pallet to fix, and the crane span structure joint uses connecting sheet etc. to connect, and establishes the earthed system such as annealed copperwire of ground terminal and 4 square millimeters on the crane span structure.

Claims (3)

1. an arch formula cable testing bridge is characterized in that, arc or the trapezoidal crane span structure section of the centre of crane span structure for upwards arching upward, and suspension arm or upright supports arm are established in the two ends of arc or trapezoidal crane span structure section.
2. arch formula cable testing bridge according to claim 1 is characterized in that, described arc or trapezoidal crane span structure section are provided with the wire earthed system.
3. arch formula cable testing bridge according to claim 1 is characterized in that, described suspension arm or upright supports arm link to each other with crane span structure through the pallet fixing device.
CN2011202668902U 2011-07-26 2011-07-26 Arched cable bridge Expired - Lifetime CN202171065U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011202668902U CN202171065U (en) 2011-07-26 2011-07-26 Arched cable bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011202668902U CN202171065U (en) 2011-07-26 2011-07-26 Arched cable bridge

Publications (1)

Publication Number Publication Date
CN202171065U true CN202171065U (en) 2012-03-21

Family

ID=45829261

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011202668902U Expired - Lifetime CN202171065U (en) 2011-07-26 2011-07-26 Arched cable bridge

Country Status (1)

Country Link
CN (1) CN202171065U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103511747A (en) * 2013-09-17 2014-01-15 兰继红 Cable bridge cable pressing assembly used for electroplating lifting machine
CN112165049A (en) * 2020-10-27 2021-01-01 济南隆凯新材料科技有限公司 Bridge frame system of multi-channel overpass combined bearing cable and assembling method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103511747A (en) * 2013-09-17 2014-01-15 兰继红 Cable bridge cable pressing assembly used for electroplating lifting machine
CN112165049A (en) * 2020-10-27 2021-01-01 济南隆凯新材料科技有限公司 Bridge frame system of multi-channel overpass combined bearing cable and assembling method

Similar Documents

Publication Publication Date Title
CN102704405B (en) Method utilizing buckle cable and anchor cable for balancing extra horizontal force
CN206071141U (en) Transformer substation framework beam
CN202171065U (en) Arched cable bridge
CN103001146A (en) Steel pipe pole operation platform and usage method thereof
RU73905U1 (en) SINGLE-RACK ANCHOR-ANGULAR SUPPORT OF THE THREE-PHASE ELECTRIC TRANSMISSION LINE (OPTIONS)
CN102758404A (en) Front fulcrum hanging basket travelling device of spatial V-shaped cable-stayed bridge
CN206128808U (en) Novel single loop cable dead end tower
CN204230807U (en) A kind of power cable crane span structure supporting structure being easy to regulate
CN103485540A (en) Method for cable-stayed reinforcement of convertor station direct-current filter suspension steel framework and steel framework
CN103738861A (en) Integral hoisting method for A type column of steel pipe of ultra-high voltage transformer station
CN203475318U (en) Cable-clamp-free hanging appliance used for anchoring stay cable at tower end in cable bent tower steel anchor beam area
CN203617651U (en) Steady and reliable abacus connector
CN203476190U (en) Electric power cable overhauling ladder
CN202790922U (en) Width adjusting tee joint of stainless steel crane span structure
CN101459320B (en) Large span cable bridge rack installation mold and installation method thereof
CN201142537Y (en) Large span cable bridge rack installation mold
CN204281159U (en) Steel wire rope tightening device
CN102927365A (en) Lengthened elbow for stainless steel bridge
CN203820360U (en) Lifting appliance for installing existing railway sound barrier plate
CN203113867U (en) Straight-line cable T-jointing steel tube rod tower
CN203879367U (en) Tower ladder structure for electric transmission line
CN202271866U (en) Method for hanging fixed contact net by utilizing beam string structure
CN202369932U (en) Bridge curtain board installation trolley
CN104973524B (en) Cable bridge inverted-type installation system on overhead vertical structural body
CN205501820U (en) Easy bridge beam slab handling frame of adjusting

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120321