CN202131007U - Long and straight workpiece hoisting tool - Google Patents
Long and straight workpiece hoisting tool Download PDFInfo
- Publication number
- CN202131007U CN202131007U CN201120224587U CN201120224587U CN202131007U CN 202131007 U CN202131007 U CN 202131007U CN 201120224587 U CN201120224587 U CN 201120224587U CN 201120224587 U CN201120224587 U CN 201120224587U CN 202131007 U CN202131007 U CN 202131007U
- Authority
- CN
- China
- Prior art keywords
- workpiece
- long
- steel wire
- wire ropes
- straight
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Load-Engaging Elements For Cranes (AREA)
Abstract
The utility model relates to a long and straight workpiece hoisting tool which is mainly used for hoisting long and straight workpieces in the shipbuilding industry, belonging to the field of shipbuilding technology. The long and straight workpiece hoisting tool comprises a cross beam (1), lugs I (2) are symmetrically arranged at the left end and the right end of the top of the cross beam (1), lugs II (3) are symmetrically arranged at the left end and the right end of the bottom of the cross beam (1), pull rings I (7) are fixedly connected on the lugs I (2), steel wire ropes I (4) are arranged on the pull rings I (7) in a penetrating way, the steel wire ropes I (4) are connected with a lifting hook of a crane, pull rings II (8) are fixedly connected on the lugs II (3), steel wire ropes II (6) are arranged on the pull rings II (8) in a penetrating way, and hooks (5) are arranged at the lower ends of the steel wire ropes II (6). In the long and straight workpiece hoisting tool, steel wire ropes sleeved at both ends of the workpiece are hung on the hooks at the two sides of the workpiece, the hoisting process is stable, moreover, the steel wire ropes on the workpiece cannot slide to the middle in the hoisting process, and the safety is better.
Description
Technical field
The utility model relates to a kind of handling frock, is mainly used in the long straight workpiece of handling in the shipbuilding industry, belongs to the marine technology field.
Background technology
In shipbuilding industry during the long straight workpiece of handling; All be that steel wire loop is contained in workpiece two, directly hang over then and carry out handling on the suspension hook that there is a disadvantage in handling like this; Be exactly when Workpiece length is longer; Its stationarity is not easy to grasp, and steel rope slides to the centre easily in the handling process, is prone to take place safety misadventure.
Summary of the invention
The purpose of the utility model is to overcome above-mentioned deficiency, provides a kind of handling the stable and good straight workpiece handling of the length frock of safety.
The purpose of the utility model is achieved in that the straight workpiece handling of a kind of length frock; Be characterized in: it comprises crossbeam, and said crossbeam top right ends is symmetrically arranged with hanger I, and said crossbeam bottom right ends is symmetrically arranged with hanger II; Be fixedly connected with draw ring I on the said hanger I; Be coated with steel rope I on the said draw ring I, said steel rope I is connected with the suspension hook of crane, is fixedly connected with draw ring II on the said hanger II; Be coated with steel rope II on the said draw ring II, the lower end of said steel rope II is provided with hook.
Compared with prior art, the beneficial effect of the utility model is:
The straight workpiece handling of a kind of length of the utility model frock, the steel rope of its workpiece two suit is hung on the hook on both sides, and its handling process is steady, and the steel rope on the workpiece can not slide to the centre in the handling process, and safety is better.
Description of drawings
Fig. 1 is the structural representation of the long straight workpiece handling frock of the utility model.
Wherein:
Crossbeam 1; Hanger I2; Hanger II3; Steel rope I4; Hook 5; Steel rope II6; Draw ring I7; Draw ring II8.
The specific embodiment
Referring to Fig. 1, the utility model relates to the straight workpiece handling of a kind of length frock, and it comprises crossbeam 1; Said crossbeam 1 top right ends is symmetrically arranged with hanger I2, and said crossbeam 1 bottom right ends is symmetrically arranged with hanger II3, and said hanger I2 goes up and is fixedly connected with draw ring I7 through bearing pin; Be coated with steel rope I4 on the said draw ring I7; Said steel rope I4 is connected with the suspension hook of crane, and said hanger II3 goes up and is fixedly connected with draw ring II8 through bearing pin, is coated with steel rope II6 on the said draw ring II8; The lower end of said steel rope II6 is provided with hook 5, and the steel rope of workpiece two suit mounts on hook 5.
Said hanger I2 and hanger II3 inboard can also be provided with some hangers, can draw ring be arranged on the hanger of correct position according to length and the weight of growing straight workpiece.
Claims (1)
1. one kind long straight workpiece handling frock; It is characterized in that: it comprises crossbeam (1), and said crossbeam (1) top right ends is symmetrically arranged with hanger I (2), and said crossbeam (1) bottom right ends is symmetrically arranged with hanger II (3); Be fixedly connected with draw ring I (7) on the said hanger I (2); Be coated with steel rope I (4) on the said draw ring I (7), said steel rope I (4) is connected with the suspension hook of crane, is fixedly connected with draw ring II (8) on the said hanger II (3); Be coated with steel rope II (6) on the said draw ring II (8), the lower end of said steel rope II (6) is provided with hook (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201120224587U CN202131007U (en) | 2011-06-29 | 2011-06-29 | Long and straight workpiece hoisting tool |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201120224587U CN202131007U (en) | 2011-06-29 | 2011-06-29 | Long and straight workpiece hoisting tool |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202131007U true CN202131007U (en) | 2012-02-01 |
Family
ID=45519786
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201120224587U Expired - Fee Related CN202131007U (en) | 2011-06-29 | 2011-06-29 | Long and straight workpiece hoisting tool |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202131007U (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102718124A (en) * | 2012-05-28 | 2012-10-10 | 中建钢构有限公司 | Anti-slipping lifting appliance |
CN103395682A (en) * | 2013-08-13 | 2013-11-20 | 上海申迪园林投资建设有限公司 | Lifting hook system and lifting method of tree with soil ball |
CN104860204A (en) * | 2015-06-05 | 2015-08-26 | 安徽瀚洋节能科技有限公司 | Auxiliary tool with large-diameter equipment lifting function |
CN104876111A (en) * | 2015-06-01 | 2015-09-02 | 安徽瀚洋节能科技有限公司 | Auxiliary tool for large-diameter equipment hoisting |
CN105947880A (en) * | 2016-06-24 | 2016-09-21 | 合肥欧克斯新型建材有限公司 | Auxiliary tool with large-diameter equipment hoisting function |
CN105967050A (en) * | 2016-05-23 | 2016-09-28 | 肥西县鑫山机械厂 | Auxiliary tool for large-diameter equipment hoisting |
CN105967046A (en) * | 2016-06-24 | 2016-09-28 | 合肥欧克斯新型建材有限公司 | Auxiliary hoisting tool for large-diameter equipment |
CN106081868A (en) * | 2016-07-03 | 2016-11-09 | 安徽碧源环保工程有限公司 | A kind of major diameter equipment lifting aid |
CN106081867A (en) * | 2016-06-30 | 2016-11-09 | 合肥天沃能源科技有限公司 | A kind of major diameter equipment lifting aid |
-
2011
- 2011-06-29 CN CN201120224587U patent/CN202131007U/en not_active Expired - Fee Related
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102718124A (en) * | 2012-05-28 | 2012-10-10 | 中建钢构有限公司 | Anti-slipping lifting appliance |
CN103395682A (en) * | 2013-08-13 | 2013-11-20 | 上海申迪园林投资建设有限公司 | Lifting hook system and lifting method of tree with soil ball |
CN104876111A (en) * | 2015-06-01 | 2015-09-02 | 安徽瀚洋节能科技有限公司 | Auxiliary tool for large-diameter equipment hoisting |
CN104860204A (en) * | 2015-06-05 | 2015-08-26 | 安徽瀚洋节能科技有限公司 | Auxiliary tool with large-diameter equipment lifting function |
CN105967050A (en) * | 2016-05-23 | 2016-09-28 | 肥西县鑫山机械厂 | Auxiliary tool for large-diameter equipment hoisting |
CN105947880A (en) * | 2016-06-24 | 2016-09-21 | 合肥欧克斯新型建材有限公司 | Auxiliary tool with large-diameter equipment hoisting function |
CN105967046A (en) * | 2016-06-24 | 2016-09-28 | 合肥欧克斯新型建材有限公司 | Auxiliary hoisting tool for large-diameter equipment |
CN106081867A (en) * | 2016-06-30 | 2016-11-09 | 合肥天沃能源科技有限公司 | A kind of major diameter equipment lifting aid |
CN106081868A (en) * | 2016-07-03 | 2016-11-09 | 安徽碧源环保工程有限公司 | A kind of major diameter equipment lifting aid |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202131007U (en) | Long and straight workpiece hoisting tool | |
CN201217608Y (en) | Integral component suspending beam for hoisting | |
CN203006738U (en) | Section bar lifting tool | |
CN203922436U (en) | A kind of carrying pole type suspension bracket | |
CN205151520U (en) | Large -scale ring rolling spare hoist | |
CN202808173U (en) | Lifting device special for lateral columns | |
CN201301169Y (en) | Lifting device special for cathode carbon block | |
CN204778292U (en) | Aluminium bar instrument of suspending in midair | |
CN201228196Y (en) | Special slings for rolling mill working roll | |
CN202131004U (en) | Balance hanging beam for combination operation of two cranes | |
CN206051268U (en) | The vehicle frame boom hoisting of quick despatch | |
CN202131011U (en) | Transitional hanging beam for double-trolley gantry crane | |
CN204079223U (en) | A kind of steel pipe lifting tool | |
CN204702397U (en) | A kind of aluminium alloy bars special hanger | |
CN203345919U (en) | Lifting tool for lifting multiple ring pieces | |
CN203186981U (en) | Suspension device with self-adjustment balancing function | |
CN202414964U (en) | Travelling crane hoisting auxiliary device | |
CN202465039U (en) | Self-locking suspending tool for wheels of railway truck | |
CN203128014U (en) | Hoisting tongs for hoisting billet steel | |
CN205662225U (en) | Become a bundle semitrailer pterygoid lamina special lifting device | |
CN201458512U (en) | Balance hanger | |
CN205346603U (en) | Pneumatic hoist of tubular pile mould is carried to tubular pile trade | |
CN205241050U (en) | I -shaped wheel lifting device | |
CN203382379U (en) | Turnover lifting device for swing bolster mud core | |
CN204778302U (en) | Aluminium alloy transport frock |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120201 Termination date: 20150629 |
|
EXPY | Termination of patent right or utility model |