CN202124824U - Floating drilling platform for bridge construction - Google Patents

Floating drilling platform for bridge construction Download PDF

Info

Publication number
CN202124824U
CN202124824U CN2011202051315U CN201120205131U CN202124824U CN 202124824 U CN202124824 U CN 202124824U CN 2011202051315 U CN2011202051315 U CN 2011202051315U CN 201120205131 U CN201120205131 U CN 201120205131U CN 202124824 U CN202124824 U CN 202124824U
Authority
CN
China
Prior art keywords
crossbeam
floating
horizontal
longeron
buoyancy aid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011202051315U
Other languages
Chinese (zh)
Inventor
范恒秀
符昭星
曹义昌
廖文华
余海
朱宝君
张洪伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Engineering Group Co Ltd
Original Assignee
China Railway First Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Engineering Group Co Ltd filed Critical China Railway First Engineering Group Co Ltd
Priority to CN2011202051315U priority Critical patent/CN202124824U/en
Application granted granted Critical
Publication of CN202124824U publication Critical patent/CN202124824U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a floating drilling platform for bridge construction, comprising a floating supporting platform, a plurality of temporary fixing devices for temporarily fixing the floating supporting platform and a hoisting system arranged on the floating supporting platform, wherein the floating supporting platform comprises a horizontal floating body, a horizontal supporting frame fixedly mounted on the horizontal floating body and a horizontal steel plate paved on the horizontal supporting frame; the horizontal floating body is composed of a plurality of buoyancy tanks assembled together; a lay-down through hole for laying a steel protecting canister for drilled pile construction down is formed on the horizontal steel plate; a lay-down channel for laying down the steel protecting canister down is correspondingly formed on the horizontal supporting frame and the horizontal floating body; and the lay-down channels are distributed right under the lay-down through hole. The floating drilling platform is rational in design, convenient for construction, low in construction cost and good in use effect; and the floating drilling platform is capable of effectively solving actual problems, including high limitation of geographical conditions on the existing floating platform, un-drivable drilled pile foundation, and un-locatable and un-drivable steel protecting canister during the drilled pile construction, etc.

Description

A kind of bridge construction is used the floating drilling platform
Technical field
The utility model relates to a kind of drilling construction platform, especially relates to a kind of bridge construction and uses the floating drilling platform.
Background technology
Canal river grand bridge master bridge is (the firm structure continuous beam of the prestressed concrete of m of 48+4 * 80+48); And the suitable bridge of the main pier foundation pier of the firm structure continuous beam of this prestressed concrete is to being followed successively by 28# pier~34# pier; Wherein 28# pier and 34# pier are for dividing dividing pier; These 5 main piers of 29# pier~33# pier all are arranged in canal river (being Shui Zhongdun), and are designed to highrise pile cap.During practice of construction, the cushion cap height 5.0m of 29# pier~5 main piers of 33# pier adds platform height 2m, and cushion cap to put into planar dimension be 26m * 19.6m, add the planar dimension 14.2 * 12.2m of platform, and the height of 5 main piers is 67m~69.4m.
During practice of construction, the covering layer of pier is more shallow in the water, does not see the fracture structure phenomenon.The stratum is single, belongs to monoclinal structure, and formation dip is comparatively mild, and main bedding is respectively N30-60 ° of E/4-10 ° of SE.The joint is " X " shape more grows, and is mostly the steep dip horn shape, and joint plane generally is closed form more, and steep candy section joint plane opens more, spacing 1m~3m, and extensibility is better.The riverbed is the U type, and deep water reaches about 22.3m deeply.Wherein, the depth of water 18.5m of 31# pier, geology from up to down is respectively: land pebble that grating is relatively poor and severely-weathered, weak weathered sandstone; The depth of water 20m of 32# pier, geology from up to down is respectively: severely-weathered sandstone, weak weathering mud stone, weak weathering mud stone and sandstone.Simultaneously, 31# pier and 32# pier do not have covering layer.
Because canal river grand bridge master bridge location in the reservoir area, is located in hilly ground, Guangan, Sichuan, be rich Liu Tan power station from 16km place, bridge location downstream, normal pool level is 213.80m before the lock of power station, thereby surpasses just flood discharge automatically of 213.8m.Do not come on the ship dry season, and only ship could come from downstream when flood season level rises, the wide 12m of power station lock, and big ship can not advance.Have only long 31m according to investigations in the reservoir area, the dull and stereotyped ship of wide 6m and high 2m, load-carrying is at 180 tons, thereby can not satisfy the working load needs.In addition, there is the artificial canal of one section width of the channel 7m in the place that Jia Lingjiang River is gone in the canal river, thereby influences marching into the arena of the large-scale ship in Jia Lingjiang River, and the barge more than the 400t that sails into from Chongqing, Wuhan receives the water route to limit into not the canal river.
Floating platform construction base case is the scheme of a comparative maturity, the existing traditional floating platform constructure scheme that is nowadays adopted all be mostly with barge container as carrier, assembly unit beam and gantry walking system in length and breadth on barge.But in the actual use, above-mentioned traditional floating platform construction basis existence receives the big defective of geographical conditions restriction, and undeveloped as water transportations such as reservoir area, Ba Qu, barge container advances when not coming, and this floating platform constructure scheme just can not satisfy construction requirement.
The utility model content
The utility model technical problem to be solved is to above-mentioned deficiency of the prior art; Provide a kind of bridge construction to use the floating drilling platform; It is reasonable in design, easy construction, construction cost is low and result of use good, can effectively solve receiving that existing floating platform exists the geographical conditions restriction is big, drilled pile basic can't injection, the steel casing can't be located to insert and practical problem such as beaten during drilled pile construction.
For solving the problems of the technologies described above; The technical scheme that the utility model adopts is: a kind of bridge construction is used the floating drilling platform; It is characterized in that: the Lift-on/Lift-off System that comprises the floating support platform, said floating support platform is carried out temporary fixed a plurality of temporary fastening devices and is laid on the said floating support platform and the construction drill stake is lifted with the steel casing; A plurality of said temporary fastening devices all are laid in the side all around of said floating support platform, and all are fastenedly connected through anchor cable between each temporary fastening device and the said floating support platform; Said floating support platform comprises horizontal buoyancy aid, be fixedly mounted on the horizontal support framework on the said horizontal buoyancy aid and the horizontal steel plate on said horizontal support framework of mating formation; Said horizontal buoyancy aid is assemblied to form by a plurality of buoyancy tanks; Be fastenedly connected through a plurality of connectors between adjacent two said buoyancy tanks; Said buoyancy tank is the cube steel box section, and the length of said cube steel box section is that 8m~12m, width are that 1m~3m and its highly are 1m~2m; Have on the said horizontal steel plate and supply the through hole of transferring that said steel casing transfers, corresponding leaving supplies the passage of transferring that said steel casing transfers on said horizontal support framework and the said horizontal buoyancy aid, and the said passage of transferring is laid in and transfers under the through hole.
Above-mentioned a kind of bridge construction is used the floating drilling platform; It is characterized in that: said horizontal buoyancy aid comprises the rectangle buoyancy aid that two structures and size are all identical; Two said rectangle buoyancy aids are parallel laying, and two said rectangle buoyancy aids are that axis of symmetry carries out symmetry and lays with the longitudinal centre line of said floating support platform; Said horizontal support framework comprises that longeron that twice are parallel laying and multiple tracks are the crossbeam of parallel laying; The structure of the said longeron of twice and longitudinal length said longeron all identical with size is not less than the longitudinal length of said rectangle buoyancy aid, and all identical and lateral length said crossbeam of the structure of the said crossbeam of multiple tracks and size is not less than the spacing between the said longeron of twice; The said longeron of twice be laid in respectively two said rectangle buoyancy aids directly over, and said longeron lays along longitudinal center's axis of said rectangle buoyancy aid, the said longeron of twice is fastenedly connected through the multiple tracks crossbeam and is one.
Above-mentioned a kind of bridge construction is used the floating drilling platform, it is characterized in that: the left and right end portions of said crossbeam is fixedly mounted on respectively on two said rectangle buoyancy aids, and the said longeron of twice is fixedly mounted on the top, the left and right sides of the said crossbeam of multiple tracks respectively.
Above-mentioned a kind of bridge construction is used the floating drilling platform; It is characterized in that: said rectangle buoyancy aid is assemblied to form with all identical buoyancy tank of size by a plurality of structures from front to back successively; The transverse width D of said rectangle buoyancy aid is identical with the length of said buoyancy tank; And the longitudinal length L=N * d of said rectangle buoyancy aid, wherein N is the quantity that is assemblied to form the buoyancy tank of said rectangle buoyancy aid, d is the width of buoyancy tank.
Above-mentioned a kind of bridge construction is used the floating drilling platform; It is characterized in that: said Lift-on/Lift-off System comprises portal frame and is installed in the lifting appliance on the said portal frame; Said portal frame comprises girder and two supporting legs that are installed in below, the girder left and right sides respectively; Two said supporting leg bottoms are equipped with and drive the walking mechanism that said portal frame moves forward and backward; The vertical walking rails that supplies said walking mechanism walking all is installed on the said longeron of twice, and said vertical walking rails is laid along longitudinal center's axis of longeron.
Above-mentioned a kind of bridge construction is used the floating drilling platform, it is characterized in that: the spacing between two said rectangle buoyancy aids is 32m ± 8m, and the longitudinal length of said rectangle buoyancy aid is 50m ± 10m; The quantity of said crossbeam is 6 roads, and the said crossbeam of multiple tracks is even laying, and the spacing between the adjacent twice crossbeam is 3m ± 0.5m.
Above-mentioned a kind of bridge construction is used the floating drilling platform; It is characterized in that: the said quantity of transferring through hole is one or more; Said horizontal steel plate is laid on the said crossbeam of multiple tracks between the said longeron of twice; Said horizontal steel plate middle part is provided with and is used to lay the through hole of transferring of transferring through hole and lays the district, and the said through hole of transferring is laid the district and is between two said rectangle buoyancy aids, and transfers through hole and all be laid between the adjacent twice crossbeam.
Above-mentioned a kind of bridge construction is used the floating drilling platform, it is characterized in that: said temporary fastening device is earth anchor or casts anchor.
Above-mentioned a kind of bridge construction is used the floating drilling platform, it is characterized in that: said longitudinal and cross beam is assemblied to form by many Pin plane frame, and the height of longitudinal and cross beam is 4m ± 1m; Said plane frame is assemblied to form by many universal rod bodies.
Above-mentioned a kind of bridge construction is used the floating drilling platform; It is characterized in that: a plurality of said temporary fastening devices comprise the temporary fastening device one that is laid in the upper reaches, said floating support platform river course of living in one side, be laid in the temporary fastening device two of downstream, said floating support platform river course of living in one side and be laid in the temporary fastening device three of the said floating support platform left and right sides respectively, and the quantity of said temporary fastening device one, temporary fastening device two and temporary fastening device three is a plurality of.
The utility model compared with prior art has the following advantages:
1, reasonable in design, erection method are flexibly and the floating drilling platform adjustable size that is assemblied to form.
2, adopt little buoyancy tank assembly unit floating platform, the practical problem that has solved the reservoir area or caused water transportation difficulty, barge container can't get into construction area owing to reasons such as geographical conditions are limited.Simultaneously, because longitudinal and cross beam is assemblied to form by many Pin plane frame, and plane frame is assemblied to form by many universal rod bodies, thereby the assembly unit of longitudinal and cross beam and fixing easy and construction effect good.In addition, utilize laying and the installation that two longerons can simple and convenient portal frame.
3, can be for drilled pile provide good operation platform, efficiently solve the difficulty that the naked rock steel pipe pile of deep water steel platform can't injection.Simultaneously, also solve the steel casing and can't locate slotting difficulty of beating, for the later naked rock large diameter borehole of deep water pile driving construction is offered reference.
4, assembly unit step is simple; Only need in advance a plurality of little buoyancy tanks to be transported to construction area; Put well side by side at the bank side of construction area or two cuboid buoyancy aids of harbour assembly unit and two cuboid buoyancy aids that will be assemblied to form afterwards, utilize the assembly unit process that jack just can easy completion longitudinal and cross beam then.
5, displacement is convenient; And can firm, a reliable operation platform be provided for drilled pile construction; Simplified the difficulty of construction of the naked rock large diameter drill hole pile of deep water greatly, not only time saving and energy saving, efficiency of construction is high; And can repeat repeatedly to use, reduced significantly the naked rock large diameter drill hole pile of deep water construction cost.After drilled pile construction is accomplished simultaneously, need not to remove the floating drilling platform, only need to use slide device that the floating drilling platform is removed and get final product, thereby further saved the engineering time.
6, practical value is high; Can effectively solve the constructional difficulties problem when the zone construction deep water bare rock drilling stake that large-scale marine equipment can't be marched into the arena; Strengthened working security and economy greatly, a reliable construction experience is provided during for construction area construction drill stakes such as reservoir area, naked rock or water transportation inconvenience later on.During actual the use, the utility model utilizes little buoyancy tank assembly unit barge to solve in the construction areas such as reservoir area or geographical conditions are limited the unapproachable construction difficult problem of barge container; Simultaneously, solved deep water bare rock drilling pile foundation can't injection and during drilled pile construction the steel casing can't locate and insert the construction difficult problem of beating.
In sum; The utility model is reasonable in design, easy construction, construction cost is low and result of use good; When improving efficiency of construction, shortening construction period; Also can practice thrift construction cost significantly, reduce the lot of manpower and material resources input, can effectively solve receiving that existing floating platform exists the geographical conditions restriction is big, drilled pile basic can't injection, the steel casing can't be located to insert and practical problem such as beaten during drilled pile construction.
Through accompanying drawing and embodiment, the technical scheme of the utility model is done further detailed description below.
Description of drawings
Fig. 1 is the structural representation of the utility model.
Fig. 2 is the vertical view of Fig. 1.
Structural representation when Fig. 3 does not mat formation horizontal steel plate and shaped steel for the utility model.
Fig. 4 is for adopting the construction view of the utility model when pier is constructed in two water.
Fig. 5 is for adopting the construction flow chart of the utility model when pier is constructed in the water.
Description of reference numerals:
The 1-anchor cable; The 2-longeron; The 3-crossbeam;
The horizontal steel plate of 4-; The little buoyancy tank of 5-; 6-transfers through hole;
The 7-earth anchor; The 8-1-girder; The 8-2-supporting leg;
The 8-3-rail; 8-4-traveling distribution beam; 8-5-traveling longitudinal beam;
The 8-6-road wheel; The vertical reinforcing member of 10-; 11-reinforced company fitting.
The specific embodiment
Like Fig. 1, Fig. 2, Fig. 3 and shown in Figure 4; The Lift-on/Lift-off System that the utility model comprises the floating support platform, said floating support platform is carried out temporary fixed a plurality of temporary fastening devices and is laid on the said floating support platform and the construction drill stake is lifted with the steel casing; A plurality of said temporary fastening devices all are laid in the side all around of said floating support platform, and all are fastenedly connected through anchor cable 1 between each temporary fastening device and the said floating support platform.Said floating support platform comprises horizontal buoyancy aid, be fixedly mounted on the horizontal support framework on the said horizontal buoyancy aid and the horizontal steel plate 4 on said horizontal support framework of mating formation; Said horizontal buoyancy aid is assemblied to form by a plurality of little buoyancy tanks 5; Be fastenedly connected through a plurality of connectors between adjacent two said little buoyancy tanks 5; Said little buoyancy tank 5 is the cube steel box section, and the length of said cube steel box section is that 8m~12m, width are that 1m~3m and its highly are 1m~2m; Have on the said horizontal steel plate 4 supply that said steel casing transfers transfer through hole 6, corresponding leaving supplies the passage of transferring that said steel casing transfers on said horizontal support framework and the said horizontal buoyancy aid, the said passage of transferring is laid in and transfers under the through hole 6.
In the present embodiment; Said Lift-on/Lift-off System comprises portal frame and is installed in the lifting appliance 12 on the said portal frame; Said portal frame comprises girder 8-1 and two supporting leg 8-2 that are installed in below, the 8-1 left and right sides respectively; Two said supporting leg 8-2 bottoms are equipped with and drive the walking mechanism that said portal frame moves forward and backward, and the vertical walking rails that supplies said walking mechanism walking all is installed on the said longeron 2 of twice, and said vertical walking rails is laid along longitudinal center's axis of longeron 2.
When actual installation is laid; Said walking mechanism comprises two road wheel 8-6 that are installed in supporting leg 8-2 bottom side by side; Said vertical walking rails comprises two one steel rail 8-3, and two said rail 8-3 are parallel laying, and traveling distribution beam 8-4 is installed directly over the said longeron 2; Traveling distribution beam 8-4 lays along longitudinal center's axis of longeron 2; And two traveling longitudinal beam 8-5 that supply two said rail 8-3 to install respectively are installed on the traveling distribution beam 8-4, and two said traveling longitudinal beam 8-5 are installed in the top, the left and right sides of traveling distribution beam 8-4 respectively, and said rail 8-3 is parallel laying with traveling distribution beam 8-4.In the actual use, also can adopt the running mechanism of other mechanism according to actual needs.
Actual the floating support platform that is assemblied to form is carried out when temporary fixed; The a plurality of said temporary fastening device that side is laid around the said floating support platform comprises the temporary fastening device one that is laid in the upper reaches, said floating support platform river course of living in one side, be laid in the temporary fastening device two of downstream, said floating support platform river course of living in one side and be laid in the temporary fastening device three of the said floating support platform left and right sides respectively, and the quantity of said temporary fastening device one, temporary fastening device two and temporary fastening device three is a plurality of.In the present embodiment, the quantity of said temporary fastening device one is 4, and the quantity of said temporary fastening device two is 2, and the quantity that is laid in the temporary fastening device three on said floating support platform left side and right side is 2.
During actual the use; Said temporary fastening device is earth anchor 7 or casts anchor; And be connected through anchor cable 1 between the corresponding electric windlass that is used with said temporary fastening device that is provided with on the said floating support platform, said electric windlass and said temporary fastening device.In the present embodiment, said temporary fastening device one, temporary fastening device two and temporary fastening device three are earth anchor 7.In conjunction with Fig. 5, when reality is laid earth anchor 7, need to confirm the quantity of laying earth anchor 7 and the installation position of each earth anchor 7 according to the temporary fixed position of said floating support platform earlier.The distribution method of each earth anchor 7 is all identical; At first according to the installation position of earth anchor 7; An anchorage block is set on the riverbed under water, and said anchorage block is fixed with two anchor cables 1, wherein anchor cable 1 with swim in the galvanized wire cage on the water surface; Said galvanized wire cage is laid with oil drum, and another root anchor cable 1 is fixed on the electric windlass that is installed on the said floating support platform.
As shown in Figure 5; Adopt the utility model when pier is constructed in the water; The Shui Zhongdun that is constructed comprises the underwater support table that is positioned at the river course, be laid in said underwater support table bottom and drilled pile that said underwater support table is supported and the pier stud that is laid in said underwater support table top, may further comprise the steps and pier in the water is carried out construction technology:
Step 1, the assembly unit of floating support platform: the bank side or the harbour of pier construction area of living in need construction water are assemblied to form said horizontal buoyancy aid through connector with a plurality of said little buoyancy tanks 5 earlier; Again said horizontal support frame fixation is installed on the said horizontal buoyancy aid that has been assemblied to form, and after the installation of said horizontal support frame fixation, horizontal steel plate 4 is mated formation on said horizontal support framework.
Before horizontal steel plate 4 mated formation; Need the quantity of construction drill stake and structure, size and the installation position of each drilled pile according to pier bottom in the said water earlier; Confirm quantity and the structure of respectively transferring through hole 6, size and the installation position of transferring through hole 6 of offering on horizontal steel plate 4, and corresponding on horizontal steel plate 4, offer all drilled piles of pedestal in the said water of construction need with transfer through hole 6; When horizontal steel plate 4 was mated formation, all that make that horizontal steel plate 4 offers were transferred through hole 6 and all are positioned at corresponding said the transferring of leaving directly over the passage on said horizontal support framework and the said horizontal buoyancy aid.
In the present embodiment; Said horizontal buoyancy aid comprises the rectangle buoyancy aid that two structures and size are all identical; Two said rectangle buoyancy aids are parallel laying, and two said rectangle buoyancy aids are that axis of symmetry carries out symmetry and lays with the longitudinal centre line of said floating support platform.Said horizontal support framework comprises that longeron 2 that twice are parallel laying and multiple tracks are the crossbeam 3 of parallel laying; The structure of the said longeron 2 of twice and longitudinal length said longeron 2 all identical with size is not less than the longitudinal length of said rectangle buoyancy aid, and all identical and lateral length said crossbeam 3 of the structure of the said crossbeam 3 of multiple tracks and size is not less than the spacing between the said longeron 2 of twice.The said longeron 2 of twice be laid in respectively two said rectangle buoyancy aids directly over, and said longeron 2 lays along longitudinal center's axis of said rectangle buoyancy aid, the said longeron 2 of twice is fastenedly connected through multiple tracks crossbeam 3 and is one.
Actual when carrying out assembly unit, the left and right end portions of said crossbeam 3 is fixedly mounted on respectively on two said rectangle buoyancy aids, and the said longeron 2 of twice is fixedly mounted on the top, the left and right sides of the said crossbeam 3 of multiple tracks respectively.That is to say, actual when carrying out assembly unit, through multiple tracks crossbeam 3 two rectangle buoyancy aids are consisted of one earlier, the left and right end portions that is about to multiple tracks crossbeam 3 is separately fixed on two said rectangle buoyancy aids.In the present embodiment, said longeron 2 is identical with the longitudinal length of said rectangle buoyancy aid, and multiple tracks crossbeam 3 all is laid in the middle part of twice longeron 2, and the middle part correspondence of twice longeron 2 is provided with the crossbeam laying district that supplies multiple tracks crossbeam 3 to lay.Said horizontal steel plate 4 is mated formation on multiple tracks crossbeam 3; And the transverse width of horizontal steel plate 4 is not more than the spacing between the twice longeron 2; The longitudinal length of horizontal steel plate 4 is not more than the longitudinal length that said crossbeam is laid the district for a short time, and said floating support platform is " H " shape platform.When reality is laid in crossbeam 3 on the said rectangle buoyancy aid, on said rectangle buoyancy aid, lay many sleepers earlier, with filling up cartridge plate on the sleeper, at last crossbeam 3 is fixed on the steel plate again.
Simultaneously; Before the horizontal steel plate 4 of mating formation on the multiple tracks crossbeam 3; Also need on multiple tracks crossbeam 3, to lay many vertical reinforcing members 10, many vertical reinforcing members 10 are even laying and it forms the layer of putting more energy into, and should reserve in the said layer of putting more energy into to supply the passage of transferring that said steel casing transfers.In the present embodiment, vertically reinforcing member 10 is a shaped steel.
During actual the laying; The said quantity of transferring through hole 6 is one or more; Said horizontal steel plate 4 is laid on the said crossbeam 3 of multiple tracks between the said longeron 2 of twice; Said horizontal steel plate 4 middle parts are provided with and are used to lay the through hole of transferring of transferring through hole 6 and lay the district, and the said through hole of transferring is laid the district and is between two said rectangle buoyancy aids, and transfer through hole 6 and all be laid between the adjacent twice crossbeam 3.On the said horizontal steel plate 4 reinforced company's fitting 11 is installed, the said fitting 8-6 of reinforced company is laid in the said through hole of transferring and lays the outside, district, and is fastenedly connected between reinforced company's fitting 11 and the said crossbeam 3 of multiple tracks.Need the quantity of construction drill stake identical in the pier in the said quantity of transferring through hole 6 and the construction water, in the present embodiment, the said quantity of transferring through hole 6 is 16.
In the present embodiment, when in the step 1 said floating support platform being carried out assembly unit, its assembly unit process is following:
101, rectangle buoyancy aid assembly unit: the bank side or the harbour of pier construction area of living in need construction water; Through connector a plurality of said little buoyancy tanks 5 are assemblied to form two said rectangle buoyancy aids respectively; And two said rectangle buoyancy aids that will be assemblied to form are put side by side; And make two said rectangle buoyancy aids abut against together and connect to form a rectangle platform for lining through fixture; The longitudinal length of said rectangle platform for lining is identical with the longitudinal length of said rectangle buoyancy aid, and the transverse width of said rectangle platform for lining is the transverse width sum of two said rectangle buoyancy aids.
Two said rectangle buoyancy aids comprise near the rectangle buoyancy aid one of bank side or harbour and the rectangle buoyancy aid of putting side by side with said rectangle buoyancy aid one two; The inboard of said rectangle buoyancy aid one is near bank side or harbour, and the outside of said rectangle buoyancy aid one is near said rectangle buoyancy aid two; The said longeron 2 of twice is respectively the longeron one that is laid in directly over the said rectangle buoyancy aid one and the longeron two that is laid in directly over the said rectangle buoyancy aid two; The left and right end portions of said crossbeam 3 is fixedly mounted on respectively on said rectangle buoyancy aid two and the rectangle buoyancy aid one.
102, the horizontal support frame fixation is installed: according to the multiple tracks crossbeam 3 of design in advance and structure, size and the installation position of twice longeron 2; And utilize two said rectangle buoyancy aids that are assemblied to form in the step 101, multiple tracks crossbeam 3 and twice longeron 2 are carried out assembly unit and fixing; When multiple tracks crossbeam 3 was carried out assembly unit, the assembly unit process of the said crossbeam 3 of multiple tracks was carried out synchronously, and the said crossbeam 3 of multiple tracks carries out assembly unit by a left side to parting into a plurality of crossbeam sections on the right side, and the fixed installation process of said horizontal support framework may further comprise the steps:
1021, the assembly unit of first crossbeam sections and longeron one and fixing: on said rectangle platform for lining; First crossbeam sections to the said crossbeam 3 of multiple tracks carries out assembly unit and fixing respectively, and the assembly unit and the fixing means of first crossbeam sections of the said crossbeam 3 of multiple tracks are all identical; And first crossbeam sections is carried out in assembly unit and the fixation procedure; On said rectangle platform for lining, said longeron one is carried out assembly unit synchronously; And according to the installation position of said longeron one of design in advance, longeron that assembly unit is accomplished is fastening to be fixed on the top, left part of the multiple tracks crossbeam 3 that assembly unit accomplishes.
First crossbeam sections of arbitrary road crossbeam 3 is carried out assembly unit and fixedly the time; Earlier assembly unit is carried out in the left part of first crossbeam sections; And according to the installation position of crossbeam 3 left parts on said rectangle buoyancy aid two of design in advance, the left part of first crossbeam sections that assembly unit is accomplished is fixed on the said rectangle buoyancy aid two; Afterwards, carry out continuous assembly unit from left to right from the left part, accomplish until assembly unit till the inside wall flush of right side beam-ends and said rectangle buoyancy aid one of crossbeam 3, then accomplish the assembly unit process of first crossbeam sections.
1022, next crossbeam section assembling: next crossbeam sections is carried out before the assembly unit; Adopt earlier said slide device with said rectangle buoyancy aid two along the translation laterally of its cross central line; And in the said rectangle buoyancy aid two translation processes laterally; Being accomplished the right side beam end position of crossbeam 3 this moment assembly unit observes; The right side beam-ends of accomplishing crossbeam 3 when assembly unit moves to said rectangle buoyancy aid one left side and itself and spacing between said rectangle buoyancy aid one longitudinal centre line when being 0.5m~D/2, stops mobile said rectangle buoyancy aid two; Afterwards, on said rectangle buoyancy aid one, the next crossbeam sections of the said crossbeam 3 of multiple tracks is carried out assembly unit respectively, and the assembling method of the next crossbeam sections of the said crossbeam 3 of multiple tracks is all identical; Wherein, D is the transverse width of said rectangle buoyancy aid.
When the next crossbeam sections of arbitrary road crossbeam 3 is carried out assembly unit; Carry out continuous assembly unit from left to right on the right side beam-ends of assembly unit completion crossbeam 3 at this moment; Till the inside wall flush of the right side beam-ends of institute's assembly unit crossbeam 3 and said rectangle buoyancy aid one, then accomplish the assembly unit process of next crossbeam sections.In the present embodiment, the slide device that is adopted in the step 1022 is a jack.
1023, repeating step 1022 repeatedly is until whole assembly unit processes of accomplishing the said crossbeam 3 of multiple tracks.
1024, the crossbeam right part is fixed: according to the installation position of crossbeam 3 right parts on said rectangle buoyancy aid one that designs in advance; The right part of the multiple tracks crossbeam 3 of assembly unit completion in the step 1023 all is fixed on the said rectangle buoyancy aid one, then accomplishes the assembly unit and the fixation procedure of multiple tracks crossbeam 3.
1025, longeron two assembly units and fixing: on said rectangle buoyancy aid one; Said longeron two is carried out assembly unit; And according to the installation position of said longeron two of design in advance, longeron that assembly unit is accomplished two is fastening to be fixed in the step 1024 top, right part of the multiple tracks crossbeam 3 that assembly unit accomplishes and fix.
In the present embodiment; Said rectangle buoyancy aid once is assemblied to form by all identical little buoyancy tank 5 of a plurality of structures and size from front to back; The transverse width D of said rectangle buoyancy aid is identical with the length of said little buoyancy tank 5; And the longitudinal length L=N * d of said rectangle buoyancy aid, wherein N is the quantity that is assemblied to form the little buoyancy tank 5 of said rectangle buoyancy aid, d is the width of little buoyancy tank 5.
Actual when said floating support platform is carried out assembling construction, the spacing between two said rectangle buoyancy aids is 32m ± 8m, and the longitudinal length of said rectangle buoyancy aid is 50m ± 10m.Spacing between the adjacent twice crossbeam 3 is 3m ± 0.5m.Said longeron 2 is assemblied to form by many Pin plane frame with crossbeam 3, and the height of longeron 2 and crossbeam 3 is 4m ± 1m.Simultaneously, be easy construction, said plane frame is assemblied to form by many universal rod bodies.
In the present embodiment; The length of said cube steel box section is that 9m, width are that 2.7m and its highly are 1.65m; The quantity of forming the said cube steel box section of said rectangle buoyancy aid is 19, and the said cube steel box section total quantity that then is assemblied to form said floating support platform is 38.Thereby the transverse width of said rectangle buoyancy aid is 9m, and the longitudinal length of said rectangle buoyancy aid is 19 * 2.7m=51.7m, and the spacing between two said rectangle buoyancy aids is 32m.The quantity of said crossbeam 3 is that 6 roads and its lateral length are 41m; 6 road crossbeams 3 are respectively crossbeam one, crossbeam two, crossbeam three, crossbeam four, crossbeam five and crossbeam six from front to back; And the spacing between crossbeam one and the crossbeam two is 3.17m, and the spacing between crossbeam two and the crossbeam three is 3.12m, and the spacing between crossbeam three and the crossbeam four is 3.1m; Spacing between crossbeam four and the crossbeam five is 3.12m, and the spacing between crossbeam five and the crossbeam six is 3.17m.Said longeron 2 is identical with the longitudinal length of said rectangle buoyancy aid; Distance between the leading section of the front side wall of said crossbeam one and said rectangle buoyancy aid is 12.1m, and the distance between the rearward end of the rear wall of said crossbeam six and said rectangle buoyancy aid is 11.6m.Distance between the front side wall of said crossbeam one to the rear wall of said crossbeam six is 27.6m.
In the present embodiment; In the rectangle buoyancy aid two translation processes laterally described in the step 1022; The right side beam-ends of accomplishing crossbeam 3 when assembly unit moves to said rectangle buoyancy aid one left side and itself and spacing between said rectangle buoyancy aid one longitudinal centre line when being 0.5m~1.5m, stops mobile said rectangle buoyancy aid two.
Step 2, the displacement of floating support platform: adopt slide device with the floating support platform that is assemblied to form in the step 1, move to the construction location place of pier in the said water.
Step 3, floating support platform are temporary fixed: adopt a plurality of said temporary fastening devices that said floating support platform is temporarily fixed at the construction location place.
Step 4, steel casing are transferred: utilize the Lift-on/Lift-off System of being installed on the said floating support platform that is temporarily fixed at the construction location place in the step 3 and the said floating support platform; And according to conventional steel casing mounting method the steel casing of construction drill stake usefulness is transferred, and fix transferring the steel casing that puts in place.
Step 5, drilled pile construction: utilize in the said floating support platform that is temporarily fixed at the construction location place in the step 3 and the step 4 and transfer the steel casing that puts in place; And, all drilled piles of said underwater support table bottom are constructed according to the job practices of drilled pile in the conventional water; Said drilled pile construction is removed a plurality of said temporary fastening devices, and is adopted said slide device that said floating support platform is removed at the construction location place of pier in said water after accomplishing.
Step 6, underwater support table and the construction of top pier stud:, on the bored piles top of accomplishing of in step 5, having constructed said underwater support table is constructed earlier according to the job practices of conventional levels cushion cap; Again according to the job practices of conventional underwater support table top pier stud, the said pier stud of construction on the said underwater support table of accomplishing of constructing.
In the present embodiment, the slide device described in the step 2 neutralization procedure five is jack.During practice of construction, adopt two identical floating drilling platforms of structure simultaneously pier in two water to be constructed.The quantity of set said temporary fastening device is 10 on each floating drilling platform.Wherein, the temporary fastening device that come-up is laid is a Bower Anchor, the heavy 15T of single Bower Anchor; The temporary fastening device that lay in downstream is a stern anchor, the heavy 15t of single stern anchor; The temporary fastening device that floating drilling platform sidepiece is laid is a side anchor, the heavy 10T of side anchor.The rope 1 of Bower Anchor is selected the wire rope of diameter 24mm for use, the rope 1 long 472m of each Bower Anchor.
The above; It only is the preferred embodiment of the utility model; Be not that the utility model is done any restriction; Everyly any simple modification that above embodiment did, change and equivalent structure are changed, all still belong in the protection domain of the utility model technical scheme according to the utility model technical spirit.

Claims (10)

1. a bridge construction is used the floating drilling platform; It is characterized in that: the Lift-on/Lift-off System that comprises the floating support platform, said floating support platform is carried out temporary fixed a plurality of temporary fastening devices and is laid on the said floating support platform and the construction drill stake is lifted with the steel casing; A plurality of said temporary fastening devices all are laid in the side all around of said floating support platform, and all are fastenedly connected through anchor cable (1) between each temporary fastening device and the said floating support platform; Said floating support platform comprises horizontal buoyancy aid, be fixedly mounted on the horizontal support framework on the said horizontal buoyancy aid and the horizontal steel plate (4) on said horizontal support framework of mating formation; Said horizontal buoyancy aid is assemblied to form by a plurality of buoyancy tanks (5); Be fastenedly connected through a plurality of connectors between adjacent two said buoyancy tanks (5); Said buoyancy tank (5) is the cube steel box section, and the length of said cube steel box section is that 8m~12m, width are that 1m~3m and its highly are 1m~2m; Have on the said horizontal steel plate (4) supply that said steel casing transfers transfer through hole (6), corresponding leaving supplies the passage of transferring that said steel casing transfers on said horizontal support framework and the said horizontal buoyancy aid, the said passage of transferring is laid in and transfers under the through hole (6).
2. use the floating drilling platform according to the described a kind of bridge construction of claim 1; It is characterized in that: said horizontal buoyancy aid comprises the rectangle buoyancy aid that two structures and size are all identical; Two said rectangle buoyancy aids are parallel laying, and two said rectangle buoyancy aids are that axis of symmetry carries out symmetry and lays with the longitudinal centre line of said floating support platform; Said horizontal support framework comprises that twice are the crossbeam (3) that the longeron of parallel laying (2) and multiple tracks are parallel laying; The structure of the said longeron of twice (2) and longitudinal length said longeron (2) all identical with size is not less than the longitudinal length of said rectangle buoyancy aid, and all identical and lateral length said crossbeam (3) of the structure of the said crossbeam of multiple tracks (3) and size is not less than the spacing between the said longeron of twice (2); The said longeron of twice (2) be laid in respectively two said rectangle buoyancy aids directly over, and said longeron (2) lays along longitudinal center's axis of said rectangle buoyancy aid, the said longeron of twice (2) is fastenedly connected through multiple tracks crossbeam (3) and is one.
3. use the floating drilling platform according to the described a kind of bridge construction of claim 2; It is characterized in that: the left and right end portions of said crossbeam (3) is fixedly mounted on respectively on two said rectangle buoyancy aids, and the said longeron of twice (2) is fixedly mounted on the top, the left and right sides of the said crossbeam of multiple tracks (3) respectively.
4. use the floating drilling platform according to claim 2 or 3 described a kind of bridge constructions; It is characterized in that: said rectangle buoyancy aid is assemblied to form by a plurality of structures buoyancy tank all identical with size (5) from front to back successively; The transverse width D of said rectangle buoyancy aid is identical with the length of said buoyancy tank (5); And the longitudinal length L=N * d of said rectangle buoyancy aid, wherein N is the quantity of the buoyancy tank (5) that is assemblied to form said rectangle buoyancy aid, d is the width of buoyancy tank (5).
5. use the floating drilling platform according to the described a kind of bridge construction of claim 3; It is characterized in that: said Lift-on/Lift-off System comprises portal frame and is installed in the lifting appliance (12) on the said portal frame; Said portal frame comprises girder (8-1) and two supporting legs (8-2) that are installed in below, girder (8-1) left and right sides respectively; Two said supporting legs (8-2) bottom is equipped with and drives the walking mechanism that said portal frame moves forward and backward; The vertical walking rails that supplies said walking mechanism walking all is installed on the said longeron of twice (2), and said vertical walking rails is laid along longitudinal center's axis of longeron (2).
6. use the floating drilling platform according to the described a kind of bridge construction of claim 4, it is characterized in that: the spacing between two said rectangle buoyancy aids is 32m ± 8m, and the longitudinal length of said rectangle buoyancy aid is 50m ± 10m; The quantity of said crossbeam (3) is 6 roads, and the said crossbeam of multiple tracks (3) is even laying, and the spacing between the adjacent twice crossbeam (3) is 3m ± 0.5m.
7. use the floating drilling platform according to claim 2 or 3 described a kind of bridge constructions; It is characterized in that: the said quantity of transferring through hole (6) is one or more; Said horizontal steel plate (4) is laid on the said crossbeam of multiple tracks (3) between the said longeron of twice (2); Said horizontal steel plate (4) middle part is provided with and is used for laying the through hole of transferring of transferring through hole (6) and lays the district; The said through hole of transferring is laid the district and is between two said rectangle buoyancy aids, and transfers through hole (6) and all be laid between the adjacent twice crossbeam (3).
8. use the floating drilling platform according to claim 1,2 or 3 described a kind of bridge constructions, it is characterized in that: said temporary fastening device is earth anchor (7) or casts anchor.
9. use the floating drilling platform according to the described a kind of bridge construction of claim 6, it is characterized in that: said longeron (2) and crossbeam (3) are assemblied to form by many Pin plane frame, and the height of longeron (2) and crossbeam (3) is 4m ± 1m; Said plane frame is assemblied to form by many universal rod bodies.
10. use the floating drilling platform according to claim 1,2 or 3 described a kind of bridge constructions; It is characterized in that: a plurality of said temporary fastening devices comprise the temporary fastening device one that is laid in the upper reaches, said floating support platform river course of living in one side, be laid in the temporary fastening device two of downstream, said floating support platform river course of living in one side and be laid in the temporary fastening device three of the said floating support platform left and right sides respectively, and the quantity of said temporary fastening device one, temporary fastening device two and temporary fastening device three is a plurality of.
CN2011202051315U 2011-06-17 2011-06-17 Floating drilling platform for bridge construction Expired - Lifetime CN202124824U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011202051315U CN202124824U (en) 2011-06-17 2011-06-17 Floating drilling platform for bridge construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011202051315U CN202124824U (en) 2011-06-17 2011-06-17 Floating drilling platform for bridge construction

Publications (1)

Publication Number Publication Date
CN202124824U true CN202124824U (en) 2012-01-25

Family

ID=45487896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011202051315U Expired - Lifetime CN202124824U (en) 2011-06-17 2011-06-17 Floating drilling platform for bridge construction

Country Status (1)

Country Link
CN (1) CN202124824U (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102303691A (en) * 2011-06-17 2012-01-04 中铁一局集团有限公司 Floating drilling platform and construction technology used for bridge pier construction in water
CN104032718A (en) * 2014-06-10 2014-09-10 中国人民解放军理工大学 Light self-floating manual-erecting elevated structure
CN104032740A (en) * 2014-06-25 2014-09-10 中国电建集团华东勘测设计研究院有限公司 Device utilizing buoyancy to reduce steel pipe pile hoisting weight
CN105088964A (en) * 2015-09-09 2015-11-25 中国铁建大桥工程局集团有限公司 Movable construction platform for bridge foundation building
CN105083486A (en) * 2015-08-03 2015-11-25 上海海洋大学 Temporary fixing device and construction method thereof
CN106812067A (en) * 2017-01-11 2017-06-09 温州万里市政工程有限公司 A kind of removable operation platform for bridge construction
CN110701388A (en) * 2019-11-04 2020-01-17 惠生(南通)重工有限公司 Temporary fixing device for oil pipe of offshore oil production platform
JP2020507516A (en) * 2017-02-02 2020-03-12 フレキシブル フローティング システム アー エス Frame structure for floating equipment
CN112663647A (en) * 2020-12-18 2021-04-16 中铁大桥局集团有限公司 Modular platform for open caisson soil borrowing construction and using method thereof
CN116289959A (en) * 2022-12-13 2023-06-23 保利长大工程有限公司 Floating lifting and lowering method and device for water pile foundation construction

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102303691A (en) * 2011-06-17 2012-01-04 中铁一局集团有限公司 Floating drilling platform and construction technology used for bridge pier construction in water
CN104032718A (en) * 2014-06-10 2014-09-10 中国人民解放军理工大学 Light self-floating manual-erecting elevated structure
CN104032740A (en) * 2014-06-25 2014-09-10 中国电建集团华东勘测设计研究院有限公司 Device utilizing buoyancy to reduce steel pipe pile hoisting weight
CN104032740B (en) * 2014-06-25 2016-05-04 中国电建集团华东勘测设计研究院有限公司 A kind of device that utilizes buoyancy to alleviate steel-pipe pile hoisting weight
CN105083486A (en) * 2015-08-03 2015-11-25 上海海洋大学 Temporary fixing device and construction method thereof
CN105088964A (en) * 2015-09-09 2015-11-25 中国铁建大桥工程局集团有限公司 Movable construction platform for bridge foundation building
CN106812067A (en) * 2017-01-11 2017-06-09 温州万里市政工程有限公司 A kind of removable operation platform for bridge construction
CN106812067B (en) * 2017-01-11 2019-02-01 温州万里市政工程有限公司 A kind of removable operation platform for bridge construction
JP2020507516A (en) * 2017-02-02 2020-03-12 フレキシブル フローティング システム アー エス Frame structure for floating equipment
JP7128211B2 (en) 2017-02-02 2022-08-30 フレキシブル フローティング システム アー エス Frame structure for floating equipment
CN110701388A (en) * 2019-11-04 2020-01-17 惠生(南通)重工有限公司 Temporary fixing device for oil pipe of offshore oil production platform
CN112663647A (en) * 2020-12-18 2021-04-16 中铁大桥局集团有限公司 Modular platform for open caisson soil borrowing construction and using method thereof
CN116289959A (en) * 2022-12-13 2023-06-23 保利长大工程有限公司 Floating lifting and lowering method and device for water pile foundation construction

Similar Documents

Publication Publication Date Title
CN202124824U (en) Floating drilling platform for bridge construction
CN102303691B (en) Floating drilling platform and construction technology used for bridge pier construction in water
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN103485288B (en) A kind ofly pass through both wired double-deck jacking culvert construction technology
WO2020248596A1 (en) Protection structure for preventing ground heave caused by tunnel grouting reinforcement and grouting method
CN108252329B (en) Assembly type comprehensive pipe gallery for bearing force of enclosure structure and construction method thereof
CN105544575B (en) A kind of bottom concrete construction method under water of use steel truss reinforcement
CN107700366B (en) Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method
CN105201012A (en) Casting cable trench after assembly of L-shaped precast concrete and construction method of casting cable trench
KR20160080028A (en) Multipurpose artifical island
CN103855650A (en) Special construction method by utilizing electricity jacking pipe
CN111576454A (en) Combined protective structure for side slope retaining wall and steel pipe pile and construction method thereof
CN111424716B (en) Oblique-pulling anchorage type suspension tunnel structure with relay extension of artificial island
CN108118690A (en) A kind of integral hoisting formula coercion underground continuous wall structure and its prefabricated and construction method
CN107489106B (en) A kind of rocky bed subaqueous bearing platform construction method
CN107620316B (en) Rock riverbed large-volume deepwater foundation construction method
CN104594379B (en) Between rail yard interior lines, be incubated culvert pipe system and burial and construction method
CN113622366B (en) Caisson wharf and construction method thereof
RU2310721C1 (en) Protection device to protect self-elevating floating drilling installation for exploratory well drilling in ice conditions and method for protection device construction
CN205116220U (en) Pour cable pit after assembly of L type precast concrete spare
CN105244835A (en) L-shaped concrete cable trench prefabricated component and production technology
CN210827529U (en) Single-pile reinforced foundation of offshore wind power anti-icing structure
KR101703441B1 (en) Cassion manufacturing method of bottom-up, pre-cast and a base plate type using floating dock, system, floating dock and cassion using thereof
CN216515566U (en) Tension type single-point mooring combined anchorage structure based on spiral anchor
CN207714358U (en) A kind of transmission line of electricity composite structure assembled cushion cap anchor rod foundation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20120125

CX01 Expiry of patent term