CN202117301U - Movable operating platform - Google Patents

Movable operating platform Download PDF

Info

Publication number
CN202117301U
CN202117301U CN2011201886350U CN201120188635U CN202117301U CN 202117301 U CN202117301 U CN 202117301U CN 2011201886350 U CN2011201886350 U CN 2011201886350U CN 201120188635 U CN201120188635 U CN 201120188635U CN 202117301 U CN202117301 U CN 202117301U
Authority
CN
China
Prior art keywords
steel pipe
vertical
platform
vertical part
movable operating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011201886350U
Other languages
Chinese (zh)
Inventor
吴瑞卿
赖泽荣
黄亮忠
凌文轩
方耿珲
方世宏
张元斌
苏毅明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou No1 Construction Engineering Co Ltd
Guangzhou Construction Co Ltd
Original Assignee
Guangzhou No1 Construction Engineering Co Ltd
Guangzhou Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou No1 Construction Engineering Co Ltd, Guangzhou Construction Co Ltd filed Critical Guangzhou No1 Construction Engineering Co Ltd
Priority to CN2011201886350U priority Critical patent/CN202117301U/en
Application granted granted Critical
Publication of CN202117301U publication Critical patent/CN202117301U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model relates to a movable operating platform which is hung on a cross purlin of a steel mould plate system. The movable operating platform comprises a platform part, and more than two hook hanging parts which are vertically arranged on the side edge of the platform part and parallel and leveled with each other, wherein each of the hook hanging parts can be hung on the cross purlin between two adjacent vertical ribs of the steel mould plate system; a pre-formed hole is formed on the edge, which is not equipped with the hook hanging part, of the platform part; a vertical steel pipe is inserted into the pre-formed hole; the movable operating platform further comprises a transversal steel pipe which is fixed with the vertical steel pipe in a crossed manner; the transversal steel pipe and the vertical steel pipe make up a steel pipe guard bar. The movable operating platform can be hung on the cross purlin below a split bolt, which needs to be installed, of the steel mould plate system according to practical demands, and taken down conveniently if the same is not in need, thus ensuring construction safety of operators.

Description

Mobilizable operating desk
Technical field
The utility model relates to the building machinery field, relates in particular to move mobilizable operating desk.
Background technology
When the concrete wall body construction uses the large steel moulding plate system; Usually this template height is that a story height adds 200mm; And because the height that can construct of people is generally limited to about 2m so difficulty very often such as the Screw arbor with nut at both-ends installation on large steel moulding plate top, and have safety problem.
For this reason, a mobilizable operating desk need be provided, make operating personnel's construction of in this operating desk, being correlated with.
Summary of the invention
The purpose of the utility model is to provide a kind of mobilizable operating desk, and it can be adapted to be installed in the existing large steel moulding plate system, and operation, safety simple, that make things convenient for the staff are installed.
For achieving the above object, the utility model has adopted following technical scheme:
A kind of mobilizable operating desk is used to hang over the purlin beam of steel form system, it is characterized in that: comprise platform part, and the lateral edges that is fixed in said platform part and concordant each other plural hook portion vertically are set; Each said hook portion all can hang on the purlin beam between adjacent two perpendicular ribs of said steel form system; The edge that hook portion is not set of said platform part is provided with preformed hole, in said preformed hole, is inserted with vertical steel pipe; Also be provided with horizontal steel pipe, said horizontal steel pipe and said vertical steel pipe composition steel pipe guardrail with said vertical steel pipe cross fixation.
Said hook portion comprise first vertical part, second vertical part and be fixedly connected on said first vertical part and said second vertical part between transverse part; Said second vertical part is fixed on the said platform part; Said first vertical part is used to hang over said horizontal purlin beam; The width of said first vertical part is less than or equal to the spacing of adjacent two perpendicular ribs, and the distance between said first vertical part and said second vertical part is greater than or equal to the thickness of said horizontal purlin beam.
The beneficial effect of the utility model is: this mobilizable operating desk can hang on the horizontal purlin beam of large steel moulding plate system according to the practice of construction needs, as long as take off when not using, installation and removal are all very convenient, and are time saving and energy saving.And this operating desk is provided with the steel pipe guardrail, can guarantee the safety that the workman constructs.
Description of drawings
Fig. 1 is the installation site sketch map of mobilizable operating desk of the utility model.
Fig. 2 is the lateral view of mobilizable operating desk of an embodiment of the utility model.
The specific embodiment
To combine accompanying drawing below, introduce the preferred implementation of the utility model in detail.
Like Fig. 1, shown in Figure 2; In existing large steel moulding plate system; Be provided with vertical perpendicular rib 20 and the horizontal purlin beam 10 vertical with perpendicular rib at the back side of template 30, perpendicular rib 20 is pasting template 30, and horizontal purlin beam 10 is fixed on the perpendicular rib 20; Just formed a space at adjacent two perpendicular ribs and horizontal purlin beam like this, the utility model utilizes this characteristic to construct just.
As shown in Figure 2; A kind of mobilizable operating desk 40 is used to hang over the horizontal purlin beam of steel form system, and it comprises platform part 42; And a lateral edges of platform part 42 is fixed in setting vertically and two concordant each other hook portion (shows a hook portion 41 among this figure; The description of hereinafter is an example with it, and the structure of another hook portion is identical with it), certainly in other embodiment of the utility model; Plural hook portion can be set according to the size of practice of construction needs and platform part, and all hook portions all are in a lateral edges of platform part 42 and concordant each other.On platform part, can lay plank or checkered steel plate, make things convenient for the workman on stand in, to carry out constructing operation, can prevent that also the workman from falling down on platform part.
Above-mentioned each hook portion 41 all can hang on the horizontal purlin beam 10 between adjacent two perpendicular ribs 20 of steel form system (being the indicated position of mark A among Fig. 1).Particularly; Hook portion 41 comprise first vertical part 411, second vertical part 413 and be fixedly connected on first vertical part 411 and second vertical part 413 between transverse part 412; Wherein, second vertical part 413 is fixed on the platform part 42, and first vertical part 411 is used to hang over horizontal purlin beam 10; The width of first vertical part 411 is less than or equal to the spacing of adjacent two perpendicular ribs, and the distance between first vertical part 411 and second vertical part 413 is greater than or equal to the thickness of horizontal purlin beam 10.
In addition, the edge that hook portion is not set of platform part 42 is provided with a plurality of preformed holes 421, in preformed hole 421, is inserted with vertical steel pipe 43; Also be provided with and the horizontal steel pipe of vertical steel pipe cross fixation (circle on the vertical steel pipe be used for schematic transverse steel pipe), many horizontal steel pipe is formed the steel pipe guardrail with vertical steel pipe, thereby prevents that workman or article from falling from platform, guarantees construction safety.In the practice of construction, generally after this mobilizable platform is hung up properly, the steel pipe guardrail is installed again.
What more than disclose only is the preferred embodiment of the utility model, can not limit the scope of the utility model certainly with this.To any conversion and the replacement of the utility model technical scheme, all in the protection domain of the utility model.

Claims (2)

1. mobilizable operating desk is used to hang over the horizontal purlin beam of steel form system, it is characterized in that: comprise platform part, and the lateral edges that is fixed in said platform part and concordant each other plural hook portion vertically are set; Each said hook portion all can hang over the horizontal purlin beam between adjacent two perpendicular ribs of said steel form system
On; The edge that hook portion is not set of said platform part is provided with preformed hole, in said preformed hole, is inserted with vertical steel pipe; Also be provided with horizontal steel pipe, said horizontal steel pipe and said vertical steel pipe composition steel pipe guardrail with said vertical steel pipe cross fixation.
2. mobilizable operating desk as claimed in claim 1; It is characterized in that: said hook portion comprise first vertical part, second vertical part and be fixedly connected on said first vertical part and said second vertical part between transverse part; Said second vertical part is fixed on the said platform part; Said first vertical part is used to hang over said horizontal purlin beam; The width of said first vertical part is less than or equal to the spacing of adjacent two perpendicular ribs, and the distance between said first vertical part and said second vertical part is greater than or equal to the thickness of said horizontal purlin beam.
CN2011201886350U 2011-06-07 2011-06-07 Movable operating platform Expired - Lifetime CN202117301U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201886350U CN202117301U (en) 2011-06-07 2011-06-07 Movable operating platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201886350U CN202117301U (en) 2011-06-07 2011-06-07 Movable operating platform

Publications (1)

Publication Number Publication Date
CN202117301U true CN202117301U (en) 2012-01-18

Family

ID=45458375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201886350U Expired - Lifetime CN202117301U (en) 2011-06-07 2011-06-07 Movable operating platform

Country Status (1)

Country Link
CN (1) CN202117301U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104960630A (en) * 2015-06-29 2015-10-07 上海外高桥造船有限公司 Broadside equipment platform
CN105035285A (en) * 2015-08-27 2015-11-11 江苏扬子鑫福造船有限公司 L-shaped hanging scaffold
CN109098425A (en) * 2018-09-21 2018-12-28 中国五冶集团有限公司 A kind of girder steel station connection structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104960630A (en) * 2015-06-29 2015-10-07 上海外高桥造船有限公司 Broadside equipment platform
CN105035285A (en) * 2015-08-27 2015-11-11 江苏扬子鑫福造船有限公司 L-shaped hanging scaffold
CN109098425A (en) * 2018-09-21 2018-12-28 中国五冶集团有限公司 A kind of girder steel station connection structure
CN109098425B (en) * 2018-09-21 2023-10-13 中国五冶集团有限公司 Steel beam operation table connection structure

Similar Documents

Publication Publication Date Title
CN101787796B (en) Suspended formwork bracing system for steel structure concrete floor slab construction
CN203531344U (en) Tool type scaffold
CN204589793U (en) A kind of bridge pad
CN202117301U (en) Movable operating platform
CN201627362U (en) Suspended formwork support device for construction of steel structured concrete slabs
CN204299145U (en) For the operating platform that external climbing tower crane support frame is installed
CN205653902U (en) Floor entrance to a cave block structure
CN203452397U (en) Safe protection rack
CN202866262U (en) Bearing hanging rack for civil construction
CN206972259U (en) A kind of movable guard rail of hydraulic pressure inverted arch trestle
CN202899600U (en) Construction site limb quick installation and removal protecting device
CN204663021U (en) Detachablely face limit early warning movable rail device
CN204663020U (en) Assembling temporary protection railing
CN202440833U (en) Structure for supporting construction elevator base on top plate of basement
CN202055535U (en) Steel storage rack in construction site
CN202209055U (en) Protection rail for construction site
CN203961300U (en) Tool-type passage
CN203320935U (en) Rear-embedded wall connecting device of scaffold
CN203440913U (en) Supporting structure for reinforced concrete corridor construction
CN203392657U (en) Machine maintenance platform
CN203924897U (en) Enclosing structure for building site
CN205935740U (en) Wooden structural floor slab equipment suspended ceiling system of existing building
CN204899228U (en) Pump line fixing device for construction
CN205224571U (en) Anchor of builder's jack
CN204919565U (en) Steel platform of use is demolishd in shoring of trench

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20120118

CX01 Expiry of patent term