CN202073077U - Assembly type template steel pipe bracing frame for water inlet transition section - Google Patents

Assembly type template steel pipe bracing frame for water inlet transition section Download PDF

Info

Publication number
CN202073077U
CN202073077U CN2011200899936U CN201120089993U CN202073077U CN 202073077 U CN202073077 U CN 202073077U CN 2011200899936 U CN2011200899936 U CN 2011200899936U CN 201120089993 U CN201120089993 U CN 201120089993U CN 202073077 U CN202073077 U CN 202073077U
Authority
CN
China
Prior art keywords
steel pipe
bracing frame
water inlet
pipe bracing
transition section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011200899936U
Other languages
Chinese (zh)
Inventor
张建花
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group No 5 Engineering Co Ltd
Original Assignee
China Gezhouba Group No 5 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 5 Engineering Co Ltd filed Critical China Gezhouba Group No 5 Engineering Co Ltd
Priority to CN2011200899936U priority Critical patent/CN202073077U/en
Application granted granted Critical
Publication of CN202073077U publication Critical patent/CN202073077U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses an assembly type template steel pipe bracing frame for a water inlet transition section, wherein a plurality of steel pipe bracing frames are connected with each other via adjusting screw rods. The assembly type template steel pipe bracing frame for a water inlet transition section adopts the above structure and the structural dimension thereof is determined according to the actual dimension of the water inlet. All the parts of the bracing frame are connected with each other via cross clips, so that the integrity and the stability of the steel pipe bracing frame is effectively ensured and the dismounting work in the later phase is also convenient in operation. Meanwhile, the gap between the bracing frame and a wooden template can be adjusted by the adjusting screw rods. A template standing mould can be installed in blocks according to the actual condition.

Description

But water inlet transition section assembled template steel pipe bracing frame
Technical field
The water inlet formwork erection that the utility model relates in the construction of power station supports the field, but particularly a kind of water inlet transition section assembled template steel pipe bracing frame.
Background technology
At water conservancy and hydropower concrete construction building field, the concrete work bodily form complexity of power plant project, big, the pouring quality requirement height of construction intensity have only high-quality all kinds of construction formwork to satisfy.The transition section template has only by meticulous Selection and Design, making, installation as power station water inlet concreting privileged sites template, could obtain good result of use, satisfies the needs of engineering.And that the formwork erection technology plays a part especially is very important, and the appropriate design of formwork-support is particularly important.
The variation of template supporting form, supporting form commonly used at present is that full wood supports, also have steel wood to support to mix and use, ubiquitous problem is that waste material, dismounting difficulty are big, the formwork erection time is long, disposable input cost height, and can not guarantee concrete pouring quality.
Summary of the invention
But technical problem to be solved in the utility model provides a kind of water inlet transition section assembled template steel pipe bracing frame, can have enough to meet the need use repeatedly, installs and removes convenient and swiftly, and can save timber.
For solving the problems of the technologies described above, the technical scheme that the utility model adopted is: but a kind of water inlet transition section assembled template steel pipe bracing frame connects by adjusting screw(rod) between a plurality of steel pipe bracing frames;
" L " shape bracing frame of described steel pipe bracing frame for being welded by steel pipe and reinforcing bar;
Described a plurality of steel pipe bracing frame size is identical.
Also be provided with many in the space that a plurality of steel pipe bracing frames surround and reinforce steel pipe.
Described reinforcing steel pipe adopts the cross card connection.
Described steel pipe bracing frame is four.
But a kind of water inlet transition section assembled template steel pipe bracing frame that the utility model provides, by adopting above-mentioned structure, physical dimension size of the present utility model can be determined according to the real size of water inlet, the cross card connection is adopted in the connection of each several part, effectively guarantee the globality and the stability of steel pipe bracing frame, also made things convenient for the dismounting work in later stage.Gap between the utility model and the wooden form can be regulated by adjusting screw(rod), and the template formwork erection can be installed according to the actual conditions piecemeal.The utlity model has following beneficial effect:
1) steel pipe bracing frame size is identical, can have enough to meet the need use repeatedly;
2) save cost, reduce disposable input;
3) saving of labor, save time, the material saving, easy construction, safe and reliable;
4) can freely assemble, flexible operation, of a tightly knit structure, firm;
5) improve workmanship, improve work efficiency, improve working environment;
6) save timber.
Description of drawings
The utility model is described in further detail below in conjunction with drawings and Examples.
Fig. 1 is an overall structure schematic diagram of the present utility model.
Fig. 2 adopts the utility model to carry out the structural representation of pouring construction.
Fig. 3 is the structural representation of steel pipe bracing frame in the utility model.
The specific embodiment
In Fig. 1, Fig. 2, but a kind of water inlet transition section assembled template steel pipe bracing frame connects by adjusting screw(rod) 3 between a plurality of steel pipe bracing frames 1.
" L " shape bracing frame of described steel pipe bracing frame 1 for being welded by steel pipe 4 and reinforcing bar 5.
Described steel pipe bracing frame 1 size is identical.
Also be provided with many in the space that a plurality of steel pipe bracing frames 1 surround and reinforce steel pipe 2.
Described reinforcing steel pipe 2 adopts the cross card connection.
The scheme of optimizing is that described steel pipe bracing frame 1 is four, connects into a Pin square frame by adjusting screw(rod) 3.
The utility model is formed a Pin square frame by steel pipe bracing frame 1 and adjusting screw(rod) 3, takes all factors into consideration the load of bracing frame, reinforces with reinforcing steel pipe 2 in inside of frame, reinforces steel pipe 2 and fixes by the cross card connection.The size of one Pin square frame is determined according to the real size of water inlet, but the size of steel pipe bracing frame 1 must be identical, helps using repeatedly and making things convenient for installation of framework like this, and has realized the standardization of frame manufacture; But the profile of framework can change as required, can be polygon promptly, is beneficial to economical with materials to a greater extent.
In Fig. 3, steel pipe bracing frame 1 is made of by welding steel pipe 4 and reinforcing bar 5, in this example, " L " shape that each steel pipe bracing frame 1 is welded, every Pin framework divides four groups, and every group of structure size is identical, assembly unit arbitrarily as required, connect assembly unit by adjusting screw(rod) 3 between every group of steel pipe support 1, adjusting screw(rod) 3 mainly plays a part to connect and regulating error; Transition section adopts up and down longitudinally and connects steel pipe 6 with each Pin framework assembling, has guaranteed the globality and the stability of bracing frame, and the connector of assembling adopts the cross card.
The utility model must install and fix at bottom wooden form 7 and carry out after finishing when mounted.At first discharging connection steel pipe 6 on wooden form 7 horizontal planes longitudinally, the steel pipe bracing frame 1 of then assembly unit being regulated the whole Pin that finishes is placed on and connects on the steel pipe 6, adopt the cross card connection to fix, the connection steel pipe 6 of steel pipe bracing frame 1 both sides is installed after the connection of horizontal direction finishes, and the top that connects steel pipe bracing frame 1 at last connects steel pipe 6.Steel pipe bracing frame 1 form of structure and the size dimension of water inlet transition section all are identical, and the size of wooden form 7 and shape change according to the change of shape of transition section.Steel pipe bracing frame 1 assembling method is identical, and it is also comparatively convenient that the later stage removes, and the steel pipe bracing frame can have enough to meet the need use repeatedly, should be widely promoted in concrete construction template formwork erection support technology field.
The utility model has flexible operation through practical test, and is safe and reliable, improves work efficiency, saves the advantage of cost.

Claims (4)

1. but a water inlet transition section assembled template steel pipe bracing frame is characterized in that: connect by adjusting screw(rod) (3) between a plurality of steel pipe bracing frames (1);
" L " shape bracing frame of described steel pipe bracing frame (1) for being welded by steel pipe (4) and reinforcing bar (5);
Described a plurality of steel pipe bracing frames (1) size is identical.
2. but a kind of water inlet transition section assembled template steel pipe bracing frame according to claim 1 is characterized in that: also be provided with many in the space that a plurality of steel pipe bracing frames (1) surround and reinforce steel pipe (2).
3. but a kind of water inlet transition section assembled template steel pipe bracing frame according to claim 2 is characterized in that: described reinforcing steel pipe (2) adopts the cross card connection.
4. but a kind of water inlet transition section assembled template steel pipe bracing frame according to claim 1, it is characterized in that: described steel pipe bracing frame (1) is four.
CN2011200899936U 2011-03-31 2011-03-31 Assembly type template steel pipe bracing frame for water inlet transition section Expired - Fee Related CN202073077U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200899936U CN202073077U (en) 2011-03-31 2011-03-31 Assembly type template steel pipe bracing frame for water inlet transition section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200899936U CN202073077U (en) 2011-03-31 2011-03-31 Assembly type template steel pipe bracing frame for water inlet transition section

Publications (1)

Publication Number Publication Date
CN202073077U true CN202073077U (en) 2011-12-14

Family

ID=45111180

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200899936U Expired - Fee Related CN202073077U (en) 2011-03-31 2011-03-31 Assembly type template steel pipe bracing frame for water inlet transition section

Country Status (1)

Country Link
CN (1) CN202073077U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105648991A (en) * 2015-12-30 2016-06-08 中国水电建设集团十五工程局有限公司 Method for constructing transition sections of through-flow unit channel of hydropower station

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105648991A (en) * 2015-12-30 2016-06-08 中国水电建设集团十五工程局有限公司 Method for constructing transition sections of through-flow unit channel of hydropower station
CN105648991B (en) * 2015-12-30 2017-08-08 中国水电建设集团十五工程局有限公司 The construction method of power station bulb-type tubular hydro set flow passage gradual change section

Similar Documents

Publication Publication Date Title
CN202007535U (en) Supporting reinforcing structure
CN201991226U (en) Flange template support structure
CN103195200A (en) Steel bar truss buckle hanging type floor support plate
CN202073077U (en) Assembly type template steel pipe bracing frame for water inlet transition section
CN203200982U (en) Steel bar truss buckling hanging type floor support plate
CN204687050U (en) A kind of mould of precast concrete rectangular beam
CN204662482U (en) A kind of set shaped steel formwork for the board-like concrete component of thick large circle
CN104060757B (en) Precast concrete frame supports shear wall wallboard
CN103882840B (en) A kind of surge shaft Cast-in-place concrete assembling falsework and mounting method thereof
CN202850041U (en) Reinforcing steel support for colligation of large-scale raft plate and ribbed beam base reinforcing steel
CN207863463U (en) A kind of fast disassembly type corbel for shuttering supporting
CN204781435U (en) Novel shear wall structure
CN205063026U (en) Basement frame
CN203569482U (en) Wholly-assembled type high-pier pier body rebar operation platform
CN209670061U (en) A kind of construction assembly with connection structure
CN202990383U (en) Channel steel guide rail controlling terrace elevation
CN202925883U (en) Large size wooden formwork surrounding purlin device
CN203795448U (en) Building foundation
CN203626212U (en) Pier stud construction operation platform quick to disassemble and assemble
CN208122294U (en) Strenthening member device
CN201420400Y (en) Supporting structure of towering reticulated shell structure
CN203361631U (en) Variable-diameter fabricated sliding mode platform of sliding mode system
CN204940999U (en) A kind of circular coal yard steel-mixed combining structure coal-stopping wall
CN204238549U (en) A kind of formwork support structure of steel reinforced concrete
CN220599154U (en) Reinforcing steel bar integrated template and reinforcing steel bar inner support thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111214

Termination date: 20160331

CF01 Termination of patent right due to non-payment of annual fee