CN202031033U - Hang fill construction hanging basket for four-lane broad width continuous beam of high-speed railway - Google Patents

Hang fill construction hanging basket for four-lane broad width continuous beam of high-speed railway Download PDF

Info

Publication number
CN202031033U
CN202031033U CN2011201127961U CN201120112796U CN202031033U CN 202031033 U CN202031033 U CN 202031033U CN 2011201127961 U CN2011201127961 U CN 2011201127961U CN 201120112796 U CN201120112796 U CN 201120112796U CN 202031033 U CN202031033 U CN 202031033U
Authority
CN
China
Prior art keywords
guiding
hanging basket
sliding
speed railway
main couple
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011201127961U
Other languages
Chinese (zh)
Inventor
王祥军
谢亮
张敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Wuxin Steel Formwork Co Ltd
Original Assignee
China Railway Wuxin Steel Formwork Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Wuxin Steel Formwork Co Ltd filed Critical China Railway Wuxin Steel Formwork Co Ltd
Priority to CN2011201127961U priority Critical patent/CN202031033U/en
Application granted granted Critical
Publication of CN202031033U publication Critical patent/CN202031033U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a hang fill construction hanging basket for a four-lane broad width continuous beam of a high-speed railway, wherein primary trusses are integrally connected through a front upper cross beam connected at the front upper end, a bridging connected at the front upper inclined plane, a vertical truss connected at the middle part and a transverse bar connected at the rear upper inclined plane, and are symmetrically arranged at the front end and the rear end of the continuous beam in the pouring direction; at least three frames of primary trusses are arranged, and each frame is provided with a corresponding running mechanism; a stiffening truss is arranged at the lower part of a bottom basket; the hang fill construction hanging basket further comprises a plurality of groups of middle guiding sliding beam devices and edge guiding sliding beam devices, and an operating platform is arranged at the rear parts of the edge guiding sliding beam devices. The hang fill construction hanging basket has good stability, and can perform synchronous pouring construction symmetrically and integrally in two directions, thereby efficiently solving the pouring problem of width single-box double-chamber or multiple-box multiple-chamber broad continuous beam for high-speed railway construction.

Description

The outstanding construction Hanging Basket of irritating of high-speed railway four live width width of cloth continuous beams
Technical field
The present invention relates to the outstanding construction equipment of irritating of a kind of bridge continuous beam, especially relate to the outstanding construction Hanging Basket of irritating of high-speed railway four live width width of cloth continuous beams.
Background technology
Hanging Basket is that the railway and the highway of large span adopts the cantilever pouring mode to finish a kind of visual plant that the beam body construction is used.When adopting Hanging Basket to build Longspan Bridge, be not subjected to such environmental effects such as bridge pier height, river be dark, directly extend construction to striding the footpath direction piecemeal from building the bridge pier part.This pouring construction process has not only been simplified the difficulty of construction of Longspan Bridge, and can save duration and the expense of setting up full framing etc. greatly, thereby adopts in the bridge design construction of being everlasting.
But the outstanding filling construction of existing continuous beam Hanging Basket only is suitable for the case beam casting and constructing of single box single chamber form of structure.For example, Chinese invention patent application CN1916289A discloses a kind of Diamond-Shape Form Traveler, main couple adopts diamond structure, between two Pin main couples, pass through to connect upper frame, underframe, front baffle and afterframe connect into integral body, the main couple bottom is provided with two running mechanisms, also comprise suspension gear and anchor device, it is that the interior continuous bridge of 13m is the case beam cast problem of single box single chamber form of structure that this Hanging Basket can better solve single width face width degree common in the present domestic high speed railway construction, but for present needs according to line construction, design has the four-track line continuous girder bridge in the high speed railway construction, its bridge fabric width degree reaches nearly 23m, its girder construction is the two chambers of single case or many casees multicell structure, the general requirements symmetric double is to the synchronous casting and constructing of integral body, and it just can not well solve the cast problem of this class continuous beam.
Summary of the invention
The technical problem to be solved in the present invention is, a kind of good stability is provided, and can carry out symmetric double to the outstanding construction Hanging Basket of irritating of the high-speed railway four live width width of cloth continuous beams of the synchronous casting and constructing of integral body.
For addressing the above problem, the technical solution used in the present invention is, the outstanding construction Hanging Basket of irritating of high-speed railway four live width width of cloth continuous beams, comprise that spacing is arranged in the main couple that roughly assumes diamond in shape on continuous beam face top, be arranged at the running mechanism of main couple bottom, be positioned at the sliding beam of guiding of main couple front end bottom, being positioned at the end basket system of the sliding beam of guiding bottom and being connected template system on the sliding beam of guiding, the preceding top rail that connects by preceding upper end between the main couple, the bridging that preceding ramp connects, the transverse truss that the middle part connects, the transverse bar that the rear portion ramp connects forms integral body, is symmetrically placed in two ends of described continuous beam front and back cast direction; Main couple is arranged has 3 Pin at least, and every Pin bottom is provided with corresponding running mechanism; The end in the key portion be provided with the reinforcement truss; Also comprise sliding boom device of guiding and the sliding boom device of limit guiding in some groups, the sliding boom device of guiding rear portion, limit also is provided with operating platform.
As a preferred embodiment of the present invention, the sliding boom device of middle guiding is mainly by the suspension bracket and the balladeur train that are anchored at described continuous beam hollow upper wall, and the sliding beam of guiding is formed; Described suspension bracket is stretched into by suspension bracket base plate support in the sliding beam of described guiding rear end under the construction state, before the Hanging Basket zero load, get except that suspension bracket under the shifting state, the rear end is stretched into described balladeur train and is supported by the balladeur train roller, front end by be articulated in described before the connection that suspends of the suspension rod of top rail upper limb; The sliding boom device of middle guiding is distributed in continuous beam cavity medium position for two groups side by side.Guiding sliding boom device in limit is mainly by the suspension bracket and the balladeur train that are anchored at bottom, the described continuous beam edge of a wing, and the sliding beam of guiding is formed; The sliding beam of guiding rear end is stretched into described support and is supported by roller, front end by be articulated in described before the connection that suspends of the suspension rod of top rail upper limb; Guiding sliding boom device in limit is distributed in continuous beam edge of a wing lower middle position for two groups side by side.
Because sliding beam of middle guiding and the sliding beam of limit guiding are by being anchored at the suspension bracket and the carriage supports of beam hollow upper wall and flange of beam bottom, sliding beam of middle guiding and the sliding beam of limit guiding roll on roller when moving, and can significantly reduce moving resistance; For increase the sliding boom device of guiding be subjected to force intensity and traveling the time stationarity, two groups of sliding boom devices of middle guiding are distributed in beam cavity medium position side by side and guiding sliding boom device in limit is distributed in the flange of beam lower middle position for two groups side by side.
As the present invention further optimization scheme, operating platform is mainly formed to sliding beam and the platform body that is connected before and after the sliding beam of the guiding rear portion 2 suspension rod and is connected this suspension rod bottom by two of the sliding boom device of limit guiding. Can make full use of the sliding beam of limit guiding like this and need not increase under the situation of other facility and just can conveniently set up movably operating platform.
As a kind of improvement of the present invention, running mechanism mainly by the front wheel frame that is anchored at segmented or all-in-one-piece guide rail on the continuous beam, is installed in support node bottom before the described main couple and support cylinder, be installed in support node behind the described main couple the rear roller frame with regulate oil cylinder and two ends and be connected before described guide rail and the main couple traveling oil cylinder of support node respectively and form.The guide rail of running mechanism is formed by worker's steel spelling arranged side by side; Front wheel frame and preceding support node lower hinge, be provided with in the turning rolls with described guide rail on the roller of the corresponding rolling in plane; Be provided with roller in the rear roller frame with the inboard corresponding rolling in described guide rail top flange.In the front and rear rolling wheel frame roller is set, can alleviates wheel load like this, disperse load, reduce the traveling resistance.
Support cylinder, adjusting oil cylinder and traveling oil cylinder are respectively by HYDRAULIC CONTROL SYSTEM, but both synchronous interaction also can be controlled each cylinder action separately by the stop valve on each branch's oil circuit of folding; Support cylinder and regulate oil cylinder and have mechanical self-locking device, the quality accident when personal safety accident that might take place when ensureing oil cylinder and fluid concrete because of unexpected pressure release.
Further, end basket system front end hangs by the many groups suspension rod that is articulated in described front beam upper limb and connects; Basket system rear end, the end by being articulated in the vertical truss upper limb in described main couple middle part suspension rod and be articulated in beam on the suspension rod suspension be connected.
The transverse bar that the vertical truss that the bridging that the preceding top rail that connects by preceding upper end between the main couple of the present invention, preceding ramp connect, middle part connect, rear portion ramp connect forms integral body, can make main couple stressed evenly, even bridge deck width is bigger, whole main truss framework still has good resistance to overturning; Main couple is symmetrically placed in two ends of described continuous beam front and back cast direction, can pour into a mould along the two ends of continuous beam simultaneously when the cast continuous beam, with the two ends stress balance of guarantee continuous beam; Main couple is arranged has 3 Pin, the concentrated load that can alleviate main couple at least; Every Pin main couple bottom is provided with corresponding running mechanism, helps ensureing enough traveling thrust; The end in the key portion the reinforcement truss is set, can solve effectively that the wide cut bridge is outstanding irritates end basket crossbeam in the construction Hanging Basket reach process to hang span excessive and cause the problem of the excessive inefficacy of end basket system amount of deflection; Sliding boom device of guiding and the sliding boom device of limit guiding in some groups are set, and are to connect needs for satisfying template; The sliding boom device of limit guiding rear portion setting operation platform can be that back anchor anchor pole removes and installs and the repair of beam body provides safety guarantee.
Description of drawings
Fig. 1 irritates the structural representation of construction Hanging Basket embodiment for high-speed railway four live width width of cloth continuous beams of the present invention are outstanding.
Fig. 2 irritates construction Hanging Basket beam type a vertical view for high-speed railway four live width width of cloth continuous beams of the present invention are outstanding.
Fig. 3 irritates construction Hanging Basket beam type b vertical view for high-speed railway four live width width of cloth continuous beams of the present invention are outstanding.
Fig. 4 irritates the A-A cross section structure schematic diagram of construction Hanging Basket beam type a for high-speed railway four live width width of cloth continuous beams of the present invention are outstanding.
Fig. 5 irritates the B-B cross section structure schematic diagram of construction Hanging Basket beam type a for high-speed railway four live width width of cloth continuous beams of the present invention are outstanding.
Fig. 6 irritates the A-A cross section structure schematic diagram of construction Hanging Basket beam type b for high-speed railway four live width width of cloth continuous beams of the present invention are outstanding.
Fig. 7 irritates the B-B cross section structure schematic diagram of construction Hanging Basket beam type b for high-speed railway four live width width of cloth continuous beams of the present invention are outstanding.
Fig. 8 irritates construction Hanging Basket beam running gear front wheel frame section structure for amplifying schematic diagram for high-speed railway four live width width of cloth continuous beams of the present invention are outstanding.
Fig. 9 irritates construction Hanging Basket beam running gear rear roller frame section structure for amplifying schematic diagram for high-speed railway four live width width of cloth continuous beams of the present invention are outstanding.
The specific embodiment
The invention will be further described below in conjunction with drawings and Examples.
Embodiment 1(cast beam type a)
With reference to accompanying drawing 1, Fig. 2, present embodiment comprises main couple 5, and main couple 5 is the diamondwise structure roughly, and two pipe nipple points connect with vertical beam, and one water chestnut limit level places above the continuous beam 30; The transverse bar 7 that the vertical truss 4 that the bridging 6 that the preceding top rail 1 that connects by preceding upper end between the main couple 5, preceding ramp connect, middle part connect, rear portion ramp connect forms whole, is symmetrically placed in two ends of described continuous beam 30 front and back cast direction; Described main couple 5 is arranged 4 Pin, and every Pin is provided with corresponding running mechanism.
With reference to accompanying drawing 1, Fig. 4 and Fig. 5.The sliding boom device of guiding comprises the sliding boom device of the middle guiding that is arranged on continuous beam 30 section middle section positions and is arranged on the sliding boom device of limit guiding below the edge of a wing, continuous beam both sides; The sliding boom device of middle guiding is mainly by support 16 that is anchored at continuous beam 30 section hollow upper walls and the roller 13 that is positioned at these support 16 bottoms, and the sliding beam 12 of guiding is formed, the sliding beam of guiding 12 rear ends are stretched in the described support 16 and by roller 13 and are supported under the Hanging Basket walking states, connections that suspend of the suspension rod 21 of front end by top rail 1 upper limb before being articulated in, the per two groups of cavity medium positions that are distributed in continuous beam 30 sections side by side of middle guiding cunning boom device; Guiding sliding boom device in limit is mainly by support 16 that is anchored at bottom, continuous beam 30 edge of a wing and the roller 13 that is positioned at these support 16 bottoms, and the sliding beam 12 of guiding is formed, the sliding beam of guiding 12 rear ends are stretched in the support 16 and by roller 13 and are supported under the Hanging Basket walking states, connections that suspend of the suspension rod 21 of front end by top rail 1 upper limb before being articulated in, limit guiding cunning boom device is distributed in continuous beam 30 section edge of a wing lower middle position for per two groups side by side; The front portion is a suspension bracket, is used for the cradle construction carrying; The rear portion is a balladeur train, the sliding beam of support guiding when being used for suspended basket.
Operating platform mainly is made up of the sliding beam 12 of two guiding of the sliding boom device of limit guiding and the platform body 15 that is connected 4 groups of suspension rods 35 of 2 of 12 front and back, the sliding beam rear portion of guiding and is connected this suspension rod bottom
With reference to accompanying drawing 1, Fig. 8, Fig. 9.Running mechanism mainly by be anchored at segmented or all-in-one-piece guide rail 22 on the continuous beam 30, be installed in preceding support node 2 bottoms of described main couple 5 front wheel frame 8 and support cylinder 3, be installed in described main couple 5 back support nodes 36 rear roller frame 18 with regulate oil cylinder 17 and two ends and be connected before described guide rail 22 and the main couple traveling oil cylinder 9 of support node 2 respectively and form.
The guide rail 22 of running mechanism is formed by worker's steel spelling arranged side by side; Both sides of support node 2 before 8 fens two groups of symmetries of front wheel frame are installed on, and 37 vertical hinged by shipping and reselling on another market are provided with the roller 23 of the corresponding rolling in plane on former and later two and the guide rail 22 in every group of turning rolls; 18 fens two groups of symmetries of rear roller frame are installed on the support node 36 of back, are provided with 4 rollers 24 with the corresponding rolling in inboard of described guide rail 22 top flanges in every group.
Support cylinder, adjusting oil cylinder and traveling oil cylinder are respectively by HYDRAULIC CONTROL SYSTEM; Both but synchronous interaction also can be controlled each cylinder action separately by the stop valve on each branch's oil circuit of folding, and for guaranteeing safety, support cylinder and adjusting oil cylinder all have mechanical self-locking device.
End basket system 10 is positioned at the bottom of main couple 5, and end basket system 10 front ends connect end basket front beam 31, and the rear end connects rear cross beam 32; Six groups of suspension rods 20 of front beam 1 upper limb of end basket system 10 front ends by being articulated in main couple 5 hang and connect; Basket system 10 rear ends, the end hang by the suspension rod 19 that is articulated in the vertical truss 4 two ends upper limbs in main couple 5 middle parts and connect; Middle part, basket system 10 rear ends, the end connects an end of 2 Chain blocks 33 with respect to the hollow position of continuous beam 30 sections, the other end of Chain block is connected with the support 16 that is anchored at continuous beam 30 respective hollow position upper walls, and the both sides, middle part are connected on the cavity lower wall of continuous beam 30 by two groups of anchor poles; In addition, in the bottom of end basket system 10 front and back crossbeams 31,32, also vertically be connected with a reinforcement truss 11 respectively.
Embodiment two (cast beam type b)
With reference to accompanying drawing 1, Fig. 3, Fig. 6, Fig. 7.Compare with embodiment one, difference is a cavities in the cancellation of continuous beam body, is single case double-chamber structure, main couple 5 is set to three Pin, the two groups of sliding beam of guiding mechanisms 16 that cancellation Chain block 33 and top are provided with, the Hanging Basket transverse width is constant, and other structures are identical with embodiment one.
During work, continuous beam 30 adopts bi-directional symmetrical to build, wherein, load is delivered to the preceding top rail 1 of main couple 5 by end basket system 10 by suspension rod 20,21, then pass to the preceding support node 2 of main couple 5, main couple 5 is transformed into load on the continuous beam 30 by the rear portion anchor pole again, and promptly preceding support node 2 is subjected to compressive load, and back support node is subjected to the load of drawing upwards; Working load when support node 2 is born Hanging Basket work by support cylinder 3 before the main couple 5.Middle part, basket system 10 rear ends, the end and the sliding boom device of guiding rear portion are anchored on the continuous beam 30, and Hanging Basket bears the cast-in-place beam body section load of half approximately.
After the construction of beam body section finished, pine removed the rear portion anchor pole of Hanging Basket on continuous beam 30, the primer fluid pressing system, and the support cylinder 3 that is positioned at main couple 5 preceding support nodes 2 shrinks, and support node is supported by front wheel frame 8 before the main couple 5; 9 actions of traveling oil cylinder, main couple 5 drive end basket system 10, sliding beam 12 and template system 38 by suspension rod and together move forward under 9 effects of traveling oil cylinder; Template system 38 holder being hung on the sliding beam 12 of guiding of the sliding boom device of guiding, and the sliding beam 12 of guiding can longitudinal sliding motion balladeur train 13 in, and it is steadily mobile forward to slide beam 12 support template systems 38 by suspension rod traction guiding when main couple 5 move forward by hydraulic oil cylinder driving; One side formwork is by two sliding beam 12 supports of guiding, and the template center of gravity is between two sliding beams 12 of guiding, to guarantee the stability in the template moving process; Internal mold 14 does not together move forward with main truss, waits to build the sections reinforcing bar binding and reserves the operating space reducing to can be when Hanging Basket reach is born a heavy burden, treat that the sections reinforcing bar binding finishes after, internal mold 14 puts in place along sliding beam 12 slippages of guiding guiding.
Be the preferred embodiments of the present invention only below, be not limited to the present invention, for a person skilled in the art, the present invention can have various changes and variation.In a word, within the spirit and principles in the present invention all, any modification of being done, be equal to replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (8)

1. high-speed railway four live width width of cloth continuous beams hang and irritate the construction Hanging Basket, comprise that spacing is arranged in the main couple that roughly assumes diamond in shape on continuous beam face top, be arranged at the running mechanism of main couple bottom, be positioned at the sliding beam of guiding of main couple front end bottom, being positioned at the end basket system of the sliding beam of guiding bottom and being connected template system on the sliding beam of guiding, it is characterized in that: the preceding top rail that connects by preceding upper end between the described main couple, the bridging that preceding ramp connects, the transverse truss that the middle part connects, the transverse bar that the rear portion ramp connects forms integral body, is symmetrically placed in two ends of described continuous beam front and back cast direction; Described main couple is arranged has 3 Pin at least, and every Pin bottom is provided with corresponding running mechanism; The described end in the key portion be provided with the reinforcement truss; Also comprise sliding boom device of guiding and the sliding boom device of limit guiding in some groups, the sliding boom device of described limit guiding rear portion also is provided with operating platform.
2. the outstanding filling construction of high-speed railway four live width width of cloth continuous beams according to claim 1 Hanging Basket is characterized in that: the sliding boom device of guiding mainly is made up of suspension bracket that is anchored at described continuous beam hollow upper wall and balladeur train and the sliding beam that leads in described; Described suspension bracket is stretched into by suspension bracket base plate support in the sliding beam of described guiding rear end under the construction state, before the Hanging Basket zero load, get except that suspension bracket under the shifting state, the rear end is stretched into described balladeur train and is supported by the balladeur train roller, front end by be articulated in described before the connection that suspends of the suspension rod of top rail upper limb; The sliding boom device of guiding is distributed in continuous beam cavity medium position for two groups side by side in described.
3. the outstanding construction Hanging Basket of irritating of high-speed railway four live width width of cloth continuous beams according to claim 1 is characterized in that: the described limit sliding boom device of guiding is mainly by the suspension bracket and the balladeur train that are anchored at bottom, the described continuous beam edge of a wing, and the sliding beam of guiding is formed; Described suspension bracket is stretched into and by suspension bracket base plate support in the sliding beam of described guiding rear end under the construction state, before the Hanging Basket zero load, get except that suspension bracket under the shifting state, the rear end is stretched into described balladeur train and is supported by the balladeur train roller, front end all the time by be articulated in described before the connection that suspends of the suspension rod of top rail upper limb; The described limit sliding boom device of guiding is distributed in continuous beam edge of a wing lower middle position for two groups side by side.
4. the outstanding construction Hanging Basket of irritating of high-speed railway four live width width of cloth continuous beams according to claim 1, it is characterized in that: described operating platform, mainly form by the sliding beam of two guiding of the sliding boom device of limit guiding and the platform body that is connected before and after the sliding beam of the guiding rear portion 2 suspension rod and is connected this suspension rod bottom.
5. the outstanding construction Hanging Basket of irritating of high-speed railway four live width width of cloth continuous beams according to claim 1 is characterized in that: described running mechanism mainly by the front wheel frame that is anchored at segmented or all-in-one-piece guide rail on the continuous beam, is installed in support node bottom before the described main couple and support cylinder, be installed in support node behind the described main couple the rear roller frame with regulate oil cylinder and two ends and be connected before described guide rail and the main couple traveling oil cylinder of support node respectively and form.
6. the outstanding construction Hanging Basket of irritating of high-speed railway four live width width of cloth continuous beams according to claim 5, it is characterized in that: the guide rail of described running mechanism is formed by worker's steel spelling arranged side by side; Described front wheel frame and preceding support node lower hinge, in described turning rolls, be provided with described guide rail on the roller of the corresponding rolling in plane; Be provided with roller in the described rear roller frame with the inboard corresponding rolling in described guide rail top flange.
7. according to claim 5 or the outstanding construction Hanging Basket of irritating of 6 described high-speed railway four live width width of cloth continuous beams, it is characterized in that: described support cylinder, adjusting oil cylinder and traveling oil cylinder are respectively by HYDRAULIC CONTROL SYSTEM; Both but synchronous interaction also can be controlled each cylinder action separately by the stop valve on each branch's oil circuit of folding; Described support cylinder and adjusting oil cylinder have the mechanical self-latching structure.
8. the outstanding construction Hanging Basket of irritating of high-speed railway four live width width of cloth continuous beams according to claim 1 is characterized in that: basket system front end of the described end hangs by the many groups suspension rod that is articulated in described front beam upper limb and connects; Basket system rear end, the end by being articulated in the vertical truss upper limb in described main couple middle part suspension rod and be articulated in beam on the suspension rod suspension be connected.
CN2011201127961U 2011-04-18 2011-04-18 Hang fill construction hanging basket for four-lane broad width continuous beam of high-speed railway Expired - Fee Related CN202031033U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201127961U CN202031033U (en) 2011-04-18 2011-04-18 Hang fill construction hanging basket for four-lane broad width continuous beam of high-speed railway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201127961U CN202031033U (en) 2011-04-18 2011-04-18 Hang fill construction hanging basket for four-lane broad width continuous beam of high-speed railway

Publications (1)

Publication Number Publication Date
CN202031033U true CN202031033U (en) 2011-11-09

Family

ID=44893335

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201127961U Expired - Fee Related CN202031033U (en) 2011-04-18 2011-04-18 Hang fill construction hanging basket for four-lane broad width continuous beam of high-speed railway

Country Status (1)

Country Link
CN (1) CN202031033U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102220740A (en) * 2011-04-13 2011-10-19 湖南中铁五新钢模有限责任公司 Cantilever-concreting construction hanging basket for four-lane and wide-width continuous beam of high-speed rail
CN103952982A (en) * 2014-05-13 2014-07-30 中交二航局第三工程有限公司 Preloading device and preloading method for hanging basket anchorage pull rod-type jack of bridge box girder

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102220740A (en) * 2011-04-13 2011-10-19 湖南中铁五新钢模有限责任公司 Cantilever-concreting construction hanging basket for four-lane and wide-width continuous beam of high-speed rail
CN102220740B (en) * 2011-04-13 2012-09-26 湖南中铁五新钢模有限责任公司 Cantilever-concreting construction hanging basket for four-lane and wide-width continuous beam of high-speed rail
CN103952982A (en) * 2014-05-13 2014-07-30 中交二航局第三工程有限公司 Preloading device and preloading method for hanging basket anchorage pull rod-type jack of bridge box girder
CN103952982B (en) * 2014-05-13 2015-12-02 中交二航局第三工程有限公司 Bridge box and beam Hanging Basket anchorage rod-pulling type jack prepressing device and preloading method

Similar Documents

Publication Publication Date Title
CN104631343B (en) From traveling rhombus keying cradle in truss type structure and suspended basket and construction method
CN102094392B (en) Lower supported hanging basket in bridge construction and application thereof
CN101324056B (en) Upside suspension type moving die carrier
CN201003145Y (en) Upward and self-walking type mobile die carrier
CN206368328U (en) A kind of box beam four moves integrally die carrier structure across one-piece casting
CN101581073B (en) Downlink movable mould frame and walking method thereof
KR101259031B1 (en) Form traveller having transversal frame, and launching method for the same
CN102220740B (en) Cantilever-concreting construction hanging basket for four-lane and wide-width continuous beam of high-speed rail
CN201169749Y (en) Simple-mounted pin connection triangle hanging basket
CN103074854A (en) Rear supporting point triangular bracket hanging basket and bridge construction method using same
CN207608836U (en) A kind of Successive interference cancellation cantilever pouring construction Diamond-Shape Form Traveler
CN101173503A (en) Three-point walking single cable face cable-dragging suspension basket
CN102395731B (en) Overhead form traveller and method
CN102660925B (en) Moveable formwork for variable-width curved bridge
CN103526697B (en) Self-propelled movable formwork for construction of double-rectangle water conservancy aqueduct
CN201261866Y (en) Down moving type movable mould frame
CN109267490B (en) Long guide beam type movable formwork and construction method thereof
CN102418534B (en) Split movable mould frame device for tunnel compartment wall, and construction method for split movable mould frame
CN108103945A (en) A kind of whole landing mould bases of cast-in-situ box girder
CN102286931B (en) Deck moving support system (MSS) bridge fabrication machine specially for construction of double-T-shaped bridge
CN105970822B (en) A kind of 50m double width upstroke movable framework and its corresponding beam-making construction method
CN203049471U (en) Rear fulcrum triangular bracket hanging basket
CN202031033U (en) Hang fill construction hanging basket for four-lane broad width continuous beam of high-speed railway
CN201574360U (en) Truss type hanging basket
CN201972099U (en) Through type hanging basket in bridge construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111109

Termination date: 20140418