CN202030994U - Rail base structure capable of resisting horizontal force and vertical force - Google Patents

Rail base structure capable of resisting horizontal force and vertical force Download PDF

Info

Publication number
CN202030994U
CN202030994U CN2011201326113U CN201120132611U CN202030994U CN 202030994 U CN202030994 U CN 202030994U CN 2011201326113 U CN2011201326113 U CN 2011201326113U CN 201120132611 U CN201120132611 U CN 201120132611U CN 202030994 U CN202030994 U CN 202030994U
Authority
CN
China
Prior art keywords
pile
foundation
rail beam
sheet pile
rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011201326113U
Other languages
Chinese (zh)
Inventor
沈迪州
卢永昌
孙艺
汤子扬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC FHDI Engineering Co Ltd
Original Assignee
CCCC FHDI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC FHDI Engineering Co Ltd filed Critical CCCC FHDI Engineering Co Ltd
Priority to CN2011201326113U priority Critical patent/CN202030994U/en
Application granted granted Critical
Publication of CN202030994U publication Critical patent/CN202030994U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

A rail base structure (21) capable of resisting horizontal force and vertical force consists of a pile foundation (8), a rail beam (9) and a rail beam foundation (10), wherein a foundation expanding structure (22) is arranged at the bottom of the rail beam (9). The rail beam (9) is supported on the pile foundation (8) and the rail beam foundation (10). The pile foundation (8) can adopt a composite structure of a steel pipe pile, a steel sheet pile, the steel pipe pile and a sheet pile, a cast-in-place pile structure, or an underground diaphragm wall structure, etc. The pile foundation (8) can be either continuously arranged or discontinuously arranged. The rail beam (9) adopts a concrete structure. Partial vertical load is transmitted to groundwork (5) by the rail beam (9) so as to decrease the vertical force of the pile foundation (8) and the buried depth of the pile foundation (8) and lower the engineering cost.

Description

A kind of track foundation structure of resisting horizontal force and vertical force
Technical field
The utility model relates to a kind of track foundation structure.
Background technology
Double sheet pile as a kind of material save, the construction equipment simpler structure, possess under the situations such as land execution conditions, concrete price comparison height application more and more widely.
Before sheet pile can adopt the structures such as combining structure, diaphragm wall of steel pipe pile, steel pipe pile and steel sheet pile.Back sheet pile can adopt structures such as the combining structure, castinplace pile, diaphragm wall of steel pipe pile, steel sheet pile, steel pipe pile and steel sheet pile.Back sheet pile can be arranged continuously, also can discontinuously arrange.
Double sheet pile structure is adopted in many container terminals, and on the sheet pile, back rail beam was arranged on the sheet pile of back, connects by pull bar between the sheet pile of front and back before preceding rail beam was arranged on, and this structure has superiority under applicable elements.This class formation, back sheet pile also can be called the track foundation structure.
On the function of load level power, the embedded depth of above-mentioned back sheet pile little and be far smaller than before the embedded depth of sheet pile.Under the situation of bearing track load behind the machine, the vertical load control often of the embedded depth of back sheet pile causes the embedded depth of back sheet pile bigger thus.
Under the situation relatively good at geological conditions, that back sheet pile vertical load is bigger, the back sheet pile of common double sheet pile structure is worth improving, can adopt the rail beam of expansion bottom surface and the combining structure of sheet pile, utilize the rail beam that enlarges the bottom surface that the part vertical load is delivered to ground, reduce the vertical force of back sheet pile, reduce the embedded depth of back sheet pile thus, reduce engineering cost.
For this reason, we propose a kind of track foundation structure of resisting horizontal force and vertical force at the back track structure of the container terminal of double sheet pile.
Summary of the invention
In order to utilize bearing capacity of foundation soil to improve the stress condition of the back sheet pile of double sheet pile, the embedded depth of sheet pile after reducing lowers engineering cost, and the utility model provides a kind of track foundation structure of resisting horizontal force and vertical force.
In order to achieve the above object, the technical solution used in the present invention is that the track foundation structure is made up of pile foundation, rail beam, rail bearer foundation, and the bottom of rail beam is provided with expansion foundation structure, and rail beam is supported on pile foundation and the rail bearer foundation.Realize reducing the embedded depth of pile foundation thus, lower engineering cost.
Adopt the track foundation structure of opposing horizontal force of the present invention and vertical force, can utilize the rail beam that enlarges the bottom surface that the part vertical load is delivered to ground, reduce the vertical force of pile foundation, reduce the embedded depth of pile foundation thus, reduce engineering cost.
The beneficial effects of the utility model have reduced the vertical force of pile foundation, reduce the embedded depth of pile foundation, reduce engineering cost.
Description of drawings
Below in conjunction with accompanying drawing the utility model is further specified.
Fig. 1 is double sheet-pile wharf structure typical section figure;
Fig. 2 is track foundation structure section figure (the pile foundation place is arranged);
Fig. 3 is track foundation structure section figure (no pile foundation place);
Fig. 4 is the Tiebar structure schematic diagram.
Among the figure: 1. double sheet-pile wharf structure, 2. preceding sheet pile structure, 3. back sheet pile structure, 4. Tiebar structure, 5. ground, 6. before sheet pile, 7. breastwork, 8. pile foundation, 9. rail beam, 10. rail bearer foundation, 11. fillers, 12. excavation lines, 13. harbour end face line, 14. harbour bottom surface lines, 15. waterlines, the 16. pull bar bodies of rod, 17. pull bar connects fastener, 18. pull bar articulated joints, 19. drag link end hook plates, 20. pull-rod nut, 21. track foundation structures, 22. enlarge foundation structure.
The specific embodiment
Fig. 1 represents double sheet-pile wharf structure typical section figure.Double sheet-pile wharf structure (1) is made up of preceding sheet pile structure (2), back sheet pile structure (3), Tiebar structure (4), ground (5), filler (11).Before sheet pile structure (2) form by preceding sheet pile (6), breastwork (7), preceding sheet pile (6) can adopt structures such as the combining structure, diaphragm wall of steel pipe pile, steel pipe pile and steel sheet pile, breastwork (7) can adopt cast-in-place concrete structure.Back sheet pile structure (3) also can be called track foundation structure (21), is made up of pile foundation (8), rail beam (9), rail bearer foundation (10), and the bottom of rail beam (9) is provided with and enlarges foundation structure (22).Rail beam (9) is supported on pile foundation (8) and the rail bearer foundation (10).Pile foundation (8) can adopt structures such as the combining structure, castinplace pile, diaphragm wall of steel pipe pile, steel sheet pile, steel pipe pile and steel sheet pile.Pile foundation (8) can be arranged continuously, also can discontinuously arrange.Rail beam (9) adopts concrete structure.Rail bearer foundation (10) adopts piece stone foundation structure, also can adopt rubble foundation structure.Tiebar structure (4) is connected to form integral body with preceding sheet pile structure (2) and back sheet pile structure (3).Tiebar structure (4) adopts steel work, specifically sees Fig. 4.Excavation line (12), harbour end face line (13), harbour bottom surface line (14), waterline (15) are as shown in the figure.
Fig. 2 represents track foundation structure section figure (the pile foundation place is arranged).Track foundation structure (21) is made up of pile foundation (8), rail beam (9), rail bearer foundation (10), and the bottom of rail beam (9) is provided with and enlarges foundation structure (22).Having pile foundation (8) to locate, rail beam (9) is supported on pile foundation (8) and the rail bearer foundation (10).
Fig. 3 represents track foundation structure section figure (no pile foundation place).Track foundation structure (21) is made up of pile foundation (8), rail beam (9), rail bearer foundation (10).The bottom of rail beam (9) is provided with and enlarges foundation structure (22).Locate in no pile foundation (8), rail beam (9) is supported on the rail bearer foundation (10).
Fig. 4 represents the Tiebar structure schematic diagram.Tiebar structure (4) is made up of the pull bar body of rod (16), pull bar connection fastener (17), pull bar articulated joint (18), drag link end hook plate (19), pull-rod nut (20), these form the assembly of pull bar, can adopt a plurality of component groups to synthesize a Tiebar structure (4) as required, perhaps suitably reduce some assemblies.Tiebar structure (4) adopts steel work, can be produced by specialized factory.

Claims (1)

1. track foundation structure (21) of resisting horizontal force and vertical force, form by pile foundation (8), rail beam (9), rail bearer foundation (10), it is characterized in that: the bottom of rail beam (9) is provided with and enlarges foundation structure (22), and rail beam (9) is supported on pile foundation (8) and the rail bearer foundation (10).
CN2011201326113U 2011-04-25 2011-04-25 Rail base structure capable of resisting horizontal force and vertical force Expired - Fee Related CN202030994U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201326113U CN202030994U (en) 2011-04-25 2011-04-25 Rail base structure capable of resisting horizontal force and vertical force

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201326113U CN202030994U (en) 2011-04-25 2011-04-25 Rail base structure capable of resisting horizontal force and vertical force

Publications (1)

Publication Number Publication Date
CN202030994U true CN202030994U (en) 2011-11-09

Family

ID=44893297

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201326113U Expired - Fee Related CN202030994U (en) 2011-04-25 2011-04-25 Rail base structure capable of resisting horizontal force and vertical force

Country Status (1)

Country Link
CN (1) CN202030994U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103882784A (en) * 2014-02-26 2014-06-25 苏州设计研究院股份有限公司 Pressure reduction and shock absorption structure between ballast bead and ground beam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103882784A (en) * 2014-02-26 2014-06-25 苏州设计研究院股份有限公司 Pressure reduction and shock absorption structure between ballast bead and ground beam

Similar Documents

Publication Publication Date Title
CN101775840B (en) Beam column node suitable for quadrate steel pipe column
CN204212145U (en) A kind of precast concrete combination sheet pile
CN201722776U (en) Beam column nodal point suitable for square steel pipe column
CN104695380B (en) The shore protection structure of a kind of plastic-steel sheet pile and concrete combination
CN111910678A (en) Novel foundation structure of offshore wind power and construction method thereof
CN207109795U (en) A kind of recyclable HC engineering methods steel diaphram wall
CN102359118B (en) Annular foundation of underground continuous wall and construction method thereof
CN104420477A (en) Photovoltaic support foundation structure applicable to tidal flat photovoltaic power station and construction method
CN201232194Y (en) Anti-deformation power transmission tower
CN202030994U (en) Rail base structure capable of resisting horizontal force and vertical force
CN204311434U (en) A kind of precast concrete combination sheet pile
CN203741782U (en) Multi-section face plate structure of high concrete faced rockfill dam
CN201502065U (en) Anchor rod joint excavation compound basis
CN103088831A (en) Overall assembly-type double-row steel pile foundation pit supporting structure
CN204000856U (en) The anti-side changeable ridigity pile of inner support grouting formula level base
CN202430742U (en) Precast slab assembly soil retaining wall
CN206385500U (en) One kind separation discharging type dock structure
CN205188982U (en) Removable system of strutting of rectangle work well
CN213805472U (en) Transmission line tower anchor rope screw pile-cushion cap foundation structure
CN204023489U (en) The compound bearing platform type sheet pile structure of a kind of pile foundation-flexible reinforcement bed course
CN2871849Y (en) Lane sharpening stand against side-pressure bottom drum
CN206512722U (en) A kind of enhanced Larsen steel plate pile supporting system
CN201883449U (en) Sea wall structure of compound pile
CN103966975A (en) File foundation-flexile reinforcement cushion layer composite bearing table type sheet-pile structure
CN101514546B (en) Upright breakwater with vibration-sunk thin-wall reinforced concrete cylinder foundation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111109

Termination date: 20200425