CN202022678U - Connecting device of crane jib and crane with same - Google Patents
Connecting device of crane jib and crane with same Download PDFInfo
- Publication number
- CN202022678U CN202022678U CN2010206966253U CN201020696625U CN202022678U CN 202022678 U CN202022678 U CN 202022678U CN 2010206966253 U CN2010206966253 U CN 2010206966253U CN 201020696625 U CN201020696625 U CN 201020696625U CN 202022678 U CN202022678 U CN 202022678U
- Authority
- CN
- China
- Prior art keywords
- drag
- line
- arm
- connecting device
- tie
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000009434 installation Methods 0.000 claims description 21
- 229910000831 Steel Inorganic materials 0.000 claims description 10
- 239000010959 steel Substances 0.000 claims description 10
- 230000008878 coupling Effects 0.000 description 6
- 238000010168 coupling process Methods 0.000 description 6
- 238000005859 coupling reaction Methods 0.000 description 6
- 230000002950 deficient Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Images
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model provides a connecting device of a crane jib and a crane with the same. The crane comprises a derrick, a jib and a pulling plate. The connecting device comprises a first inhaul cable and a second inhaul cable. One end of the first inhaul cable is connected with the pulling plate, and the other end of the first inhaul cable is connected with the jib. The pulling plate and the jib are connected through the second inhaul cable. The connecting device of the crane jib and the crane with the connecting device can satisfy the requirement for stability of the whole crane, simultaneously can improve the connecting length of the jib, and can prevent the jib from being damaged due to the overlarge deflection, thereby avoiding accidents.
Description
Technical field
The utility model relates to the crawler crane field, relates to a kind of connecting device of crane arm particularly and has a kind of hoisting crane of this connecting device.
Background technology
At present, in the crawler crane of prior art, when mast plays arm, in order to solve the excessive problem of arm self, usually adopt single drag-line (also claiming the waist rope), wherein the upper end of single drag-line is connected to the support of arm-tie by bearing pin, and the lower end is connected to arm by bearing pin.But the defective that exists in the prior art is that in order to satisfy the requirement of complete machine stability, the syndeton length of arm has been subjected to the restriction of arm self sag.
Yet along with the continuous increase of crawler crane design and making tonnage, the arm syndeton length is more and more longer.How to resolve when mast plays arm, amount of deflection is excessive is damaged with accidents caused problem because of self for arm, is crawler crane design-calculated difficult point always.
The utility model content
The technical problems to be solved in the utility model is to provide a kind of connecting device of crane arm and has a kind of hoisting crane of this connecting device, can be under the situation that satisfies the complete machine stability requirement, increase the syndeton length of arm, and can avoid being damaged with accidents caused problem because of arm self amount of deflection is excessive.
A kind of connecting device of crane arm is provided according to an aspect of the present utility model, described hoisting crane comprises mast, arm and arm-tie, described connecting device comprises first drag-line, one end of described first drag-line is connected to described arm-tie and the other end is connected to described arm, and described connecting device further comprises second drag-line that connects described arm-tie and described arm.
Further, on the described arm rope pulley was installed, an end of described second drag-line is connected to described arm-tie and the other end is walked around the described rope pulley of crossing and is connected to described mast.
Further, described arm-tie is installed with first installation bracket that corresponds respectively to described first drag-line and described second drag-line and have connecting bore, and is installed with second installation bracket that corresponds respectively to described first drag-line and described second drag-line and have connecting bore on described arm.
Further, the upper end of each in described first drag-line and described second drag-line is formed with upper end hole, pass each upper end hole in described first drag-line and described second drag-line by bearing pin and be connected in described first installation bracket on the described arm-tie corresponding one, the lower end of each in described first drag-line and described second drag-line is formed with down stomidium, connects by bearing pin each the lower end in described first drag-line and described second drag-line is connected in described second installation bracket of described arm corresponding one.
Further, described arm-tie is installed with first installation bracket with holes that corresponds respectively to described first drag-line and described second drag-line, and is installed with second installation bracket with holes corresponding to described first drag-line on described arm.
Further comprise the support that is arranged between described first drag-line or second drag-line and the described arm-tie.
Further comprise and be arranged on described first drag-line or second drag-line and described arm-tie or/and the support between the jib.
Further comprise the support that is arranged between described first drag-line or second drag-line and the described arm.
Further, described connecting device comprises with respect to two described first drag-lines that are symmetrically distributed with respect to the axis of length direction of described arm and/or two described second drag-lines being symmetrically distributed with respect to the axis with respect to length direction of described arm.
Further, described support is the rod like parts that two ends are formed with bracket holes respectively.
Further, described first drag-line and/or described second drag-line are steel ropes.
Provide a kind of hoisting crane according to another aspect of the present utility model, comprise above-mentioned connecting device.
According to the connecting device of crane arm of the present utility model, can under the situation that satisfies the complete machine stability requirement, increase the syndeton length of arm, and can avoid being damaged with accidents caused problem because of arm self amount of deflection is excessive.
Description of drawings
In order fully to disclose the utility model, make those skilled in the art can realize the utility model according to the record of specification sheets, the spy provides the following drawings, and in conjunction with the accompanying drawings the utility model is had been described in detail.But accompanying drawing and respective embodiments explanation only are for illustrative purposes, but not are used to limit the utility model.
Fig. 1 shows the scheme drawing that is installed in the two rope linkage couplings on the crawler crane boom.
Fig. 2 is the partial enlarged drawing at the C place among Fig. 1.
Fig. 3 be A among Fig. 1 to view, it shows the connection structure of second drag-line in two rope linkage couplings among Fig. 1.
Fig. 4 be B among Fig. 1 to view, it shows the connection structure of first drag-line in two rope linkage couplings among Fig. 1.
The specific embodiment
Specifically describe preferred embodiment of the present utility model with reference to the accompanying drawings.
With reference to accompanying drawing 1, show the two rope linkage couplings that are installed on the crawler crane boom, wherein, crawler crane comprises mast 50, arm 10, arm-tie 40.Wherein, the upper end of mast 50 is fixed in the upper end of arm-tie 40, and the free end of arm 10 is fixed in the lower end of arm-tie 40.Mast 50 passes through arm-tie 40 with arm 10 pull-ups.
Comprise two groups of drag-lines (being also referred to as first drag-line 30 and second drag-line 20) according to of the present utility model pair of rope linkage coupling, first drag-line 30 and second drag-line 20 can be steel rope (or steel rope drag-lines), also can be other can load-bearing the rope form parts.See also Fig. 3 and Fig. 4,, be installed with the installation bracket 42,43 of band connecting bore, and on arm 10, be installed with the installation bracket 31 of band connecting bore at the side of arm-tie 40 for drag-line being installed between arm-tie 40 and the arm 10.The lengthwise position of this installation bracket 42,43 on arm-tie 40 is corresponding to the position that second drag-line 30 and first drag-line 20 will be installed, and this installation bracket 31 position on arm 10 is corresponding to the position that first drag-line 20 will be installed.The position corresponding to second drag-line 20 will be installed on arm 10 was provided with rope pulley 21.In the utility model, there is no particular limitation for the shape of installation bracket 42,43,31 and structure, as long as provide the hole that drag-line can be installed for arm-tie 40 or arm 10.
Introduce first drag-line 30 earlier.The installation constitution of first drag-line 30 is illustrated in the accompanying drawing 3.With reference to accompanying drawing 3 as seen, first drag-line 30 comprises that 301,302, two steel rope drag-lines 301,302 of two steel rope drag-lines are symmetrically distributed with respect to the axis of its length direction.The top and bottom of drag-line 301 are formed with upper end hole 3012 and following stomidium 3013 respectively, and the top and bottom of drag-line 302 are formed with upper end hole (figure is mark not) and following stomidium (figure is mark not) respectively.Can be connected to arm-tie 40 by the upper end that bearing pin connects drag-line 301, for example, pass the upper end hole 3012 of drag-line 301 and the connecting bore on the installation bracket 43 on the arm-tie 40 by pin.Equally, the lower end that connects drag-line 301 by bearing pin is connected to arm 10.Similarly, can be by the way the top and bottom of drag-line 302 be connected to arm-tie 40 and arm 10 respectively.
When the length of drag-line 301,302 and the distance between arm-tie 40 and the arm 10 (for example do not match, the length of drag-line is less than the distance between arm-tie and the arm) time, utilize one or more supports to adjust the length of drag-line, promptly bring in the length that prolongs drag-line by support being connected one of drag-line, support can be arranged between jib 10 and the drag-line 301,302, perhaps also can be arranged between arm-tie 40 and the drag-line 301,302.Wherein, support is a rod like parts, and its two ends are formed with bracket holes respectively, can support is connected with drag-line or support is connected with arm-tie by the bearing pin connection mode.Shown in Figure 3, utilize two supports 32 to be connected the upper end of drag-line 301 to prolong the length of drag-line 301.
Introduce second drag-line 20 now.The installation constitution of second drag-line 20 is illustrated in the accompanying drawing 4.With reference to accompanying drawing 4 as seen, second drag-line 20 comprises that 201,202, two steel rope drag-lines of two steel rope drag-lines are symmetrically distributed with respect to the axis of its length direction.The upper end of steel rope drag-line 201 is formed with upper end hole 2012, and the upper end of steel rope drag-line 202 also is formed with upper end hole (figure is mark not).Can connect the carriage 42 (also promptly, being connected to arm-tie) that the upper end of drag-line 201,202 is connected to arm-tie 40 by bearing pin, for example, pass the upper end hole 2012 of drag-line 201 and the connecting bore on the installation bracket 42 on the arm-tie 40 by pin.The lower end of drag-line 201,202 is walked around and is fixed in being connected on the mast 50 behind the rope pulley 21 excessively on the arm 10, can certainly be connected on the miscellaneous part, for example turntable.Fig. 2 shows the lower end of being fixed in the concrete structure of crossing rope pulley 21 on the arm 10 and also showing drag-line 201,202 and passes the situation that this crosses rope pulley 21.
The utility model has solved problems of the prior art by above-mentioned structure, can increase the syndeton length of arm under the situation that satisfies the complete machine stability requirement, and has avoided the accident that is damaged and causes because of arm self amount of deflection is excessive.
Be preferred embodiment of the present utility model only below, be not limited to the utility model.In a preferred embodiment, the included two groups of drag-lines (first drag-line and second drag-line) of this pair rope linkage coupling comprise two drag-lines 301,302 and 201,202 respectively, but the utility model is not limited thereto, the quantity of drag-line can be other number, for example three groups, four groups, decide as required.
In addition, each mounting structure of organizing drag-line can be consistent, also can be different, and they can adopt the mounting structure of first drag-line of describing in the foregoing description 30 respectively, also can adopt the mounting structure of the second above-mentioned drag-line 20.
For a person skilled in the art, the utility model can have various changes and variation.All any modifications of within spirit of the present utility model and principle, being done, be equal to replacement, improvement etc., all should be included within the protection domain of the present utility model.
Claims (10)
1. the connecting device of a crane arm, described hoisting crane comprises mast, arm and arm-tie, described connecting device comprises first drag-line, one end of described first drag-line is connected to described arm-tie and the other end is connected to described arm, it is characterized in that described connecting device further comprises second drag-line that connects described arm-tie and described arm.
2. connecting device according to claim 1 is characterized in that, on the described arm rope pulley is installed, and an end of described second drag-line is connected to described arm-tie and the other end is walked around the described rope pulley of crossing and is connected to described mast.
3. connecting device according to claim 1, it is characterized in that, described arm-tie is installed with first installation bracket that corresponds respectively to described first drag-line and described second drag-line and have connecting bore, and is installed with second installation bracket that corresponds respectively to described first drag-line and described second drag-line and have connecting bore on described arm.
4. connecting device according to claim 3, it is characterized in that, the upper end of each in described first drag-line and described second drag-line is formed with upper end hole, pass each upper end hole in described first drag-line and described second drag-line by bearing pin and be connected in described first installation bracket on the described arm-tie corresponding one, the lower end of each in described first drag-line and described second drag-line is formed with down stomidium, connects by bearing pin each the lower end in described first drag-line and described second drag-line is connected in described second installation bracket of described arm corresponding one.
5. connecting device according to claim 2, it is characterized in that, described arm-tie is installed with first installation bracket with holes that corresponds respectively to described first drag-line and described second drag-line, and is installed with second installation bracket with holes corresponding to described first drag-line on described arm.
6. connecting device according to claim 1 is characterized in that, further comprises being arranged on described first drag-line or second drag-line and described arm-tie or/and the support between the jib.
7. according to each described connecting device among the claim 1-6, it is characterized in that described connecting device comprises two described first drag-lines being symmetrically distributed with respect to the axis of the length direction of described arm and/or two described second drag-lines that are symmetrically distributed with respect to the axis of the length direction of described arm.
8. according to each described connecting device among the claim 1-6, it is characterized in that described support is the rod like parts that two ends are formed with bracket holes respectively.
9. connecting device according to claim 7 is characterized in that, described first drag-line and/or described second drag-line are steel ropes.
10. a hoisting crane comprises according to each described connecting device among the claim 1-10.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010206966253U CN202022678U (en) | 2010-12-31 | 2010-12-31 | Connecting device of crane jib and crane with same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010206966253U CN202022678U (en) | 2010-12-31 | 2010-12-31 | Connecting device of crane jib and crane with same |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202022678U true CN202022678U (en) | 2011-11-02 |
Family
ID=44847638
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010206966253U Expired - Lifetime CN202022678U (en) | 2010-12-31 | 2010-12-31 | Connecting device of crane jib and crane with same |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202022678U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103112786A (en) * | 2013-02-06 | 2013-05-22 | 徐工集团工程机械股份有限公司 | Auxiliary bracing connection device for carrying arm support |
CN105035977A (en) * | 2015-09-10 | 2015-11-11 | 徐工集团工程机械股份有限公司 | Waist line device, cantilever crane bearing device and crane |
CN107601304A (en) * | 2017-10-18 | 2018-01-19 | 徐工集团工程机械股份有限公司 | A kind of plate drawing system for being used to fix auxiliary operating mode |
WO2019111642A1 (en) * | 2017-12-06 | 2019-06-13 | コベルコ建機株式会社 | Intermediate support holder for construction machinery |
-
2010
- 2010-12-31 CN CN2010206966253U patent/CN202022678U/en not_active Expired - Lifetime
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103112786A (en) * | 2013-02-06 | 2013-05-22 | 徐工集团工程机械股份有限公司 | Auxiliary bracing connection device for carrying arm support |
CN103112786B (en) * | 2013-02-06 | 2015-06-24 | 徐工集团工程机械股份有限公司 | Auxiliary bracing connection device for carrying arm support |
CN105035977A (en) * | 2015-09-10 | 2015-11-11 | 徐工集团工程机械股份有限公司 | Waist line device, cantilever crane bearing device and crane |
CN107601304A (en) * | 2017-10-18 | 2018-01-19 | 徐工集团工程机械股份有限公司 | A kind of plate drawing system for being used to fix auxiliary operating mode |
WO2019111642A1 (en) * | 2017-12-06 | 2019-06-13 | コベルコ建機株式会社 | Intermediate support holder for construction machinery |
US11319196B2 (en) | 2017-12-06 | 2022-05-03 | Kobelco Construction Machinery Co., Ltd. | Intermediate support holder for construction machinery |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101979308B (en) | Tower crane, pull rod structure for balance arm thereof and mounting method for structure | |
CN202022678U (en) | Connecting device of crane jib and crane with same | |
CN100567129C (en) | A kind of hoisting device for loop wheel machine | |
CN102701086A (en) | Method and device for improving lateral load capacity of arm support, and crane | |
CN102020208B (en) | Novel arm support system for crawler crane | |
CN203112390U (en) | Boom guying device of crane and whole ground crane | |
CN202483439U (en) | Counter-weight self-assembly and self-disassembly device for rotary drilling rig | |
CN202657871U (en) | Waist rope connecting structure of crane and crane comprising waist rope connecting structure | |
CN201809032U (en) | Self-adjusting stay device with combinable hanger | |
CN202924633U (en) | Cargo boom pull rod and tower crane comprising cargo boom pull rod | |
CN105645275A (en) | Cable hoisting crane and construction method thereof | |
CN206157710U (en) | Strong machine that rams and become width of cloth cantilever crane thereof | |
CN205998882U (en) | Possesses the gantry of object function of weighing | |
CN103641000A (en) | Crane and super-lifting device thereof | |
CN105317031B (en) | A kind of ship lift main equipment room bridge main beam hanging method | |
CN203715125U (en) | Crane as well as guying device thereof | |
CN205046544U (en) | Ram horn frame device and strong machine that rams by force | |
CN210480692U (en) | Tower crane becomes vice structure and has its tower crane | |
CN201850091U (en) | Tower crane and balance arm pull rod structure thereof | |
CN202924635U (en) | Tower crane jib and tower crane comprising same | |
CN203529798U (en) | Lifting device and crane | |
CN207046729U (en) | A kind of arm-tie bracket | |
CN202022677U (en) | Wheeled crane and variable amplitude assistant arm thereof | |
CN206069242U (en) | Combination type arm support and crane gear | |
CN201923798U (en) | Arm support system for novel crawler crane |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee | ||
CP01 | Change in the name or title of a patent holder |
Address after: 410013 No. 361 South silver basin, Hunan, Changsha Patentee after: ZOOMLION HEAVY INDUSTRY SCIENCE&TECHNOLOGY Co.,Ltd. Address before: 410013 No. 361 South silver basin, Hunan, Changsha Patentee before: CHANGSHA ZOOMLION HEAVY INDUSTRY SCIENCE AND TECHNOLOGY DEVELOPMENT Co.,Ltd. |
|
CX01 | Expiry of patent term | ||
CX01 | Expiry of patent term |
Granted publication date: 20111102 |