CN107601304A - A kind of plate drawing system for being used to fix auxiliary operating mode - Google Patents
A kind of plate drawing system for being used to fix auxiliary operating mode Download PDFInfo
- Publication number
- CN107601304A CN107601304A CN201710970727.6A CN201710970727A CN107601304A CN 107601304 A CN107601304 A CN 107601304A CN 201710970727 A CN201710970727 A CN 201710970727A CN 107601304 A CN107601304 A CN 107601304A
- Authority
- CN
- China
- Prior art keywords
- arm
- tie
- auxiliary
- principal
- principal arm
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000010276 construction Methods 0.000 abstract description 3
- 238000004458 analytical method Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 230000001965 increasing effect Effects 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 230000003028 elevating effect Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Jib Cranes (AREA)
Abstract
The invention discloses a kind of plate drawing system for being used to fix auxiliary operating mode, including principal arm arm-tie, waist rope, arm-tie after auxiliary, arm-tie and auxiliary support before auxiliary, described principal arm arm-tie one end is connected with the junction of principal arm and auxiliary, arm-tie both ends are connected with the auxiliary support and auxiliary respectively before the auxiliary, the waist rope both ends are connected with the principal arm and the principal arm arm-tie respectively, arm-tie one end and the auxiliary support free end after the auxiliary, the other end is connected with the principal arm arm-tie, the arm-tie tie point of tie point with the waist rope on the principal arm arm-tie on the principal arm arm-tie overlaps after the auxiliary.The present invention has simple in construction, can reduce arm support weight, improve arm support stressing conditions, improve the characteristics of principal arm opens arm ability and security.
Description
Technical field
The present invention relates to a kind of plate drawing system for being used to fix auxiliary operating mode, belong to crane technical field.
Background technology
With the quickening of Urbanization in China, economic fast development, the scale of state fundamental construction is increasing, needs
The weight and lifting altitude for the article to be lifted are increasing, and crawler crane increasingly shows its superiority, and crawler type rises
Heavy-duty machine has obtained swift and violent development.It is secondary to be commonly designed installation in order to improve its lifting altitude and work range for crawler crane
Arm operating mode.
After crane arm support typically assembles on ground, by itself luffing ability by arm support cantilever lifting to operating angle.
Horizontal cantilever lifting state, arm support is one long thin press-bending structure, due to the deadweight of arm support, the whole arm support of arm support especially center section
Downward amount of deflection can be produced, initial deformation will be further increased under arm support axial separation effect caused by luffing power, and cause two
Secondary deformation, so as to increase the structural stress of arm support.Further, arm support length is longer, and arm support weight is heavier, and arm support will have unstability
Danger;To improve the cantilever lifting ability of long-armed operating mode boom system, arm support cantilever lifting security is improved, it usually needs increase waist rope dress
Put, as shown in Figure 1.
Prior art still suffers from following shortcoming:
1. angle is smaller between arm-tie and auxiliary support after auxiliary, auxiliary support axial force is larger, otherwise auxiliary support is from high material
The material of matter, otherwise more complicated, heavier-weight that structure is done, cost are larger;
2. after auxiliary near arm-tie and principal arm hinge area(Such as a-quadrant in Fig. 2), there is stress concentration phenomenon, it is necessary to which special add
Strength is managed, and can increase the arm support weight of principal arm system;
3. during cantilever lifting, angle is smaller between principal arm arm-tie and principal arm system, arm support length more long angle therebetween is smaller, and angle is got over
Small, caused arm support axial force is bigger.Arm support can produce a downward amount of deflection during cantilever lifting, because the effect of waist rope can make master
Angle between arm arm-tie and principal arm becomes smaller(As shown in figure 3, Fig. 3 of comparison diagram 2), the increasing of arm support axial force, cantilever lifting safety
Property reduce;
4. arm-tie dumpling is selected after auxiliary is required for individually welding, processing, production cost height with waist rope dumpling point diverse location, each dumpling point;
5. tilting moment caused by the weight of boom system itself is bigger is bigger, the amount of deflection of caused arm support is also got over during cantilever lifting
Greatly, caused waist rope power is also bigger, and complete machine cantilever lifting difficulty is bigger, and cantilever lifting security is lower.
The content of the invention
The technical problem to be solved by the invention is to provide a kind of simple in construction, arm support weight can be reduced, improve arm support by
Power situation, improve the plate drawing system that principal arm opens arm ability and security.
In order to solve the above technical problems, the technical solution adopted by the present invention is:
It is a kind of to be used to fixing the plate drawing system of auxiliary operating mode, including after principal arm arm-tie, waist rope, auxiliary before arm-tie, auxiliary arm-tie with
And auxiliary support, described principal arm arm-tie one end are connected with the junction of principal arm and auxiliary, before the auxiliary arm-tie both ends respectively with
Auxiliary support and the auxiliary connection, the waist rope both ends are connected with the principal arm and the principal arm arm-tie respectively, described
Arm-tie one end and the auxiliary support free end, the other end are connected with the principal arm arm-tie after auxiliary, and arm-tie exists after the auxiliary
Tie point of the tie point with the waist rope on the principal arm arm-tie overlaps on the principal arm arm-tie.
The waist rope is arranged on the principal arm deflection of arm support maximum.
The waist rope is hinged with the principal arm arm-tie, and hinge is drawn the waist rope with the principal arm altogether with arm-tie after the auxiliary
Plate is hinged.
Arm-tie includes 2 groups after the waist rope, the principal arm arm-tie and the auxiliary, is symmetrically distributed in the two of the principal arm
On the mainmast of side.
Connector after 2 auxiliarys between arm-tie and the auxiliary support by isosceles triangle connects.
Arm-tie uses steel plate after the principal arm arm-tie and the auxiliary, and the waist rope uses steel cable.
The beneficial effect that the present invention is reached:
1. relative to prior art, angle increases between arm-tie and auxiliary support after auxiliary of the invention, auxiliary support axial direction
Power accordingly reduces, and contributes to the light-weight design of auxiliary support, and auxiliary weight support frame mitigates, and cost reduces, and cantilever lifting security increases
Add, elevating capacity gets a promotion;
2. arm-tie is articulated with principal arm arm-tie after auxiliary, relative to prior art, after can reducing auxiliary in principal arm system
Arm-tie dumpling point, it is possible to reduce corresponding manufacturing procedure, reduce production cost;Simultaneously in the absence of in prior art(In Fig. 2
A-quadrant)The phenomenon of stress concentration, boom system structure is correspondingly simple, and can reduce the weight of principal arm arm support, cantilever lifting security
Increase, elevating capacity get a promotion;
3. arm-tie is articulated with principal arm arm-tie after auxiliary, auxiliary arm-tie has a point being lifted up relative to principal arm arm-tie
Power,(Such as Fig. 5, shown in Fig. 6, Fs1/Fs2 is principal arm arm-tie power;Fh is arm-tie power after auxiliary, and Fh1/Fh2 is arm-tie power after auxiliary
Component in all directions;Fy is waist rope power)Can avoid in prior art due to the effect of waist rope make principal arm arm-tie with
The phenomenon that angle diminishes between principal arm, and can increase angle between principal arm arm-tie and principal arm, reduce arm support axial force, cantilever lifting
Security increase;
4. angle reduces between arm-tie and auxiliary support after auxiliary, arm-tie stress is corresponding more after auxiliary during arm-tie stress before equal auxiliary
It is small,(Such as Fig. 7, shown in Fig. 8, Fb is auxiliary support axial force;Fh is arm-tie power after auxiliary, and Fh3/Fs4 is arm-tie power edge after auxiliary
The component of all directions;Fq is arm-tie power before auxiliary, the component of arm-tie power in all directions before Fq1/ Fq2 auxiliarys)Contribute to pair
The light-weight design of arm-tie, reduces cost after arm;
5. the weight of boom system and arm-tie itself is significantly reduced, caused tilting moment reduces, cantilever lifting when institute
The amount of deflection of arm support is caused also to reduce, complete machine cantilever lifting difficulty reduces, the increase of cantilever lifting security.
Brief description of the drawings
Fig. 1 is band waist rope jib structure schematic diagram of the prior art;
Fig. 2 is in the prior art with waist rope arm support stressed zone schematic diagram;
Fig. 3 is in the prior art with waist rope arm support downwarp structural representation;
Fig. 4 is schematic structural view of the invention;
Fig. 5 is plate drawing system force analysis figure;
Fig. 6 is plate drawing system force analysis exploded view;
Fig. 7 is auxiliary support force analysis chart;
Fig. 8 is auxiliary support force analysis exploded view;
Fig. 9 is example structure schematic diagram;
Figure 10 is embodiment partial enlarged drawing.
Embodiment
The invention will be further described below in conjunction with the accompanying drawings.Following examples are only used for clearly illustrating the present invention
Technical scheme, and can not be limited the scope of the invention with this.
Such as Fig. 4, Fig. 9, shown in Figure 10, a kind of plate drawing system for being used to fix auxiliary operating mode, including principal arm arm-tie c, waist rope
B, arm-tie f and auxiliary support e before arm-tie d, auxiliary after auxiliary, arm-tie d includes 2 groups after waist rope b, principal arm arm-tie c and auxiliary,
It is symmetrically distributed on principal arm a both sides mainmast, principal arm arm-tie c one end is connected with principal arm a and auxiliary junction, is drawn before auxiliary
Plate f both ends are connected with auxiliary support e and auxiliary respectively, and waist rope b both ends are hinged with principal arm a and principal arm arm-tie c respectively, waist rope
B positions are located at deflection of arm support maximum, and the amount of deflection that can play reduction arm support acts on, arm-tie d one end and auxiliary branch after 2 auxiliarys
Connected between frame e free ends by the connector of isosceles triangle, the arm-tie d other ends are total to 2 waist rope b respectively after 2 auxiliarys
Hinge is hinged with principal arm arm-tie c.
Described above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, without departing from the technical principles of the invention, some improvement and deformation can also be made, these are improved and deformation
Also it should be regarded as protection scope of the present invention.
Claims (6)
1. a kind of plate drawing system for being used to fix auxiliary operating mode, it is characterized in that, including principal arm arm-tie(c), waist rope(b), after auxiliary
Arm-tie(d), arm-tie before auxiliary(f)And auxiliary support(e), the principal arm arm-tie(c)One end and principal arm(a)With the connection of auxiliary
Place connects, arm-tie before the auxiliary(f)Both ends respectively with the auxiliary support(e)And auxiliary connection, the waist rope(b)Both ends
Respectively with the principal arm(a)And the principal arm arm-tie(c)Connect, arm-tie after the auxiliary(d)One end and the auxiliary support
(e)Free end, the other end and the principal arm arm-tie(c)Connect, arm-tie after the auxiliary(d)In the principal arm arm-tie(c)Upper company
Contact and the waist rope(b)In the principal arm arm-tie(c)On tie point overlap.
2. a kind of plate drawing system for being used to fix auxiliary operating mode according to claim 1, it is characterized in that, the waist rope(b)
It is arranged on the principal arm(a)Deflection of arm support maximum.
3. a kind of plate drawing system for being used to fix auxiliary operating mode according to claim 2, it is characterized in that, the waist rope(b)
With the principal arm arm-tie(c)It is be hinged, the waist rope(b)With arm-tie after the auxiliary(d)Hinge and the principal arm arm-tie altogether(c)Hinge
Connect.
4. a kind of plate drawing system for being used to fix auxiliary operating mode according to claim 3, it is characterized in that, the waist rope(b)、
The principal arm arm-tie(c)And arm-tie after the auxiliary(d)Including 2 groups, the principal arm is symmetrically distributed in(a)Both sides mainmast
On.
5. a kind of plate drawing system for being used to fix auxiliary operating mode according to claim 4, it is characterized in that, 2 auxiliarys
Arm-tie afterwards(d)With the auxiliary support(e)Between connected by the connector of isosceles triangle.
6. a kind of plate drawing system for being used to fix auxiliary operating mode according to claim 1, it is characterized in that, the principal arm arm-tie
(c)And arm-tie after the auxiliary(d)Using steel plate, the waist rope(b)Using steel cable.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710970727.6A CN107601304B (en) | 2017-10-18 | 2017-10-18 | Pulling plate system for fixing working condition of auxiliary arm |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710970727.6A CN107601304B (en) | 2017-10-18 | 2017-10-18 | Pulling plate system for fixing working condition of auxiliary arm |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107601304A true CN107601304A (en) | 2018-01-19 |
CN107601304B CN107601304B (en) | 2024-06-14 |
Family
ID=61077144
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710970727.6A Active CN107601304B (en) | 2017-10-18 | 2017-10-18 | Pulling plate system for fixing working condition of auxiliary arm |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107601304B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113501447A (en) * | 2021-07-08 | 2021-10-15 | 徐工集团工程机械股份有限公司建设机械分公司 | Crane and method for lifting main arm of crane |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102001590A (en) * | 2010-12-03 | 2011-04-06 | 徐州重型机械有限公司 | Wheeled crane and luffing jib thereof |
CN202022678U (en) * | 2010-12-31 | 2011-11-02 | 长沙中联重工科技发展股份有限公司 | Connecting device of crane jib and crane with same |
CN102689847A (en) * | 2012-06-04 | 2012-09-26 | 徐州重型机械有限公司 | Telescopic-boom crane and superlift device thereof |
CN103601082A (en) * | 2013-11-22 | 2014-02-26 | 中联重科股份有限公司 | Crane and arm rising method thereof |
CN104692265A (en) * | 2015-01-29 | 2015-06-10 | 徐工集团工程机械股份有限公司 | Waist rope structure |
CN104909286A (en) * | 2015-05-13 | 2015-09-16 | 徐工集团工程机械股份有限公司 | Crawler crane boom structure and crawler crane |
CN207390868U (en) * | 2017-10-18 | 2018-05-22 | 徐工集团工程机械股份有限公司 | A kind of plate drawing system for being used to fix auxiliary operating mode |
-
2017
- 2017-10-18 CN CN201710970727.6A patent/CN107601304B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102001590A (en) * | 2010-12-03 | 2011-04-06 | 徐州重型机械有限公司 | Wheeled crane and luffing jib thereof |
CN202022678U (en) * | 2010-12-31 | 2011-11-02 | 长沙中联重工科技发展股份有限公司 | Connecting device of crane jib and crane with same |
CN102689847A (en) * | 2012-06-04 | 2012-09-26 | 徐州重型机械有限公司 | Telescopic-boom crane and superlift device thereof |
CN103601082A (en) * | 2013-11-22 | 2014-02-26 | 中联重科股份有限公司 | Crane and arm rising method thereof |
CN104692265A (en) * | 2015-01-29 | 2015-06-10 | 徐工集团工程机械股份有限公司 | Waist rope structure |
CN104909286A (en) * | 2015-05-13 | 2015-09-16 | 徐工集团工程机械股份有限公司 | Crawler crane boom structure and crawler crane |
CN207390868U (en) * | 2017-10-18 | 2018-05-22 | 徐工集团工程机械股份有限公司 | A kind of plate drawing system for being used to fix auxiliary operating mode |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113501447A (en) * | 2021-07-08 | 2021-10-15 | 徐工集团工程机械股份有限公司建设机械分公司 | Crane and method for lifting main arm of crane |
Also Published As
Publication number | Publication date |
---|---|
CN107601304B (en) | 2024-06-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102002936B (en) | Dynamic compactor capable of realizing amplitude-variable followup of A-bracket with arm support | |
US4171597A (en) | Crane boom and telescopic section for it | |
CN102491194B (en) | Crane super-lifting device and all-terrain crane with the crane super-lifting device | |
CN107601304A (en) | A kind of plate drawing system for being used to fix auxiliary operating mode | |
CN207390868U (en) | A kind of plate drawing system for being used to fix auxiliary operating mode | |
CN107531464A (en) | Crane tower | |
CN107917785A (en) | A kind of girder steel stability test load loading device based on lever principle | |
WO2013139116A1 (en) | Arm joint for truss arm, truss arm, and crane with truss arm | |
CN102001590A (en) | Wheeled crane and luffing jib thereof | |
CN204847837U (en) | Single beam bridge crane main girder structure | |
JP5374915B2 (en) | Crane weight structure | |
CN110159051A (en) | Substation framework | |
CN101811646A (en) | Crawler crane with lateral reinforcement structure | |
CN206307907U (en) | Novel lightweight loading trolley | |
CN209384124U (en) | A kind of steel truss girder purlin piece turnover hoisting structure | |
CN210001478U (en) | Arm frame assembly and crane | |
CN105584941B (en) | A kind of truss arm reducing machine and crawler crane | |
CN102408070A (en) | Standard knot for crane and tower crane | |
CN202022677U (en) | Wheeled crane and variable amplitude assistant arm thereof | |
CN102398863A (en) | Support structure capable of improving jib bearing capacity and crane with the support structure | |
CN202226576U (en) | Pull rod system of luffing jib tower crane and luffing jib tower crane | |
CN205838399U (en) | A kind of band waist rope jib | |
CN110127540A (en) | Arm support component and crane | |
CN212893604U (en) | Cargo boom and balance arm integrated root section structure of flat-top tower crane | |
CN103395706B (en) | Hoisting crane and telescopic boom thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant |