CN202011886U - Hot air outlet pipe of hot blast stove - Google Patents

Hot air outlet pipe of hot blast stove Download PDF

Info

Publication number
CN202011886U
CN202011886U CN2011200811662U CN201120081166U CN202011886U CN 202011886 U CN202011886 U CN 202011886U CN 2011200811662 U CN2011200811662 U CN 2011200811662U CN 201120081166 U CN201120081166 U CN 201120081166U CN 202011886 U CN202011886 U CN 202011886U
Authority
CN
China
Prior art keywords
brick
layer
hot air
outlet pipe
semi
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011200811662U
Other languages
Chinese (zh)
Inventor
陈维汉
刘世聚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENAN YUXING HOT BLAST STOVE ENGINEERING TECHNOLOGY Co Ltd
Original Assignee
HENAN YUXING HOT BLAST STOVE ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENAN YUXING HOT BLAST STOVE ENGINEERING TECHNOLOGY Co Ltd filed Critical HENAN YUXING HOT BLAST STOVE ENGINEERING TECHNOLOGY Co Ltd
Priority to CN2011200811662U priority Critical patent/CN202011886U/en
Application granted granted Critical
Publication of CN202011886U publication Critical patent/CN202011886U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a hot air outlet pipe of a hot blast stove, and effectively solves the problems that brick masonries among the walls of a combustion chamber are destroyed, an arch crown collapses, air is released from the hot air outlet pipe, and the service life of a blast furnace hot blast stove is short. An inner brick layer is arranged outside an outer brick layer; a composite brick is arranged outside the outer brick layer; heavy brick supporting layers are arranged below a semi-ring composite brick behind the composite brick; a semi-circular steel fiber casting material arch ring is arranged above the semi-ring composite brick; supporting bricks are arranged on the outer side of a junction of the semi-ring composite brick and the semi-circular steel fiber casting material arch ring; fixed bricks are arranged outside the supporting bricks; spraying layers are arranged outside fiber cotton felt layers outside light brick layers between the inner heavy brick layer of the combustion chamber and a stove shell, and extend into an outlet pipe on the outer wall of the stove shell; the fiber cotton felt layers and the light brick layers are arranged on the spraying layers in sequence; and the light brick layers are connected with the outer brick layer. When the stove shell upward displaces due to thermal expansion and the brick masonries in the combustion chamber downwards displace due to thermal shrinkage, various stress at the junction can effectively absorbed or resisted, and the problems of the serious damage of the hot air pipe and the damage of the arc crown are avoided.

Description

A kind of hot air furnace hot air outlet pipe
One, technical field
The utility model relates to a kind of hot air furnace hot air outlet pipe.
Two, background technology
The high pressure-temperature gas (hot blast) that produces in blast funnace hot blast stove must just can be delivered in the bustle pipe of blast furnace by hot air duct, the position that most is easy to go wrong in hot air duct is exactly the hot-blast outlet pipeline section that is provided with on the combustion chamber wall of blast funnace hot blast stove, Here it is connects pipeline section between blast furnace and hot blast cupola combustion chamber wall and the hot blast valve, its structure design is to the combustion chamber of blast funnace hot blast stove, hot air duct, and the safe and stable operation of hot blast valve is vital, irrational mix can cause the damage of the brick structures in the hot-blast outlet pipe and between combustion chamber wall under the interaction of the loading stress of the furnace shell of blast funnace hot blast stove and anti-equipment structure and thermal stresses, can cause the combustion chamber vault to cave in when serious, or hot-blast outlet pipe seriously runs wind and burnt redly, and then influence blast funnace hot blast stove integral body working life.Therefore, how to reduce thermal stresses and mechanical stress between hot-blast outlet pipe and vault body of wall, and the transverse compressive stress that is subjected to when how to solve hot-blast outlet pipe by light material, be the key issue on the hot-blast outlet pipe.
Three, summary of the invention
At above-mentioned situation, for overcoming the prior art defective, the purpose of the utility model just provides a kind of hot air furnace hot air mountain pass pipe, the damage that can effectively solve brick structures between combustion chamber wall, and the combustion chamber vault caves in and hot-blast outlet pipe runs wind and blast funnace hot blast stove short problem in work-ing life.
The technical scheme that the utility model solves is, the internal layer brick is placed on the periphery wall of outer brick layer, constitute two-layer annular and build layer by laying bricks or stones, have on the outer brick layer periphery wall with combustion chamber internal layer heavy brick layer and closely build together modular tile by laying bricks or stones, there is the semi-ring modular tile that places on the outer brick layer periphery wall at the rear of modular tile, there is the heavy brick supporting layer that places the internal layer heavy brick layer outside, combustion chamber the below of semi-ring modular tile, there is the semicircle steel fiber castable arch ring that places on the outer brick layer periphery wall top of semi-ring modular tile, there is the support brick that is fixed on the heavy brick supporting layer in the outside of semi-ring modular tile and semicircle steel fiber castable arch ring intersection, there is the fixedly brick of building by laying bricks or stones in the internal layer heavy brick layer of combustion chamber in the outside of supporting brick, between combustion chamber internal layer heavy brick layer and furnace shell the first light cinder brick layer is arranged, the first cellucotton carpet veneer is arranged on the periphery wall of the first light cinder brick layer, the sprayed coating that places in the furnace shell is arranged on the periphery wall of the first cellucotton carpet veneer, sprayed coating extends out in furnace shell in the outlet pipe on the furnace shell outer wall, have successively on the sprayed coating respectively and the first cellucotton carpet veneer, the second cellucotton carpet veneer that the first light cinder brick layer is connected and the second light cinder brick layer, second light cinder brick layer inside are built layer by laying bricks or stones with two-layer annular and are connected.
The utility model can be in the furnace shell heat expansion effectively absorbs or resists the various stress of junction because of pyrocondensation during to bottom offset to top offset and combustion chamber brick structures, has avoided the badly damaged and impaired problem of vault of heating duct.
Four, description of drawings
Fig. 1 is a front view of the present utility model.
Fig. 2 is that the B-B of Fig. 1 of the present utility model is to front view.
Fig. 3 is that the A-A of Fig. 1 of the present utility model is to front view.
Five, embodiment
Below in conjunction with accompanying drawing embodiment of the present utility model is elaborated.
Provide by Fig. 1-Fig. 3, structure of the present utility model is, internal layer brick layer 1 places on the periphery wall of outer brick layer 2, constitute two-layer annular and build layer by laying bricks or stones, on outer brick layer 2 periphery wall modular tile 4 of closely building by laying bricks or stones together with combustion chamber internal layer heavy brick layer 3 is arranged, the rear of modular tile has the semi-ring that places on outer brick layer 2 periphery wall to make up special 6, there is the heavy brick supporting layer 5 that places the internal layer heavy brick layer outside, combustion chamber the below of semi-ring modular tile, there is the semicircle steel fiber castable arch ring 7 that places on outer brick layer 2 periphery wall top of semi-ring modular tile, there is the support brick 8 that is fixed on the heavy brick supporting layer 5 in the outside of semi-ring modular tile and semicircle steel fiber castable arch ring intersection, there is the fixedly brick 16 of building by laying bricks or stones in the internal layer heavy brick layer of combustion chamber in the outside of supporting brick, combustion chamber internal layer heavy brick layer and 18 of furnace shells have the first light cinder brick layer 11, the first cellucotton carpet veneer 12 is arranged on the periphery wall of the first light cinder brick layer, the sprayed coating 13 that places in the furnace shell is arranged on the periphery wall of the first cellucotton carpet veneer, sprayed coating extends out in furnace shell in the outlet pipe 17 on the furnace shell outer wall, have successively on the sprayed coating respectively and the first cellucotton carpet veneer 12, second cellucotton carpet veneer 15 that the first light cinder brick layer 11 is connected and the second light cinder brick layer, 14, the second light cinder brick layer inside are built layer by laying bricks or stones with two-layer annular and are connected.
All on same camber line, the front portion of internal layer brick layer is to constitute by knife-edge is brick to the periphery wall of the front portion of said internal layer brick layer 1 and outer brick layer 2 and modular tile 4 and combustion chamber internal layer heavy brick layer 3 together, and the rear portion is built by laying bricks or stones together by " z " font brick 10 and constituted; The front portion that places internal layer brick layer 1 and outer brick layer 2 and the interlayer coulisse 9 between the rear portion are arranged between said combustion chamber internal layer heavy brick layer 3 and the heavy brick supporting layer 5; The width of said heavy brick supporting layer 5 bottoms is greater than 2 times of the outlet pipe outside diameter on the furnace shell outer wall, and tapered semi-ring modular tile 6 outsides that are fixed on the outlet pipe central horizontal and locate; Said support brick 8 is built by laying bricks or stones at the top of semi-ring modular tile 6 and fixedly between the brick 16; Said semi-ring modular tile 6 tops are equipped with the fibrefelt of the semicircular in shape of 10mm on outer brick layer 2 periphery wall, the up semicircle steel fiber castable arch ring 7 of the periphery wall of semicircular fibrefelt, the arch springing of semicircle steel fiber castable arch ring is supported on the semi-ring modular tile, both sides are fixing by supporting brick 8, between semicircle steel fiber castable arch ring and semi-ring modular tile 5~10mm gap is arranged, to guarantee certain displacement each other; The first light cinder brick layer 11 is two-layer between the combustion chamber internal layer heavy brick layer 3 and the first cellucotton carpet veneer 12; The second light cinder brick layer 14 covers downwards to the periphery wall of heavy brick supporting layer 5 and semicircle steel fiber castable arch ring 7; The internal diameter size of said semicircle steel fiber castable arch ring 7 is identical with the internal diameter size of semi-ring modular tile 6; The said second cellucotton carpet veneer 15 is gone back silico-calcium flaggy.
Wherein, the first cellucotton carpet veneer 12 is the packing layers between the first light cinder brick layer 11 and the sprayed coating 13, the second cellucotton carpet veneer 15 is the packing layers between the second light cinder brick layer 14 and the sprayed coating, first, the effect of capable insulation of the second cellucotton carpet veneer tool and adjustment structure size, the arch springing both sides of semicircle steel fiber castable arch ring are to limit by supporting brick 8, the fixedly brick 16 of building by laying bricks or stones in internal layer heavy brick layer 3 is arranged outside it, modular tile 4 effect of manageing it converts radial force circumferentially to and axially loaded, and can realize closely building by laying bricks or stones of outer brick layer 2 and combustion chamber internal layer heavy brick layer 3, build by laying bricks or stones after assembling in advance having made, and strict control brickwork joint size.Heavy brick supporting layer 5 is built by laying bricks or stones outside combustion chamber internal layer heavy brick layer 3, it is brick layer and the capable weight capacity of tool that progressively extends out from heavy brick layer, for Stability Analysis of Structures, the width of its bottom must not be lower than 2 times of outlet pipe outside diameter of heating duct, and progressively be narrowed on the central horizontal face of heating duct, and be provided with on tool top and support brick 8, it is built by laying bricks or stones at the topmost of semi-ring modular tile 6 and builds by laying bricks or stones between the fixedly brick 16 in combustion chamber internal layer heavy brick layer 3.
The utility model is when bottom, combustion chamber furnace brickwork during to certain position, in the certain limit of hot-blast outlet, builds heavy brick supporting layer 5 by laying bricks or stones in the periphery of combustion chamber internal layer heavy brick layer 3 and joins simultaneously and build modular tile 4 and semi-ring modular tile 6 to the hot-blast outlet central plane.Next outwards build the internal layer brick layer 1 and the outer brick layer 2 of the outlet pipe 17 of hot blast by laying bricks or stones from the combustion chamber, attention stays interlayer coulisse 9 between respective combustion chamber internal layer heavy brick layer 3 and heavy brick supporting layer 5, and the internal layer brick layer 1 and the outer brick layer 2 of the outlet pipe of attention hot blast are also temporarily built heavy brick supporting layer 5 places by laying bricks or stones.Continue to build by laying bricks or stones modular tile 4 and combustion chamber internal layer heavy brick layer 3, the internal layer brick layer 1 at the outlet pipe place of hot blast and the first half of outer brick layer 2 on heavy brick supporting layer 5, with a semi-ring group brick 6 is the semicircle steel fiber castable arch ring 7 of basis cast, note staying the slit between semicircle steel fiber castable arch ring 7 and the outer brick layer 2, the building by laying bricks or stones of heavy brick supporting layer 5 is that the bottom is wide and top is received little gradually, it is contraction-like to be ladder, surpass both sides, semi-ring modular tile 6 back and build support brick 8 by laying bricks or stones, place it between the fixedly brick 16 of building by laying bricks or stones in semi-ring modular tile 6 lastblocks and the combustion chamber internal layer heavy brick layer 3, the rest part of heavy brick supporting layer 5 recovers to build by laying bricks or stones with the first light cinder brick layer 11, and doing like this is in order to strengthen location and the support to heating duct and semicircle steel fiber castable arch ring 7.It is respectively the first light cinder brick layer 11 that in the furnace shell other built by laying bricks or stones, and it is outer to be the first cellucotton carpet veneer 12 and the interior sprayed coating 13 of furnace shell.Continue building by laying bricks or stones of internal layer brick layer 1 and outer brick layer 2 again, till hot blast valve, sufficient light cinder brick layer 14 outside internal layer brick layer 1 in the outlet pipe 17 and the outer brick layer 2, the outside is the second cellucotton carpet veneer 15 again, is the sprayed coating 13 in the outlet pipe 17 outside it.
The utility model has strengthened stability of structure, prevented that effectively heating duct from leaking the imagination because of the hot blast that distortion causes, and can bear structural stress and thermal stresses impact to greatest extent to pipeline and body of heater, effectively avoided because of heating duct damages the appearance of phenomenon of caving in of the vault cause, thereby prolonged the work-ing life of hotblast stove.

Claims (9)

1. hot air furnace hot air outlet pipe, it is characterized in that, internal layer brick layer (1) places on the periphery wall of outer brick layer (2), constitute two-layer annular and build layer by laying bricks or stones, have on outer brick layer (2) periphery wall with combustion chamber internal layer heavy brick layer (3) and closely build together modular tile (4) by laying bricks or stones, there is the semi-ring modular tile (6) that places on outer brick layer (2) periphery wall at the rear of modular tile, there is the heavy brick supporting layer (5) that places the internal layer heavy brick layer outside, combustion chamber the below of semi-ring modular tile, there is the semicircle steel fiber castable arch ring (7) that places on outer brick layer (2) periphery wall top of semi-ring modular tile, there is the support brick (8) that is fixed on the heavy brick supporting layer (5) in the outside of semi-ring modular tile and semicircle steel fiber castable arch ring intersection, there is the fixedly brick (16) of building by laying bricks or stones in the internal layer heavy brick layer of combustion chamber in the outside of supporting brick, the first light cinder brick layer (11) is arranged between combustion chamber internal layer heavy brick layer and furnace shell (18), the first cellucotton carpet veneer (12) is arranged on the periphery wall of the first light cinder brick layer, the sprayed coating (13) that places in the furnace shell is arranged on the periphery wall of the first cellucotton carpet veneer, sprayed coating extends out in furnace shell in the outlet pipe (17) on the furnace shell outer wall, have successively on the sprayed coating respectively and the first cellucotton carpet veneer (12), the second cellucotton carpet veneer (15) that the first light cinder brick layer (11) is connected and the second light cinder brick layer (14), second light cinder brick layer inside are built layer by laying bricks or stones with two-layer annular and are connected.
2. hot air furnace hot air outlet pipe according to claim 1, it is characterized in that, the periphery wall of the front portion of said internal layer brick layer (1) and outer brick layer (2) and modular tile (4) and combustion chamber internal layer heavy brick layer (3) is all on same camber line, the front portion of internal layer brick layer is to constitute by knife-edge is brick together, and the rear portion is built by laying bricks or stones together by " z " font brick (10) and constituted.
3. hot air furnace hot air outlet pipe according to claim 1, it is characterized in that the front portion that places internal layer brick layer (1) and outer brick layer (2) and the interlayer coulisse (9) between the rear portion are arranged between said combustion chamber internal layer heavy brick layer (3) and the heavy brick supporting layer (5).
4. hot air furnace hot air outlet pipe according to claim 1, it is characterized in that, the width of said heavy brick supporting layer (5) bottom is greater than 2 times of the outlet pipe outside diameter on the furnace shell outer wall, and tapered semi-ring modular tile (6) outside that is fixed on outlet pipe central horizontal face place.
5. hot air furnace hot air outlet pipe according to claim 1 is characterized in that, said support brick (8) is built by laying bricks or stones at the top of semi-ring modular tile (6) and fixedly between the brick (16).
6. hot air furnace hot air outlet pipe according to claim 1, it is characterized in that, said semi-ring modular tile (6) top is equipped with the fibrefelt of the semicircular in shape of 10mm on outer brick layer (2) periphery wall, semicircle steel fiber castable arch ring (7) is arranged on the periphery wall of semicircular fibrefelt, the arch springing of semicircle steel fiber castable arch ring is supported on the semi-ring modular tile, both sides are fixing by supporting brick (8), between semicircle steel fiber castable arch ring and semi-ring modular tile 5~10mm gap arranged.
7. hot air furnace hot air outlet pipe according to claim 1 is characterized in that, the first light cinder brick layer (11) is two-layer between the combustion chamber internal layer heavy brick layer (3) and the first cellucotton carpet veneer (12).
8. hot air furnace hot air outlet pipe according to claim 1 is characterized in that, the second light cinder brick layer (14) covers downwards to the periphery wall of heavy brick supporting layer (5) and semicircle steel fiber castable arch ring (7).
9. hot air furnace hot air outlet pipe according to claim 1 is characterized in that, the internal diameter size of said semicircle steel fiber castable arch ring (7) is identical with the internal diameter size of semi-ring modular tile (6).
CN2011200811662U 2011-03-25 2011-03-25 Hot air outlet pipe of hot blast stove Expired - Fee Related CN202011886U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200811662U CN202011886U (en) 2011-03-25 2011-03-25 Hot air outlet pipe of hot blast stove

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200811662U CN202011886U (en) 2011-03-25 2011-03-25 Hot air outlet pipe of hot blast stove

Publications (1)

Publication Number Publication Date
CN202011886U true CN202011886U (en) 2011-10-19

Family

ID=44782499

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200811662U Expired - Fee Related CN202011886U (en) 2011-03-25 2011-03-25 Hot air outlet pipe of hot blast stove

Country Status (1)

Country Link
CN (1) CN202011886U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108193010A (en) * 2018-03-09 2018-06-22 中冶京诚工程技术有限公司 The inside lining building structure of hot air duct and hot air duct junctions inside lining building structure
CN111609417A (en) * 2019-10-28 2020-09-01 中建材创新科技研究院有限公司 Hot cigarette pipeline sealing connection structure
CN114107586A (en) * 2021-12-10 2022-03-01 中冶南方武汉钢铁设计研究院有限公司 Hot blast stove system and hot blast outlet combined brick

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108193010A (en) * 2018-03-09 2018-06-22 中冶京诚工程技术有限公司 The inside lining building structure of hot air duct and hot air duct junctions inside lining building structure
CN108193010B (en) * 2018-03-09 2023-04-28 中冶京诚工程技术有限公司 Lining building structure of hot air pipeline and three-fork lining building structure of hot air pipeline
CN111609417A (en) * 2019-10-28 2020-09-01 中建材创新科技研究院有限公司 Hot cigarette pipeline sealing connection structure
CN114107586A (en) * 2021-12-10 2022-03-01 中冶南方武汉钢铁设计研究院有限公司 Hot blast stove system and hot blast outlet combined brick
CN114107586B (en) * 2021-12-10 2023-02-07 中冶南方武汉钢铁设计研究院有限公司 Hot blast stove system and hot blast outlet combined brick

Similar Documents

Publication Publication Date Title
EP3031933B1 (en) Hot-blast stove construction method
CN202011886U (en) Hot air outlet pipe of hot blast stove
CN108603660B (en) Top combustion hot blast stove
CN100578127C (en) Fluidized calcining furnace ball arc furnace top and method of forming same
CN202730166U (en) Hot air outlet structure of hot-blast stove
CN204939514U (en) Blast funnace hot blast stove hot air duct masonry construction
CN109652603B (en) Semi-pouring type blast furnace hot blast stove pipeline and construction method thereof
CN208545452U (en) A kind of non-circular channels hot air duct masonry construction
CN108193010B (en) Lining building structure of hot air pipeline and three-fork lining building structure of hot air pipeline
CN101387408A (en) Domestic lining structure for large-sized circulating fluidized bed boiler
CN108996927B (en) Double-chamber shaft kiln with cooling support upright post
CN107739766A (en) The resistance to material segmentation building construction method of top combustion stove
CN207231233U (en) A kind of refractory lining masonry construction for lifting Kaldo Furnace furnace life
CN205669037U (en) Low stress branch pipe tee connection ball mouth structure
CN203517788U (en) Porous body burning combustor of remixing coal gas whirl flow with premix gas
CN203938685U (en) Hotblast stove taper arch crown supporting device
CN103822472B (en) A kind of cylindrical shape turns round the castable furnace binding of hot equipment
CN208008844U (en) A kind of hot air duct structure and hot air delivery system
CN205954045U (en) Connection structure of hot -blast person in charge of blast furnace hot stove and hot -blast standpipe
CN100593680C (en) Inside lining structure of hot-air pipe expansion joint of blast heating furnace
CN201348250Y (en) Gas leakage prevention heat accumulating type burner
CN205191632U (en) Chain line's independent vault structure is hanged in match of top combustion stove circular arc
CN204693412U (en) experimental furnace burner
CN208058161U (en) A kind of Double-set Cylindrical Type high-temperature furnace smoke pipeline with inside holding
CN108165694B (en) Hot air pipeline structure and hot air conveying system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111019

Termination date: 20150325

EXPY Termination of patent right or utility model