The traversing dolly of a kind of pipe laying barge
Technical field
The innovation of the utility model and a kind of ocean engineering field pipe laying barge pipelaying work device.
Background technique
China's oil and gas production cumulative year after year, and the main cause that significantly increases of oil and gas production is the increase of Chinese offshore oil and gas output.Offshore production oil gas mainly relies on submarine pipeline to carry, so the effect that submarine pipeline is laid in the oil gas conveying is more and more important.Will relate to the transportation problem of pipeline on the pipe laying barge production line, in order to improve pipe laying efficient, need design by-effect line and main production line, the by-effect line is used for carrying out the pretreatment of pipeline, after finishing, pretreatment needs by traversing dolly, the pipeline that pretreatment is finished is transported on the main production line, and then improves the pipelaying work efficient of main production line.
Summary of the invention:
The technical problem that the utility model solves provides a kind of traversing dolly, in the pipelaying work, realizes the lifting pipeline at sea, and the picking-up pipeline moves horizontally.
The utility model technology contents is, a kind of pipe laying barge is equipped with oil hydraulic cylinder with traversing dolly, and when traversing dolly entered the handing-over zone, hydraulic cylinder piston rod was released, and with V-type support jack-up, and then pipeline held up from the by-effect line.Traversing dolly mainly relies on motor reducer that power is provided, and connects rotating shaft by coupling, drives the sprocket rotation on the chain wheel support, by being connected closed chain on the traversing dolly with traversing dolly move left and right.The peak of traversing dolly must be lower than the minimum point of pipeline, when traversing dolly enters cross-connecting area, pipeline jack-up is come highly must surpass the peak of by-effect line, take pipeline then away, be transported on the main production line, repeat this and get the pipe step, finish the transition of pipeline, 6 meters of traversing dolly displacement distances, 20 meters/minute of maximum travelling speeds.
The beneficial effects of the utility model are, this traversing dolly has solved on the pipe laying barge pipeline in the commentaries on classics preface problem of auxilliary production line to main production line.By this device, saved the time of utilizing of loop wheel machine on the pipe laying barge, pretreated work station is provided.
Description of drawings
Below in conjunction with drawings and Examples the utility model is described further.
Fig. 1 for pipe laying barge with traversing dolly plan view
Fig. 2 for pipe laying barge with traversing dolly side view
Fig. 3 gets pipe operation (dolly wait) figure for pipe laying barge with traversing dolly
Fig. 4 gets pipe operation (dolly moves to left) figure for pipe laying barge with traversing dolly
Fig. 5 gets pipe operation (dolly enters cross-connecting area) figure for pipe laying barge with traversing dolly
Fig. 6 gets pipe operation (jack-up pipeline) figure for pipe laying barge with traversing dolly
Fig. 7 gets pipe operation (taking pipeline away) figure for pipe laying barge with traversing dolly
1-V type support wherein; The 2-back shaft; The 3-guide cylinder; The 4-oil hydraulic cylinder; The 5-rotating shaft; The 6-coupling; The 7-motor reducer; The 8-sprocket wheel; The 9-chain; The 10-roller; The 11-bearing pin; The 12-guide rail; 13-chain wheel support; The traversing dolly of 14-; The 15-pipeline; 16 by-effect lines; 17-master's production line; The traversing dolly peak of 18-; 19-pipeline minimum point; 20-by-effect line peak
Embodiment:
As shown in Figure 1 and Figure 2, on the traversing dolly 14 oil hydraulic cylinder 4 is housed, when traversing dolly 14 enters when zone handing-over, oil hydraulic cylinder 4 piston rods are released, and with V-type support 1 jack-up, and then pipeline 15 are held up from by-effect line 16.The traversing dolly 14 main motor reducers 7 that rely on provide power, connect rotating shaft 5 by coupling 6, the sprocket wheel 8 that drives on the chain wheel support 13 rotates, and by being connected closed chain 9 on the traversing dolly 14 with traversing dolly 14 move left and right, thereby realizes the function of transhipment pipeline 15.Wherein V-type support 1 plays the trustship effect, and back shaft 2 plays 1 effect of jack-up V-type support, and guide cylinder 3 guarantees that back shaft 2 vertically rises, and does not swing.Oil hydraulic cylinder 4 is used to provide jacking power, and rotating shaft 5 and coupling 6 are used for transmitting the moment of torsion of motor, guarantees two traversing dolly 14 same moved further.Motor reducer 7 is used to provide power.Sprocket wheel 8 and chain 9 are formed chain-driven, realize the move left and right of traversing dolly 14.Roller 10 and guide rail 12 guarantee that traversing dolly 14 can move along certain orientation, can sideslip.Bearing pin 11 is used for connecting the piston rod of V-type support 1 and oil hydraulic cylinder 4.Chain wheel support 13 is used for fixing sprocket wheel 8.
As shown in Figure 3, traversing dolly 14 is got in the pipe operation, waits for.
As shown in Figure 4, traversing dolly 14 is got in the pipe operation, and traversing dolly 14 is moved to the left.
As shown in Figure 5, traversing dolly 14 is got in the pipe operation, and when traversing dolly 14 enters cross-connecting area, traversing dolly peak 18 must be lower than pipeline minimum point 19.
As shown in Figure 6, traversing dolly 14 is got in the pipe operation, and the pipeline 15 of traversing dolly 14 jack-up highly must surpass by-effect line peak 20.
As shown in Figure 7, traversing dolly 14 is got in the pipe operation, and traversing dolly 14 is taken pipeline 15 away, and pipeline 15 is transported on the main production line 17.