CN201937208U - Cable-releasing stand for cabling in cable channel - Google Patents

Cable-releasing stand for cabling in cable channel Download PDF

Info

Publication number
CN201937208U
CN201937208U CN2010206492897U CN201020649289U CN201937208U CN 201937208 U CN201937208 U CN 201937208U CN 2010206492897 U CN2010206492897 U CN 2010206492897U CN 201020649289 U CN201020649289 U CN 201020649289U CN 201937208 U CN201937208 U CN 201937208U
Authority
CN
China
Prior art keywords
cable
channel
steel pipe
hollow steel
cabling
Prior art date
Application number
CN2010206492897U
Other languages
Chinese (zh)
Inventor
马骏
汪新平
崔洪波
严正
Original Assignee
鄂州供电公司配电中心
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 鄂州供电公司配电中心 filed Critical 鄂州供电公司配电中心
Priority to CN2010206492897U priority Critical patent/CN201937208U/en
Application granted granted Critical
Publication of CN201937208U publication Critical patent/CN201937208U/en

Links

Abstract

The utility model provides a cable-releasing stand for cabling in a cable channel. The cable-releasing stand is characterized in that a cylindrical hollow steel pipe, a triangular bracket and a traction pulley are comprised and are all can be embedded in the cable channel, wherein the triangular bracket is welded with one end of the cylindrical hollow steel pipe via an angle steel; and the traction pulley is fixed on the triangular bracket via bolts and is just opposite to a pipe port of the hollow steel pipe. In the utility model, a channel inlet can be formed for leading the cable to enter into the cable channel, and a channel outlet can be also formed for facilitating the access/exit of the cable and avoiding the protecting layer of the cable from being damaged by the friction between the cable and the channel, so that the entire cabling process is time-saving and labor-saving, and the cost is lowered.

Description

A kind of pay off rack that is used for the cable duct cabling

Technical field

The utility model relates to a kind of aid of cable laying, specifically is a kind of pay off rack that is used for the cable duct cabling.

Background technology

In present cable duct laying work construction; generally all need a large amount of manpowers to assist mechanical traction; when the cable head is come in and gone out cable duct; because the quality of cable is big; cable duct is narrow, the bad grasp of cable duct radian of coming in and going out, and the friction of cable and pipe surface is excessive; the friction of cable and cable duct usually occurs and cause the impaired phenomenon of cable covering, and whole steps wastes time and energy.This outer cable is drawn in cable trough, and part also has the scratch phenomenon, and these have had a strong impact on the progress and the quality of construction, has stayed potential safety hazard also for later cable operation.

Summary of the invention

The utility model is carried according to the deficiencies in the prior art provides a kind of cable duct that is used for to lay, make things convenient for cabling turnover cable duct; avoid cable and pipeline friction; and cause cable covering impaired, guarantee that whole laid processes is smooth, and time saving and energy saving pay off rack.

Described a kind of pay off rack that is used for the cable duct cabling is formed by being embedded in the cable tube cylinder type hollow steel pipe, A-frame and hauling block, A-frame is by the end welding of angle steel and cylinder type hollow steel pipe, hauling block is by being bolted on the A-frame, and over against the mouth of pipe of hollow steel pipe.

The beneficial effects of the utility model:

1. accelerate the progress of pipeline laying, fulfiled construction task ahead of schedule, avoided meeting the heavy-duty service of city net heavy-haul line during the kurtosis summer;

2. in the cable laying engineering,, alleviated workmen's labour intensity, reduced the amount of labour used, shortened the construction period, saved cost by application to the cable pay off rack;

The utility model both can be provided with conduit entrance, played the effect that trailing cable enters cable tube, can also be arranged on pipe outlet, made things convenient for the discrepancy of cable, avoided cable and pipeline friction, and caused cable covering impaired; Make whole laid processes time saving and energy saving, reduce cost.

Description of drawings:

Fig. 1 is a structural representation of the present utility model;

Fig. 2 is user mode figure of the present utility model.

Among the figure: the 1-hollow steel pipe, the 2-A-frame, the 3-hauling block, the 4-bolt, the 5-cable tube, 6-pull rope, 7-are crossed the line pulley, the 8-rope sling, the 9-cable, 10-twists mill.

Embodiment:

The utility model is described in further detail below in conjunction with accompanying drawing.Among Fig. 1, described a kind of pay off rack that is used for the cable duct cabling is formed by being embedded in cable tube 5 interior cylinder type hollow steel pipes 1, A-frame 2 and hauling block 3, A-frame 2 is by the end welding of angle steel and cylinder type hollow steel pipe 1, hauling block 3 is fixed on the A-frame 2 by bolt 4, and over against the mouth of pipe of hollow steel pipe 1.

Hollow steel pipe 1 can mate according to the cable caliber, can be embedded in the cable tube 5 and closely connection of realization, the model of hauling block 3 is directly mated according to the steel wire rope yarn of trailing cable, and hauling block 3 usefulness bolts 4 fix, can conveniently take off, directly change according to the steel wire rope yarn and change.

When needing the exhibition payout, as Fig. 2, near an end of strand mill a pay off rack that is used to draw is installed at cable tube 5, the pay off rack that was used for line in the other end installation one of cable tube 5, the frame pin of the A-frame 2 of two pay off racks all up, on whole laying-out, be provided with a plurality of line pulleys 7 of crossing, cable 9 enters the cable tube 5 from the hauling block 3 of crossing the anti-coil holder of line by the pull rope 6 of traction end, and pass and draw the hauling block 3 of preventing coil holder, passed line pulley 7 again, and closely be connected with cable on being fixed on strand mill 10 by rope sling 8; After strand mill 10 drive pull ropes are stressed, cable 9 can be thereupon towards moved by force direction, when cable 9 is come a side pipe mouth, cross line pulley 7 and cable 9 can be controlled at an angle with rational, and enter cable duct alleviating under the condition of resistance, because we have placed lubricant in the cable tube 9, so cable 9 can slide in pipeline smoothly, pull rope 6 has reduced resistance by hauling block 3 in this process, and makes cable stressed evenly, smoothly cable is pulled out another mouth of pipe of pipeline.

Let slip in the journey cable pay off rack in the exhibition of whole cable and can be close together with the cable furrow bank after stressed, A-frame 2 can control its do not produce slip, so pay off rack can be highly stable, pay off rack makes cable 9 smoothly by pipeline, and is not subjected to any injury.

Claims (1)

1. pay off rack that is used for the cable duct cabling, it is characterized in that: described pay off rack is formed by being embedded in the interior cylinder type hollow steel pipe of cable tube (5) (1), A-frame (2) and hauling block (3), A-frame (2) is by the end welding of angle steel and cylinder type hollow steel pipe (1), hauling block (3) is fixed on the A-frame (2) by bolt (4), and over against the mouth of pipe of hollow steel pipe (1).
CN2010206492897U 2010-12-09 2010-12-09 Cable-releasing stand for cabling in cable channel CN201937208U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206492897U CN201937208U (en) 2010-12-09 2010-12-09 Cable-releasing stand for cabling in cable channel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206492897U CN201937208U (en) 2010-12-09 2010-12-09 Cable-releasing stand for cabling in cable channel

Publications (1)

Publication Number Publication Date
CN201937208U true CN201937208U (en) 2011-08-17

Family

ID=44448717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206492897U CN201937208U (en) 2010-12-09 2010-12-09 Cable-releasing stand for cabling in cable channel

Country Status (1)

Country Link
CN (1) CN201937208U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102856842A (en) * 2012-09-27 2013-01-02 国家电网公司 Sleeved cable laying pulley bracket
CN105071292A (en) * 2015-08-10 2015-11-18 中铁武汉电气化局集团第一工程有限公司 Huge mountain area high-voltage power cable laying method and steering pulley device
CN107086532A (en) * 2017-06-16 2017-08-22 北京城建北方设备安装有限责任公司 Pipeline opening cable laying device
CN107302206A (en) * 2017-06-16 2017-10-27 北京城建北方设备安装有限责任公司 The auxiliary mould of cable laying
CN108258620A (en) * 2018-01-18 2018-07-06 深圳市龙供供电服务有限公司 The cable construction method of cable shaft
CN110474257A (en) * 2019-07-23 2019-11-19 河南帝禾建设工程有限公司 Pipeline inner cable laying method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102856842A (en) * 2012-09-27 2013-01-02 国家电网公司 Sleeved cable laying pulley bracket
CN105071292A (en) * 2015-08-10 2015-11-18 中铁武汉电气化局集团第一工程有限公司 Huge mountain area high-voltage power cable laying method and steering pulley device
CN107086532A (en) * 2017-06-16 2017-08-22 北京城建北方设备安装有限责任公司 Pipeline opening cable laying device
CN107302206A (en) * 2017-06-16 2017-10-27 北京城建北方设备安装有限责任公司 The auxiliary mould of cable laying
CN108258620A (en) * 2018-01-18 2018-07-06 深圳市龙供供电服务有限公司 The cable construction method of cable shaft
CN110474257A (en) * 2019-07-23 2019-11-19 河南帝禾建设工程有限公司 Pipeline inner cable laying method

Similar Documents

Publication Publication Date Title
CN104260826B (en) A kind of tensile test system and method for pipe laying barge
CN201501729U (en) Air turning device of equipment
CN101969183B (en) Saddle-type line-lifting device and construction method thereof
CN201458596U (en) Crane with self-dismounting device
CN102733768B (en) Continuous pipeline tripping device
CN101769131B (en) Conveying mechanism used for oil drilling
CN204897040U (en) Automatic car that receive and releases of optical cable
CN106451242B (en) The carrying method of underground cable conveying device
CN105896398B (en) A kind of electric cable with large cross-section laying method
US20160130108A1 (en) Device and method for winding and unwinding a parallel wire strand horizontally
CN102290742B (en) Tension stringing construction technology
CN102354926A (en) Large-section conductor tension stringing construction method
CN100440660C (en) Mechanical laying method for overlength large section cable
CN103633583B (en) Bridge running line method under cable based on combined type running line cage
CN204913181U (en) Big pipe diameter pipe welding is with butt joint adjusting device
CN204737624U (en) Hoist wire rope anti -swing system
US7712726B1 (en) Machine for pulling wire through a conduit
CN206645744U (en) There is the hoist engine of solidus adjustment function under without stress
CN103241586B (en) Under shed telpher and cable installatition construction method
CN202799819U (en) Reel type electric translational sprinkling machine
CN104671137A (en) Retractable towing winch of submarine cable embedding machine
CN102815627A (en) Automatic traction system for large-scale tower-type crane standard-knot removal and installation
CN204140004U (en) A kind of continuous oil pipe operation equipment
CN201664895U (en) Winding device for binding pulling wires
CN206083314U (en) Towed conduit clean device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20121214

Address after: 436000 power distribution management, Room 303, Ezhou power supply company, 16 situ Road, Hubei, Ezhou

Patentee after: Power distribution center of Ezhou power company

Patentee after: State Grid Corporation of China

Address before: 436000 power distribution management, Room 303, Ezhou power supply company, 16 situ Road, Hubei, Ezhou

Patentee before: Power distribution center of Ezhou power company

Effective date of registration: 20121214

Address after: 436000 power distribution management, Room 303, Ezhou power supply company, 16 situ Road, Hubei, Ezhou

Patentee after: Power distribution center of Ezhou power company

Patentee after: State Grid Corporation of China

Address before: 436000 power distribution management, Room 303, Ezhou power supply company, 16 situ Road, Hubei, Ezhou

Patentee before: Power distribution center of Ezhou power company

C41 Transfer of patent application or patent right or utility model
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Effective date: 20121214

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110817

Termination date: 20181209