CN201933370U - Compressing device for construction of ballastless track plate - Google Patents

Compressing device for construction of ballastless track plate Download PDF

Info

Publication number
CN201933370U
CN201933370U CN2011200081636U CN201120008163U CN201933370U CN 201933370 U CN201933370 U CN 201933370U CN 2011200081636 U CN2011200081636 U CN 2011200081636U CN 201120008163 U CN201120008163 U CN 201120008163U CN 201933370 U CN201933370 U CN 201933370U
Authority
CN
China
Prior art keywords
hold down
down gag
fragments
crossbeam
track slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011200081636U
Other languages
Chinese (zh)
Inventor
唐文喜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Original Assignee
Fourth Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd filed Critical Fourth Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Priority to CN2011200081636U priority Critical patent/CN201933370U/en
Application granted granted Critical
Publication of CN201933370U publication Critical patent/CN201933370U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a compressing device for construction of a ballastless track plate, which comprises an L-shaped steel frame, a reinforcing steel bar with external threads and a nut matched with the reinforcing steel bar, wherein the L-shaped steel frame consists of a cross beam and a support beam which are vertical to each other; and a vertical through slot is arranged on the cross beam for the reinforcing steel bar to pass through. Through the compressing function of the cross beam and the tensioning function of the reinforcing steel bar, the displacement of the track plate is limited in the vertical direction, the track plate is ensured not to float in the mortar filling process after fine adjustment, and the construction precision is ensured.

Description

The fragments-free track slab construction hold down gag
Technical field
The utility model relates to a kind of fragment-free track slab pavement construction equipment, is specifically related to a kind of fragments-free track slab construction hold down gag.
Background technology
Special line for passenger trains non-fragment orbit structure mainly is made up of three parts from top to bottom: track plate, sacked cement emulsified asphalt slurry and concrete bed.In the track slab pavement process, at first accurately be placed on the track plate on the precalculated position with the track slab precision adjustment device, cement injection emulsified asphalt slurry in the infusion bag that between track plate and concrete bed, places in advance then, in filling process, thereby the constraint that is subjected to infusion bag and upper rail guidance tape around the mortar causes track plate come-up, and the location that influences track plate in the vertical direction is accurate.
Therefore, need to explore a kind of hold down gag, guarantee that the track plate after the accurate adjustment is non-rising when mortar injection, guarantee construction precision.
Summary of the invention
In view of this, the purpose of this utility model is to provide a kind of fragments-free track slab construction hold down gag, can limit the displacement of track plate in the vertical direction, guarantees that the track plate after the accurate adjustment is non-rising when mortar injection, guarantees construction precision.
Fragments-free track slab construction hold down gag of the present utility model, comprise L shaped steelframe, be with externally threaded reinforcing bar and with the screw thread steel nut engaged, described L shaped steelframe is made up of orthogonal crossbeam and brace summer, has the vertical groove that passes for reinforcing bar on the crossbeam.
Further, described brace summer is connected with the horizontal base seat board away from an end end of crossbeam;
Further, described L shaped steelframe and horizontal base seat board are made by channel-section steel;
Further, described vertical groove extends along the crossbeam length direction;
Further, described nut one end is connected with the circular metal backing plate, and the diameter of circular metal backing plate is greater than the groove width of vertical groove;
Further, described nut is a wing nut, is symmetrically connected with two wing bars on its outer wall.
The beneficial effects of the utility model are: in the track slab construction process, after track slab precision adjustment finishes, reinforcing bar is anchored on the concrete bed, and the reinforcing bar that anchoring is finished is in plumbness, after making reinforcing bar pass the vertical groove of L shaped steelframe then, vertically place L shaped steelframe, the crossbeam of L shaped steelframe is closely contacted with the track plate, and brace summer or horizontal base seat board are supported on the concrete bed, overlap top nut at last on reinforcing bar, screw nut, promptly finish the installation of hold down gag, the cement emulsified asphalt mortar perfusion is finished, and mortar expansion is finished, after mortar strength reaches 2MPa, can remove hold down gag; The utility model has limited the displacement of track plate in the vertical direction by the pressuring action of crossbeam and the tension effect of reinforcing bar, guarantees that the track plate after the accurate adjustment is non-rising when mortar injection, has guaranteed construction precision.
Description of drawings
In order to make the purpose of this utility model, technical scheme and advantage clearer, below in conjunction with accompanying drawing the utility model is described in further detail, wherein:
Fig. 1 is a front view of the present utility model;
Fig. 2 is a vertical view of the present utility model.
The specific embodiment
Fig. 1 is a front view of the present utility model, and Fig. 2 is a vertical view of the present utility model; As shown in the figure, fragments-free track slab construction hold down gag of the present utility model, comprise L shaped steelframe, with externally threaded reinforcing bar 1 and with the nut 2 of reinforcing bar 1 threaded engagement, described L shaped steelframe is made up of orthogonal crossbeam 3 and brace summer 4, has the vertical groove 5 that passes for reinforcing bar 1 on the crossbeam 3.
As further improvement of the utility model, described brace summer 4 is connected with horizontal base seat board 6 away from an end end of crossbeam 3; Usage level bed plate 6 is supported on the concrete bed 9, and horizontal base seat board 6 is bigger with the contact surface of concrete bed 9, makes the utility model more firm.
As further improvement of the utility model, described L shaped steelframe and horizontal base seat board 6 are made by channel-section steel; Horizontal base seat board 6 can be made by a channel-section steel, and brace summer 4 also can be made by a channel-section steel; Crossbeam 3 is welded by two blocks of relative channel-section steels, reserves certain distance between them, is vertical groove 5; Use the channel-section steel to be base material, material is simple and easy to, and is easy to make.
As further improvement of the utility model, described vertical groove 5 extends along crossbeam 3 length directions; Vertically groove 5 extends along crossbeam 3 length directions, and flute length is longer, and reinforcing bar 1 can be in move left and right in the vertical groove 5, to regulate the contact length of crossbeam 3 and track plate 11.
As further improvement of the utility model, described nut 2 one ends are connected with circular metal backing plate 7, and the diameter of circular metal backing plate 7 is greater than the groove width of vertical groove 5; Circular metal backing plate 7 has increased the contact area of nut 2 with crossbeam 3, has strengthened fastening force.
As further improvement of the utility model, described nut 2 is a wing nut, is symmetrically connected with two wing bars 8 on its outer wall; When turning wing nut, convenient laborsaving.
In the track slab construction process, after 11 accurate adjustments of track plate finish, reinforcing bar 1 is anchored at (anchorage depth should be 100 ~ 150mm on the concrete bed 9, use epoxy resin to fix), and the reinforcing bar 1 that anchoring is finished is in plumbness, after making reinforcing bar 1 pass the vertical groove 5 of L shaped steelframe then, vertically place L shaped steelframe, the crossbeam 3 of L shaped steelframe is closely contacted with track plate 11, horizontal base seat board 6 is supported on the concrete bed 9, the last nut 2 that puts band circular metal backing plate 7 on reinforcing bar 1 screws nut 2, promptly finishes the installation of hold down gag, cement emulsified asphalt mortar 10 perfusions are finished, mortar 10 expands and finishes, and after mortar 10 intensity reach 2MPa, can remove hold down gag; The utility model has limited the displacement of track plate 11 in the vertical directions by the pressuring action of crossbeam 3 and the tension effect of reinforcing bar 1, guarantees that the track plate 11 after the accurate adjustment is non-rising when mortar 10 perfusions, has guaranteed construction precision.
Explanation is at last, above embodiment is only unrestricted in order to the explanation the technical solution of the utility model, although by the utility model being described with reference to preferred embodiment of the present utility model, but those of ordinary skill in the art is to be understood that, can make various changes to it in the form and details, and the spirit and scope of the present utility model that do not depart from appended claims and limited.

Claims (6)

1. fragments-free track slab construction hold down gag, it is characterized in that: comprise L shaped steelframe, be with externally threaded reinforcing bar and with the screw thread steel nut engaged, described L shaped steelframe is made up of orthogonal crossbeam and brace summer, has the vertical groove that passes for reinforcing bar on the crossbeam.
2. fragments-free track slab construction hold down gag according to claim 1 is characterized in that: described brace summer is connected with the horizontal base seat board away from an end end of crossbeam.
3. fragments-free track slab construction hold down gag according to claim 2 is characterized in that: described L shaped steelframe and horizontal base seat board are made by channel-section steel.
4. fragments-free track slab construction hold down gag according to claim 1 is characterized in that: described vertical groove extends along the crossbeam length direction.
5. according to any described fragments-free track slab construction hold down gag of claim 1 to 4, it is characterized in that: described nut one end is connected with the circular metal backing plate, and the diameter of circular metal backing plate is greater than the groove width of vertical groove.
6. according to any described fragments-free track slab construction hold down gag of claim 1 to 4, it is characterized in that: described nut is a wing nut, is symmetrically connected with two wing bars on its outer wall.
CN2011200081636U 2011-01-12 2011-01-12 Compressing device for construction of ballastless track plate Expired - Fee Related CN201933370U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200081636U CN201933370U (en) 2011-01-12 2011-01-12 Compressing device for construction of ballastless track plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200081636U CN201933370U (en) 2011-01-12 2011-01-12 Compressing device for construction of ballastless track plate

Publications (1)

Publication Number Publication Date
CN201933370U true CN201933370U (en) 2011-08-17

Family

ID=44444898

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200081636U Expired - Fee Related CN201933370U (en) 2011-01-12 2011-01-12 Compressing device for construction of ballastless track plate

Country Status (1)

Country Link
CN (1) CN201933370U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103362042A (en) * 2012-04-04 2013-10-23 中铁十一局集团第一工程有限公司 Concrete elevation gradient controller
CN103669131A (en) * 2012-09-24 2014-03-26 中铁十九局集团第二工程有限公司 Plate pressing device
CN108978371A (en) * 2018-08-23 2018-12-11 中国五冶集团有限公司 Track plates pressing device and track plates compress construction method
CN109267434A (en) * 2018-10-18 2019-01-25 中南大学 A kind of fragment-free track slab is Z-shaped to withhold stabilising arrangement
CN110616596A (en) * 2019-09-25 2019-12-27 长兴科腾实业有限公司 Positioning and adjusting device used in support of track pad
CN113338092A (en) * 2021-06-21 2021-09-03 湖北木之君工程材料有限公司 Method for repairing damage of ballastless track filling layer

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103362042A (en) * 2012-04-04 2013-10-23 中铁十一局集团第一工程有限公司 Concrete elevation gradient controller
CN103362042B (en) * 2012-04-04 2015-08-26 中铁十一局集团第一工程有限公司 A kind of concrete elevation gradient controller
CN103669131A (en) * 2012-09-24 2014-03-26 中铁十九局集团第二工程有限公司 Plate pressing device
CN108978371A (en) * 2018-08-23 2018-12-11 中国五冶集团有限公司 Track plates pressing device and track plates compress construction method
CN109267434A (en) * 2018-10-18 2019-01-25 中南大学 A kind of fragment-free track slab is Z-shaped to withhold stabilising arrangement
CN110616596A (en) * 2019-09-25 2019-12-27 长兴科腾实业有限公司 Positioning and adjusting device used in support of track pad
CN113338092A (en) * 2021-06-21 2021-09-03 湖北木之君工程材料有限公司 Method for repairing damage of ballastless track filling layer

Similar Documents

Publication Publication Date Title
CN201933370U (en) Compressing device for construction of ballastless track plate
CN101413249B (en) Method for positioning and mounting large-scale bridge support
CN202390730U (en) Fine adjustment device for mounting a track
CN103267508A (en) Flatness detection gauge of non-ballasted track roadbed slab, and detection method
CN204570492U (en) Cable stayed bridge cable guide pipe detent mechanism
CN202705826U (en) Top face elevation controller of plate-type ballastless track base plate
CN206591407U (en) A kind of skirt piles positioner constructed for roadbed, pavement engineering
CN104594143A (en) Inner supporting type screw adjuster and track skeleton positioning method
CN111364296B (en) Rail fastener for track traffic
CN204343116U (en) Inner supporting type screw regulator
CN104141264A (en) Plate-type ballastless track laying precision keeping method
CN107653756B (en) A kind of city rail U-type groove plate-type ballastless railway roadbed track plates bearing adjuster and its application method
CN202688802U (en) Slab limiting device for construction of slab ballastless track curved section
CN201660815U (en) Ballastless track plate construction floating-prevention and side-drifting limiting stopper
CN206887652U (en) A kind of support body for improving ballastless track bed section of track framework coarse adjustment precision
CN201144377Y (en) Straight line-shaped temporary fixing rack
CN201679232U (en) Adjustable support template mandril
CN203007752U (en) Ballastless road bed template fixed device
CN205276077U (en) A erection bracing foot device for moderate -low speed magnetic levitation switch buttress
CN203866657U (en) Internal support frame track panel frame used for narrow ballast bed ballastless track laying
CN201151859Y (en) Feet of double block type ballastless track construction equipment
CN101280542A (en) Coal mine narrow gauge railway monolithic road-bed
CN201593145U (en) Flotation limiter for construction pits of ballastless track plate
CN202730563U (en) Compressing and edge-sealing device for construction of ballastless track
CN204163356U (en) A kind of equipment installing inner wall panel

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110817

Termination date: 20200112