CN201924365U - Steel sheet pile and tube pile combined foundation ditch supporting structure - Google Patents

Steel sheet pile and tube pile combined foundation ditch supporting structure Download PDF

Info

Publication number
CN201924365U
CN201924365U CN2011200130863U CN201120013086U CN201924365U CN 201924365 U CN201924365 U CN 201924365U CN 2011200130863 U CN2011200130863 U CN 2011200130863U CN 201120013086 U CN201120013086 U CN 201120013086U CN 201924365 U CN201924365 U CN 201924365U
Authority
CN
China
Prior art keywords
pile
steel sheet
foundation ditch
sheet pile
row
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011200130863U
Other languages
Chinese (zh)
Inventor
李仁民
方磊
龚文宗
李青苗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Original Assignee
Southeast University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University filed Critical Southeast University
Priority to CN2011200130863U priority Critical patent/CN201924365U/en
Application granted granted Critical
Publication of CN201924365U publication Critical patent/CN201924365U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Revetment (AREA)

Abstract

The utility model discloses a steel sheet pile and tube pile combined foundation ditch supporting structure, which relates to a steel sheet pile and prestressed tube pile combined foundation ditch supporting structure, and belongs to the technical field of geotechnical engineering. The structure comprises wall rear earth surface parallel with the earth surface, and a foundation ditch bottom; front row steel sheet pipes and rear row prestressed tube piles are longitudinally distributed between the wall rear earth surface and the foundation ditch bottom in parallel; front row pile ring beams are distributed at upper ends of the front row steel sheet pipes; rear row pile ring beams are distributed at upper ends of the rear row prestressed tube piles; and front and rear line pile connecting beams are arranged between the front row pile ring beams and the rear row prestressed tube piles. The structure realizes the purposes that the structure is simple, the construction process is convenient and rapid, the structure is applicable to soft soil and various soil conditions, and the cost is saved.

Description

A kind of steel sheet pile pile tube combined foundation ditch support structure
Technical field
The utility model relates to a kind of steel sheet pile and pile for prestressed pipe combined foundation ditch support structure and job practices thereof, belongs to the technical field of geotechnical engineering.
Background technology
Retaining Structure with Double-row Piles is meant the parallel stake of two rows is set in foundation soil, two campshed pile bodies rectangular or quincuncial arrangement in front and back is provided with collar tie beam on two campsheds top, and connects with the contact beam, along hole wall parallel direction, form door figure space structure, be the space statically-indeterminate structure, integral rigidity is big, can effectively limit foundation pit deformation, under external load effect complicated and changeable, can adjust the internal force of supporting and protection structure itself automatically, make it to adapt to complicated and often unpredicted loading condition.
Traditional double-row pile generally adopts bored pile.Bored pile has the bearing capacity height, can passing through various soil property complexity or soft or hard, to change big soil layer (as the rock stratum of all kinds of cohesive soils, sand, crushed gravel soil, decomposed rock and many interlayers), construction technology ripe and to advantages such as the surrounding buildings influence are little.But bored pile has, and construction link is more, technical requirements is high, technology is complicated, construction and shortcomings such as curing time length, cost height.
Steel sheet pile as a kind of building material in the bridge construction cofferdam, large-scale pipeline lays, the retaining soil of interim irrigation canals and ditches excavation, dash, the husky wall harbour of retaining, the unloading apron revetment plays a significant role on the engineerings such as retaining wall levee revetment.Steel sheet pile does that the cofferdam is not only green, environmental protection but also speed of application is fast, operating expenses is low, has good water-proof function.In pattern foundation pit supporting structure, also progressively begin in recent years to use.But in general, steel sheet pile supporting and protection structure belongs to the flexible support structure, is out of shape relative campshed supporting and protection structure and wants big.
Prestressed concrete pipe pile is to use more a kind of preformed pile type since late 1980s in China.Advantages such as technology is simple because this type has, reliable in quality, speed of application is fast, cost is lower, easy to detect, thereby in the engineering piles on basis, obtained using quite widely.But pile for prestressed pipe is used less in foundation pit supporting construction because the relative bored pile of anti-horizontal loading is low.
Summary of the invention
The utility model purpose provides a kind of simple in structure, and work progress is simple and efficient, is applicable to weak soil and various soil condition, saves the steel sheet pile pile tube combined foundation ditch support structure of cost.
A kind of steel sheet pile pile tube combined foundation ditch support structure, comprise at the bottom of the face of land behind the wall parallel, the foundation ditch with the face of land, behind the wall at the bottom of the foundation ditch of the face of land between parallel longitudinal arrange front-seat steel sheet pile, back row's pile for prestressed pipe, campshed collar tie beam before the upper end of front-seat steel sheet pile is arranged, the upper end cloth postpone campshed collar tie beam of back row's pile for prestressed pipe, campshed contact beam before and after being provided with between preceding campshed collar tie beam, the back campshed collar tie beam.
The supporting method of steel sheet pile pile tube combined foundation ditch support structure of the present utility model comprises the steps:
The first step: according to site condition and computational analysis, determine front-seat steel sheet pile and back row's pile for prestressed pipe combined foundation ditch support structure, comprise that spacing and array pitch between the pile for prestressed pipe are arranged in the long and front-seat steel sheet pile of stake, a back long, back row's pile for prestressed pipe of front-seat steel sheet pile;
Second step: the front-seat steel sheet pile of constructing;
The 3rd step: arrange pile for prestressed pipe after adopting static pressure construction;
The 4th step: campshed collar tie beam, back campshed collar tie beam and front and back campshed are got in touch beam before the construction respectively;
The 5th step: excavation pit;
The 6th step:, build bed course, construction base plate and agent structure to clearing up, flatten in the end, foundation ditch hole;
The 7th step: backfill, campshed collar tie beam, back campshed collar tie beam and front and back campshed contact beam are extracted steel sheet pile before removing.
The utility model adopts technique scheme, and compared with prior art have following advantage: steel sheet pile of the present utility model can be used as supporting and protection structure, also can be used as water-stop curtain simultaneously, does not have the native problem of stream between stake, is applicable to weak soil and various soil condition; Form space truss structure together with back row's pile for prestressed pipe, integral rigidity is big, can effectively control foundation pit deformation, reduces the pile body moment of flexure.Steel sheet pile and prestressing pipe pile construction simple and fast, easy to control the quality can reclaim behind the steel sheet pile construction, recycle environmental protection.
Description of drawings
Fig. 1 is a kind of structural representation of the present utility model.
The specific embodiment
Below in conjunction with accompanying drawing the technical solution of the utility model is elaborated:
As shown in Figure 1, a kind of steel sheet pile pile tube combined foundation ditch support structure, comprise at the bottom of the face of land 6 behind the wall parallel, the foundation ditch 7 with the face of land, behind the wall at the bottom of the face of land 6 and the foundation ditch between 7 parallel longitudinal arrange front-seat steel sheet pile 1, back row's pile for prestressed pipe 2, campshed collar tie beam 3 before the upper end of front-seat steel sheet pile 1 is arranged, the upper end cloth postpone campshed collar tie beam 4 of back row's pile for prestressed pipe 2, campshed contact beam 5 before and after being provided with between preceding campshed collar tie beam 3, the back campshed collar tie beam 4.
The supporting method of steel sheet pile pile tube combined foundation ditch support structure of the present utility model comprises the steps:
The first step: according to site condition and computational analysis, determine front-seat steel sheet pile and back row's pile for prestressed pipe combined foundation ditch support structure, comprise that spacing and array pitch between the pile for prestressed pipe 2 are arranged in the long and front-seat steel sheet pile 1 of stake, a back long, back row's pile for prestressed pipe 2 of front-seat steel sheet pile 1;
Second step: the front-seat steel sheet pile 1 of constructing;
The 3rd step: arrange pile for prestressed pipe 2 after adopting static pressure construction;
The 4th step: campshed collar tie beam 3, back campshed collar tie beam 4 and front and back campshed are got in touch beam 5 before the construction respectively;
The 5th step: excavation pit;
The 6th step:, build bed course, construction base plate and agent structure to clearing up, flatten in the end, foundation ditch hole;
The 7th step: backfill, campshed collar tie beam 3, back campshed collar tie beam 4 and front and back campshed contact beam 5 are extracted steel sheet pile before removing.
Front-seat steel sheet pile 1 of the present utility model adopts the steel sheet pile of solid matter snapping; Back row's pile for prestressed pipe 2 adopts pile for prestressed pipe, and the stake footpath is 400mm ~ 600mm, and pile spacing is generally 2.5 times of stake footpaths, and array pitch is generally 3~5 times of stake footpaths; Connect with the contact beam in the middle of two campsheds of front and back.The utility model may further comprise the steps: (a) according to site condition and computational analysis, determine front-seat steel sheet pile and back row's pile for prestressed pipe combined foundation ditch support structure, comprise the length of front-seat steel sheet pile, stake long and spacing, the array pitch etc. of back row's pile for prestressed pipe; (b) the front-seat steel sheet pile of constructing; (c) arrange pile for prestressed pipe behind the employing static pressure construction; (d) Guan Liang on construction campshed stake top and the contact beam between the campshed; (e) excavation pit; (f) end, foundation ditch hole, cleared up, flattens, build bed course, construction base plate and agent structure; (g) Guan Liang above the steel sheet pile is removed in backfill, extracts steel sheet pile.

Claims (1)

1. steel sheet pile and pile tube combined foundation ditch support structure, it is characterized in that: as the front-seat steel sheet pile (1) of supporting and protection structure and water-stop curtain, steel sheet pile (1) and back row's pile for prestressed pipe (2) are formed space truss structure by front-seat pile block collar beam (3), back campshed top beam (4) and front and rear row side pile cap beam (5).
CN2011200130863U 2011-01-17 2011-01-17 Steel sheet pile and tube pile combined foundation ditch supporting structure Expired - Fee Related CN201924365U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200130863U CN201924365U (en) 2011-01-17 2011-01-17 Steel sheet pile and tube pile combined foundation ditch supporting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200130863U CN201924365U (en) 2011-01-17 2011-01-17 Steel sheet pile and tube pile combined foundation ditch supporting structure

Publications (1)

Publication Number Publication Date
CN201924365U true CN201924365U (en) 2011-08-10

Family

ID=44428224

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200130863U Expired - Fee Related CN201924365U (en) 2011-01-17 2011-01-17 Steel sheet pile and tube pile combined foundation ditch supporting structure

Country Status (1)

Country Link
CN (1) CN201924365U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102116031A (en) * 2011-01-17 2011-07-06 东南大学 Steel sheet pile and tubular pile combined base pit supporting structure and supporting method thereof
CN103741685A (en) * 2014-01-24 2014-04-23 王立明 Prestressed concrete steel tube and corresponding prestressed concrete steel tube supporting structure
CN103866779A (en) * 2014-02-26 2014-06-18 镇海建设集团有限公司 Construction method of water stopping surrounding and protecting structure of soft soil foundation building foundation pit
CN104005421A (en) * 2014-05-23 2014-08-27 上海市水利工程设计研究院有限公司 Double-row pile foundation retaining wall combined with foundation pit support and construction method thereof
CN105696603A (en) * 2016-04-11 2016-06-22 中铁建大桥工程局集团第四工程有限公司 Truss supporting and steel sheet pile supporting device and method for deep excavation of trenches

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102116031A (en) * 2011-01-17 2011-07-06 东南大学 Steel sheet pile and tubular pile combined base pit supporting structure and supporting method thereof
CN103741685A (en) * 2014-01-24 2014-04-23 王立明 Prestressed concrete steel tube and corresponding prestressed concrete steel tube supporting structure
CN103741685B (en) * 2014-01-24 2015-12-09 王立明 Comprise the pre-stressed steel pipe concrete truss support structure of pre-stressed steel pipe concrete
CN103866779A (en) * 2014-02-26 2014-06-18 镇海建设集团有限公司 Construction method of water stopping surrounding and protecting structure of soft soil foundation building foundation pit
CN103866779B (en) * 2014-02-26 2016-01-13 黄吉永 A kind of construction method of sealing space enclosing structure of soft foundation building foundation pit
CN104005421A (en) * 2014-05-23 2014-08-27 上海市水利工程设计研究院有限公司 Double-row pile foundation retaining wall combined with foundation pit support and construction method thereof
CN105696603A (en) * 2016-04-11 2016-06-22 中铁建大桥工程局集团第四工程有限公司 Truss supporting and steel sheet pile supporting device and method for deep excavation of trenches

Similar Documents

Publication Publication Date Title
CN1837512B (en) Combined cofferdam of steel slab pile and steel pipe pile an method for manufacturing the same
CN102116031A (en) Steel sheet pile and tubular pile combined base pit supporting structure and supporting method thereof
CN202689008U (en) Supporting structure for double-row prefabricated high-strength concrete thin-walled steel pipe pile foundation pit
CN203768912U (en) Double prestressing force high-strength concrete rectangular pile foundation ditch supporting construction
CN201924365U (en) Steel sheet pile and tube pile combined foundation ditch supporting structure
CN102140798A (en) Steel sheet pile and tubular pile combined base pit supporting structure and supporting method therefor
CN104912082A (en) Inclined assembled double-row steel sheet pile foundation pit supporting structure and construction method thereof
CN102116030A (en) Combined bracing structure for foundation pit and construction method thereof
CN108661073A (en) A kind of barrier wall structure and its construction method
CN107700474A (en) A kind of existing construction foundation reinforcement means and campshed formula diaphram wall
CN105649000A (en) Back pressure backfilling shallow-buried excavation construction method for tunnel undercrossing gully
CN202689009U (en) Steel sheet pile and tubular pile combined foundation pit supporting structure
CN203096745U (en) Multi-row pile foundation pit supporting structure
CN208934002U (en) A kind of barrier wall structure
CN202559363U (en) Foundation pit supporting structure for underground diaphragm wall with steel structure
CN111622234B (en) Unloading type thin-wall box-type retaining wall supported by obliquely and vertically combined steel pipe pile and construction process
CN101285302B (en) Method for reinforcing caisson of concrete dam
CN112854144A (en) Construction structure of earth-rock dam on deep sludge layer and construction method thereof
CN204645058U (en) A kind ofly be provided with the H type Double-row-piles Structure adding core rotary churning pile
CN103088831A (en) Overall assembly-type double-row steel pile foundation pit supporting structure
CN204690681U (en) The building block of large swallow-tail form slope protection concrete
CN111424675A (en) Construction method of ultra-large pile spacing deep foundation pit supporting system
CN207419441U (en) A kind of campshed formula diaphram wall
CN102828534A (en) Inclination rectification reinforcing method for disaster damage diseased deep pile foundation building
CN115748601A (en) Dam leakage repairing method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110810

Termination date: 20160117

EXPY Termination of patent right or utility model