CN201713978U - Molded metal strip plate ceiling-connecting system - Google Patents

Molded metal strip plate ceiling-connecting system Download PDF

Info

Publication number
CN201713978U
CN201713978U CN2010202573471U CN201020257347U CN201713978U CN 201713978 U CN201713978 U CN 201713978U CN 2010202573471 U CN2010202573471 U CN 2010202573471U CN 201020257347 U CN201020257347 U CN 201020257347U CN 201713978 U CN201713978 U CN 201713978U
Authority
CN
China
Prior art keywords
keel
fixture block
metal batten
ceiling
metal strip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010202573471U
Other languages
Chinese (zh)
Inventor
裴健
江世贵
张永煜
薛伟朋
马承刚
刘朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jiushixing Jianan Design & Construction Co Ltd
TAIYUAN RAILWAY CONSTRUCTION Co Ltd ZHONGTIE 6-BUREAU GROUP
China Railway Sixth Group Co Ltd
Original Assignee
Beijing Jiushixing Jianan Design & Construction Co Ltd
TAIYUAN RAILWAY CONSTRUCTION Co Ltd ZHONGTIE 6-BUREAU GROUP
China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jiushixing Jianan Design & Construction Co Ltd, TAIYUAN RAILWAY CONSTRUCTION Co Ltd ZHONGTIE 6-BUREAU GROUP, China Railway Sixth Group Co Ltd filed Critical Beijing Jiushixing Jianan Design & Construction Co Ltd
Priority to CN2010202573471U priority Critical patent/CN201713978U/en
Application granted granted Critical
Publication of CN201713978U publication Critical patent/CN201713978U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to the field of ceiling construction, in particular to a molded metal strip plate ceiling-connecting system which solves the problems that the existing ceiling keel is heavy, and has low manufacturing precision, complex connection and low mounting speed and the like. The molded metal strip plate ceiling-connecting system comprises a main keel which is provided with a first positioning hole, and a hanging rod is arranged in the first positioning hole in a penetrating manner; the upper end of the hanging rod is fixed with the main keel, the lower end thereof is connected with a U-shaped keel, and the top surface thereof is provided with a second positioning hole; and side wings are connected at the bottom ends of two side surfaces of the U-shaped keel, and provided with mounting holes, the mounting holes are internally and respectively provided with elastic windproof clamping blocks which are distributed symmetrically along the center line, parallel to a metal strip plate clamping block of the U-shaped keel, and vertical to the U-shaped keel, one end of the metal strip plate clamping block is connected with the side wings, and wholly pressed below the side wings, and one end of the elastic windproof clamping block is connected with the side wings. The molded metal strip plate ceiling-connecting system can realize the stable and convenient connection with the steel structure system, and has the advantages of convenient and rapid mounting, high mounting quality, simple operation, high working efficiency and quick construction speed.

Description

Shaped metal batten suspended ceiling connecting system
Technical field
The utility model relates to the furred ceiling construction field, is specially a kind of shaped metal batten suspended ceiling connecting system.
Background technology
At present domestic in the railway system, just starting the upsurge that Large scale construction is transformed, railway stations at different levels all begin or plan to begin not have the construction transformation project of platform post awning.Awning furred ceiling outward appearance all adopts the metal batten gap design of Ministry of Railways's regulation, and aluminium sheet connected system and mounting technique have only constantly perfect and transformation could adapt to fast-developing at present construction situation.
The metal batten keel connected system of furred ceiling in the past, primary and secondary skeletal frame are all relatively heavier, and make that precision is not high, fabrication cycle is long, difficult quality guarantee; In the practice of construction, metal batten connects more loaded down with trivial details, and buckle speed is slow, and syndeton is unreliable, and do not have any draught exclusion device that prevents that metal batten from coming off, be difficult to satisfy at present large tracts of land furred ceiling construction high standard such as no platform post awning, work energetically the fast needs of doing the construction situation.Especially for some special engineerings, improvement projects such as station that normal operation uses, venue are arranged as ground, in furred ceiling construction, necessarily require to influence the normal use in place below it, scaffold is set up in inconvenience, and suspended ceiling connecting system in the past can't satisfy these requirements, because adopt traditional furred ceiling mode to construct, only the turnover material will pile with platform, not only the tissue difficulty of shelf work post, turnover material gives passenger transportation management's influence at station very big.Therefore development metal batten connected system, improvement system mounting technique exquisite, that finalize the design is to realize the key of furred ceiling quality, progress, safety, economic goal.
Summary of the invention
The utility model provides a kind of shaped metal batten suspended ceiling connecting system in order to solve relatively heavier, the problems such as the making precision is not high, connection is loaded down with trivial details, installation rate slow, bad adaptability of keel in the existing furred ceiling construction.
The utility model is to adopt following technical scheme to realize: a kind of shaped metal batten suspended ceiling connecting system, comprise and the fixing main joist of adjacent steel structure H shaped steel purlin bottom flange epithelium overlap joint, have first locating hole at interval on the main joist, run through in first locating hole that the screw suspension rod being set; The suspension rod upper end is fixed by nut with main joist, the U type keel that the lower end is connected with that Open Side Down and be arranged in parallel with main joist, the end face of U type keel has and corresponding second locating hole of first position of positioning hole at interval, and the suspension rod lower end is fixed in second locating hole by nut; The bottom, two sides of U type keel is connected with flank respectively, have the shaped metal batten installing hole on the flank at interval, be provided with along its center line symmetric arrangement in the installing hole and be parallel to the metal batten fixture block of U type keel, metal batten fixture block one end is connected with flank and integral body is suppressed in the flank below, also be provided with in the installing hole along its center line symmetric arrangement and perpendicular to the windproof fixture block of elasticity of U type keel, windproof fixture block one end of elasticity is connected with flank, and the windproof fixture block of elasticity is positioned at metal batten fixture block both sides.
Described U type keel are made of two sides and an end face, the flank of U type keel and bottom, two sides, installing hole on the flank, the windproof fixture block of metal batten fixture block and elasticity all can whole machine-shaping, constitute the distinctive windproof keel of the present invention (being also referred to as secondary joist of the present utility model), because the metal batten fixture block in the installing hole is positioned at different planes with flank, there is certain assemblage gap between the two, this assemblage gap almost equates with the thickness of metal batten, so can choose two metal batten fixture blocks of respective distance on the flank according to the width of shaped metal batten, utilize the metal batten fixture block of any two correspondences on the flank and the toughness of metal batten to fix with the bound edge of metal batten, metal batten is perpendicular to that windproof keel install, after installing and fixing, the windproof fixture block of elasticity in the respective metal batten fixture block outside can be pulled to vertical direction along the junction of itself and flank, further location reinforcement effect is played in the both sides of metal batten, make whole ceiling system can bear the wind-force of big grade.
First locating hole and second locating hole are the strip hole, can be convenient to arbitrarily adjust the position of suspension rod in locating hole, thereby realize the position adjustment between main joist and the U type keel.
Adopt structure design of the present utility model, can carry out firmly, be connected fast between H shaped steel purlin and main joist, main joist and windproof keel, windproof keel and the metal batten, the physical dimension that makes metal batten connect keel can be selected in any range, improved the buckle mode, solved the buckle speed that runs in the batten installation process slow, prevent the draught exclusion device problem that batten comes off, in a word, compared with prior art, the utlity model has following advantage:
1, suspended ceiling connecting system of the present utility model is applied in the furred ceiling installation, can realizes firm with steel structure system, the convenient connection, quick and easy for installation, economical and practical;
2, installation quality height reduces work high above the ground intensity, improves the safety factor grade, can effectively ensure the construction safety, safe in utilization of the existing work planes of special engineering such as station;
3, the syndeton between the primary and secondary skeletal frame after metal batten installs, can realize height, the function of directional trim in length and breadth quickly and easily by structures such as suspension rod and locating holes;
4, simple to operate, furred ceiling is quick and easy for installation, and the workman grasps easily, high efficiency, and speed of application is fast;
5, this furred ceiling connection system considered simultaneously on the furred ceiling face or below operating condition, therefore be convenient to maintenance;
Summary, the utility model reasonable in design, ingenious, simple for production, be used for the furred ceiling construction technique, can effectively improve the construction quality of engineering, reach economic, safety, purpose efficiently, being particularly useful for setting up construction such as equipment installation, the piping erection of scaffold or the scaffold building height is big, difficulty is big, expense is high furred ceiling operation, conditions of similarity, the space furred ceiling of large span and furred ceiling face top should have enough operating modes such as working space.
Description of drawings
Fig. 1 is a syndeton schematic diagram of the present utility model;
Fig. 2 is the lateral view of Fig. 1;
Fig. 3 is the structural representation of U type keel and flank thereof among Fig. 1;
Fig. 4 is the 1-1 sectional view of Fig. 3;
Fig. 5 is the 2-2 sectional view of Fig. 3;
Among the figure: 1-H shaped steel purlin; The 2-main joist; 3-first locating hole; The 4-suspension rod; The 5-nut; 6-U type keel; 7-second locating hole; The 8-flank; The 9-installing hole; 10-metal batten fixture block; The windproof fixture block of 11-elasticity; The 12-metal batten.
The specific embodiment
A kind of shaped metal batten suspended ceiling connecting system as shown in Figure 1, 2, comprises and the fixing main joist 2 of adjacent steel structure H shaped steel purlin 1 bottom flange epithelium overlap joint, has to run through in first locating hole, 3, the first locating holes 3 at interval on the main joist 2 screw suspension rod 4 is set; Suspension rod 4 upper ends and main joist 2 are fixing by nut 5, the U type keel 6 that the lower end is connected with that Open Side Down (being inverted U) and be arranged in parallel with main joist, the end face of U type keel 6 has and corresponding second locating hole 7 in first locating hole, 3 positions at interval, suspension rod 4 lower ends are fixed in second locating hole 7 by nut 5, and first locating hole 3 and second locating hole 7 are the strip hole; Shown in Fig. 3,4,5, the bottom, two sides of U type keel 6 is connected with flank 8 respectively, have shaped metal batten installing hole 9 on the flank 8 at interval, be provided with along its center line symmetric arrangement in the installing hole 9 and be parallel to the metal batten fixture block 10 of U type keel 6, metal batten fixture block one end is connected with flank and integral body is suppressed in the flank below, also be provided with in the installing hole 9 along its center line symmetric arrangement and perpendicular to the windproof fixture block 11 of the elasticity of U type keel 6, windproof fixture block 11 1 ends of elasticity are connected with flank, and the windproof fixture block 11 of elasticity is positioned at metal batten fixture block 10 both sides.
With the railway station awning is example, and it is as follows to adopt ceiling connecting structure of the present utility model to carry out the step of furred ceiling construction:
1, measurement and positioning unwrapping wire
According to furred ceiling design construction measurement scheme, according to the actual conditions at scene, each platform is established the major control line of 2 road parallel longitudinal lines (being parallel to line direction) as east-west direction, guarantees vertical straightness accuracy.According to former I road parallel lines, emit two control points of every axis on the ground, utilize total powerstation to project on the main couple, and make a mark with the red symbol pen, stride whenever then and hang up logical line.
Utilize and emit vertical control point on the ground, utilize the total powerstation horizontal direction to revolve and turn 90 degrees, project on the purlin, at the 1-2 of each platform axle, the 25-26 axle is respectively put horizontal (horizontal path) line, and makes a mark with the red symbol pen, as the foundation of the horizontal control of furred ceiling.With transit or total powerstation the coordinate control point is led on furred ceiling face structure or the keel.Laterally line, vertical hanging wire is determined control sideline, inclination angle and the absolute altitude of each bar (piece) ceiling board and keel.
The furred ceiling absolute altitude draws instruments such as establishing available non-prism total powerstation, laser range finder, level gauge.
2, primary and secondary skeletal frame is installed and is proofreaied and correct
Main joist is 40 * 4 galvanizing angle steel, the first long locating hole of 50mm is driven on one side of angle steel, the hole center distance is 150mm, and main joist requires to be welded in steel work purlin bottom flange epithelium, and spacing is 1 meter, length is according to the actual measurement of on-the-spot purlin spacing, with the effective lap length of i iron purlin greater than 80mm, the fillet weld both sides are elongated, face of weld adopts preservative treatment, angle steel is necessary for whole section, must not dock, overlap.U type keel add that two flanks constitute special windproof keel, and thickness is 1.0mm, the preservative treatment of surface black baking vanish, suspension rod is a M8 galvanizing screw rod, and the link of suspension rod and U type keel is fixed, the elongated mantle fiber of screw rod, the suspension rod theoretical length is 130-160mm, and the suspension rod spacing is 800mm.U type keel and suspension rod march into the arena and qualified by inspection after, assemble on ground, the end that suspension rod is fixing penetrates in second locating hole of holding successfully on the U type keel, the other end is tightened with nut, refills two nuts then, is used to lift being connected of back and main joist.After U type keel and suspension rod assembling are finished,, must there be two personal two ropes to winch to the top simultaneously from ground during lifting by manually lifting to awning from ground, the rope of lifting usefulness must be solid reliable, makes regular check on, and finds to have fracture of wire, phenomenons such as wearing and tearing are changed immediately.U type keel are installed after winching to the awning top, suspension rod are penetrated in first locating hole of accomplishing fluently on the main joist, adjust the keel height according to the absolute altitude line that truss two ends band is good, then double nut about screw rod and the main joist employing is fixedly tightened,
3, ceiling board vertical transport
Utilize rope that furred ceiling system is hung firmly forward to draw and hang work plane (keel below)
4, ceiling board fixed installation
Metal batten (on-gauge plate) amplifier that will have bound edge is to the correspondence position below, use nylon rope to winch on the awning, bound edge with metal batten is anchored in the installing hole of U type keel correspondence again, the bound edge and the corresponding metal batten mouth fixture block of metal batten are fixed, then the windproof fixture block of corresponding elasticity is depressed.
5, the metal batten adjustment is proofreaied and correct
Adjust correction with regulating the absolute altitude of bolt with metal batten, inclination angle, axis, skew, plate seam, planeness etc., make it to reach designing requirement.The principle of adjusting is: vertical hanging wire, and laterally horizontal sliding guarantees that the position of every block of plate and absolute altitude are accurate, and big face vertically becomes line, and plate stitches evenly, the requirement of planeness compliant.
Suspended ceiling connecting system described in the utility model is successful Application on multinomial actual engineering, has obtained significantly through benefit, and the utility model is enumerated following case history:
Case history one:
Station, Taiyuan 1-4 platform does not have post awning engineering in construction on December 25,26 days to 2008 November in 2008, the wherein about 32000m of platform shed furred ceiling area 2All platforms all are the operation passenger platform, electric locomotive traction, and the 27500W contact net is all charged, furred ceiling maximum height 13.8m, workload is big, operation danger, and the duration is tight, construction period is on the occasion of closing on spring transportation, train arrival ﹠ leaving density is big, and the volume of the flow of passengers is multiplied, and passenger's traffic can not be affected in the construction; Furred ceiling duration of a project pressure is huge, also must parallel flowing water construction with the platform construction organization that is carrying out simultaneously on preceding working procedure steel roof truss, purlin operation and part ground.If adopt traditional furred ceiling mode to construct, only turnover expects to pile with platform, and not only the tissue difficulty of shelf work post, turnover material gives passenger transportation management's influence at station very big.
Adopt shaped metal batten ceiling system described in the utility model and corresponding construction method of installation thereof to construct, and succeed.Realized the speed at the thousands of square meters of construction section day furred ceiling, 5 day time, 32000m are only used in the continuous construction of a platform furred ceiling operation 2Furred ceiling was all finished in 29 days, guaranteed finishing of total duration, acceptance of engineering quality is all qualified, and a routine security incident does not take place, and save more than 130 ten thousand yuan of cost direct costs, for having guaranteed that the station, Taiyuan normally runs the indirect value and the social benefit of generation and have more importantly meaning.
Case history two:
Station, Jiujiang reconstruction and extension project of Hot work in progress at present is that station, Jiujiang does not have platform post awning and is about 500 meters, and width is about (single platform) 17 meters, and the ceiling board construction area is about 60000 square meters, and furred ceiling adopts the inferior white aluminium alloy plate of 180/120 bar shaped, thickness of slab 1.0MM.Aluminium-plastic panel closing in construction area is about 6000 square meters, and material adopts the thick white aluminum veneer of 2.5MM.The absolute altitude of awning peak is about 19 meters, and the absolute altitude of minimum point is about 15 meters.Because job site complicated condition, abominable, the position of formal engineering is born the interim processing district of several units of taking part in building of underground construction substantially, the construction passage is occupied, can not rise shared place basically.
In order to change the passive situation of this no operatton face, guarantee that the node duration finishes on schedule, project management department has carried out detailed investigation to the influence factor at scene, and in conjunction with the construction experience of relevant works, adopt shaped metal batten ceiling system described in the utility model and corresponding construction method of installation thereof to construct, utilize a tangent space to carry out construction organization with all strength.Quality safety is controlled in order, has reached the duration target of expection, and has saved more than 240 ten thousand yuan of cost direct costs, has obtained obvious social and economic benefit.

Claims (2)

1. shaped metal batten suspended ceiling connecting system, it is characterized in that comprising and the fixing main joist (2) of adjacent steel structure H shaped steel purlin (1) bottom flange epithelium overlap joint, main joist (2) is gone up at interval and is had first locating hole (3), runs through in first locating hole (3) that screw suspension rod (4) being set; Suspension rod (4) upper end is fixing by nut (5) with main joist (2), the U type keel (6) that the lower end is connected with that Open Side Down and be arranged in parallel with main joist, the end face of U type keel (6) has and first locating hole (3) corresponding second locating hole in position (7) at interval, and suspension rod (4) lower end is fixed in second locating hole (7) by nut (5); The bottom, two sides of U type keel (6) is connected with flank (8) respectively, flank (8) is gone up and is had shaped metal batten installing hole (9) at interval, be provided with in the installing hole (9) along its center line symmetric arrangement, and the metal batten fixture block (10) that is parallel to U type keel (6), metal batten fixture block one end is connected with flank, and integral body is suppressed in the flank below, also be provided with in the installing hole (9) along its center line symmetric arrangement, and the windproof fixture block of elasticity (11) perpendicular to U type keel (6), windproof fixture block (11) one ends of elasticity are connected with flank, and the windproof fixture block of elasticity (11) is positioned at metal batten fixture block (10) both sides.
2. according to claims 1 described shaped metal batten suspended ceiling connecting system, it is characterized in that first locating hole (3) and second locating hole (7) are the strip hole.
CN2010202573471U 2010-07-10 2010-07-10 Molded metal strip plate ceiling-connecting system Expired - Lifetime CN201713978U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202573471U CN201713978U (en) 2010-07-10 2010-07-10 Molded metal strip plate ceiling-connecting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202573471U CN201713978U (en) 2010-07-10 2010-07-10 Molded metal strip plate ceiling-connecting system

Publications (1)

Publication Number Publication Date
CN201713978U true CN201713978U (en) 2011-01-19

Family

ID=43459977

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202573471U Expired - Lifetime CN201713978U (en) 2010-07-10 2010-07-10 Molded metal strip plate ceiling-connecting system

Country Status (1)

Country Link
CN (1) CN201713978U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101899879A (en) * 2010-07-10 2010-12-01 中铁六局集团有限公司 Shaped metal batten suspended ceiling connecting system
CN104632246A (en) * 2014-09-01 2015-05-20 北车建设工程有限责任公司 Large-span underground structure
CN109724784A (en) * 2018-12-28 2019-05-07 广东大粤新能源科技股份有限公司 A kind of screw thread tension force test method of photovoltaic board mounting structure
CN110485618A (en) * 2019-09-09 2019-11-22 苏州美瑞德建筑装饰有限公司 A kind of Fast Installation structure of Super High abnormity furred ceiling

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101899879A (en) * 2010-07-10 2010-12-01 中铁六局集团有限公司 Shaped metal batten suspended ceiling connecting system
CN101899879B (en) * 2010-07-10 2011-11-30 中铁六局集团有限公司 Shaped metal batten suspended ceiling connecting system
CN104632246A (en) * 2014-09-01 2015-05-20 北车建设工程有限责任公司 Large-span underground structure
CN109724784A (en) * 2018-12-28 2019-05-07 广东大粤新能源科技股份有限公司 A kind of screw thread tension force test method of photovoltaic board mounting structure
CN110485618A (en) * 2019-09-09 2019-11-22 苏州美瑞德建筑装饰有限公司 A kind of Fast Installation structure of Super High abnormity furred ceiling

Similar Documents

Publication Publication Date Title
CN104563494B (en) A kind of conversion support system for socket joint dish button steel tube frame and construction
CN202899016U (en) Arched steel truss bridge with slide rails
CN105804305B (en) Corrugated metal plate ceiling system and its installation method
CN204040464U (en) A kind of slab form supporting construction
CN201713978U (en) Molded metal strip plate ceiling-connecting system
CN204475846U (en) A kind of conversion support system for socket joint dish button steel tube frame
CN202578055U (en) Shed used for coke oven building construction and adjustable in height and width
CN110629691A (en) Totally-enclosed sound barrier structure for noise reduction engineering of high-speed railway
CN101899879B (en) Shaped metal batten suspended ceiling connecting system
CN203213372U (en) F-shaped hanging piece and suspended ceiling system employing same
CN216476308U (en) Vertical adjusting structure of template system
CN203222920U (en) Building block type steel truss dome structure of hydropower station
CN110965489A (en) Subway insertion type totally-enclosed sound barrier and construction method
CN211621284U (en) Subway insertion type totally-enclosed sound barrier
CN204959995U (en) Modular structure of room roof beam
CN203856069U (en) High-rise building steel structure
CN205637282U (en) Wave metal sheet furred ceiling
CN101775876A (en) Spacial steel roof truss
CN204960126U (en) A floor beam structure for villa
CN202899436U (en) B-type beam-column member
CN202323724U (en) Outer template
CN204959980U (en) Simple to operate's floor connection structure
CN205077615U (en) A floor outer wall lightweight steel construction for villa
CN207484299U (en) A kind of grade separation bridge steel structural shielding canopy
CN202187455U (en) Suspended-ceiling suspension device below a floor support plate in a steel structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20110119

Effective date of abandoning: 20111130