CN201705276U - Well completion and flow string of horizontal well - Google Patents

Well completion and flow string of horizontal well Download PDF

Info

Publication number
CN201705276U
CN201705276U CN2010202231900U CN201020223190U CN201705276U CN 201705276 U CN201705276 U CN 201705276U CN 2010202231900 U CN2010202231900 U CN 2010202231900U CN 201020223190 U CN201020223190 U CN 201020223190U CN 201705276 U CN201705276 U CN 201705276U
Authority
CN
China
Prior art keywords
sealing
intubate
iii
layering
drum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010202231900U
Other languages
Chinese (zh)
Inventor
齐月魁
单桂栋
刘长军
王晓梅
韩莉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dagang Oilfield Group Co Ltd
Original Assignee
Dagang Oilfield Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dagang Oilfield Group Co Ltd filed Critical Dagang Oilfield Group Co Ltd
Priority to CN2010202231900U priority Critical patent/CN201705276U/en
Application granted granted Critical
Publication of CN201705276U publication Critical patent/CN201705276U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to a well completion and flow string of a horizontal well and overcomes the defect that the open hole packer of a horizontal section cannot effectively pack an oil-water layer because the diameters of the well are irregular in the well completion construction of the open hole sand control screen pipe of the existing horizontal well. A well completion string is fixedly installed at the horizontal well section in an open hole shaft. The stage collar, the casing nipple, the external packer I, the blind plate, the casing, the layered seal bore I, the upper screen pipe, the layered seal bore II, the casing nipple, the external packer II, the casing, the external packer III, the casing nipple, the layered seal bore III, the lower screen pipe, the well cleaning valve, the lower screen pipe and the guide shoe of the well completion string are sequentially and fixedly connected. An acid cleaning string, top-sealed bottom-open string, bottom-sealed top-open string or commingling string is installed in the well completion string. The utility model has the advantages that since the well completion technology of the horizontal well is combined with the late-stage oil production technology, the segmental sealing effect between the well completion string and the open hole shaft is improved, the bottom water coning is delayed and the goals of controlling water and increasing oil are realized.

Description

The completion of horizontal well, flow string
Affiliated technical field
The utility model relates to a kind of horizontal well production tubing string, especially relates to a kind of completion, flow string of horizontal well, and this flow string is particularly suitable for the horizontal well production operation of limit bottom water reservoir.
Background technology
Along with the development of petroleum exploration and development technology, adopt the horizontal well technology development of fields, become effective technology means that improve oil recovery rate, well yield, exploitation remaining oil, reduce production cost per tone oil.Horizontal well is many based on the well cementation perforation completion at present, and the bottom water coning control water problems of horizontal segment can solve by shutoff in the pipe, optimum perforation technology; For the horizontal well with the limit bottom water reservoir, completion mode adopts the bare screen sand control completion usually, because the irregular effectively packing oil-water-layer of horizontal segment open hole packer that causes of hole diameter; After water content rose, conventional completion tubular column can't control effectively, and makes the horizontal well High-efficient Production increase difficulty.For the horizontal well completion that has the limit bottom water reservoir, the main packer that adopts is with two borders of water layer card envelope, the middle technology that connects with blind pipe, and is easy and simple to handle although this technology has, the advantage that cost is relatively low, in case but after the water outlet, because horizontal well does not have segmentation, it is all very difficult to implement machinery or chemical water shutoff, behind water exit interval of shutoff, end water can be very fast around arriving another interval, do not have too big effect to delaying bottom water coning, cause the limit bottom water coning, the failure of control water.
The utility model content
In order to overcome in the construction of existing level well bare screen sand control completion, because the irregular effectively packing oil-water-layer of horizontal well bore hole section packer that makes of hole diameter, cause the deficiency of limit bottom water coning, the failure of control water, the utility model provides a kind of completion, flow string of horizontal well.
The technical scheme that its technical problem that solves the utility model adopts is: the completion of horizontal well, flow string, net horizontal section have top oil reservoir, water layer, bottom oil reservoir, and the net horizontal section in uncased wellbore is installed with completion tubular column; The sizing collar of the sleeve pipe lower end of completion tubular column, casing nipple, external packer of pipe I, blind plate, sleeve pipe, layering sealing drum I, last screen casing, layering sealing drum II, casing nipple, external packer of pipe II, sleeve pipe, external packer of pipe III, casing nipple, layering sealing drum III, following screen casing, flushing valve, following screen casing, guide shoe are fixedly connected sequentially; The pickling tubing string is installed in the completion tubular column or seals up to adopt under lower tubular column or the envelope and adopt tubing string or close and adopt tubing string; The intubate of pickling tubing string lower end is inserted in the flushing valve; Adopt tubing string under sealing up and adopt lower tubular column, sealing, close the flushing valve top that the lower end of adopting tubing string is positioned at completion tubular column.The oil pipe of pickling tubing string, give up, oil pipe, packer, oil pipe, sealing intubate II, oil pipe, constant pressure valve, sealing intubate III, safety joint, oil pipe, ball-and-seat, perforated pipe, intubate be fixedly connected sequentially, intubate is inserted in the flushing valve; Packer is positioned at the last screen casing middle part of completion tubular column, sealing intubate II, sealing intubate III lay respectively in the layering sealing drum II, layering sealing drum III of completion tubular column, and sealing intubate II, sealing intubate III and layering sealing drum II, layering sealing drum III are interference fit.Seal up and adopt the giving up of lower tubular column, oil pipe, sealing intubate I, oil pipe, sealing intubate II, oil pipe, constant pressure valve, sealing intubate III, safety joint, perforated pipe, block head and be fixedly connected sequentially; Sealing intubate I, sealing intubate II, sealing intubate III lay respectively in the layering sealing drum I, layering sealing drum II, layering sealing drum III of completion tubular column, and sealing intubate I, sealing intubate II, sealing intubate III and layering sealing drum I, layering sealing drum II, layering sealing drum III are interference fit.Envelope is adopted down the giving up of tubing string, oil pipe, sealing intubate I, perforated pipe, sealing intubate II, oil pipe, constant pressure valve, sealing intubate III, safety joint, block head and is fixedly connected sequentially; Sealing intubate I, sealing intubate II, sealing intubate III lay respectively in the layering sealing drum I, layering sealing drum II, layering sealing drum III of completion tubular column, and sealing intubate I, sealing intubate II, sealing intubate III and layering sealing drum I, layering sealing drum II, layering sealing drum III are interference fit.Close and adopt the giving up of tubing string, oil pipe, sealing intubate I, perforated pipe, sealing intubate II, oil pipe, constant pressure valve, sealing intubate III, safety joint, perforated pipe, block head and be fixedly connected sequentially; Sealing intubate I, sealing intubate II, sealing intubate III lay respectively in the layering sealing drum I, layering sealing drum II, layering sealing drum III of completion tubular column, and sealing intubate I, sealing intubate II, sealing intubate III and layering sealing drum I, layering sealing drum II, layering sealing drum III are interference fit.
The beneficial effects of the utility model are, horizontal well completion tubular pile is combined with the later stage flow string,, improve segmented seal effect between completion tubular column and the uncased wellbore by the sealing between completion tubular column and the flow string, delay bottom water coning, realize the purpose of water-control oil-increasing.
Description of drawings
Fig. 1 is the completion of the utility model horizontal well, the completion tubular column schematic diagram of flow string.
Fig. 2 is the completion of the utility model horizontal well, the pickling working string schematic diagram of flow string.
Fig. 3 is that completion, the sealing up of flow string of the utility model horizontal well adopted the lower tubular column schematic diagram.
Fig. 4 adopts the tubing string schematic diagram under the envelope of completion, flow string of the utility model horizontal well.
Fig. 5 is that completion, the closing of flow string of the utility model horizontal well adopted the tubing string schematic diagram.
Among the figure: 1. sleeve pipe, 2. sizing collar, 3. casing nipple, 4. external packer of pipe I, 5. blind plate, 6. layering sealing drum I, 7. go up screen casing, 8. layering sealing drum II, 9. external packer of pipe II, 10. external packer of pipe III, 11. layering sealing drum III, 12. flushing valves, 13. guide shoe, 14. oil pipes, 15. give up, 16. sealing intubate I, 17. packers, 18. sealing intubate II, 19. constant pressure valve, 20. sealing intubate III, 21. safety joints, 22. ball-and-seat, 23. perforated pipes, 24. times screen casings, 25. the end plug, 26. intubate, 100. completion tubular columns, 101. the top oil reservoir, 102. water layers, 103. bottom oil reservoirs, 110. pickling tubing string, adopt lower tubular column 120. seal up, adopt tubing string under 130. envelopes, 140. close and adopt tubing string.
The specific embodiment
Be described further below in conjunction with completion, the flow string of drawings and Examples the utility model horizontal well.
The net horizontal section that the completion of the utility model horizontal well, flow string are positioned at has top oil reservoir 101, water layer 102, bottom oil reservoir 103.Net horizontal section in uncased wellbore is installed with completion tubular column 100 (referring to accompanying drawing 1); There are sizing collar 2, casing nipple 3, external packer of pipe I 4, blind plate 5, sleeve pipe 1, layering sealing drum I 6 in sleeve pipe 1 lower end of completion tubular column 100, upward screen casing 7, layering sealing drum II 8, casing nipple 3, external packer of pipe II 9, external packer of pipe III 10, casing nipple 3, layering sealing drum III 11, following screen casing 24, flushing valve 12, following screen casing 24, guide shoe 13 are fixedly connected sequentially; Above-mentioned parts can connect the sleeve pipe 1 that is uneven in length as required therein when connecting.External packer of pipe I 4 is in angle buildup interval, can be equipped with the quantity of external packer of pipe I 4 as required, and 2 external packer of pipe I 4 are installed usually.
The layering sealing drum I 6 of completion tubular column 100, layering sealing drum II 8, layering sealing drum III 11 are tubular, endoporus has the annular groove more than 1, seal is installed in the annular groove, and seal is an interference fit with the sealing intubate external surface that inserts wherein, forms sealing.Seal wherein is generally the rubber material.
The effect of completion tubular column 100 is that well bore is implemented well cementing operation, for next step pickling operation and separate zone production operation are got ready.
Pickling tubing string 110 is installed in the completion tubular column 100, seal up adopt lower tubular column 120, envelope is down adopted tubing string 130, is closed arbitrary tubing string of adopting in the tubing string 140; The intubate 26 of pickling tubing string 110 lower ends is inserted in the flushing valve 12; Adopt tubing string 130 under sealing up and adopt lower tubular column 120, sealing, close flushing valve 12 tops that the lower end of adopting tubing string 140 is positioned at completion tubular column 100.
The oil pipe 14 of pickling tubing string 110 (referring to accompanying drawing 2), give up 15, packer 17, sealing intubate II 18, constant pressure valve 19, sealing intubate III 20, safety joint 21, ball-and-seat 22, perforated pipe 23, intubate 26 be fixedly connected sequentially; Above-mentioned parts is when connecting, can connect the oil pipe 14 that is uneven in length as required therein, make packer 17 be positioned at last screen casing 7 middle parts or the top of completion tubular column 100, sealing intubate II 18, sealing intubate III 20 lay respectively in the layering sealing drum II 8, layering sealing drum III 11 of completion tubular column 100, and sealing intubate II 18, sealing intubate III 20 are interference fit with layering sealing drum II 8, layering sealing drum III 11.The packer 17 preferred olive shape packers of pickling tubing string 110, upper lifting pipe post when being convenient to sand plug.
The effect of pickling tubing string 110 is that well bore is carried out the pickling operation, and after the pickling operation was finished, external packer of pipe II 9, the external packer of pipe III 10 of the envelope completion tubular column 100 that expands were finished the work of packing oil-water-layer, and the producing well section is divided into upper and lower two sections.
Seal up adopt lower tubular column 120 (referring to accompanying drawing 3) give up 15, oil pipe 14, sealing intubate I 16, sealing intubate II 18, constant pressure valve 19, sealing intubate III 20, safety joint 21, perforated pipe 23, block head 25 be fixedly connected sequentially; Above-mentioned parts is when connecting, can connect the oil pipe 14 that is uneven in length as required therein, make sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 lay respectively in the layering sealing drum I 6 of completion tubular column 100, layering sealing drum II 8, the layering sealing drum III 11, sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 are interference fit with layering sealing drum I 6, layering sealing drum II 8, layering sealing drum III 11.
Envelope is adopted down giving up 15, oil pipe 14, sealing intubate I 16, perforated pipe 23, sealing intubate II 18, constant pressure valve 19, sealing intubate III 20, safety joint 21, block head 25 and be fixedly connected sequentially of tubing string 130 (referring to accompanying drawing 4); Above-mentioned parts is when connecting, can connect the oil pipe 14 that is uneven in length as required therein, make sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 lay respectively in the layering sealing drum I 6 of completion tubular column 100, layering sealing drum II 8, the layering sealing drum III 11, sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 are interference fit with layering sealing drum I 6, layering sealing drum II 8, layering sealing drum III 11.
Close adopt tubing string 140 (referring to accompanying drawing 5) give up 15, oil pipe 14, sealing intubate I 16, perforated pipe 23, sealing intubate II 18, constant pressure valve 19, sealing intubate III 20, safety joint 21, perforated pipe 23, block head 25 be fixedly connected sequentially; Above-mentioned parts is when connecting, can connect the oil pipe 14 that is uneven in length as required therein, make sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 lay respectively in the layering sealing drum I 6 of completion tubular column 100, layering sealing drum II 8, the layering sealing drum III 11, sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 are interference fit with layering sealing drum I 6, layering sealing drum II 8, layering sealing drum III 11.
Giving up in the utility model 15 given up for back-off; Safety joint 21 is disconnection sand washing safety joint.
When implementing to change layer operation, if appearring in the tubing string of oil reservoir part, sand buries situation, as long as the upper lifting pipe post is to rated value, disconnection sand washing safety joint 21 will be thrown off, with the tubing string proposition well head of disconnection sand washing safety joint more than 21.
Use the utility model horizontal well completion, flow string, at first with completion tubular column 100, pickling tubing string 110, seal up adopt lower tubular column 120, the envelope under adopt tubing string 130, close adopt tubing string 140 assemble respectively finish after, cement the well earlier, the pickling operation, carry out oil producing operation again, its step is as follows:
A, well cementation: at first completion tubular column 100 is lowered in the uncased wellbore, make score layer sealing drum I 6 be positioned at top oil reservoir 101 upper ends, layering sealing drum II 8 is positioned at top oil reservoir 101 and water layer 102 boundarys, and layering sealing drum III 11 is positioned at water layer 102 and bottom oil reservoir 103 boundarys; Last screen casing 7 is positioned at top oil reservoir 101, and following screen casing 24 is positioned at bottom oil reservoir 103; Then, setting pipe external packer I 4; Cementing well in the annular space of completion tubular column 100 and uncased wellbore again.
B, pickling: at first the blind plate in the completion tubular column 100 5 is bored and open; Pickling tubing string 110 is lowered in the completion tubular column 100, the intubate 26 of pickling tubing string 110 lower ends is inserted in the flushing valve 12 again; The packer 17 of pickling tubing string 110 is positioned at the middle part or the top of screen casing 7, and sealing intubate II 18, sealing intubate III 20 lay respectively in the layering sealing drum II 8, layering sealing drum III 11 of completion tubular column 100; Then, set packer 17.
Inject pickle in the annular space between completion tubular column 100 and pickling tubing string 110, pickle enters completion tubular column 100 by last screen casing 7 and flows downward with bore hole annulus, process screen casing 24, perforated pipe 23 down enters in the pickling tubing string 110, upwards returns well head through ball-and-seat 22 again;
After the pickling end of job, set the external packer of pipe II 9 and the external packer of pipe III 10 of completion tubular column 100; Pickling tubing string 110 is proposed pit shaft.
C, oil producing operation:, in completion tubular column 100, be lowered to seal up and adopt lower tubular column 120, envelope and down adopt tubing string 130, close arbitrary tubing string of adopting in the tubing string 140 and produce according to the oil producing operation needs.
When the oil reservoir of needs closed upper portion reservoir exploitation bottom, adopt giving up of lower tubular column 120 and 15 be connected the oil pipe lower end sealing up, send in the completion tubular column, sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 lays respectively at the layering sealing drum I 6 of completion tubular column 100, layering sealing drum II 8, in the layering sealing drum III 11, sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 and layering sealing drum I 6, layering sealing drum II 8, layering sealing drum III 11 is an interference fit, perforated pipe 23 is positioned at screen casing 24 places down, and the block head 25 of lower end is positioned at the top of flushing valve 12; The oil pipe of 15 tops of giving up is proposed pit shaft.Subsequently, can be lowered to oil well pump or other oil production equipments carry out oil producing operation.
When the oil reservoir of needs sealings reservoir exploitation top, bottom, envelope is adopted giving up of tubing string 130 down 15 be connected the oil pipe lower end, send in the completion tubular column; Sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 lay respectively in the layering sealing drum I 6, layering sealing drum II 8, layering sealing drum III 11 of completion tubular column 100, and sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 are interference fit with layering sealing drum I 6, layering sealing drum II 8, layering sealing drum III 11; Perforated pipe 23 is positioned at screen casing 7 places, and the block head 25 of lower end is positioned at the top of flushing valve 12; The oil pipe of 15 tops of giving up is proposed pit shaft.Subsequently, can be lowered to oil well pump or other oil production equipments carry out oil producing operation.
When needs are exploited bottom oil reservoir and top oil reservoir simultaneously, adopt giving up of tubing string 140 and 15 be connected the oil pipe lower end closing, send in the completion tubular column; Sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 lay respectively in the layering sealing drum I 6, layering sealing drum II 8, layering sealing drum III 11 of completion tubular column 100, and sealing intubate I 16, sealing intubate II 18, sealing intubate III 20 are interference fit with layering sealing drum I 6, layering sealing drum II 8, layering sealing drum III 11; Perforated pipe 23 between layering sealing drum I 6 and the layering sealing drum II 8 is positioned at screen casing 7 places, and the perforated pipe 23 of sealing intubate III 20 belows is positioned at screen casing 24 places down; The block head 25 of lower end is positioned at the top of flushing valve 12; The oil pipe of 15 tops of giving up is proposed pit shaft.Subsequently, can be lowered to oil well pump or other oil production equipments carry out oil producing operation.
It should be noted that, the foregoing description is example and unrestricted the present invention, according to basic principle of the present invention, can also design horizontal well completion, pickling, flow string more than 2 oil reservoirs, those skilled in the art can design a lot of alternate embodiments and not break away from the scope of claims.

Claims (6)

1. the completion of a horizontal well, flow string, net horizontal section has top oil reservoir, water layer, bottom oil reservoir at least, it is characterized in that:
Net horizontal section in uncased wellbore is installed with completion tubular column (100); The sizing collar (2) of sleeve pipe (1) lower end of completion tubular column (100), casing nipple (3), external packer of pipe I (4), blind plate (5), sleeve pipe (1), layering sealing drum I (6), last screen casing (7), layering sealing drum II (8), casing nipple (3), external packer of pipe II (9), sleeve pipe (1), external packer of pipe III (10), casing nipple (3), layering sealing drum III (11), following screen casing (24), flushing valve (12), following screen casing (24), guide shoe (13) are fixedly connected sequentially;
Pickling tubing string (110) is installed in the described completion tubular column (100) or seals up to adopt under lower tubular column (120) or the envelope and adopt tubing string (130) or close and adopt tubing string (140); The intubate (26) of pickling tubing string (110) lower end is inserted in the flushing valve (12) of completion tubular column (100); Adopt tubing string (130) under sealing up and adopt lower tubular column (120), sealing, close flushing valve (12) top that the lower end of adopting tubing string (140) is positioned at completion tubular column (100).
2. according to completion, the flow string of the described horizontal well of claim 1, it is characterized in that: the oil pipe (14) of described pickling tubing string (110), give up (15), oil pipe (14), packer (17), oil pipe (14), sealing intubate II (18), oil pipe (14), constant pressure valve (19), sealing intubate III (20), safety joint (21), oil pipe (14), ball-and-seat (22), perforated pipe (23), intubate (26) are fixedly connected sequentially; Packer (17) is positioned at last screen casing (7) middle part or the top of completion tubular column (100), sealing intubate II (18), sealing intubate III (20) lay respectively in the layering sealing drum II (8), layering sealing drum III (11) of completion tubular column (100), and sealing intubate II (18), sealing intubate III (20) are interference fit with layering sealing drum II (8), layering sealing drum III (11).
3. according to completion, the flow string of the described horizontal well of claim 1, it is characterized in that: described give up (15), oil pipe (14), sealing intubate I (16), oil pipe (14), sealing intubate II (18), oil pipe (14), constant pressure valve (19), sealing intubate III (20), safety joint (21), perforated pipe (23), the block head (25) of adopting lower tubular column (120) sealed up is fixedly connected sequentially; Sealing intubate I (16), sealing intubate II (18), sealing intubate III (20) lay respectively in the layering sealing drum I (6), layering sealing drum II (8), layering sealing drum III (11) of completion tubular column (100), and sealing intubate I (16), sealing intubate II (18), sealing intubate III (20) are interference fit with layering sealing drum I (6), layering sealing drum II (8), layering sealing drum III (11).
4. according to completion, the flow string of the described horizontal well of claim 1, it is characterized in that: give up (15), oil pipe (14), sealing intubate I (16), perforated pipe (23), sealing intubate II (18), oil pipe (14), constant pressure valve (19), sealing intubate III (20), safety joint (21), the block head (25) of adopting tubing string (130) under the described envelope are fixedly connected sequentially; Sealing intubate I (16), sealing intubate II (18), sealing intubate III (20) lay respectively in the layering sealing drum I (6), layering sealing drum II (8), layering sealing drum III (11) of completion tubular column (100), and sealing intubate I (16), sealing intubate II (18), sealing intubate III (20) are interference fit with layering sealing drum I (6), layering sealing drum II (8), layering sealing drum III (11).
5. according to completion, the flow string of the described horizontal well of claim 1, it is characterized in that: described give up (15), oil pipe (14), sealing intubate I (16), perforated pipe (23), sealing intubate II (18), oil pipe (14), constant pressure valve (19), sealing intubate III (20), safety joint (21), perforated pipe (23), the block head (25) of adopting tubing string (140) of closing is fixedly connected sequentially; Sealing intubate I (16), sealing intubate II (18), sealing intubate III (20) lay respectively in the layering sealing drum I (6), layering sealing drum II (8), layering sealing drum III (11) of completion tubular column (100), and sealing intubate I (16), sealing intubate II (18), sealing intubate III (20) are interference fit with layering sealing drum I (6), layering sealing drum II (8), layering sealing drum III (11).
6. according to completion, the flow string of the described arbitrary horizontal well of claim 2~5, it is characterized in that: described giving up (15) given up for back-off; Described safety joint (21) is disconnection sand washing safety joint.
CN2010202231900U 2010-06-11 2010-06-11 Well completion and flow string of horizontal well Expired - Lifetime CN201705276U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202231900U CN201705276U (en) 2010-06-11 2010-06-11 Well completion and flow string of horizontal well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202231900U CN201705276U (en) 2010-06-11 2010-06-11 Well completion and flow string of horizontal well

Publications (1)

Publication Number Publication Date
CN201705276U true CN201705276U (en) 2011-01-12

Family

ID=43442431

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202231900U Expired - Lifetime CN201705276U (en) 2010-06-11 2010-06-11 Well completion and flow string of horizontal well

Country Status (1)

Country Link
CN (1) CN201705276U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864921A (en) * 2010-06-11 2010-10-20 大港油田集团有限责任公司 Well completion and oil production string of horizontal well and well completion and oil production processes thereof
CN102817597A (en) * 2012-08-31 2012-12-12 中国石油化工股份有限公司 Three-layer insertion pipe mechanical water exploration and plugging method and water exploration and plugging pipe column
CN102966314A (en) * 2012-11-16 2013-03-13 西南石油大学 Horizontal well central pipe and water control method thereof
CN103122760A (en) * 2013-03-01 2013-05-29 中国海洋石油总公司 Completion pipe string for suspending bottom water coning
CN103998783A (en) * 2011-12-15 2014-08-20 雷兹生产有限公司 Horizontal and vertical well fluid pumping system
CN104213846A (en) * 2013-06-05 2014-12-17 中国石油天然气股份有限公司 Cased hole completion multi-section-fractured horizontal well selective production pipe column and working method thereof
CN107288572A (en) * 2017-07-18 2017-10-24 中国石油集团渤海钻探工程有限公司 Blind hole type circulates isolating tool
CN104420858B (en) * 2013-08-23 2017-10-24 天津大港油田钻采技术开发公司 Hierarchical process tubing string

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864921A (en) * 2010-06-11 2010-10-20 大港油田集团有限责任公司 Well completion and oil production string of horizontal well and well completion and oil production processes thereof
CN101864921B (en) * 2010-06-11 2013-05-01 大港油田集团有限责任公司 Well completion and oil production string of horizontal well and well completion and oil production processes thereof
CN103998783B (en) * 2011-12-15 2018-01-23 雷兹生产有限公司 Horizontal and vertical well fluid pumping system
CN103998783A (en) * 2011-12-15 2014-08-20 雷兹生产有限公司 Horizontal and vertical well fluid pumping system
CN102817597A (en) * 2012-08-31 2012-12-12 中国石油化工股份有限公司 Three-layer insertion pipe mechanical water exploration and plugging method and water exploration and plugging pipe column
CN102817597B (en) * 2012-08-31 2015-04-15 中国石油化工股份有限公司 Three-layer insertion pipe mechanical water exploration and plugging method and water exploration and plugging pipe column
CN102966314B (en) * 2012-11-16 2014-10-01 西南石油大学 Horizontal well central pipe and water control method thereof
CN102966314A (en) * 2012-11-16 2013-03-13 西南石油大学 Horizontal well central pipe and water control method thereof
CN103122760A (en) * 2013-03-01 2013-05-29 中国海洋石油总公司 Completion pipe string for suspending bottom water coning
CN103122760B (en) * 2013-03-01 2015-06-10 中国海洋石油总公司 Completion pipe string for suspending bottom water coning
CN104213846A (en) * 2013-06-05 2014-12-17 中国石油天然气股份有限公司 Cased hole completion multi-section-fractured horizontal well selective production pipe column and working method thereof
CN104213846B (en) * 2013-06-05 2016-07-13 中国石油天然气股份有限公司 Cased hole completion multistage frac water horizontal well selectivity mining tubular column and method of work thereof
CN104420858B (en) * 2013-08-23 2017-10-24 天津大港油田钻采技术开发公司 Hierarchical process tubing string
CN107288572A (en) * 2017-07-18 2017-10-24 中国石油集团渤海钻探工程有限公司 Blind hole type circulates isolating tool
CN107288572B (en) * 2017-07-18 2019-04-12 中国石油集团渤海钻探工程有限公司 Blind hole type recycles isolating tool

Similar Documents

Publication Publication Date Title
CN101864921B (en) Well completion and oil production string of horizontal well and well completion and oil production processes thereof
CN201705276U (en) Well completion and flow string of horizontal well
CN109653707B (en) Method for dewatering and increasing oil by filling packing body particles in oil and gas well of fractured oil and gas reservoir
CN201705219U (en) Lateral drilling gravel pack completion string
CN101975041B (en) Well cementing method for avoiding coal bed and device thereof
CN103643931A (en) Completion and fracture integrated pipe column of offshore openhole horizontal well and construction method of pipe column
CN106050199A (en) Synthetic drainage and gas production device and method
CN103452531B (en) Oil pipe under underbalance, no killing well gaslift, turn the method for taking out, examining pump and maintenance oil pipe
CN105649578A (en) Vertical-well double-layer partial-pressure commingling method and device for coalbed methane
CN201738822U (en) String for upper horizontal well cementation and lower screen pipe gravel pack completion
CN205858311U (en) A kind of bore hole staged fracturing completion tubular column
CN203239303U (en) Extraction device used for injection and extraction of same well
CN102278101B (en) Subdivided layer watered oil extraction pipe column
CN210134883U (en) Injection-production integrated pipe column in same well
JP7297353B1 (en) Natural gas hydrate - shallow gas - deep gas multi-source multi-method joint mining system and method
CN101871334B (en) Blocking technological method of drillable oil layer
CN204266988U (en) A kind of pilot-controlled switch sliding sleeve
CN103470221B (en) Method made by the connection that pump was taken out and examined to oil pipe under underbalance, no killing well gaslift, axle
CN203939477U (en) A kind of formation testing and completion practice integrated pipe column
US20030066649A1 (en) Single well combination oil production/water dump flood apparatus and methods
CN1456785A (en) Selective multi-stage inner pipe cementing process and cemented tubular column there from
CN204716201U (en) A kind of pilot-controlled switch sliding sleeve
CN209430180U (en) It is layered de-plugging tubular column structure
CN202645511U (en) Horizontal well segmental production string
CN107989578A (en) A kind of recyclable nitrogen jet current of coiled tubing pumps drainage system and method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20110112

Effective date of abandoning: 20130501

RGAV Abandon patent right to avoid regrant