CN201671317U - Attached scaffold supporting device with improved structure - Google Patents

Attached scaffold supporting device with improved structure Download PDF

Info

Publication number
CN201671317U
CN201671317U CN2010202012655U CN201020201265U CN201671317U CN 201671317 U CN201671317 U CN 201671317U CN 2010202012655 U CN2010202012655 U CN 2010202012655U CN 201020201265 U CN201020201265 U CN 201020201265U CN 201671317 U CN201671317 U CN 201671317U
Authority
CN
China
Prior art keywords
termination
adheres
bracing
scaffold
strutting arrangement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010202012655U
Other languages
Chinese (zh)
Inventor
时远东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CSCEC Strait Construction and Development Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd filed Critical Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority to CN2010202012655U priority Critical patent/CN201671317U/en
Application granted granted Critical
Publication of CN201671317U publication Critical patent/CN201671317U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model relates to an attached scaffold supporting device with an improved structure which comprises an attached supporting frame connected between a scaffold and a building structure. The attached scaffold supporting device is characterized by also comprising a lifting end, a flexible lengthening section and a fixing end connected in sequence from the outer to the inner in a removable way, wherein the fixing end is connected with the building structure, and the lifting end is connected with a guide rail on the inner side of the scaffold in a matching and guiding way via a guide wheel on the outer side of the lifting end. The utility model can adapt to the connection of the scaffold and the building side beam with a complex structure so as to achieve the construction standards.

Description

Structure improved scaffold adheres to bracing or strutting arrangement
Technical field
The utility model relates to a kind of scaffold erecting device of the realm of building construction, and particularly a kind of structure improved scaffold adheres to bracing or strutting arrangement.
Background technology
In the building operations of lifting false work, be to adopt to adhere to bracing frame and be connected between scaffold and the building structure basically.Adopt the conventional bracing frame that adheres to, when the building curb girder that runs into labyrinth (as the girder of arc beam, balcony beam, length≤200m or air-conditioning plate reversed beam etc.), because the conventional support frame structure that adheres to is fixed, can't adjust self length according to the spacing between scaffold and the building structure, therefore cause lack of standardization, the indivedual force requests of installation not reach, may destroy problems such as building finished product easily.
Summary of the invention
In order to solve existing in prior technology the problems referred to above, the utility model provides a kind of structure improved scaffold to adhere to bracing or strutting arrangement, and the installation that it can adapt between the building curb girder of scaffold and labyrinth is connected, thereby reaches standard construction.
Technical solutions of the utility model are to constitute like this, a kind of structure improved scaffold adheres to bracing or strutting arrangement, it comprises the bracing frame that adheres to that is connected between scaffold and the building structure, it is characterized in that: the described bracing frame that adheres to comprises that the lifting termination that detachably connects successively from outside to inside, flexible extension reach fixedly termination, described fixedly termination is connected with building structure, and described lifting termination cooperates guiding to be connected by guide wheel device that is installed on its outside and the guide rail that is installed on the scaffold inboard.
The utility model is owing to set up flexible extension at the middle part of adhering to bracing frame, therefore can be according to the situation of job site, adopt the flexible extension of appropriate length to adapt to the installation requirements of various building structure, installation between the building curb girder of scaffold and labyrinth is connected also can reaches standard construction.
Compared to prior art, the utlity model has following advantage: (1) scaffold described in the utility model adheres to bracing or strutting arrangement can be changed along with the variation of building structure, adapt to the installation of various building structure, the installation that especially adapts between the building curb girder of scaffold and labyrinth is connected; (2) simple in structure, easy disassembly; (3) result of use is good, can accomplish very installation specification.
Description of drawings
Fig. 1 is the utility model embodiment organigram.
Fig. 2 is the enlarged diagram that adheres to bracing frame among Fig. 1.
Fig. 3 is the vertical view (having increased guide rail among the figure) of Fig. 2.
Fig. 4 is the A-A revolved sectional view of Fig. 3.
Number in the figure explanation: 1, scaffold, 2, building structure, 3, promote the termination, 4, extension flexibly, 5, fixing termination, 6, guide wheel device, 7, guide rail, 8, through-wall bolt, 9, elongated slot, 10, bolt assembly, 11, stressed suspension ring, 12, the load-bearing bracing or strutting arrangement.
The specific embodiment
Below in conjunction with specification drawings and specific embodiments the utility model content is elaborated:
The embodiment organigram that adheres to bracing or strutting arrangement as Fig. 1-Figure 4 shows that a kind of structure improved scaffold that the utility model provides, it comprises the bracing frame that adheres to that is connected between scaffold 1 and the building structure 2, it is characterized in that: the described bracing frame that adheres to comprises that the lifting termination 3, the flexible extension 4 that detachably connect successively from outside to inside reach fixedly termination 5, described fixedly termination 5 is connected with building structure 2, and described lifting termination 3 cooperates guiding to be connected by the guide wheel device 6 that is installed on its outside with the guide rail 7 that is installed on scaffold 1 inboard.
Described fixedly termination 5 is connected with pre-buried via hole in being embedded in building structure 2 by through-wall bolt 8, and described fixedly termination 5 is provided with and is used for regulating the through-wall bolt 8 and the fixing elongated slot 9 of the concrete link position of termination 5.Described fixedly termination 5 adopts elongated slot 9 to be connected with through-wall bolt 8, can effectively prevent pre-buried off normal, makes more convenient to operate.
Described lifting termination 3 with flexibly between the extension 4 and flexibly extension 4 with fixedly be connected by bolt assembly 10 respectively between the termination 5.
Also be connected with stressed suspension ring 11 and load-bearing bracing or strutting arrangement 12 on the described lifting termination 3.
Described lifting termination 3, flexibly extension 4 and fixedly termination 5 adopt a pair of channel-section steel of setting back-to-back and the junction plate of being located between two channel-section steels to be welded respectively.
The utility model operating principle is described as follows:
In Fig. 1, promote termination 3 and be used for independently bearing and scaffold all is passed in the building structure 2 from heavy load and working load, and be used for reinforcing other annex (as stressed suspension ring 11 and load-bearing bracing or strutting arrangement 12) in the above.Stressed suspension ring 11 are installed in by lateral pin and promote on the termination 3, hang sychronisation and electric block below, and it is stressed to be delivered in the building structure 2 by the stress point that promotes on the termination 3 again.Load-bearing bracing or strutting arrangement 12 is installed in by lateral pin and promotes on the termination 3, and load-bearing bracing or strutting arrangement 12 can play the purpose of fall arrest when promoting, and after lifting, is used for bearing the deadweight of scaffold 1 support body.The length of extension 4 can be adjusted length processing according to the construction needs flexibly, thereby can adjust the length of adhering to bracing frame, makes and adheres to the installation requirement that bracing frame can adapt to different building structure 2.Fixedly termination 5 is used for the whole bracing frame that adheres to is fixed in the building structure 2, adopts the through-wall bolt 8 and the floor of building structure 2 to fix.Guide wheel device 6 is installed in the outside that promotes termination 3, cooperates guiding to be connected with the guide rail 7 that is installed on scaffold 1 inboard, is used for guaranteeing the verticality of scaffold 1 support body.

Claims (5)

1. a structure improved scaffold adheres to bracing or strutting arrangement, it comprises the bracing frame that adheres to that is connected between scaffold (1) and the building structure (2), it is characterized in that: the described bracing frame that adheres to comprises that the lifting termination (3) that detachably connects successively from outside to inside, flexible extension (4) reach fixedly termination (5), described fixedly termination (5) is connected with building structure (2), and described lifting termination (3) cooperates guiding to be connected by the guide wheel device (6) that is installed on its outside guide rail (7) inboard with being installed on scaffold (1).
2. structure improved scaffold according to claim 1 adheres to bracing or strutting arrangement, it is characterized in that: described fixedly termination (5) is connected with the pre-buried via hole that is embedded in the building structure (2) by through-wall bolt (8), and described fixedly termination (5) is provided with and is used for regulating the through-wall bolt (8) and the fixing elongated slot (9) of the concrete link position of termination (5).
3. structure improved scaffold according to claim 1 and 2 adheres to bracing or strutting arrangement, it is characterized in that: described lifting termination (3) with flexibly between the extension (4) and flexibly extension (4) with fixedly be connected by bolt assembly (10) respectively between termination (5).
4. structure improved scaffold according to claim 1 and 2 adheres to bracing or strutting arrangement, it is characterized in that: also be connected with stressed suspension ring (11) and load-bearing bracing or strutting arrangement (12) on the described lifting termination (3).
5. structure improved scaffold according to claim 1 and 2 adheres to bracing or strutting arrangement, it is characterized in that: described lifting termination (3), flexibly extension (4) and fixedly termination (5) adopt a pair of channel-section steel of setting back-to-back and the junction plate of being located between two channel-section steels to be welded respectively.
CN2010202012655U 2010-05-25 2010-05-25 Attached scaffold supporting device with improved structure Expired - Lifetime CN201671317U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202012655U CN201671317U (en) 2010-05-25 2010-05-25 Attached scaffold supporting device with improved structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202012655U CN201671317U (en) 2010-05-25 2010-05-25 Attached scaffold supporting device with improved structure

Publications (1)

Publication Number Publication Date
CN201671317U true CN201671317U (en) 2010-12-15

Family

ID=43328729

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202012655U Expired - Lifetime CN201671317U (en) 2010-05-25 2010-05-25 Attached scaffold supporting device with improved structure

Country Status (1)

Country Link
CN (1) CN201671317U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104929358A (en) * 2015-06-23 2015-09-23 上海建工四建集团有限公司 Multifunctional wall attachment support of attachment type overall electric lifting scaffold and use method
CN111877729A (en) * 2020-07-21 2020-11-03 上海建工二建集团有限公司 Attached lifting scaffold

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104929358A (en) * 2015-06-23 2015-09-23 上海建工四建集团有限公司 Multifunctional wall attachment support of attachment type overall electric lifting scaffold and use method
CN111877729A (en) * 2020-07-21 2020-11-03 上海建工二建集团有限公司 Attached lifting scaffold

Similar Documents

Publication Publication Date Title
CN204781899U (en) That adheres to whole electric lift scaffold of formula multi -functionally attaches wall support
CN106429896B (en) A kind of special-shaped C-type beam for tower crane
CN207268073U (en) Novel flexible formwork bearing frame
CN102777030A (en) Method for building up formwork construction platform of lift shaft
CN201671317U (en) Attached scaffold supporting device with improved structure
KR20110014341A (en) Tower ctane wall bracing with a safety fence
CN205444889U (en) Support arrangement for horizontal prefabricated component
CN206345617U (en) Building tower crane attachment device is received in a kind of
CN101906870A (en) Suspended scaffolding
CN202023353U (en) Integral lifting scaffold for building operations
CN205527294U (en) Cross hanging beam
CN202689498U (en) Liftable scaffold for simple and easy building outer wall
CN204343647U (en) A kind of the shaped steel suspension scaffolding bracing frame
CN210858054U (en) Regularization construction elevator connects material platform
CN204079226U (en) A kind of movable beam string hanging apparatus that can increase rigidity when tubular truss lifts
CN203257080U (en) Adjustable overhang supporting device for building construction
CN214885646U (en) Material platform drawknot connecting piece
CN210140988U (en) Hydraulic climbing formwork bearing triangular frame lengthening device
CN207293997U (en) A kind of chassis suitable for ultra-large type derrick crane
CN111908334A (en) Method for assembling and disassembling portal crane and auxiliary support structure
CN201142537Y (en) Large span cable bridge rack installation mold
CN107780644B (en) Operation platform for elevator shaft construction and use method thereof
CN209686839U (en) Spandrel girder on attachment type raise scaffold combined type
CN111704058A (en) Hoisting device
CN221663453U (en) Bracket truss for operation platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CSCEC STRAIT CONSTRUCTION AND DEVELOPMENT CO., LTD

Free format text: FORMER NAME: THE THIRD COMPANY OF CHINA SEVENTH ENGINEERING BUREAU CO., LTD.

CP03 Change of name, title or address

Address after: 98-1 No. 350003 Fujian province Fuzhou Mawei District Jiangbin East Avenue

Patentee after: CSCEC Strait Construction and Development Co., Ltd.

Address before: Fuzhou City, Fujian Province, 350000 North Road, No. 148 in the construction of the third construction company seven

Patentee before: The Third Company of China Seventh Engineering Bureau Co., Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20101215