CN201501729U - Air turning device of equipment - Google Patents

Air turning device of equipment Download PDF

Info

Publication number
CN201501729U
CN201501729U CN2009202389409U CN200920238940U CN201501729U CN 201501729 U CN201501729 U CN 201501729U CN 2009202389409 U CN2009202389409 U CN 2009202389409U CN 200920238940 U CN200920238940 U CN 200920238940U CN 201501729 U CN201501729 U CN 201501729U
Authority
CN
China
Prior art keywords
fixed pulley
link
equipment
hoist cable
turning device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009202389409U
Other languages
Chinese (zh)
Inventor
陈言华
肖贵成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Tenth Construction Co Ltd
Original Assignee
Sinopec Tenth Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Tenth Construction Co Ltd filed Critical Sinopec Tenth Construction Co Ltd
Priority to CN2009202389409U priority Critical patent/CN201501729U/en
Application granted granted Critical
Publication of CN201501729U publication Critical patent/CN201501729U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model aims to provide an air turning device of equipment, which comprises a balance beam, wherein a first lifting lug and a second lifting lug are respectively arranged on the two ends of the top surface of the balance beam, a balance sling is installed between the first and the second lifting lugs, a first hanging ring and a second hanging ring are respectively installed at the two ends of the bottom of the balance beam, a first fixed pulley is mounted on the first hanging ring, a first rope sling is mounted in the first fixed pulley, a second fixed pulley is mounted on the second hanging ring, and a second rope sling is mounted in the second fixed pulley. The utility model only uses one crane to complete the turning process of piping equipment, has easy operation, high security and no swaying during the turning process.

Description

The aerial turning device of equipment
Technical field
The utility model relates to a kind of hanging device, the aerial turning device of specifically a kind of equipment.
Background technology
Pipelines such as large-scale hot-flow flue, flue need within it that portion increases lining after completing, because diameter is bigger, the lining part can't integral manufacturing, need lining with the inner-walls of duct lower part complete after, the upset pipeline continues to make second half lining.In some camp site, because the restriction of condition can't use positioner to come pipeline is overturn, can only lean on the upset that cooperatively interacts of two cranes, difficulty is bigger, and in case cooperate badly, very easily makes equipment swing occur, the formation potential safety hazard.
Summary of the invention
The purpose of this utility model provides the aerial turning device of a kind of equipment, and it only can either finish switching process to pipe-line equipment with a crane, operates easily during upset, and is safe, can not swing.
The utility model for achieving the above object, be achieved through the following technical solutions: comprise equalizing bar, equalizing bar end face two ends are provided with first hanger and second hanger respectively, the balance hoist cable is installed between first hanger and second hanger, two ends, equalizing bar bottom surface are installed first link and second link respectively, and first fixed pulley is installed on first link, and the first annular hoist cable is installed in first fixed pulley, second fixed pulley is installed on second link, the second annular hoist cable is installed in second fixed pulley.The equalizing bar bottom is provided with chute, and first link and the second link top are equipped with slide block, and slide block is installed in the chute.The wheel shaft of first fixed pulley is provided with pointer.
Advantage of the present utility model is: reasonable in design, only can either finish switching process to pipe-line equipment with a crane, and operate easily during upset, safe, be applicable to the aerial switching process of multiple main equipment, flip angle is convenient to grasp.
Description of drawings
Fig. 1 is a structural representation of the present utility model; Fig. 2 is that the A-A of Fig. 1 analyses and observe the structure for amplifying scheme drawing.
The specific embodiment
The aerial turning device of equipment described in the utility model comprises equalizing bar 1, equalizing bar 1 end face two ends are provided with first hanger 2 and second hanger 3 respectively, balance hoist cable 4 is installed between first hanger 2 and second hanger 3, two ends, equalizing bar 1 bottom surface are installed first link 5 and second link 6 respectively, first fixed pulley 7 is installed on first link 5, install in first fixed pulley 7 to install on first annular hoist cable 8, the second links 6 in second fixed pulley, 9, the second fixed pulleys 9 the second annular hoist cable 10 is installed.During use, the suspension hook 14 of crane is hung on the balance hoist cable 4, the first annular hoist cable 8 and the second annular hoist cable 10 are enclosed within the pipe-line equipment both sides respectively, start crane, pipeline is hung ground, apply external force along the pipeline tangential direction this moment, pipeline begins turning, first fixed pulley 7 and second fixed pulley 8 can effectively reduce the first annular hoist cable 8 and the second annular hoist cable 10 friction force when together rotating with pipeline, make the pipeline upset more smooth and easy, after turning to proper angle, remove external force, pipeline promptly stops upset.Applying external force along the pipeline tangential direction adopts variety of way all can, for example hour can directly come the pipeline application of force when pipeline by the workman with hand, make its upset, pipe diameter can use rope sling after tension on the pipeline when big, pull rope sling, utilize the friction force between rope sling and the pipeline to make pipeline realize upset.
In order to make the utility model can be applicable to the pipe-line equipment of multiple different size, can chute 11, the first links 5 be set in equalizing bar 1 bottom and second link, 6 tops all are provided with slide block 12, slide block 12 is installed in the chute 11.Slide block 12 can slide in chute 11, when the line size of need upsets hour, can make first link 5 and second link 6 near the center of equalizing bars 1, reduce the distance between the first annular hoist cable 8 and the second annular hoist cable 10; When the line size of need upsets is big, first link 5 and the direction of second link 6 to equalizing bar 1 two ends are moved, increase the distance between the first annular hoist cable 8 and the second annular hoist cable 10.
The utility model is grasped flip angle for the ease of the workmen, and pointer 13 can be set on the wheel shaft of first fixed pulley 7.During upset, the workmen cooperates the known pipeline and the girth of pulley by the angle that observation pointer 13 turns over, and just can calculate the angle that pipeline rotates.

Claims (3)

1. the aerial turning device of equipment, it is characterized in that: comprise equalizing bar (1), equalizing bar (1) end face two ends are provided with first hanger (2) and second hanger (3) respectively, balance hoist cable (4) is installed between first hanger (2) and second hanger (3), equalizing bar (1) two ends, bottom surface are installed first link (5) and second link (6) respectively, first link (5) is gone up first fixed pulley (7) is installed, the first annular hoist cable (8) is installed in first fixed pulley (7), second link (6) is gone up second fixed pulley (9) is installed, and the second annular hoist cable (10) is installed in second fixed pulley (9).
2. the aerial turning device of equipment according to claim 1 is characterized in that: equalizing bar (1) bottom is provided with chute (11), and first link (5) and second link (6) top are equipped with slide block (12), and slide block (12) is installed in the chute (11).
3. the aerial turning device of equipment according to claim 1 and 2 is characterized in that: the wheel shaft of first fixed pulley (7) is provided with pointer (13).
CN2009202389409U 2009-09-27 2009-09-27 Air turning device of equipment Expired - Lifetime CN201501729U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009202389409U CN201501729U (en) 2009-09-27 2009-09-27 Air turning device of equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009202389409U CN201501729U (en) 2009-09-27 2009-09-27 Air turning device of equipment

Publications (1)

Publication Number Publication Date
CN201501729U true CN201501729U (en) 2010-06-09

Family

ID=42452666

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009202389409U Expired - Lifetime CN201501729U (en) 2009-09-27 2009-09-27 Air turning device of equipment

Country Status (1)

Country Link
CN (1) CN201501729U (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102009909A (en) * 2010-11-19 2011-04-13 太原重工股份有限公司 Multi-lifting point hanger for lifting nuclear power station module
CN102120544A (en) * 2011-02-23 2011-07-13 上海华钢不锈钢有限公司 Hoisting device for arranging large stainless steel U-tube wooden boxes
CN102635732A (en) * 2012-04-13 2012-08-15 中国海洋石油总公司 Process for mounting relatively long pipeline
CN102992215A (en) * 2012-10-15 2013-03-27 铜陵有色建安钢构有限责任公司 Slippage type lifting device
CN103693546A (en) * 2013-12-17 2014-04-02 鞍钢重型机械有限责任公司 Hanging tool for forged AP1000 nuclear power main pipeline and quick hoisting method
CN106315390A (en) * 2016-09-14 2017-01-11 四川航泰航空装备有限公司 Universal heavy object suspending equipment for airplane
CN106957007A (en) * 2017-04-24 2017-07-18 中国葛洲坝集团第工程有限公司 A kind of super-large diameter penstock equipment for supporting patient with burn and turn-over method
CN108516454A (en) * 2018-04-20 2018-09-11 上海市机械施工集团有限公司 A kind of hanging apparatus of prefabricated components
CN108862001A (en) * 2018-07-26 2018-11-23 西安长峰机电研究所 A kind of lifting turnover device
CN109665435A (en) * 2019-01-07 2019-04-23 武汉船用机械有限责任公司 A kind of turning tool and turn-over method
CN109911764A (en) * 2019-03-27 2019-06-21 长光卫星技术有限公司 Multi-functional overturning hanging device
CN110255359A (en) * 2019-06-03 2019-09-20 中铁大桥局集团有限公司 It is a kind of for lifting the suspender of segment girder steel

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102009909A (en) * 2010-11-19 2011-04-13 太原重工股份有限公司 Multi-lifting point hanger for lifting nuclear power station module
CN102120544A (en) * 2011-02-23 2011-07-13 上海华钢不锈钢有限公司 Hoisting device for arranging large stainless steel U-tube wooden boxes
CN102635732A (en) * 2012-04-13 2012-08-15 中国海洋石油总公司 Process for mounting relatively long pipeline
CN102992215A (en) * 2012-10-15 2013-03-27 铜陵有色建安钢构有限责任公司 Slippage type lifting device
CN103693546A (en) * 2013-12-17 2014-04-02 鞍钢重型机械有限责任公司 Hanging tool for forged AP1000 nuclear power main pipeline and quick hoisting method
CN103693546B (en) * 2013-12-17 2015-10-28 鞍钢重型机械有限责任公司 The fast hoisting method of forging AP1000 main nuclear power pipeline
CN106315390A (en) * 2016-09-14 2017-01-11 四川航泰航空装备有限公司 Universal heavy object suspending equipment for airplane
CN106957007A (en) * 2017-04-24 2017-07-18 中国葛洲坝集团第工程有限公司 A kind of super-large diameter penstock equipment for supporting patient with burn and turn-over method
CN108516454A (en) * 2018-04-20 2018-09-11 上海市机械施工集团有限公司 A kind of hanging apparatus of prefabricated components
CN108862001A (en) * 2018-07-26 2018-11-23 西安长峰机电研究所 A kind of lifting turnover device
CN109665435A (en) * 2019-01-07 2019-04-23 武汉船用机械有限责任公司 A kind of turning tool and turn-over method
CN109911764A (en) * 2019-03-27 2019-06-21 长光卫星技术有限公司 Multi-functional overturning hanging device
CN110255359A (en) * 2019-06-03 2019-09-20 中铁大桥局集团有限公司 It is a kind of for lifting the suspender of segment girder steel

Similar Documents

Publication Publication Date Title
CN201501729U (en) Air turning device of equipment
CN103723622B (en) Trident connecting rod Self-adjusting coils suspender
CN204150943U (en) A kind of Novel hook device
CN202321978U (en) Combined lifting appliance for metallurgical environment
CN201473192U (en) Lifting tool
CN102992203B (en) Simple hoisting device for steel structure bridge installation
CN201334306Y (en) Hoisting machine for upright post member
CN204847923U (en) Hoist anti -swing puts device
CN202265818U (en) Automatic hooking and unhooking rammer device
CN201729574U (en) Steel tube hoisting tool used for steel tube tower
CN201722053U (en) Hoisting mechanism used for upright column hoisting
CN202379593U (en) Runner hanging structure of large-sized impulse water turbine
CN202465029U (en) Cable hoisting tool
CN205590168U (en) Overturning lifting device
CN201128650Y (en) Transitional sling
CN203754234U (en) Safety device for lifting hook assembly of pipe lifting machine
CN204490327U (en) Joist steel hoisting clamp
CN203653069U (en) Self-adjusting coiling lifting appliance for three-way connecting rod
CN203959653U (en) A kind of for changing the hanger structure of furnace roller
CN106185626A (en) It is applicable to packaged type auxiliary turning device and the method for large volume and wt pts
CN202529725U (en) Novel crane
CN201605579U (en) Tubular pile industrial steel cage suspending device
CN202116257U (en) Lever for tuyere sleeve installation construction
CN101734549A (en) Lifting sling
CN203632119U (en) Tightener

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SINOPEC TENTH CONSTRUCTION COMPANY

Free format text: FORMER NAME: NO.10 CONSTRUCTION CORP., SINOPEC

CP01 Change in the name or title of a patent holder

Address after: 255438 No. 29, Linzi, Zibo District, Shandong, Jianshe Road

Patentee after: SINOPEC Tenth Construction Company

Address before: 255438 No. 29, Linzi, Zibo District, Shandong, Jianshe Road

Patentee before: No.10 Construction Corp., SINOPEC

CX01 Expiry of patent term

Granted publication date: 20100609

CX01 Expiry of patent term