CN201497792U - Switch testing device - Google Patents

Switch testing device Download PDF

Info

Publication number
CN201497792U
CN201497792U CN2009201940428U CN200920194042U CN201497792U CN 201497792 U CN201497792 U CN 201497792U CN 2009201940428 U CN2009201940428 U CN 2009201940428U CN 200920194042 U CN200920194042 U CN 200920194042U CN 201497792 U CN201497792 U CN 201497792U
Authority
CN
China
Prior art keywords
switch
test device
micro computer
described micro
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009201940428U
Other languages
Chinese (zh)
Inventor
王彦鹏
高建卫
袁永飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foryou Multimedia Electronics Co Ltd
Original Assignee
Foryou Multimedia Electronics Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foryou Multimedia Electronics Co Ltd filed Critical Foryou Multimedia Electronics Co Ltd
Priority to CN2009201940428U priority Critical patent/CN201497792U/en
Application granted granted Critical
Publication of CN201497792U publication Critical patent/CN201497792U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a switch testing device, which comprises a switch testing cramping apparatus and an operation component, wherein the switch testing cramping apparatus comprises a motor, and is controlled by a microcomputer, the microcomputer is provided with switching time display unit, and the microcomputer is connected with the operation component. The switch testing device can respectively and reliably test the use performance of the switches.

Description

A kind of switch test device
Technical field
The utility model relates to the field tests of circuit structure part or equipment, exactly is meant a kind of switch test device.
Background technology
In order to guarantee product quality, switch must carry out the test in switch performance and life-span, promptly switch is repeated the on-off action to test its usability and life-span.But, present switch test device is by pure hardware controls, has only a counter, a plurality of by the shared counter of slowdown monitoring switch, so can only count synchronously, after test is finished, by judging manually whether switch is qualified, can not write down and demonstrate the life-span of each switch exactly respectively more at last.In theory, switch is made mistakes and once just should be considered as the life-span and expire, and normally can not be considered as certified products even recover afterwards again.And test fixture does not before have this arbitration functions.
The utility model content
At above-mentioned defective, the purpose of this utility model is to provide a kind of switch test device, can test out the usability of switch respectively reliably.
In order to solve above technical matters, the switch test device that the utility model provides, comprise switch testing anchor clamps and functional unit, described switch testing anchor clamps include motor, described switch testing anchor clamps are by microcomputerized control, described micro computer is provided with switch and finishes the number of times display unit, and described micro computer is connected with described functional unit.
Preferably, described micro computer is provided with the direction setting unit of control motor sense of rotation.
Preferably, described micro computer is provided with the switch number display unit.
Preferably, described micro computer is provided with the qualified number of times setup unit of switch.
Preferably, described micro computer is provided with switch residue degree display unit.
Preferably, described micro computer is provided with the qualified judging unit of switch.
Preferably, described micro computer is provided with display screen.
Preferably, described display screen is a LCD display.
Preferably, described motor is a stepper motor; Described functional unit is some buttons.
The switch test device that the utility model provides comprises switch testing anchor clamps and functional unit, and described switch testing anchor clamps include motor, and described switch testing anchor clamps are by microcomputerized control, and described micro computer is connected with described functional unit.The switch test device that the utility model provides is provided with some unit by the control of micro computer realization to the switch test fixture on micro computer, compared with prior art, this switch test device can test out the usability of switch respectively reliably.
Especially, the switch test device that the utility model provides, can set some number of times of finishing on time counting unit finishing of micro computer shows, and appear on the display screen, when the switch cisco unity malfunction of certain numbering, corresponding switch is finished number of times and is shown and will stop, and the number of times of finishing of other switches shows unaffected.When switch failed to reach the qualified number of times of setting, the switch judging unit had corresponding whether qualified demonstration.Therefore can realize the counting respectively of different switches and judge whether switch is qualified.
Description of drawings
Fig. 1 is the structural representation of switch test device in the utility model;
Fig. 2 is the duty chart of display screen among Fig. 1.
Embodiment
For those skilled in the art can understand technical scheme provided by the utility model better, set forth below in conjunction with specific embodiment.
See also Fig. 1, this figure is the structural representation of switch test device in the utility model.
The switch test device that the utility model provides comprises switch testing anchor clamps 1 and action button 3, and switch testing anchor clamps 1 include stepper motor, and the switch testing anchor clamps are by the microcomputerized control that has LCD display 2, and micro computer is connected with action button 3.Micro computer is provided with the qualified number of times setup unit of direction setting unit, switch number display unit, switch, the switch of control motor sense of rotation and finishes number of times display unit, switch residue degree display unit, the qualified judging unit of switch.This device also is provided with shell 4, and switch testing anchor clamps 1, action button 3 and micro computer are encapsulated in the housing.
See also Fig. 2, this figure is the duty chart of display screen among Fig. 1.The workflow of the switch test device that the utility model provides is as follows:
Preparation process: 1, direction setting step, this step is used for setting the sense of rotation of stepper motor, and " changeing clockwise " indicates present setting sense of rotation, can adjust by action button; 2, number of times is set step, and this step is used for setting the test total degree, and setting here is 100,000 times, can adjust with button; 3, residue degree is set, and shows in the hurdle below this hurdle and this time tests remaining work number of times, and the meaning that shows among the figure is to test also to remain 86768 times; 4, information indicating is set, when the operator occur operational when wrong, can the demonstration error reason in the hurdle below this hurdle, with pilot operationp person's proper operation; 5, display switch numbering is set, and is that (SW1~SW5), can increase and decrease revises software and gets final product for the numbering of 5 switches below " switch " row; 6, finish number of times and set, the number of times that the display switch test has been finished, during start, at " finishing number of times " row, all counters are all started from scratch and are increased progressively synchronously.Stepper motor is made back and forth movement in certain angle, so that rotating disk compressing switch makes it closed, disconnects.
Then, press " beginning (START) " action button, when stepper motor moved to a side and stops, micro computer detected all switches, if all switches are all normal, then at " finishing number of times " row, all counters all add one; Stepper motor moves to opposite side and stops then, and micro computer detects all switches again, if all switches are all normal, then all adds one again at all counters of " finishing number of times " row, goes round and begins again.When micro computer detects some switches when unusual, the pairing counter of this switch has just fixed, " a plurality of counters " implementation method of tally function respectively that Here it is." the good not judgement " the inside, a hurdle on the right can show " NG " printed words simultaneously.Test is proceeded, up to all switches all unusual or reach test number (TN) till.The meaning of 10 data presentation of row of " finishing number of times " in Fig. 2 chart is: except that No. 3 switches, other switches have all carried out 13232 tests, and all in good condition at present, test still underway; And the data on No. 3 switch the right fix 10289, and the meaning is in the time of the 10289th time, and micro computer detects this switch and occurred once closed or the disconnection mistake, and demonstrate " NG " printed words in " good denys to judge " hurdle on the right.The pairing counter of switch of only makeing mistakes just can fix, and the counter of other switches still can continue to beat synchronously (i.e. counting), until makeing mistakes or testing and finish.In good time the report an error realization of function that Here it is.This function has been arranged, anchor clamps can accurate recording go out switch which time the time make mistakes, this function is very important for switch testing.Concerning the high request occasion, switch make mistakes once just should be judged to bad.
More than all rolling counters forward scopes all can reach (scope: 0~99999999), certainly continue expansion, do not repeat them here 100,000,000 times to satisfy actual needs.
Certainly; the above only is a preferred implementation of the present utility model; should be understood that; for those skilled in the art; under the prerequisite that does not break away from the utility model principle; can also make some improvements and modifications, these improvements and modifications also should be considered as protection domain of the present utility model.

Claims (9)

1. switch test device, comprise switch testing anchor clamps and functional unit, described switch testing anchor clamps include motor, it is characterized in that, described switch testing anchor clamps are by microcomputerized control, described micro computer is provided with switch and finishes the number of times display unit, and described micro computer is connected with described functional unit.
2. switch test device according to claim 1 is characterized in that, described micro computer is provided with the direction setting unit of control motor sense of rotation.
3. switch test device according to claim 1 is characterized in that described micro computer is provided with the switch number display unit.
4. switch test device according to claim 1 is characterized in that, described micro computer is provided with the qualified number of times setup unit of switch.
5. switch test device according to claim 1 is characterized in that, described micro computer is provided with switch residue degree display unit.
6. switch test device according to claim 1 is characterized in that, described micro computer is provided with the qualified judging unit of switch.
7. switch test device according to claim 1 is characterized in that described micro computer is provided with display screen.
8. switch test device according to claim 7 is characterized in that, described display screen is a LCD display.
9. switch test device according to claim 1 is characterized in that, described motor is a stepper motor; Described functional unit is some buttons.
CN2009201940428U 2009-09-04 2009-09-04 Switch testing device Expired - Fee Related CN201497792U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009201940428U CN201497792U (en) 2009-09-04 2009-09-04 Switch testing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009201940428U CN201497792U (en) 2009-09-04 2009-09-04 Switch testing device

Publications (1)

Publication Number Publication Date
CN201497792U true CN201497792U (en) 2010-06-02

Family

ID=42440996

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009201940428U Expired - Fee Related CN201497792U (en) 2009-09-04 2009-09-04 Switch testing device

Country Status (1)

Country Link
CN (1) CN201497792U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103163458A (en) * 2011-12-19 2013-06-19 海洋王照明科技股份有限公司 Rotary switch testing control circuit and testing tool
CN104215531A (en) * 2013-05-30 2014-12-17 深圳市海洋王照明工程有限公司 Key switch lift test circuit
CN104569797A (en) * 2013-10-22 2015-04-29 珠海格力电器股份有限公司 Service life test system of contact-type switch and service life test method
CN109994029A (en) * 2019-05-16 2019-07-09 唐山宝乐智能科技股份有限公司 Switch experiment platform

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103163458A (en) * 2011-12-19 2013-06-19 海洋王照明科技股份有限公司 Rotary switch testing control circuit and testing tool
CN104215531A (en) * 2013-05-30 2014-12-17 深圳市海洋王照明工程有限公司 Key switch lift test circuit
CN104215531B (en) * 2013-05-30 2017-02-08 深圳市海洋王照明工程有限公司 Key switch lift test circuit
CN104569797A (en) * 2013-10-22 2015-04-29 珠海格力电器股份有限公司 Service life test system of contact-type switch and service life test method
CN109994029A (en) * 2019-05-16 2019-07-09 唐山宝乐智能科技股份有限公司 Switch experiment platform

Similar Documents

Publication Publication Date Title
CN201497792U (en) Switch testing device
US20050015682A1 (en) System and method for performing guided procedures
US20190004087A1 (en) Electronic product test jig
JPH1086336A (en) Automatically controlling apparatus for process of replacing press plate in printing machine
CN104034990A (en) Remote control testing method and system
CN101561471B (en) Vehicle instrument circuit board combined detection table and detection method thereof
CN103852718A (en) Testing system and method for keyboard
CN112056760B (en) One-stop test system and method
CN107526354B (en) Automatic test method and test device for electric vehicle controller
US8635502B2 (en) Debug card and method for diagnosing faults
JP3688164B2 (en) Display device for injection molding machine
CN108198638A (en) Shutdown breaker routine test system and method based on soft logic
CN201497793U (en) Switch testing device
CN102781211A (en) Part installing system
JPH0387671A (en) Diagnostic device for electro-mechanical system device
KR100817851B1 (en) Method for electronic components error self-diagnostic
JPH0326130A (en) Controller
CN201421490Y (en) Vehicle-mounted instrument circuit board combined checking platform
CN209802686U (en) Dehumidifier testing arrangement with from judging production mode
CN105954023B (en) A kind of power type machine for testing torsion
TWI233494B (en) Backboard diagnostic system and method
CN219936021U (en) Fool-proof device for full-automatic testing of touch circuit
JPH0435283A (en) Television receiver
CN218675208U (en) Terminal control unit PCB testing arrangement
CN218917556U (en) Tool testing device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100602