CN201473216U - Steel bar mounting hanger - Google Patents
Steel bar mounting hanger Download PDFInfo
- Publication number
- CN201473216U CN201473216U CN 200920175418 CN200920175418U CN201473216U CN 201473216 U CN201473216 U CN 201473216U CN 200920175418 CN200920175418 CN 200920175418 CN 200920175418 U CN200920175418 U CN 200920175418U CN 201473216 U CN201473216 U CN 201473216U
- Authority
- CN
- China
- Prior art keywords
- crossbeam
- suspension bracket
- column
- hanging box
- fixedly connected
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Reinforcement Elements For Buildings (AREA)
Abstract
A steel bar mounting hanger comprises a door-shaped hanging frame and a hoisting device; the door-shaped hanging frame comprises upright posts and a cross beam; lower ends of two upright posts of the door-shaped hanging frame are fixedly connected with a flat-plate base; and the hoisting device is arranged on the lower side at the middle part of the cross beam of the door-shaped hanging frame and comprises a hoisting ring fixedly connected with the lower side of the middle part of the cross beam and a chain hoist mounted on the hoisting ring. The hanger breakthroughs the traditional operation specifications for mounting a reinforcing cage, and the reinforcing cage is interposed into a molding plate through the chain hoist on the steel hanger, thereby facilitating installation of the reinforcing cage and facilitating rectification and improvement; and the hanger is extremely favorable for popularization and application on the relative engineering construction site.
Description
Technical field
The utility model relates to a kind of special-purpose lifting device that is used for reinforcement installation, particularly relates to a kind of reinforcement installation suspension bracket.
Background technology
At present, most engineerings generally are to create the scope of operation by following chock a tree, used in making timber for boats in the steel reinforcement cage fabrication and installation, and when the steel reinforcement cage installation process, the position of beam steel cage and post muscle is wayward, in case steel reinforcement cage is put into template, it is also quite difficult to carry out the reinforcing bar rectification again.Therefore press for a kind of special tool and address this problem, particularly a kind of lifting device of special use.
The utility model content
In order to solve the problem that exists in the above-mentioned engineering construction, the utility model proposes a kind of reinforcement installation suspension bracket, this suspension bracket has been broken through traditional steel reinforcement cage fitting operation rules, by the bottle gouard moved by hands on the steel suspension bracket steel reinforcement cage is put into template, promptly make things convenient for steel reinforcement cage to install, also be convenient to rectification.
Content of the present utility model is: a kind of reinforcement installation suspension bracket, comprise a font hanging box and a lifting appliance, and door font hanging box comprises column and crossbeam, the lower end of two columns of described door font hanging box is fixedly connected with flat base; Described lifting appliance is arranged on the middle part downside of a crossbeam of font hanging box.
Described lifting appliance comprises the hoisting ring of the middle part downside that is fixedly connected on crossbeam and is installed in bottle gouard moved by hands on the hoisting ring.
Described bottle gouard moved by hands is connected with hoisting ring by hook, and described reinforcing bar suspension ring are installed or weld together by fastener and crossbeam.
The column and the crossbeam bonded assembly corner of described door font hanging box are fixedly connected with reinforced liner.Described column and flat base junction are provided with oblique reinforced liner.
Install or weld together by fastener between described door font column, crossbeam, flat base and the reinforced liner.
Described column and crossbeam adopt section steel manufacture.
The beneficial effects of the utility model are:
This reinforcement installation suspension bracket utilizes lifting appliance earlier steel reinforcement cage to be sling, be convenient to workman's colligation stirrup and intert main muscle, after treating that the steel reinforcement cage colligation finishes, by lifting appliance steel reinforcement cage is put into template again, and can in let-in process, adjust the position of steel reinforcement cage at any time, make it reach ideal position, improve the success ratio of steel reinforcement cage installation and the quality of installation thereof; It is easy to operate, is convenient to the reinforcing bar rectification, can raise labour efficiency.
The crucial force part of this suspension bracket is provided with reinforced liner, has further improved the load-carrying capacity and the safety in utilization that change suspension bracket, and the bulk strength height, and not fragile, be protected service life.
Description of drawings
Fig. 1 is the main TV structure scheme drawing of this reinforcement installation suspension bracket
Fig. 2 is the left view of Fig. 1
Fig. 3 is the structural representation under the running condition of this reinforcement installation suspension bracket
The specific embodiment
Embodiment one: referring to Fig. 1, Fig. 2, Fig. 3, among the figure 1 be hanging box column, 2 for flat base, 3 for the suspension ring of lifting appliance, 4 for the reinforced liner between column and the flat base, 5 reinforced liners for column and crossbeam bonded assembly corner, 6 for bottle gouard moved by hands, 7 for lifting rope, 8 for steel reinforcement cage, 9 be the crossbeams of template, 10 hanging boxes.
Reinforcement installation suspension bracket shown in the figure comprises a font hanging box and a lifting appliance, and door font hanging box comprises column and crossbeam, and the lower end of two columns of described door font hanging box is fixedly connected with flat base; Described lifting appliance is arranged on the middle part downside of a crossbeam of font hanging box.Described lifting appliance comprises the hoisting ring of the middle part downside that is fixedly connected on crossbeam and is installed in bottle gouard moved by hands on the hoisting ring.Described bottle gouard moved by hands is connected with hoisting ring by hook, and described reinforcing bar suspension ring are installed or weld together by fastener and crossbeam.The column and the crossbeam bonded assembly corner of described door font hanging box are fixedly connected with reinforced liner.Described column and flat base junction are provided with oblique reinforced liner.Install or weld together by fastener between described door font column, crossbeam, flat base and the reinforced liner.Described column and crossbeam adopt section steel manufacture.
In the time of use, this suspension bracket is arranged on correct position, earlier steel reinforcement cage is sling by bonded assembly lifting rope on the bottle gouard moved by hands of lifting appliance bottom, allow the workman's colligation stirrup and the main muscle that interts, after treating that the steel reinforcement cage colligation finishes, by lifting appliance steel reinforcement cage is put into template again, and can in let-in process, adjust the position of steel reinforcement cage at any time, make it reach ideal position, improve the success ratio of steel reinforcement cage installation and the quality of installation thereof.
Claims (6)
1. a reinforcement installation suspension bracket comprises a font hanging box and a lifting appliance, and door font hanging box comprises column and crossbeam, it is characterized in that: the lower end of two columns of described door font hanging box is fixedly connected with flat base; Described lifting appliance is arranged on the middle part downside of a crossbeam of font hanging box.
2. reinforcement installation suspension bracket according to claim 1 is characterized in that: described lifting appliance comprises the hoisting ring of the middle part downside that is fixedly connected on crossbeam and is installed in bottle gouard moved by hands on the hoisting ring.
3. reinforcement installation suspension bracket according to claim 2 is characterized in that: described bottle gouard moved by hands is connected with hoisting ring by hook, and described reinforcing bar suspension ring are installed or weld together by fastener and crossbeam.
4. reinforcement installation suspension bracket according to claim 1 is characterized in that: the column and the crossbeam bonded assembly corner of described door font hanging box are fixedly connected with reinforced liner; Described column and flat base junction are provided with oblique reinforced liner.
5. reinforcement installation suspension bracket according to claim 4 is characterized in that: install or weld together by fastener between described door font column, crossbeam, flat base and the reinforced liner.
6. the reinforcement installation suspension bracket described according to the arbitrary claim of claim 1-5 is characterized in that: described column and crossbeam adopt section steel manufacture.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200920175418 CN201473216U (en) | 2009-08-24 | 2009-08-24 | Steel bar mounting hanger |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200920175418 CN201473216U (en) | 2009-08-24 | 2009-08-24 | Steel bar mounting hanger |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201473216U true CN201473216U (en) | 2010-05-19 |
Family
ID=42409460
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200920175418 Expired - Fee Related CN201473216U (en) | 2009-08-24 | 2009-08-24 | Steel bar mounting hanger |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201473216U (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102587661A (en) * | 2012-03-22 | 2012-07-18 | 广东中城建设集团有限公司 | Method for constructing tall-section structural column of reinforced concrete frame |
CN103072004A (en) * | 2013-01-21 | 2013-05-01 | 湖南省第五工程有限公司 | Installation method of electric hoist hanger |
CN104453243A (en) * | 2014-12-03 | 2015-03-25 | 武汉建工集团股份有限公司 | Erection device and method for steadily feeding cast-in-place concrete beam into mold |
CN104453231A (en) * | 2014-12-07 | 2015-03-25 | 苏州汇诚智造工业设计有限公司 | Gantry type building construction lifting device as well as manufacturing method and construction method thereof |
CN105274929A (en) * | 2014-10-22 | 2016-01-27 | 吉林省久盛绿色建材股份有限公司 | All-in-one assembling machine for road construction |
CN108277921A (en) * | 2017-12-29 | 2018-07-13 | 上海建工二建集团有限公司 | Combined hoisting system suitable for waffle slab steel bar construction |
CN109469083A (en) * | 2018-10-31 | 2019-03-15 | 中建三局第建设工程有限责任公司 | Foundation beam steel reinforcement cage assembly system and its construction method |
CN110172965A (en) * | 2019-06-04 | 2019-08-27 | 江苏中南建筑产业集团有限责任公司 | Diaphram wall steel bar segmentation formula constructing device and construction method |
-
2009
- 2009-08-24 CN CN 200920175418 patent/CN201473216U/en not_active Expired - Fee Related
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102587661B (en) * | 2012-03-22 | 2014-03-26 | 广东中城建设集团有限公司 | Method for constructing tall-section structural column of reinforced concrete frame |
CN102587661A (en) * | 2012-03-22 | 2012-07-18 | 广东中城建设集团有限公司 | Method for constructing tall-section structural column of reinforced concrete frame |
CN103072004A (en) * | 2013-01-21 | 2013-05-01 | 湖南省第五工程有限公司 | Installation method of electric hoist hanger |
CN103072004B (en) * | 2013-01-21 | 2015-05-06 | 湖南省第五工程有限公司 | Installation method of electric hoist hanger |
CN105274929A (en) * | 2014-10-22 | 2016-01-27 | 吉林省久盛绿色建材股份有限公司 | All-in-one assembling machine for road construction |
CN105274929B (en) * | 2014-10-22 | 2017-07-28 | 吉林久盛生态环境科技股份有限公司 | Road construction assembly all-in-one |
CN104453243A (en) * | 2014-12-03 | 2015-03-25 | 武汉建工集团股份有限公司 | Erection device and method for steadily feeding cast-in-place concrete beam into mold |
CN106348188A (en) * | 2014-12-07 | 2017-01-25 | 苏州汇诚智造工业设计有限公司 | Method for manufacturing gantry type building construction lifting device |
CN104453231A (en) * | 2014-12-07 | 2015-03-25 | 苏州汇诚智造工业设计有限公司 | Gantry type building construction lifting device as well as manufacturing method and construction method thereof |
CN108277921A (en) * | 2017-12-29 | 2018-07-13 | 上海建工二建集团有限公司 | Combined hoisting system suitable for waffle slab steel bar construction |
CN109469083A (en) * | 2018-10-31 | 2019-03-15 | 中建三局第建设工程有限责任公司 | Foundation beam steel reinforcement cage assembly system and its construction method |
CN110172965A (en) * | 2019-06-04 | 2019-08-27 | 江苏中南建筑产业集团有限责任公司 | Diaphram wall steel bar segmentation formula constructing device and construction method |
CN110172965B (en) * | 2019-06-04 | 2021-08-10 | 江苏中南建筑产业集团有限责任公司 | Sectional construction device and construction method for underground continuous wall reinforcing steel bars |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201473216U (en) | Steel bar mounting hanger | |
CN202080812U (en) | Dedicated sling system for large-scaled reinforcing cage | |
CN203602256U (en) | Hoisting portal frame | |
CN201172574Y (en) | Precast beam reinforced bar hoisting rack | |
CN202296815U (en) | Hoisting support rod for large-tonnage large-span structure | |
CN202643090U (en) | Aluminium profile hanging basket | |
CN201762035U (en) | Simple crane movable arm | |
CN102398849A (en) | Method for moving whole crawler crane down to dock | |
CN201212004Y (en) | Wheel center spreader | |
CN201526154U (en) | Lifting device for a cylindrical architecture | |
CN203392111U (en) | Prefabricated concrete wall plate transporting device | |
CN203715156U (en) | Convenient crane | |
CN213016153U (en) | Combined crawling ladder for construction | |
CN201151954Y (en) | Steel column and concrete column connection structure | |
CN202609753U (en) | Hoisting supporting rod for large-size structural member | |
CN201424346Y (en) | Crane for clamping coal block | |
CN201649667U (en) | Reinforcement cage immersion guide frame | |
CN2839223Y (en) | The construction lifting appliance in floor type steel structure circle storehouse | |
CN212667224U (en) | Steel reinforcement cage transport vechicle | |
CN215711274U (en) | Perpendicular transport means encorbelments | |
CN215803102U (en) | Auxiliary frame for hanging basket | |
CN221235063U (en) | Balancing Liang Diaogou assembly equipment suitable for construction of oversized hydraulic pile hammer | |
CN217627094U (en) | Hoisting device for overturning and overhauling water guide mechanism | |
CN201297031Y (en) | Entirety pulling yoke for movable mould base | |
CN202625601U (en) | Column-base plate auxiliary assembly device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100519 Termination date: 20180824 |