CN201446210U - Gasification forging continuous heating furnace - Google Patents

Gasification forging continuous heating furnace Download PDF

Info

Publication number
CN201446210U
CN201446210U CN2009200145221U CN200920014522U CN201446210U CN 201446210 U CN201446210 U CN 201446210U CN 2009200145221 U CN2009200145221 U CN 2009200145221U CN 200920014522 U CN200920014522 U CN 200920014522U CN 201446210 U CN201446210 U CN 201446210U
Authority
CN
China
Prior art keywords
gas
pouch chamber
heating furnace
forging
laryngeal pouch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009200145221U
Other languages
Chinese (zh)
Inventor
周世强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WANFANGDIAN SHIQIANG BEARING PRODUCTION CO Ltd
Original Assignee
WANFANGDIAN SHIQIANG BEARING PRODUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WANFANGDIAN SHIQIANG BEARING PRODUCTION CO Ltd filed Critical WANFANGDIAN SHIQIANG BEARING PRODUCTION CO Ltd
Priority to CN2009200145221U priority Critical patent/CN201446210U/en
Application granted granted Critical
Publication of CN201446210U publication Critical patent/CN201446210U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to a gasification forging continuous heating furnace, which comprises a gas generator and a forging billet heating furnace which are connected by a laryngeal pouch chamber, and is characterized in that the bottom of the forging billet heating furnace is of a ladder-shaped structure, and a high-temperature zone and a low-temperature zone are formed in a hearth; three nozzles are arranged in the high-temperature zone of the hearth, and the gas inlet ends of the three nozzles are fixedly connected the three gas outlets of the laryngeal pouch chamber; the gas inlet end of the laryngeal pouch chamber is connected with the gas outlet end of the gas generator, and a spiral preheater is arranged in the flue of the forging billet heating furnace and utilizes the excess heat of the heating furnace to heat the air flowing into the gas generator so as to save energy. The utility model utilizes the best short water jacket to directly supply hot air needed by gas conversion, reduces fuel, water and gas consumption, can reduce environmental pollution and greatly improve forging quality.

Description

Gasification forging continuous reheating furnace
Technical field
The utility model relates to a kind of heating furnace, particularly relates to a kind of heating furnace that forge piece blank reheating is carried out preheating.
Background technology
To carry out The pre-heat treatment to forge piece blank reheating during forging, the most of column type body of heater that adopts of present widely used coal gas forge furnace, the stove a heatable brick bed that is located at scarfing cinder box, particularly heating furnace is flat, does not have high low-temperature space, material section preheating oxidation is serious, firing rate is slow, and this has not only reduced the quality of forging, and has reduced production efficiency, improved production cost, and power consumption is big.
Summary of the invention
The stove a heatable brick bed that the purpose of this utility model provides a kind of heavy caliber, low pressure and short distance row coal gas formula forging heating furnace body, forging heating furnace body is stepped, can increase substantially pre-thermal mass of forging and production efficiency, cut down the consumption of energy, and security of operation.
The technical scheme that adopts is:
Gasification forging continuous reheating furnace, comprise gas generator, forge piece blank reheating heating furnace and laryngeal pouch chamber, the furnace bottom that it is characterized in that described blank heating stove is a stepped construction, and formation low-temperature space and high-temperature region are provided with a plurality of boccas in the high-temperature region of the burner hearth of blank heating stove in burner hearth; In the flue of blank heating stove, be provided with spiral preheating device, the blast pipe of spiral preheating device is connected with the air outlet of peripheral hardware air blast, the air outlet of spiral preheating device is connected with first discharge pipe and second discharge pipe, first discharge pipe is connected with an end of a blast pipe, the other end of the blast pipe blast cap interior with being arranged on gas generator is connected, second discharge pipe is connected with the air inlet that divides the wind jar, divide the gas outlet of wind jar to be connected with a plurality of secondary wind inleting tubes, a plurality of secondary wind inleting tubes connect with corresponding bocca respectively; The gas inlet end of laryngeal pouch chamber and the gas exit end of gas generator are fixedly connected into an overall structure, and the gas exit end of laryngeal pouch chamber and the gas entry end of blank preheating furnace connect into an overall structure; The front end face of the inwall of laryngeal pouch chamber is an arcwall face, and the bottom of laryngeal pouch chamber is provided with the storage ash-pit; The front end face of laryngeal pouch chamber is provided with a plurality of coal gas and portals, a plurality of coal gas portal respectively be arranged on burner hearth in a plurality of boccas corresponding; The gas inlet end of a plurality of boccas is separately fixed in coal gas on the front end face of corresponding laryngeal pouch chamber portals.
Be provided with spiral preheating device in the flue of forging heating furnace, so that make full use of the waste heat that heating furnace produces, save the energy, the air outlet of spiral type heated device is connected with first discharge pipe and second discharge pipe.First discharge pipe is connected with a blast pipe.Second discharge pipe is connected with dividing the wind jar, divides the wind jar to be provided with a plurality of gas outlets, is connected with secondary wind inleting tube respectively, each secondary wind inleting tube and corresponding bocca connection.The blank intake mechanism of forging (or claiming blank) heating furnace is a known technology, comprises liftout platform, hydraulic cylinder, hydraulic pump.
The utlity model has following advantage:
1, the forge furnace size the is matched required hot gas of gas burner, directly giving gas with the short water jacket of the best transforms required hot gas, reduces fuel and aqueous vapor consumption.
2, adopt bore diffusion type torch firing (burner), do not tie coal tar, do not produce the high temperature streamline, improve body of heater service life (more than 3 times) heating furnace and adopt at the bottom of the terraced wall furnace, make the high low-temperature space of heating furnace clearly demarcated, improve heating quality, shorten oxidizing process, prolong stove a heatable brick bed service life (more than 2 times).
Gasification forging continuous reheating furnace is than a large amount of coal gas forge furnaces that use are energy-conservation more than 30% now, blank oxidization burning loss rate reduces about 1.5%, coal-iron ratio is more than 1: 6, various flue gases, oxide emissions is lower than national requirements for environmental protection, the most of column type body of heater that adopts of gasification forging continuous reheating furnace, the scarfing cinder basin. no fire grate, water logging lime-ash comb coal, best short water jacket, do not have to press and add water automatically, used hot gas when the hot gas that produces gives gas generation: one, the whole hot wind supplies of secondary wind (utilizing surplus temperature heating), owing to be provided with the laryngeal pouch chamber, constitute heavy caliber, low pressure, short distance row coal gas formula body of heater, coal gas forms whirlwind within it, sulfide and heavy metal deposition (are promptly stored up ash-pit) in the laryngeal pouch chamber store, remove during low temperature---do not have before the coal, when chimney has negative pressure (no draft) dust in the laryngeal pouch is not removed in heating clamber with a wind.
3, body of heater is equipped with the visual row pressure extra heavy pipe of low temperature and body of heater is not had press safe and reliable, leaves the easy-opening fire door, is beneficial to scarfing cinder and lights a fire, leave three prepurging cinclides, and can handle coal-fired coking, leave a perspective mouth, to observe coal seam thickness and fired state, look the type water tank outside being equipped with, be convenient to water jacket and add water.The coal gas forge furnace is taked the anti-burn off dirt of hot whirlwind, the dedusting (double dust collection) of laryngeal pouch formula low temperature feedback, and small-bore row's coal gas, the diffusion type torch firing also leaves enough coal gas mixed combustion spaces; Adopt hydraulic pressure liftout mode, be beneficial to continuous heating; Long apart from preheating section, be beneficial to the blank preheating; The heating of best cell section high temperature is beneficial to Fast Heating; At the bottom of the terraced wall furnace, make high low-temperature space clearly demarcated, alleviate oxidation and improve stove a heatable brick bed service life; Preheater is placed with partially and is beneficial to air-flow and is flowed to the low temperature direction by high temperature, makes fire door flame little, and the blank pre-heat effect is good.
4, reduce pollution on the environment.
5, increase substantially forging quality.
Description of drawings
Fig. 1 is the structural representation of a kind of embodiment of the present utility model.
Fig. 2 is the A-A view of Fig. 1.
Fig. 3 is the B-B view of Fig. 1.
Fig. 4 is laryngeal pouch chamber and bocca assembling schematic diagram.
The specific embodiment
Gasification forging continuous reheating furnace is made up of gas generator 23 and forge piece blank reheating heating furnace 24.
Gas generator comprises body of heater 25, covers to be equipped with on body of heater 25 to add coal bunker 1 and prepurging hole 22.Be provided with at the discharging opening place that adds coal bunker 1 and put coal valve 2, be provided with water jacket 4 on the inwall of the burner hearth part of body of heater 25, water jacket 4 is connected with air accumulator 9 by pipeline 26, and safe pressure release valve 8 is installed on the air accumulator 9.Air accumulator 9 is connected with a blast pipe 27 by pipeline.When water vapour pressure in the air accumulator 9 greater than when setting value, safe pressure release valve starts pressure release.Be provided with blast cap 6 in body of heater 25 bottoms, blast cap 6 is connected with first discharge pipe 28 of spiral preheater by a blast pipe 27.The blast pipe 17 of spiral preheating device 12 is connected with air blast.Furnace wall arranged outside in body of heater 25 bottoms has water box 7, and water box 7 communicates with the inlet opening of body of heater 25, makes body of heater 25 bottoms have water, with water seal blast cap 6.On the furnace wall of body of heater 25, be provided with peep hole 3 and fire door 5.
The forge piece blank reheating heating furnace comprises three boccas 11 and spiral preheater 12 that body of heater 25, laryngeal pouch chamber 29, hydraulic cylinder 13, liftout platform 14, hydraulic pump 16, the structure of heating furnace is identical.Spiral preheater 12 is arranged in the flue 19 of body of heater 25 of blank heating stove.
Gas generator 23 is connected with blank heating stove 24 by laryngeal pouch chamber 29. and the gas inlet end of laryngeal pouch chamber 29 and the gas exit end of gas generator 23 are fixedly connected into an overall structure; The gas exit end of laryngeal pouch chamber 29 and the gas entry end of blank heating stove 24 connect into an overall structure. and the front end face 30 of the inwall of laryngeal pouch chamber 29 is arcwall face, so that the coal gas that enters forms circulation in laryngeal pouch chamber 29. 29 bottoms, laryngeal pouch chamber are provided with storage ash-pit 10. and are provided with three coal gas and portal 32 in that the front end face 30 of laryngeal pouch chamber 29 is laterally equidistant, the rear end of three boccas 11 (air inlet end) is separately fixed at corresponding coal gas and portals in 32. bocca 11 flares, bocca 11 front ends are positioned at the high-temperature region 35 of blank heating stove 24. and the furnace bottom 33 of blank heating stove is stepped construction, form low-temperature space 34 and high-temperature region 35 in the burner hearth, wherein the blank entrance point is a low-temperature space. the air outlet of spiral preheating device 12 is connected with first discharge pipe 28 and second discharge pipe 36, first discharge pipe 28 is connected with a blast pipe 27, being equiped with air intake valve 20. second discharge pipes 36 on a blast pipe 28 is connected with the air inlet that divides wind jar 15, be equiped with the second air intake valve 21 on second discharge pipe 36, divide wind jar 15 that three gas outlets are arranged, three gas outlets are connected with the inlet end of three secondary wind inleting tubes 31 respectively, and the outlet side of three secondary wind inleting tubes 31 connects with corresponding bocca 11 respectively.
The feeding mechanism of blank heating stove is known, comprises frame 18, hydraulic cylinder 13, liftout platform 14 and hydraulic pump 16.Need a plurality of forge piece blank reheating of heating to be successively placed on and expect to feed continuously in the blank heating stove 24 by above-mentioned hydraulic mechanism on the platform, successively through low-temperature space 34, export by discharging opening after entering high-temperature region 33.

Claims (2)

1. gasification forging continuous reheating furnace, comprise gas generator (23), forge piece blank reheating heating furnace (24) and laryngeal pouch chamber (29), the furnace bottom (33) that it is characterized in that described blank heating stove (24) is a stepped construction, forms low-temperature space (34) and high-temperature region (35) and be provided with a plurality of boccas (11) in burner hearth in the high-temperature region (35) of the burner hearth of blank heating stove (24); In the flue (19) of blank heating stove (24), be provided with spiral preheating device (12), the blast pipe (17) of spiral preheating device (12) is connected with the air outlet of peripheral hardware air blast, the air outlet of spiral preheating device (12) is connected with first discharge pipe (28) and second discharge pipe (36), first discharge pipe (28) is connected with an end of a blast pipe (27), the other end of a blast pipe (27) blast cap (6) interior with being arranged on gas generator (23) is connected, second discharge pipe (36) is connected with the air inlet that divides wind jar (15), divide the gas outlet of wind jar (15) to be connected with a plurality of secondary wind inleting tubes (31), a plurality of secondary wind inleting tubes (31) connect with corresponding bocca (11) respectively; The gas exit end of the gas inlet end of laryngeal pouch chamber (29) and gas generator (23) is fixedly connected into an overall structure, and the gas exit end of laryngeal pouch chamber (29) and the gas entry end of blank preheating furnace connect into an overall structure; The front end face (30) of the inwall of laryngeal pouch chamber (29) is an arcwall face, and the bottom of laryngeal pouch chamber (29) is provided with storage ash-pit (10); The front end face (30) of laryngeal pouch chamber (29) is provided with a plurality of coal gas and portals (32), a plurality of coal gas portal (32) respectively be arranged on burner hearth in a plurality of boccas (11) corresponding; The gas inlet end of a plurality of boccas (11) is separately fixed at coal gas on the front end face (30) of corresponding laryngeal pouch chamber (29) and portals in (32).
2. gasification forging continuous reheating furnace according to claim 1 is characterized in that described bocca (11) is for tubaeform.
CN2009200145221U 2009-06-11 2009-06-11 Gasification forging continuous heating furnace Expired - Lifetime CN201446210U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009200145221U CN201446210U (en) 2009-06-11 2009-06-11 Gasification forging continuous heating furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009200145221U CN201446210U (en) 2009-06-11 2009-06-11 Gasification forging continuous heating furnace

Publications (1)

Publication Number Publication Date
CN201446210U true CN201446210U (en) 2010-05-05

Family

ID=42550920

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009200145221U Expired - Lifetime CN201446210U (en) 2009-06-11 2009-06-11 Gasification forging continuous heating furnace

Country Status (1)

Country Link
CN (1) CN201446210U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101920303B (en) * 2009-06-11 2013-01-02 瓦房店世强轴承制造有限公司 Gasification forging continuous reheating furnace

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101920303B (en) * 2009-06-11 2013-01-02 瓦房店世强轴承制造有限公司 Gasification forging continuous reheating furnace

Similar Documents

Publication Publication Date Title
CN205090598U (en) Coal -fired powder boiler of vertical extreme misery tubular construction
CN205258015U (en) Si liepu activation furnace
CN204345615U (en) Biomass chain boiler row boiler heating system
CN204213928U (en) A kind of helical structure self-preheating type burner
CN103388815B (en) Horizontal type triple-pass chain-grate boiler combusting coal and biomass fuel
CN206266508U (en) Radiant tube gas generator
CN202350105U (en) Dual-purpose electronic temperature-controlled constant-temperature boiler using biomass fuel and coal
CN101920303B (en) Gasification forging continuous reheating furnace
CN202432680U (en) Reverse gas fire pipe environment-friendly air heating furnace
CN102012029B (en) Heat-storing combustion apparatus and biomass gas heating system
CN201446210U (en) Gasification forging continuous heating furnace
CN203744230U (en) Coal production gas integrated chain grate boiler
CN217004419U (en) Multi-fuel energy-saving steam generator
CN210568368U (en) Biomass briquette fuel semi-gasification combustion pressure-bearing boiler
CN201212729Y (en) Biomass granular fuel boiler
CN2901154Y (en) Gasifying room burning boiler
CN102997251A (en) Liquid waste and exhaust gas recycling system for chemical by-products
CN203534218U (en) Recovery and utilization system for heat of flue gas discharged from normalizing treatment
CN203240744U (en) Energy saving boiler
CN106398772A (en) Radiant-tube gas generator
CN202221089U (en) Small-sized medical waste incinerator with horizontal spray gun
CN204922921U (en) Fire energy -efficient extreme misery of living beings pipe steam boiler
CN201772617U (en) Carbon and hydrogen co-combustion pressure boiler
CN206266647U (en) Radiant tube is reduced directly shaft furnace
CN110440578A (en) A kind of vertical and cylindrical tubular heater

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20100505

Effective date of abandoning: 20090611

RGAV Abandon patent right to avoid regrant