Simple greenhouse assembling structure Download PDFInfo
- Publication number
- CN201398337Y CN201398337Y CN2009201376929U CN200920137692U CN201398337Y CN 201398337 Y CN201398337 Y CN 201398337Y CN 2009201376929 U CN2009201376929 U CN 2009201376929U CN 200920137692 U CN200920137692 U CN 200920137692U CN 201398337 Y CN201398337 Y CN 201398337Y
- Authority
- CN
- China
- Prior art keywords
- frame group
- greenhouse
- unit frame
- sheet material
- package assembly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A40/00—Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
- Y02A40/10—Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
- Y02A40/25—Greenhouse technology, e.g. cooling systems therefor
Landscapes
- Greenhouses (AREA)
Abstract
The utility model discloses a simple greenhouse assembling structure which comprises a wall surface and a top surface, wherein the wall surface and the top surface comprise at least one unit frame group, the unit frame group is formed through a framework fixing with a plate, all the unit frame groups are connected in locking mode through fasteners, and the end portion of one unit frame group is connected with another unit frame group which is split-jointed with the unit frame group for location through a connector. As sheet materials which form the wall surface of a greenhouse and the framework adopt integral modularized design, consumers do not need to assemble sheet materials themselves, and the frame groups of all the parts are connected for location through simple fasteners, thereby the assembly of a greenhouse is simpler and easier, furthermore, if a sunlight-transparent sheet of one of the frame groups is damaged, the frame group can be disassembled only through opening the fastener, which does not need to disassemble the whole greenhouse, thereby the repairing and the maintenance of the greenhouse are more convenient and easier, and the frame groups can be split-jointed andextended in space at will according to needed length, which enables the greenhouse to have more flexible assembling property.
Description
Technical field
The relevant a kind of greenhouse of the utility model is meant a kind of simple greenhouse package assembly especially.
Background technology
The greenhouse can printing opacity for having, insulation, is used for the facility of cultivated plant.In the season that is not suitable for plant growing, can be provided breeding time and increase output, be used for plant cultivation such as low temperature season warm season vegetable, flowers, forest more or grow seedlings etc.
And as the outer simple greenhouse that uses of family, be mostly by being decomposed into the smaller units body by splicing and combining.The structure of its splicing mainly is to be combined into hothouse framework by the rod member with mating groove, and the light-passing board that constitutes the greenhouse wall is to be embedded in the mating groove of rod member from the top-down cunning of frame ends that constitutes, and the light-passing board at the top in greenhouse is also to be to finish splicing and combining of greenhouse with this from the frame ends cunning that constitutes is embedded in the mating groove of rod member in addition.But there is following shortcoming in actual use in the simple greenhouse of this structure:
1, owing to be to piece together the embedding light-passing board again after constituting framework by rod member, and multiple joint, section bar and accessory are various, thereby the splicing assembling that makes greenhouse effort comparatively.
2, printing opacity edges of boards portion needs to fix with sealing strip or glass cement, and light-passing board is deviate from after stressed easily, has potential safety hazard.
2, because light-passing board is to need to be embedded in the mating groove of rod member from the frame ends cunning successively that constitutes, if wherein light-passing board of greenhouse one sidewall damages, when needing place under repair to change, the top in greenhouse must be removed, just can be with the end embedding mating groove of new light-passing board from framework, so, make the repairing attended operation effort in greenhouse loaded down with trivial details.
The utility model content
It is convenient that the purpose of this utility model provides a kind of order assembling, simple greenhouse's package assembly that maintenance is more time saving and energy saving
For achieving the above object, solution of the present utility model is:
A kind of simple greenhouse package assembly, this greenhouse is made of wall and end face, wherein wall and end face are made of at least one unit frame group, this unit frame group is made of frame fixation one sheet material, carry out snap close by fastener between each unit frame group and connect, the end of unit frame group is positioned with another unit frame group of its splicing by joint and is connected in addition.
Described sheet material is transparent PC plate, sunlight board, adhesive plaster or glass material.
Described sheet material is that wood is moulded plate, iron wire or iron net.
Described unit frame group comprises by a framework and cooperates the sheet material of fixing with framework, and the metal tube of formation framework is the reeded shape tube of a side moulding, and the A/F of this groove is less than the vallecular cavity width; And the ora terminalis of sheet material is provided with the screens bar of diameter greater than the slot opening width.
Described framework by front and back two cross bars and about two vertical poles constitute, at the end cross of two vertical poles welding punching brace, in the punching of the end of two cross bars; Be fastenedly connected with screw or pulling rivet.
Described framework by front and back two cross bars and about two vertical poles constitute, in the formed connected contact pin of the end of two cross bars welding " L " type, in the punching of the end of two vertical poles; Be fastenedly connected with screw or pulling rivet.
Described sheet material is folder net adhesive plaster, and its four limit portions form lasso, and it is to fill in the screens bar, and the external diameter of lasso is greater than the width of slot opening.
Described each two edge that partly the frame group is adjacent are the interlocking of adaptive buckle by " U " type buckle simultaneously, are provided with lockhole on buckle, also are provided with lockhole in addition on edge.
Be folded with the tack sealing strip between described each adjacent unit frame group.
The end that described each unit frame group matches is provided with nipple, cooperates each frame group lower end, unit pin to have the positioning joint of connection; Wall unit frame group is connected locking with the unit frame group of end face by " C " type buckle.
After adopting such scheme, greenhouse structure of the present utility model has following advantage:
1, because the modularity design that the light-passing board that constitutes each wall of greenhouse and framework all be one, the consumer need not to assemble voluntarily sheet material, and the frame group of each several part during by easy fastener row connect the location, so make the assembling in greenhouse simplify more, easily capable.
When if the sheet material of 2 its center groups damages, only need open fastener and these frame assembling and dismantling can be removed, need not to be dismantled in whole greenhouse, so make the repairing in greenhouse safeguard more convenient and easy.
3, this frame group can be carried out the splicing extension of any space according to the length of needs, makes the greenhouse have assembly more flexibly.
Description of drawings
Fig. 1 is entire combination figure of the present utility model;
Fig. 2 is a partial exploded view of the present utility model;
Fig. 3 is the schematic perspective view of the utility model frame group;
Fig. 4 is the three-dimensional exploded view of the utility model frame group;
Fig. 5 is the assembled sectional view of the utility model frame group;
Fig. 6 is the schematic perspective view of another embodiment of the utility model frame group;
Fig. 7 is the three-dimensional exploded view of another embodiment of the utility model frame group;
Fig. 8 is the group cutaway view of another embodiment of the utility model frame group
Fig. 9 is number of assembling steps 1 schematic diagram of the present utility model;
Figure 10 is number of assembling steps 2 schematic diagrames of the present utility model;
Figure 11 is number of assembling steps 3 schematic diagrames of the present utility model.
Embodiment
As shown in Figure 1, 2, simple greenhouse of the present utility model package assembly, this greenhouse is made of four walls and two oblique top faces, and each wall and each oblique top face are made of one and more than one unit frame group, carry out snap close by fastener, fastener between each unit frame group and are located by connecting.
The front face 1 of its medium temperature chamber is made of two unit frame groups 11, a doorframe group 12 and three triangle frame groups 13, and doorframe group 12 is by two rail rods 14 are spacing up and down; The rear surface 2 in greenhouse is made of three unit frame groups 21 and two triangle frame groups 22; The left and right sides wall 3 in greenhouse respectively is made of at least one unit frame group 31 in addition; The two oblique top faces 4 in greenhouse respectively are made of at least one unit frame group 41.
Cooperate shown in Fig. 3,4,5, this sentences the unit frame group 31 that constitutes greenhouse side wall surface 3 and describes, this unit frame group 31 comprises by a framework a and cooperates the sheet material b that fixes with framework a, this framework a by front and back two cross bar a1 and about two vertical pole a2 constitute, the metal tube A that then forms framework a is the shape tube that a side forms groove A1, and the opening A11 width of this groove A1 is less than vallecular cavity A12 width; At the end cross of two vertical pole a2 welding punching brace a21, this brace a21 is an iron plate, then at the end punching a11 of two cross bar a1; This sheet material b is the PC sunlight board of printing opacity, and the thickness of this sheet material b is filled in screens bar c less than the width of opening A11 in sheet material b left and right end portions, and the diameter of this screens bar c is greater than the width of sheet material b thickness and groove A1 opening A11, to make two expansions of sheet material b; End about sheet material b is slipped among the groove A1 of two vertical pole a2, paste mackintosh d in the upper and lower end parts of sheet material b again, two ends are filled among the groove A1 of two cross bar a1 up and down again, because two ends, the left and right sides size of sheet material b is greater than the width of metal tube A groove A1 opening A11, when two cross bar a1 and two vertical pole a2 lock, promptly carry out fastening with screw or pulling rivet, two vertical pole a2 can outwards move to cooperate the width of cross bar a1, meanwhile, there is the screens bar c that fills in sheet material b both sides, just be equipped among the opening A11 of groove A1 can not deviate from, play the screens effect, make the sheet material b can be because of not stressed and be extruded; This screens bar c not only has the screens function, also have sealing function simultaneously, and the mackintosh d of sheet material c upper and lower side makes being in sheet material b and cooperating of framework a sealing state, and is then better at the insulation and the effect of heat insulation that are assembled into greenhouse in season, greenhouse.This sheet material b also can be materials such as PC plate or glass, as when being PC plate or glass material, can only need to increase sealing strip in its limit portion and get final product without screens bar c.
Cooperate shown in Fig. 6,7,8, another embodiment for unit frame group, it comprises by a framework a equally and cooperates with framework a and presss from both sides net adhesive plaster b ', this framework a by front and back two cross bar a1 and about two vertical pole a2 constitute, the metal tube A that then forms framework a is the shape tube that a side forms groove A1, and the opening A11 width of this groove A1 is less than vallecular cavity A12 width; At the formed connected contact pin a12 of the end of two cross bar a1 welding " L " type, this formed connected contact pin a12 is an iron plate equally, then at the end punching a22 of two vertical pole a2; Four limit portions of this folder net adhesive plaster b ' form lasso b1 ', and fill in screens bar c, and the external diameter of lasso b1 ' is greater than the width of groove A1 opening A11; The lasso b1 ' that will press from both sides four limit portions of net adhesive plaster b ' respectively slips among the groove A1 of two vertical pole a2 and two channel bar a1, when two cross bar a1 and two vertical pole a2 being locked with screw or pulling rivet, because the size of folder net adhesive plaster b ' the four lasso b1 ' of limit portion can play the screens effect equally greater than the width of groove A1 opening A11.Folder net adhesive plaster b ' can be because of not stressed and be extruded.Utilize the material characteristic of folder net adhesive plaster b ', make it to be in sealing state with cooperating of framework a, then better at the insulation and the effect of heat insulation that are assembled into greenhouse in season, greenhouse.
As Fig. 9 to Figure 11 and cooperate shown in Figure 2, greenhouse of the present utility model is when assembling, be earlier the margin up and down of the doorframe group 12 of greenhouse front face 1 to be positioned at two rail rods 14 up and down, piece together with other two position-limiting unit frame groups 11 again and lean on, and three triangle frame groups 13 are pieced together the upper end that leans against doorframe group 12 and each unit frame group 11, two adjacent edges of each part frame group are connected by " U " type buckle 5, be the interlocking of adaptive buckle 5 simultaneously, on buckle 5, be provided with lockhole 51, on the edge of each part frame group, also be provided with lockhole simultaneously, be that the triangle frame group 13 that straight forming has locking plate 141 to be mated is passed through the screw interlocking on the rail rods 14 herein, and each the frame group that connects by buckle 5 is locked by screw again; In addition between each adjacent frame group, be folded with tack sealing strip 0, with the insulation that improves the greenhouse and heat insulation effect; Further replenish fit clearance in the end that each frame group matches by nipple 6, to improve the globality of each frame group assembling.Unit frame group 31 with greenhouse two side walls 3 is vertical being resisted against on the front face 1 two ends architrave again, connect snap close by buckle 5 simultaneously, and the abutting end of lower end is fixed by joint 7, be gripped with tack sealing strip 0 between the frame group that matches equally, meanwhile, two unit frame group 41 assemblies in a certain angle of the two oblique top faces 4 in greenhouse are close together, its end is spacing by nipple 8, this unit frame group and the cooperation edge that is adjacent carry out snap close by fastener, each unit frame group 41 of end face is adjacent the edge that wall cooperates and connects snap close by " C " type buckle 9 herein, the match adjacent edge of two unit frame groups of 9 pairs of this buckles has a sealing function, so just form a preceding frame set of a greenhouse completed assembled, cooperate shown in Figure 9.
As shown in figure 10, the formation frame set that will constitute the part of the part of two side, greenhouse 2 and two oblique top faces 3 again forms another frame set by nipple 8 and " C " type buckle 9 again.So can form several frame set, the needs of greenhouse size be connected setting according to the individual.
Again as shown in figure 11, the frame set that respectively combines is docking together, and connects locking by fastener 5, and cooperates the positioning joint 7 of each frame group lower end, unit pin promptly to form a complete simple greenhouse.
Certainly, the sheet material 6 in this structure also can adopt wood to mould other sheet materials such as plate, iron net, can also form an easy storeroom according to above-mentioned assembling mode and do the use of pet chamber as storing use or cage chamber.
This shows that the utility model has following advantage by the unit frame group of each modularity design in the simple greenhouse of piecing together by assembling:
1, the modularity of each unit frame group design, frame structure makes the consumer need not to assemble voluntarily Light-passing board, sealing strip or beat glass cement;
2, parts are few, and the order assembling is easier;
3, the greenhouse can carry out according to consumer's needs increase and the minimizing of frame set quantity, and is right The space has a flexibly expansion and prolongs and the function of dwindling;
4, the screens bar at sheet material two ends or the setting of lasso form reinforced structure, and sheet material is being subjected to Be difficult for deviating from firm, safety after the power;
5, this sheet material adopts transparent PC plate, sunlight board, adhesive plaster or glass namely to form the greenhouse; And Adopt opaque wood to mould plate and namely form material storage room; Adopt iron wire or iron net can form pet The chamber;
If 6 wherein certain unit frame group damage and can be dismantled in individual greenhouse, namely can carry out The replacing of unit frame group.
Claims (10)
1, a kind of simple greenhouse package assembly, this greenhouse is made of wall and end face, it is characterized in that: wall and end face are made of at least one unit frame group, this unit frame group is made of frame fixation one sheet material, carry out snap close by fastener between each unit frame group and connect, the end of unit frame group is positioned with another unit frame group of its splicing by joint and is connected in addition.
2, simple greenhouse as claimed in claim 1 package assembly, it is characterized in that: sheet material is transparent PC plate, sunlight board, adhesive plaster or glass material.
3, simple greenhouse as claimed in claim 1 package assembly, it is characterized in that: sheet material is that wood is moulded plate, iron wire or iron net.
4, as claim 1,2 or 3 described simple greenhouse package assemblies, it is characterized in that: unit frame group comprises by a framework and cooperates the sheet material of fixing with framework, the metal tube that forms framework is the reeded shape tube of a side moulding, and the A/F of this groove is less than the vallecular cavity width; And the ora terminalis of sheet material is provided with the screens bar of diameter greater than the slot opening width.
5, simple greenhouse as claimed in claim 4 package assembly is characterized in that: framework by front and back two cross bars and about two vertical poles constitute, at the end cross welding punching brace of two vertical poles, in the punching of the end of two cross bars; Be fastenedly connected with screw or pulling rivet.
6, simple greenhouse as claimed in claim 4 package assembly is characterized in that: framework by front and back two cross bars and about two vertical poles constitute, in the formed connected contact pin of the end of two cross bars welding " L " type, in the punching of the end of two vertical poles; Be fastenedly connected with screw or pulling rivet.
7, simple greenhouse as claimed in claim 1 package assembly is characterized in that: sheet material is folder net adhesive plaster, and its four limit portions form lasso, and it is to fill in the screens bar, and the external diameter of lasso is greater than the width of slot opening.
8, simple greenhouse as claimed in claim 1 package assembly is characterized in that: each two edge that partly the frame group is adjacent be the interlocking of adaptive buckle by " U " type buckle simultaneously, is provided with lockhole on buckle, and other also is provided with lockhole on edge.
9, simple greenhouse as claimed in claim 1 package assembly is characterized in that: be folded with the tack sealing strip between each adjacent unit frame group.
10, simple greenhouse as claimed in claim 1 package assembly, it is characterized in that: the end that each unit frame group matches is provided with nipple, cooperates each frame group lower end, unit pin to have the positioning joint of connection; Wall unit frame group is connected locking with the unit frame group of end face by " C " type buckle.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009201376929U CN201398337Y (en) | 2009-04-13 | 2009-04-13 | Simple greenhouse assembling structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009201376929U CN201398337Y (en) | 2009-04-13 | 2009-04-13 | Simple greenhouse assembling structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201398337Y true CN201398337Y (en) | 2010-02-10 |
Family
ID=41658130
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009201376929U Expired - Fee Related CN201398337Y (en) | 2009-04-13 | 2009-04-13 | Simple greenhouse assembling structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201398337Y (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2012151754A1 (en) * | 2011-05-12 | 2012-11-15 | Tan Zaineng | Indoor enclosure for plants growing in controlled environment |
GB2539487A (en) * | 2015-06-18 | 2016-12-21 | Pure Glass Greenhouse Ltd | Greenhouse |
CN106465658A (en) * | 2015-08-19 | 2017-03-01 | 杭州雷博实业有限公司 | Greenhouse |
CN110089314A (en) * | 2019-04-29 | 2019-08-06 | 深圳中海世纪建筑设计有限公司 | A kind of green energy conservation smart greenhouse |
-
2009
- 2009-04-13 CN CN2009201376929U patent/CN201398337Y/en not_active Expired - Fee Related
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2012151754A1 (en) * | 2011-05-12 | 2012-11-15 | Tan Zaineng | Indoor enclosure for plants growing in controlled environment |
GB2539487A (en) * | 2015-06-18 | 2016-12-21 | Pure Glass Greenhouse Ltd | Greenhouse |
GB2539487B (en) * | 2015-06-18 | 2022-04-06 | Pure Glass Greenhouse Ltd | Greenhouse |
CN106465658A (en) * | 2015-08-19 | 2017-03-01 | 杭州雷博实业有限公司 | Greenhouse |
CN110089314A (en) * | 2019-04-29 | 2019-08-06 | 深圳中海世纪建筑设计有限公司 | A kind of green energy conservation smart greenhouse |
CN110089314B (en) * | 2019-04-29 | 2021-06-22 | 深圳中海世纪建筑设计有限公司 | Green energy-saving intelligent greenhouse |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201398337Y (en) | Simple greenhouse assembling structure | |
CN204837285U (en) | Plastic film vegetable greenhouse | |
CN218388891U (en) | Ventilative formula planting device of joint | |
CN110159017A (en) | A kind of transparent greenhouse of precision assembly formula | |
CN202081700U (en) | Bone ash box combined device | |
CN211982912U (en) | Agricultural greenhouse convenient to dismantle | |
KR20160126661A (en) | Modular Frameworks for Vegetable Garden | |
EP2775072A1 (en) | Fence and siding system | |
CN209218939U (en) | Aquarium with heat insulation function | |
CN201310223Y (en) | Wood plastic wall plate structure | |
CN219125032U (en) | Dendrobium officinale tissue culture frame | |
KR200469237Y1 (en) | Frame for wood windows and doors | |
CN214994870U (en) | Simulation plant wall | |
CN215683700U (en) | Novel room is cultivated to agricultural | |
CN217232355U (en) | Connecting structure of greenhouse ridge | |
CN205596719U (en) | Make things convenient for rattan that climbs of beta pruning to net | |
CN215223443U (en) | Linkage greenhouse assembly framework | |
CN111296339B (en) | Crayfish overwintering culture greenhouse and assembling method thereof | |
CN215602625U (en) | Multifunctional combined dual-purpose frame for living and breeding bees | |
CN215802436U (en) | Hang indoor view wall in pocket formula gardens | |
CN210491806U (en) | Plug-in type emulation plant afforestation frame | |
CN201171507Y (en) | Pure glass art bar stool | |
CN211129385U (en) | Combined assembled bird display cage | |
CN114142794B (en) | Installation and fixation assembly for solar photovoltaic cell panel | |
CN2435929Y (en) | Combined nest-honey screenwork |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100210 Termination date: 20170413 |
|