CN201374538Y CN200920041988U CN200920041988U CN201374538Y CN 201374538 Y CN201374538 Y CN 201374538Y CN 200920041988 U CN200920041988 U CN 200920041988U CN 200920041988 U CN200920041988 U CN 200920041988U CN 201374538 Y CN201374538 Y CN 201374538Y
Authority
CN
China
Prior art keywords
arm
cross
double
connecting plate
cross arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN200920041988U
Other languages
Chinese (zh)
Inventor
徐海
丁永辉
葛亚平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU KENENG ELECTRIC ENGINEERING CONSULTATION Co Ltd
Original Assignee
JIANGSU KENENG ELECTRIC ENGINEERING CONSULTATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU KENENG ELECTRIC ENGINEERING CONSULTATION Co Ltd filed Critical JIANGSU KENENG ELECTRIC ENGINEERING CONSULTATION Co Ltd
Priority to CN200920041988U priority Critical patent/CN201374538Y/en
Application granted granted Critical
Publication of CN201374538Y publication Critical patent/CN201374538Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model discloses a 110KV double-circuit T-connection steel tube pole. The 110KV double-circuit T-connection steel tube pole comprises a main pole, a mainline cross arm and a T-connection cross arm. The mainline cross arm and the T-connection cross arm are arranged on the main pole, and the T-connection cross arm and the mainline cross arm are stratified to be arranged in space and form an included angle. When a double-circuit line is switched in from one side of the mainline cross arm, the double-circuit line is switched out from the other side of the mainline cross arm and one side of the T-connection cross arm, wherein the other side of the mainline cross arm is opposite to the one side. The utility model can preferably satisfy the requirements of conductor to electric clearance of a tower body in T-connection, can optimize the size of the cross arm, and has clear structure transmission path and more reasonable stress. Moreover, the utility model solves the problem that the traditional T-connection angle steel tower has large occupied area and great amount of tower materials and basis materials, and can effectively save energy.

Description

The 110KV double-loop T connection steel pipe pole
Technical field
The utility model relates to a kind of steel pipe pole, and particularly relevant for a kind of 110KV double-loop T connection steel pipe pole.
Background technology
In transmission line construction, transformation, limited by economic strength and national conditions, except that the part transmission line changes into the cable laying, most of transmission line will adopt built on stilts form and long-term existence.
Traditional 110kVT connects tower and generally adopts conventional double loop angle steel tower layout pattern, finishes T in the cross-arm head and connects, and only can satisfy that one-sided T connects or bilateral different directions T connects.And traditional four loop angle steel tower layout patterns, can satisfy the double loop double T connects, but cross-arm is arranged in same plane, T connects and is limited in scope, when T connects angle when big, angle steel tower and bottom basic stress complexity, cause tower material and basic material amount bigger, investment cost is higher, and because the angle steel tower member is many, the structural elements manufacturing is relative longer with processing date and foundation construction date.In addition, the tradition four loop spatial volumes of angle steel tower own are bigger, usually take larger area land resource when coming into operation, especially use in areas such as city, cities and towns and bring often such as building removal and transformation of facility problems such as underground piping, pipeline, to city, town planning and construction influence greatly, the work for resident living and local plan department causes inconvenience; And circuit layout in angle steel tower space, four loops is salubrious inadequately, attractive in appearance, and maintenance has certain difficulty in the running.
The utility model content
The utility model proposes a kind of 110KV double-loop T connection steel pipe pole, the T that can satisfy wider scope connects angle, and simple in structure, easy construction, and can save the area.
The utility model comprises that mobile jib, main line cross-arm and T connect cross-arm.Main line cross-arm and T connect cross-arm and are installed on the mobile jib, and T connects cross-arm and the layering setting spatially of main line cross-arm and forms an angle, when double loop was inserted by a side of this main line cross-arm, this double loop was picked out with the side that this T connects cross-arm by this main line cross-arm another side relative with this side.
In the utility model, the number of degrees of angle are 45 degree or 90 degree.
In the utility model, the main line cross-arm is to be installed on the mobile jib by the first shaft connecting plate and the first cross-arm connecting plate, wherein the first shaft connecting plate passes mobile jib and is provided with, and the first cross-arm connecting plate is arranged on the main line cross-arm, and the first shaft connecting plate connects the first cross-arm connecting plate.
In the utility model, it is to be installed on the mobile jib by the second shaft connecting plate and the second cross-arm connecting plate that T connects cross-arm, wherein the second shaft connecting plate passes mobile jib and is provided with, and the second cross-arm connecting plate is arranged on T and connects on the cross-arm, and the second shaft connecting plate connects the second cross-arm connecting plate.
The utility model T connects cross-arm and main line cross-arm layering interlaced arrangement has angle, and has better met when T connects lead the cross-arm size has been optimized in the requirement of body of the tower electric clearance, and structure power transmission route is clear and definite, more reasonable stress; Solved that traditional T connects that angle steel tower floor space is big, tower material and the big problem of basic material amount, effectively saved the energy; Reduced influence, reduced the transformation of building removal and facilities such as underground piping, pipeline, more helped protecting environment city and town planning, construction and view.
Description of drawings
Figure 1 shows that the front view of the 110KV double-loop T connection steel pipe pole of the utility model one embodiment.
The mobile jib, main line cross-arm and the T that Figure 2 shows that the 110KV double-loop T connection steel pipe pole of the utility model one embodiment connect the vertical view that cross-arm is connected.
Figure 3 shows that the schematic diagram of the abutted flange of the steel pipe pole that connects mobile jib in the 110KV double-loop T connection steel pipe pole of the utility model one embodiment.
Figure 4 shows that the connection diagram that is installed on mobile jib according to cross-arm in the double-loop T connection steel pipe pole of the utility model one embodiment.
Embodiment
For above-mentioned and other purpose, feature and advantage of the present utility model can be become apparent, preferred embodiment cited below particularly, and conjunction with figs. are described in detail below.
Figure 1 shows that the front view of the 110KV double-loop T connection steel pipe pole of the utility model one embodiment.Please refer to Fig. 1, double-loop T connection steel pipe pole 100 comprises that mobile jib 3, main line cross-arm 1 and T connect cross-arm 2.Main line cross-arm 1 and T connect cross-arm 2 and are installed on mobile jib 3, and T connects cross-arm 2 and main line cross-arm 1 layering setting spatially and forms an angle.
The mobile jib, main line cross-arm and the T that Figure 2 shows that the 110KV double-loop T connection steel pipe pole of the utility model one embodiment connect the vertical view that cross-arm is connected.As shown in Figure 2, in the present embodiment, T connects cross-arm 2 and spatially forms 90 degree angles with main line cross-arm 1, T connects the angle that cross-arm 2 and main line cross-arm 1 can spatially form other number of degrees among other embodiment, for example 45 spend, yet the utility model is not as limit, and the operator can set according to the actual requirements.
In the present embodiment, double-loop T connection steel pipe pole 100 also comprises insulator 4 and wire jumper 5.Insulator 4 is isolated double loop W and double-loop T connection steel pipe pole 100, and wire jumper 5 is used for conducting the electric current of double loop W.
For instance, main line cross-arm 1 comprises dual-side 1a, 1b in the present embodiment, and T connects cross-arm 2 and also comprises dual- side 2a, 2b, specifically as shown in Figure 2.When 110KV double loop W when the side 1a of main line cross-arm 1 (ground wire cross-arm) inserts, double loop W picks out via side 1b, is gone out by side 2a or side 2b tap simultaneously.
Figure 3 shows that the schematic diagram of the abutted flange of the steel pipe pole that connects mobile jib in the 110KV double-loop T connection steel pipe pole of the utility model one embodiment.Mobile jib 3 comprises the steel pipe pole more than a section, and each section steel pipe pole adopts abutted flange 12 to connect, and abutted flange 12 has firm, the on-deformable characteristics of connection, can bear big load action.
Figure 4 shows that the connection diagram that is installed on mobile jib according to cross-arm in the double-loop T connection steel pipe pole of the utility model one embodiment.As shown in Figure 4, in the utility model, it is to be installed on mobile jib 3 by shaft connecting plate 7, cross-arm connecting plate 6 and bolt 11 that main line cross-arm 1 or T connect cross-arm 2, wherein shaft connecting plate 7 passes mobile jib 3 and is provided with, cross-arm connecting plate 6 is arranged on main line cross-arm 1 or T connects on the cross-arm 2, and bolt 11 connects shaft connecting plate 7 and cross-arm connecting plate 6.
In the present embodiment, main line cross-arm 1 or T connect cross-arm 2 and also comprise terminal shrouding 13, cross-arm thread gripping-board 8, cross-arm handrail 9 and cross-arm handrail girth member 10, are convenient to the operator and carry out maintenance work.Terminal shrouding 13 is arranged at the end that main line cross-arm 1 or T connect cross-arm 2, and cross-arm thread gripping-board 8, cross-arm handrail 9, cross-arm handrail girth member 10 are and are welded in main line cross-arm 1 or T connects on the cross-arm 2, and wherein insulator 4 is for hanging on cross-arm thread gripping-board 8.
In sum, in the utility model, T connects cross-arm and main line cross-arm layering interlaced arrangement has angle, and has better met when T connects lead the cross-arm size has been optimized in the requirement of body of the tower electric clearance, and structure power transmission route is clear and definite, more reasonable stress; Solved that traditional T connects that angle steel tower floor space is big, tower material and the big problem of basic material amount, effectively saved the energy; Reduced influence, reduced the transformation of building removal and facilities such as underground piping, pipeline, more helped protecting environment city and town planning, construction and view.
Concrete case study on implementation only is a preferable case study on implementation of the present utility model described in the utility model, is not to be used for limiting practical range of the present utility model.Be that all equivalences of doing according to the content of the utility model claim change and modification, all should be as technology category of the present utility model.

Claims (7)

1. a 110KV double-loop T connection steel pipe pole is characterized in that, comprising:
Mobile jib;
The main line cross-arm is installed on this mobile jib; And
T connects cross-arm, be installed on this mobile jib, and this T connects cross-arm and this main line cross-arm layering setting spatially and forms an angle,
When double loop was inserted by a side of this main line cross-arm, this double loop was picked out with the side that this T connects cross-arm by this main line cross-arm another side relative with this side.
2. 110KV double-loop T connection steel pipe pole according to claim 1 is characterized in that, wherein the number of degrees of this angle are 45 degree.
3. 110KV double-loop T connection steel pipe pole according to claim 1 is characterized in that, wherein the number of degrees of this angle are 90 degree.
4. 110KV double-loop T connection steel pipe pole according to claim 1, it is characterized in that, wherein this main line cross-arm is to be installed on this mobile jib by the first shaft connecting plate and the first cross-arm connecting plate, wherein this first shaft connecting plate passes this mobile jib and is provided with, this first cross-arm connecting plate is arranged on this main line cross-arm, and this this first shaft connecting plate connects this first cross-arm connecting plate.
5. 110KV double-loop T connection steel pipe pole according to claim 1, it is characterized in that, wherein to connect cross-arm be to be installed on this mobile jib by the second shaft connecting plate and the second cross-arm connecting plate to this T, wherein this second shaft connecting plate passes this mobile jib and is provided with, this second cross-arm connecting plate is arranged on this T and connects on the cross-arm, and the second shaft connecting plate connects this second cross-arm connecting plate.
6. 110KV double-loop T connection steel pipe pole according to claim 1 is characterized in that wherein this mobile jib comprises the steel pipe pole more than a section.
7. 110KV double-loop T connection steel pipe pole according to claim 6 is characterized in that, wherein the steel pipe pole of this mobile jib adopts abutted flange to connect.
CN200920041988U 2009-03-20 2009-03-20 110KV double-circuit T-connection steel tube pole Expired - Lifetime CN201374538Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200920041988U CN201374538Y (en) 2009-03-20 2009-03-20 110KV double-circuit T-connection steel tube pole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200920041988U CN201374538Y (en) 2009-03-20 2009-03-20 110KV double-circuit T-connection steel tube pole

Publications (1)

Publication Number Publication Date
CN201374538Y true CN201374538Y (en) 2009-12-30

Family

ID=41500619

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200920041988U Expired - Lifetime CN201374538Y (en) 2009-03-20 2009-03-20 110KV double-circuit T-connection steel tube pole

Country Status (1)

Country Link
CN (1) CN201374538Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669968A (en) * 2013-11-28 2014-03-26 苏州踵力重型机械有限公司 Combined steel pipe rod

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669968A (en) * 2013-11-28 2014-03-26 苏州踵力重型机械有限公司 Combined steel pipe rod

Similar Documents

Publication Publication Date Title
CN101510679B (en) 110KV double-loop T connection steel pipe pole
CN104196125B (en) A kind of modular architectural connector and building
CN201374538Y (en) 110KV double-circuit T-connection steel tube pole
CN203626360U (en) Four-pillar steel tube pole for high voltage transmission
CN1566592A (en) Support for superhigh-voltage electricity transmission line
CN202131820U (en) Y-shaped steel tube iron tower
CN201554255U (en) High intensity mixed-pressure power transmission steel tower
CN204163193U (en) A kind of modular architectural connector and building
CN201319483Y (en) Cable terminal pole
CN207260730U (en) A kind of double loop cable termination tower
CN207813168U (en) Singly cut-off π sections towers in double loop
CN203257165U (en) Double-loop tension support with circuit turn angle ranging from 90 degrees to 130 degrees
CN203097398U (en) 220kV/110kV four-circuit narrow-base steel tube tower
CN210888265U (en) Open loop tower
CN201252381Y (en) Power line single-circuit T connection steel pipe pole
CN205724627U (en) A kind of three-dimensional compact outlet structure being applicable to transformer station 330kV GIS
CN204590410U (en) A kind of outdoor power transformation framework cantilever steel girder
CN201786071U (en) Single-circuit T connecting steel pipe tower
CN203594260U (en) Combined steel pipe pole
CN104895391A (en) External inserted cross arm connecting device for steel pipe rods
CN201771245U (en) Door type electric steel pipe tower
CN203656365U (en) Combination-type transition cable leading cage based on cable leading towards lower bridge surface
CN202674539U (en) Vertical diameter-changing height-adjusting device universally used for ocean platform bridge frames
CN206299900U (en) For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed
CN203334758U (en) Pi connection special-shape steel pipe rod

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20091230

Effective date of abandoning: 20090320