Electric multifunctional trial run device for drilling equipment Download PDFInfo
- Publication number
- CN201372719Y CN201372719Y CN200920301549U CN200920301549U CN201372719Y CN 201372719 Y CN201372719 Y CN 201372719Y CN 200920301549 U CN200920301549 U CN 200920301549U CN 200920301549 U CN200920301549 U CN 200920301549U CN 201372719 Y CN201372719 Y CN 201372719Y
- Authority
- CN
- China
- Prior art keywords
- shaft
- drilling equipment
- driven shaft
- test run
- bearing seat
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model relates to a trial run device for maintenance of petroleum drilling equipment, in particular to an electric multifunctional trial run device for drilling equipment, which comprises a base, a driving device, a driven shaft, a first bearing seat, a second bearing seat, a chain wheel and a belt pulley, wherein the driving device, the first bearing seat and the second bearing seat are fixedly arranged on the base in sequence; a power output shaft of the driving device is connected together with one end of the driven shaft, while the other end of the driven shaft penetrates through the first bearing seat and is arranged inside the second bearing seat; and the driven shaft between the first bearing seat and the second bearing seat is fixedly provided with the chain wheel and the belt pulley. The trial run device has seasonable and compact structure and convenient use, drives the chain wheel and the belt pulley through the driving device, and can carry out trial run on various drilling equipments, with the characteristics of simple installation and operation, convenient carry, safety and reliability, low equipment cost, easy repair and maintenance and the like.
Description
One, technical field
The utility model relates to the test run device that the oil-well drilling equipment maintenance is used, and is a kind of multifunctional electric drilling equipment test run device.
Two, background technology
In the repair procedures of oil and gas well drilling equipment, must carry out test run at present to the equipment of repairing completion.Because oil and gas well drilling equipment mostly is main equipment, and the test run device of existing drilling equipment is each drilling equipment design one cover test run device, has the following disadvantages in actual use: the equipment cost height, maintain time-consuming effort, occupied ground is many, transportation is inconvenient.
Three, summary of the invention
The utility model provides a kind of multifunctional electric drilling equipment test run device, the equipment cost height that its test run device that has solved existing oil and gas well drilling equipment exists, maintains time-consuming effort, occupied ground is many, transportation is inconvenient problem.
The technical solution of the utility model realizes by following measure: a kind of multifunctional electric drilling equipment test run device comprises base, drive unit, driven shaft, clutch shaft bearing seat, second bearing support, sprocket wheel and belt pulley; Drive unit, clutch shaft bearing seat and second bearing support are fixedly mounted on the base successively, one end of the power output shaft of drive unit and driven shaft links together, the other end of driven shaft passes the clutch shaft bearing seat and is installed in second bearing support, is installed with sprocket wheel and belt pulley on the driven shaft between the clutch shaft bearing seat and second bearing support.
Be further optimization and/or improvements below to above-mentioned utility model technical scheme:
Above-mentioned drive unit can be high voltage motor, and an end of the power output shaft of high voltage motor and driven shaft links together.
Above-mentioned drive unit can comprise ac motor and governing box, and the output shaft of ac motor and the power input shaft of governing box link together, and an end of the power output shaft of governing box and driven shaft links together.
Between the output shaft of above-mentioned ac motor and the power input shaft of governing box shaft coupling can be arranged; One end of shaft coupling and the output shaft of ac motor are fixed together, and the other end of shaft coupling and the power input shaft of governing box are fixed together.
Above-mentioned drive unit can adopt ac variable-frequency electric motor.
Between above-mentioned power output shaft and the driven shaft clutch assembly can be arranged; One end and the power output shaft of clutch assembly are fixed together, and an end of the other end of clutch assembly and driven shaft is fixed together.
Between above-mentioned sprocket wheel and the belt pulley the 3rd bearing support can be arranged, the 3rd bearing support is fixedly mounted on the base, and the driven shaft between sprocket wheel and the belt pulley is installed on the 3rd bearing support.
Above-mentioned governing box can be the hydraulic speed-regulating case.
Above-mentioned clutch assembly can be the air clutch assembly.
Above-mentioned belt pulley can be installed on the driven shaft at sprocket wheel rear portion.
The utility model reasonable and compact in structure, easy to use, it drives sprocket wheel and belt pulley by drive unit, can carry out test run to multiple drilling equipment, has that fitting operation is simple, easy to carry, safe and reliable, equipment cost is low, maintenance is easy to characteristics.
Four, description of drawings
Accompanying drawing 1 is the main TV structure schematic diagram of the utility model most preferred embodiment.Accompanying drawing 2 is the transmission schematic diagram that the utility model is connected with winch.
Accompanying drawing 3 is the transmission schematic diagram that the utility model is connected with rotating disk.Accompanying drawing 4 is the transmission schematic diagram that the utility model is connected with borehole pump.
Coding in the accompanying drawing is respectively: 1 is base, and 2 is ac motor, and 3 is governing box, and 4 is driven shaft, 5 is the clutch shaft bearing seat, and 6 is second bearing support, and 7 is sprocket wheel, 8 is belt pulley, and 9 is the output shaft of ac motor, and 10 is the power input shaft of governing box, 11 is power output shaft, and 12 is shaft coupling, and 13 are clutch assembly, 14 is the 3rd bearing support, and 15 is driving-chain, and 16 is the drive sprocket of winch, 17 is the drive sprocket of rotating disk, and 18 is driving belt, and 19 is the driving pulley of borehole pump.
Five, the specific embodiment
The utility model is not subjected to the restriction of following embodiment, can determine concrete embodiment according to the technical solution of the utility model and actual conditions.
Below in conjunction with most preferred embodiment and accompanying drawing the utility model is further described:
Shown in accompanying drawing 1,2,3,4, this multifunctional electric drilling equipment test run device comprises base 1, drive unit, driven shaft 4, clutch shaft bearing seat 5, second bearing support 6, sprocket wheel 7 and belt pulley 8; Drive unit, clutch shaft bearing seat 5 and second bearing support 6 are fixedly mounted on the base 1 successively, the power output shaft 11 of drive unit links together with an end of driven shaft 4, the other end of driven shaft 4 passes clutch shaft bearing seat 5 and is installed in second bearing support 6, is installed with sprocket wheel 7 and belt pulley 8 on the driven shaft 4 between the clutch shaft bearing seat 5 and second bearing support 6.
Can according to actual needs above-mentioned multifunctional electric drilling equipment test run device be made further optimization and/or improvements:
Drive unit can be high voltage motor, and the power output shaft 11 of high voltage motor links together with an end of driven shaft 4.
Shown in accompanying drawing 1,2,3,4, drive unit comprises ac motor 2 and governing box 3, and the output shaft 9 of ac motor links together with the power input shaft 10 of governing box, and the power output shaft 11 of governing box links together with an end of driven shaft 4.
Shown in accompanying drawing 1,2,3,4, between the output shaft 9 of ac motor and the power input shaft 10 of governing box shaft coupling 12 is arranged; One end of shaft coupling 12 and the output shaft 9 of ac motor are fixed together, and the other end of shaft coupling 12 and the power input shaft of governing box 10 are fixed together.
Shown in accompanying drawing 1,2,3,4, drive unit can adopt ac variable-frequency electric motor.
Shown in accompanying drawing 1,2,3,4, between power output shaft 11 and the driven shaft 4 clutch assembly 13 is arranged; One end and the power output shaft 11 of clutch assembly 13 are fixed together, and an end of the other end of clutch assembly 13 and driven shaft 4 is fixed together.
Shown in accompanying drawing 1,2,3,4, there are the 3rd bearing support 14, the three bearing supports 14 to be fixedly mounted on the base 1 between sprocket wheel 7 and the belt pulley 8, the driven shaft 4 between sprocket wheel 7 and the belt pulley 8 is installed on the 3rd bearing support 14.
Shown in accompanying drawing 1,2,3,4, governing box 3 is the hydraulic speed-regulating case.The equipment that can realize treating the repairing completion of test run by the hydraulic speed-regulating case carries out stepless speed regulation, to satisfy its various operating mode demands.
Shown in accompanying drawing 1,2,3,4, clutch assembly 13 is the air clutch assembly.
Shown in accompanying drawing 1,2,3,4, belt pulley 8 is installed on the driven shaft 4 at sprocket wheel 7 rear portions, so that when winch or rotating disk are carried out test run, can only driving belt 18 be taken off and be enclosed within the bottom of second bearing support 6 from belt pulley 8, and need not dismantle second bearing support 6 to take off driving belt 18.
Above technical characterictic has constituted most preferred embodiment of the present utility model, and it has stronger compliance and best implementation result, can increase and decrease non-essential technical characterictic according to actual needs, satisfies the demand of different situations.
Below be the course of work of the utility model most preferred embodiment:
As shown in Figure 2, the winch test run: first setting winch, the drive sprocket 16 of centering sprocket wheel 7 and winch fixes winch, connects the gas circuit of driving-chain 15 and winch, and sprocket wheel 7 links together by the drive sprocket 16 of driving-chain 15 with winch.Start ac motor 2, the work by clutch assembly 13 control sprocket wheels 7 and stopping to be regulated the rotating speed of sprocket wheels 7 by governing box 3, and winch is worked under various rotating speeds, satisfies various working condition requirements and carries out test run.
As shown in Figure 3, rotating disk test run: rotating disk is installed earlier, the drive sprocket 17 of centering sprocket wheel 7 and rotating disk, fix rotating disk, connect driving-chain 15, sprocket wheel 7 links together by the drive sprocket 17 of driving-chain 15 with rotating disk, and rotary drive chain lacks a row than winch, but can be connected on the sprocket wheel 7 too.Start ac motor 2, the work by clutch assembly 13 control sprocket wheels 7 and stopping to be regulated the rotating speed of sprocket wheels 7 by governing box 3, and turntable vehicle is worked under various rotating speeds, satisfies various working condition requirements and carries out test run.
As shown in Figure 4, borehole pump test run: borehole pump is installed earlier, the driving pulley 19 of centering belt pulley 8 and borehole pump, hang up driving belt 18, after fixing borehole pump, connect cooling water pipeline and fluid end mud line, belt pulley 8 links together by the driving pulley 19 of driving belt 18 with borehole pump, and test run can replace mud with clear water.Start ac motor 2, the work by clutch assembly 13 control belt pulleys 8 and stopping to be regulated the rotating speed of belt pulleys 8 by governing box 3, and borehole pump is worked under various rotating speeds, satisfies various working condition requirements and carries out test run.
The gear test run: gear is installed, and first belt pulley of centering belt pulley 8 and gear fixes gear and connects the gas circuit pipeline, and belt pulley 8 links together by the driving pulley of driving belt 18 with gear.Start ac motor 2, the work by clutch assembly 13 control belt pulleys 8 and stopping to be regulated the rotating speed of belt pulleys 8 by governing box 3, and gear is worked under various rotating speeds, satisfies various working condition requirements.
Claims (10)
1, a kind of multifunctional electric drilling equipment test run device is characterized in that comprising base, drive unit, driven shaft, clutch shaft bearing seat, second bearing support, sprocket wheel and belt pulley; Drive unit, clutch shaft bearing seat and second bearing support are fixedly mounted on the base successively, one end of the power output shaft of drive unit and driven shaft links together, the other end of driven shaft passes the clutch shaft bearing seat and is installed in second bearing support, is installed with sprocket wheel and belt pulley on the driven shaft between the clutch shaft bearing seat and second bearing support.
2, multifunctional electric drilling equipment test run device according to claim 1 is characterized in that drive unit is a high voltage motor, and an end of the power output shaft of high voltage motor and driven shaft links together.
3, multifunctional electric drilling equipment test run device according to claim 1, it is characterized in that drive unit comprises ac motor and governing box, the output shaft of ac motor and the power input shaft of governing box link together, and an end of the power output shaft of governing box and driven shaft links together.
4, multifunctional electric drilling equipment test run device according to claim 3 is characterized in that between the power input shaft of the output shaft of ac motor and governing box shaft coupling being arranged; One end of shaft coupling and the output shaft of ac motor are fixed together, and the other end of shaft coupling and the power input shaft of governing box are fixed together.
5, multifunctional electric drilling equipment test run device according to claim 3 is characterized in that drive unit adopts ac variable-frequency electric motor.
6, according to claim 1 or 2 or 3 or 4 or 5 described multifunctional electric drilling equipment test run devices, it is characterized in that between power output shaft and the driven shaft clutch assembly being arranged; One end and the power output shaft of clutch assembly are fixed together, and an end of the other end of clutch assembly and driven shaft is fixed together.
7, multifunctional electric drilling equipment test run device according to claim 6 is characterized in that the 3rd bearing support is arranged between sprocket wheel and the belt pulley, and the 3rd bearing support is fixedly mounted on the base, and the driven shaft between sprocket wheel and the belt pulley is installed on the 3rd bearing support.
8, multifunctional electric drilling equipment test run device according to claim 7 is characterized in that governing box is the hydraulic speed-regulating case.
9, multifunctional electric drilling equipment test run device according to claim 8 is characterized in that clutch assembly is the air clutch assembly.
10, multifunctional electric drilling equipment test run device according to claim 9 is characterized in that belt pulley is installed on the driven shaft at sprocket wheel rear portion.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200920301549U CN201372719Y (en) | 2009-03-24 | 2009-03-24 | Electric multifunctional trial run device for drilling equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200920301549U CN201372719Y (en) | 2009-03-24 | 2009-03-24 | Electric multifunctional trial run device for drilling equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201372719Y true CN201372719Y (en) | 2009-12-30 |
Family
ID=41498800
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN200920301549U Expired - Fee Related CN201372719Y (en) | 2009-03-24 | 2009-03-24 | Electric multifunctional trial run device for drilling equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201372719Y (en) |
-
2009
- 2009-03-24 CN CN200920301549U patent/CN201372719Y/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2012006951A1 (en) | Tower assembly transmission numerical controlled oil extractor | |
US11448050B1 (en) | Universal electric well service rig | |
CN102953676A (en) | Drill power system | |
CN201372719Y (en) | Electric multifunctional trial run device for drilling equipment | |
CN201293083Y (en) | Unfolding aheading speed reducer for hydraulic coupling | |
CN205087837U (en) | Subside formula winch and carousel integration actuating mechanism | |
CN201810200U (en) | Hydraulic independent driven turntable device for petroleum drilling machine | |
CN100451293C (en) | Driller design scheme | |
CN206016672U (en) | Rotating disk fluid pressure drive device | |
CN202082462U (en) | Electric rotating tap for hydraulic decoking machine related to delayed coking device | |
CN202990985U (en) | Flywheel energy storage oil pumping machine | |
CN205349304U (en) | Balanced type pylon formula beam -pumping unit | |
CN103032052A (en) | Flywheel energy-storing oil pumping unit | |
CN201111505Y (en) | Novel energy-saving high-power petroleum well drilling reel cart | |
CN201786246U (en) | Independent driving rotary table apparatus for petroleum drilling machine | |
CN204200361U (en) | Oil electricity is two drives well repairing machine transmission system | |
CN201992021U (en) | Ahead speed-reducing box of hydraulic torque converter | |
CN202990984U (en) | Wind power direct drive oil pumping unit | |
CN206655655U (en) | Double motor-driven oil-well rig top drive systems of AC frequency conversion | |
CN101718188B (en) | Tower-type pulley block transmission oil jack | |
CN207144810U (en) | Drilling machinery equipment testing device | |
CN200985741Y (en) | Hollow motor directly driving top-drive drill means | |
CN203685143U (en) | Constant-power energy-saving multispeed driving device | |
CN201206424Y (en) | Testing device for multifunction boring equipment | |
CN205025379U (en) | Electronic workover rig of on -vehicle compound power |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20091230 Termination date: 20150324 |
|
EXPY | Termination of patent right or utility model |