CN201362846Y - Bagged scattered solid for grout hole forming in concrete weight body - Google Patents

Bagged scattered solid for grout hole forming in concrete weight body Download PDF

Info

Publication number
CN201362846Y
CN201362846Y CNU2009200787863U CN200920078786U CN201362846Y CN 201362846 Y CN201362846 Y CN 201362846Y CN U2009200787863 U CNU2009200787863 U CN U2009200787863U CN 200920078786 U CN200920078786 U CN 200920078786U CN 201362846 Y CN201362846 Y CN 201362846Y
Authority
CN
China
Prior art keywords
concrete
bagged
grout hole
tubular bag
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2009200787863U
Other languages
Chinese (zh)
Inventor
向建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 7 Co Ltd
Original Assignee
Sinohydro Bureau 7 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 7 Co Ltd filed Critical Sinohydro Bureau 7 Co Ltd
Priority to CNU2009200787863U priority Critical patent/CN201362846Y/en
Application granted granted Critical
Publication of CN201362846Y publication Critical patent/CN201362846Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

Disclosed is a bagged scattered solid for grout hole forming in a concrete weight body and relates to a replacement part for an embedded pipe for grout hole forming in the concrete weight body in the water conservancy and hydropower grouting project. The bagged scattered solid comprises a tubular bag and filling in the tubular bag; wherein both ends of the tubular bag are bound with sealing ropes. When in use, a drilling machine is not needed for drilling holes, the bagged scattered solid can be applicable to normal concrete and roller compacted concrete, not only solves the problem of not easy pipe pulling of the pipe pulling method, but also solves the problem that the pipe pulling method cannot be used for the roller compacted concrete, and avoids the defects of large pipe consumption by the pipe laying method.

Description

In concrete ballast body, form the bagged loose objects of grout hole
Technical field
Form the bagged loose objects of grout hole in concrete ballast body, relate to a kind ofly in the water conservancy and hydropower grouting works, the pre-buried tubing of the grout hole pore-forming in the concrete ballast body substitutes part.
Background technology
At present, in the water conservancy and hydropower grouting works, the hole forming method in the known concrete ballast body has three kinds, and they are respectively:
1, extubation: utilize steel pipe when the concrete of being built does not also finally condense, steel pipe is upwards pulled up,, form the hole, to reach the purpose of non-rig pore-forming to reach when concrete also is in plastic state.Its advantage is: without the rig pore-forming, also do not consume pre-buried tubing, saved expense.And shortcoming is: 1) operation inconvenience at the construction field (site), and consumption is artificial; 2) need operating personnel to grasp concrete time of setting well, otherwise operate just failure, and do not have the chance of 2 operations; 3) can't be used in the roller compacted concrete.
2, pipe laying method: steel pipe or plastic pipe pore-forming promptly are installed in concrete in advance.Its advantage is: simple to operate, labor intensive is few, need not rig pore-creating.Shortcoming is: expend a large amount of tubing, and also can't be used for roller compacted concrete.
3, rig port-creating method: promptly build the back that finishes and hole with rig at concrete ballast body.The method interrupts reinforcing bar easily, and it is higher to expend cost.
The said method hole is as shown in Figure 1 and Figure 2: the 4th, and Hydraulic and Hydro-Power Engineering fabric structure parting, the 5th, concrete is grout hole (also be pore-forming to be solved in the utility model partly) partly, and the 6th, concrete.
Summary of the invention
Problem to be solved in the utility model is exactly that a kind of rig boring that do not need is provided at above deficiency, can be applicable to the bagged loose objects of the formation grout hole of normal concrete and roller compacted concrete.Its technical scheme is as follows:
It comprises the filler in tubular bag and the tubular bag, pricks at the tubular bag two ends and seals rope.
The beneficial effect that compared with prior art the utlity model has is:
1, to make its diameter by the sack (polybag) of cast that sand or mud are packed into consistent with port size for the utility model, (about 30~50cm) suitable cylindric built-in fittings are to substitute the pre-buried tubing in " pipe laying method " for length and concrete (but normal concrete, also roller compacted concrete) making bed thickness, constantly stack with the rising of concreting, before concreting finishes, stack and finish.In concrete, to form the column three-dimensional core that looses, then, before grouting, with the mode of cleaning bottom of hole with sand in the hole or mud cleaning grout hole, to reach the purpose that in concrete, realizes pore-creating.
2, use the utility model both to solve " extubation " and be difficult for " tube drawing " operation, and be subjected to the difficult problem of concrete coagulating time restriction, simultaneously also solved the difficult problem that " extubation " can not be used for roller compacted concrete, the shortcoming of also having avoided " pipe laying method " to consume tubing in a large number.Simple in structure, all possessing advantage on the economy He on the operability.
3, use the utility model, do not need rig pore-creating, can avoid the direct Drilling concrete of rig, reduce the wearing and tearing of drill bit, save drill bit.
4, the utility model is adapted at pore-creating in the grinding coagulation soil body more.Because the rigidity of pre-buried tubing and protrude concrete surface, when grinding concrete construction, vibrations are ground can't be in this regional work, and makes pore-creating can't utilize " extubation " or " pipe laying method " to realize; And pre-buried bagged loose objects is semiflexible, and vibrations are ground and can be pressed, and therefore, have only pre-buried bagged loose objects just can realize pore-creating in the grinding coagulation soil body.
5, use the utility model to be not limited in concrete bodies, make grout hole, can also be used for dam in concrete (particularly at roller compacted concrete) body inverted vertical hole and the pore-forming of direct plumb line hole.Also can be used on the pore-forming of drain hole of dam gallery.
Description of drawings
Fig. 1 is the utility model bagged loose objects structural representation.
Fig. 2 is a Hydraulic and Hydro-Power Engineering building foundation grout hole layout schematic diagram.
Fig. 3 is that Hydraulic and Hydro-Power Engineering building foundation grout hole section is arranged schematic diagram.
Fig. 4 is the vertical section constructional drawing of the utility model first floor concreting (making) and the pre-buried embodiment of bagged loose objects.
Fig. 5 is that the utility model i layer concrete is built the vertical section constructional drawing that (making) and i layer bagged loose objects stack pre-buried embodiment.
The specific embodiment
The utility model comprises the filler 3 in tubular bag 2 and the tubular bag 2, pricks at tubular bag 2 two ends and seals rope 1.Tubular bag 2 is selected polybag for use, is shaped as circle, and its length is 30-50cm, and its diameter is consistent with the diameter of grout hole.Filler 3 in the tubular bag 2 is sand or mud.
The hole forming method that utilizes the utility model to form grout hole in concrete ballast body may further comprise the steps:
1, make bagged loose objects:
1. roll of plastic being made diameter is that drilling diameter, length are the round tubular bag 2 of 30~50cm.
2. with in filler 3 (preferably sand or mud) each tubular bag of packing into, two ends are pricked and are extremely sealed with sealing rope 1 (preferably thin galvanized wire), form long 30~50cm, and diameter is the cylindric bagged loose objects 7 of drilling diameter.
2, before ballast concreting, measure the position emit pore-forming, first floor bagged loose objects 7 is placed on the position of pore-forming, making first floor concrete 6.1 (normal concrete or roller compacted concrete all are suitable for).
When 3, next layer concrete is built, repeat above program,, build i layer concrete 6.2 until placing i layer bagged loose objects 7.1.
4, after concrete rises to the grouting high level and reaches intensity, before grouting and rock pore-creating, the bagged loose objects of imbedding in the concrete is formed grout hole with high-pressure blast or water under high pressure with the grains of sand in the hole or earth cleaning back.
In making concrete process,, can correct at any time if the position of bagged loose objects is mobile to some extent.

Claims (5)

1, in concrete ballast body, forms the bagged loose objects of grout hole, it is characterized in that it comprises filler (3) in tubular bag (2) and the tubular bag (2), pricks at tubular bag (2) two ends and seals rope (1).
2, the bagged loose objects that forms grout hole in concrete ballast body according to claim 1 is characterized in that tubular bag (2) selects polybag for use.
3, the bagged loose objects that in concrete ballast body, forms grout hole according to claim 1, the length that it is characterized in that tubular bag (2) is 30-50cm, the diameter of tubular bag (2) is consistent with the diameter of grout hole.
4, the bagged loose objects that forms grout hole in concrete ballast body according to claim 1 is characterized in that the circle that is shaped as of tubular bag (2).
5, the bagged loose objects that forms grout hole in concrete ballast body according to claim 1 is characterized in that the filler (3) in the tubular bag (2) is sand or mud.
CNU2009200787863U 2009-01-21 2009-01-21 Bagged scattered solid for grout hole forming in concrete weight body Expired - Lifetime CN201362846Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2009200787863U CN201362846Y (en) 2009-01-21 2009-01-21 Bagged scattered solid for grout hole forming in concrete weight body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2009200787863U CN201362846Y (en) 2009-01-21 2009-01-21 Bagged scattered solid for grout hole forming in concrete weight body

Publications (1)

Publication Number Publication Date
CN201362846Y true CN201362846Y (en) 2009-12-16

Family

ID=41473506

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2009200787863U Expired - Lifetime CN201362846Y (en) 2009-01-21 2009-01-21 Bagged scattered solid for grout hole forming in concrete weight body

Country Status (1)

Country Link
CN (1) CN201362846Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103213196A (en) * 2013-03-29 2013-07-24 大连大金马基础建设有限公司 Prestressed concrete square pile spiral pipe driving device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103213196A (en) * 2013-03-29 2013-07-24 大连大金马基础建设有限公司 Prestressed concrete square pile spiral pipe driving device
CN103213196B (en) * 2013-03-29 2015-10-28 大连大金马基础建设有限公司 Prestressed concrete square pile spiral-tube driving device

Similar Documents

Publication Publication Date Title
CN103590425B (en) A kind of Peaty soft soil stratum subway station construction technology
CN102691296B (en) Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof
CN100462507C (en) Construction method for pulling-resistant and pressure-resistant slip casting pipe pile
CN103147442B (en) Ultra-deep foundation pit press-grouting pile and prestressed anchor combined supporting construction method
CN104612134A (en) Cast-in place pile post-grouting construction method for pouring construction
CN104895055A (en) Building grouting pile foundation construction method
CN110984221A (en) Construction method for reinforcing end socket at initial end of air shaft and guide wall structure
CN105464074A (en) Manual hole digging pile high polymer grouting protection structure and construction method thereof
CN102011591A (en) Grouting process for working surface of deep well
CN102535458A (en) Reinforced cement-soil anchor bolt and construction method thereof
CN107178077A (en) Overburden layer grouting and reinforcing structure and its design method on a kind of karst area solution cavity
CN103343690B (en) Construction method of shaft antiseep structure used when large section of inclined shaft passes through aquifer
CN203441498U (en) Anti-seepage structure for large-section water-bearing layer passing shaft of inclined shaft
CN110593254A (en) Construction method of cast-in-situ bored pile in stratum with karst cave in joint zone
CN104762956A (en) Method for forming novel pile based on construction waste recycled aggregate
CN204959787U (en) Novel tower crane combination formula basis
CN207377561U (en) The bad water-bearing layer positioning targeting slip casting Mine Shaft Lining of rock section and constructing device
CN105040705A (en) Ground foundation treatment construction technology under multi-karst-cave geological conditions
CN110500119B (en) Waterproof consolidation structure construction method for penetrating through debris flow accumulation body tunnel
CN201362846Y (en) Bagged scattered solid for grout hole forming in concrete weight body
CN205382942U (en) Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility
CN203891785U (en) Special joint pipe assembly for throwing of gravels in pipe of hydrogeological water well
CN203475486U (en) Basement producing no water buoyancy
CN216040465U (en) Ecological roadbed structure in sponge city based on original road
CN111519647A (en) Novel foundation suitable for marine soft foundation treatment and reinforcement and construction method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20091216