CN201362553Y - Aquatic large-sized reinforcing cage hoisting roll-over device - Google Patents

Aquatic large-sized reinforcing cage hoisting roll-over device Download PDF

Info

Publication number
CN201362553Y
CN201362553Y CNU2008202376669U CN200820237666U CN201362553Y CN 201362553 Y CN201362553 Y CN 201362553Y CN U2008202376669 U CNU2008202376669 U CN U2008202376669U CN 200820237666 U CN200820237666 U CN 200820237666U CN 201362553 Y CN201362553 Y CN 201362553Y
Authority
CN
China
Prior art keywords
reinforcement cage
steel reinforcement
reinforcing cage
swivel mount
hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008202376669U
Other languages
Chinese (zh)
Inventor
章德春
王延长
牟翔
耿树成
杨春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FORTH ENGINEERING OF ZHONGTIE BRIDGE BUREAU CO LTD
Original Assignee
FORTH ENGINEERING OF ZHONGTIE BRIDGE BUREAU CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FORTH ENGINEERING OF ZHONGTIE BRIDGE BUREAU CO LTD filed Critical FORTH ENGINEERING OF ZHONGTIE BRIDGE BUREAU CO LTD
Priority to CNU2008202376669U priority Critical patent/CN201362553Y/en
Application granted granted Critical
Publication of CN201362553Y publication Critical patent/CN201362553Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model relates to an aquatic large-sized reinforcing cage hoisting roll-over device, which comprises a reinforcing cage and a rotating bracket, wherein the rear end of the reinforcing cage is arranged on the rotating bracket, so that the reinforcing cage rotates while being hoisted, and a reinforcing hoop of the reinforcing cage is hung by a tipped plate of the rotating bracket so as to support a rear supporting point when in hoisting and to play the safety protection effect. The aquatic large-sized reinforcing cage hoisting roll-over device has the advantages that a single-hook floating crane can be utilized to rapidly hoist the large-sized reinforcing cage in profound zone; an arc supporting beam can ensure the contact among a plurality of main bars of the reinforcing cage and can ensure the completeness of the sections of the reinforcing cage; and four tipped plates which are uniformly distributed on the arc beam are utilized to hang the reinforcing hoop of the reinforcing cage, so that the reinforcing cage is free from rotating relative to the rotating bracket when rotating to the vertical state. The system has the advantages that the hoisting workload of the reinforcing cage is small, the operation safety is high, the requirement on the coordination of the operation driver is low, the labor intensity is reduced, the aquatic floating hoisting configuration requirement is low, the hoisting time of the reinforcing cage is short, the device investment is reduced and the pile forming period can be shortened.

Description

Above-water large-scale reinforcement cage hoisting and overturning device
Technical field
The utility model relates to a kind of bored pile reinforcement cage hoisting and overturning device waterborne, be specially adapted to the long pile cages lifting of abyssal zone major diameter, install, belong to technical field of building construction.
Background technology
Current, large diameter borehole perfusion multi-column pier foundation is widely used in the bridge deep water foundation, during bored pile construction waterborne, steel reinforcement cage needs after the workshop sectional making is finished on the coast, be transported to the pier position with the construction boats and ships, use two loop wheel machines again, or separate unit double hook loop wheel machine is transferred the steel reinforcement cage sections to the hole after horizontality is lifted by crane into plumbness, owing to the harmony and the skill level of crane operator operation are had relatively high expectations with two loop wheel machines or separate unit double hook loop wheel machine lifting steel reinforcement cage, for major diameter, the long segment steel reinforcement cage, because diameter is big, from great, said method causes the hook that rises of two suspension hooks sometimes, put the inharmonious of hook, and collide other member and cause steel reinforcement cage to damage, hull is hit, accidents such as operating personal is injured, prolonged the steel reinforcement cage set-up time, it is more to cause in the hole boring mud to precipitate once more, strengthens the difficulty in the clear hole of secondary, has influenced the pile cycle.
Summary of the invention
The utility model proposes a kind of above-water large-scale reinforcement cage hoisting and overturning device, be intended to overcome the existing in prior technology defective, make the scene, safely, promptly will lie in a horizontal plane in the steel reinforcement cage on the hull with a single hook crane barge, lift by crane into plumbness, shorten the pile cycle on bored pile basis.
Technical solution of the present utility model: it is characterized in that comprising steel reinforcement cage and swivel mount two parts, wherein steel reinforcement cage is bearing on the swivel mount rear end when placing, during reinforcement cage hoisting, only lift by crane front end, the rear end swivel mount rotates with the variation of steel reinforcement cage angle, tangle steel reinforcement cage reinforcement hoop, rear fulcrum supporting and safety precaution effect when bearing lifting by breaking tip plate.
Advantage of the present utility model: adopt a single hook crane barge just can carry out the fast hoisting of abyssal zone large-scale reinforcement cage; The arc supporting beam can guarantee many main muscle contacts of steel reinforcement cage, guarantees the integraty of steel reinforcement cage sections; Utilize uniform on the arc beam four to break tip plate and tangle steel reinforcement cage and strengthen hoop, guarantee that steel reinforcement cage can be when not being rotated into plumbness and swivel mount generation slide relative.This system have guarantee that the reinforcement cage hoisting working out is little, processing safety is high, to operation driver harmony require low, labour intensity reduces, crane barge configuration requirement waterborne is low, the reinforcing bar cage hoisting time short, reduction equipment drops into, save the advantage in pile cycle.
Description of drawings
Fig. 1 is that the steel reinforcement cage level is placed on the scheme drawing on the dull and stereotyped barge.
Fig. 2 is the scheme drawing that reinforcement cage hoisting becomes plumbness.
Fig. 3 is the swivel mount elevational schematic view.
Fig. 4 is a swivel mount A-A sectional schematic diagram.
Fig. 5 is a swivel mount B-B sectional schematic diagram.
Among the figure 1 is dull and stereotyped barge, the 2nd, crane barge, the 3rd, and suspender, the 4th, steel reinforcement cage, the 5th, steel reinforcement cage is strengthened hoop, the 6th, interim pad, the 7th, undersetting, the 8th, upper bracket, the 9th, roller pin, the 10th, longeron, the 11st, end floor beam, the 12nd, center member, the 13rd, arc supporting beam, the 14th is played pin plate socket, the 15th, breaks tip plate.
The specific embodiment
Contrast accompanying drawing 1, its structure is the end that swivel mount is fixed on dull and stereotyped barge 1, and steel reinforcement cage 4 leading portions are fixed on the dull and stereotyped barge 1 by interim pad 6, and steel reinforcement cage 4 back segments are fixed on the swivel mount, and crane barge 2 connects suspender 3.
Contrast accompanying drawing 2, its structure is that steel reinforcement cage 4 is lifted by crane by crane barge 2 and suspender 3, steel reinforcement cage 4 and dull and stereotyped barge 1 in vertical state, the reinforcement hoop 5 on swivel mount is broken tip plate 15 and is tangled.
Contrast accompanying drawing 3, its structure be swivel mount by undersetting 7, upper bracket 8, roller pin 9, longeron 10, end floor beam 11, center member 12, arc supporting beam 13, play pin plate socket 14, break tip plate 15 and form, wherein swivel mount undersetting 7 joins by roller pin 9 with swivel mount upper bracket 8, swivel mount undersetting 7 is located in dull and stereotyped barge 1 end, form the steel framework on two end floor beams 11, a center member 12 and two longerons 10, upper bracket 8 is established at longeron 10 middle parts, and arc supporting beam 13 is located on the end floor beam 11.
Contrast accompanying drawing 4, the steel reinforcement cage rear fulcrum is placed on the swivel mount of dull and stereotyped barge 1, and arc supporting beam 13 is fixed on end floor beam 11 tops, establishes on the arc supporting beam 13 and plays tip plate socket 14, play tip plate 15 usefulness latches and fix, break tip plate 15 and block steel reinforcement cage reinforcement hoop 5 with playing tip plate socket 14.
Contrast accompanying drawing 5, its structure are to have upper bracket 8, upper bracket 7 to be fixed on the dull and stereotyped barge 1 in the middle of two longerons 10, are connected with roller pin 9 between upper bracket and undersetting.
Two arc supporting corbels firmly wait to lift an end of steel reinforcement cage on the described swivel mount, play tip plate socket 14 for 4 and are evenly distributed on the arc supporting beam 13, will break tip plate 15 and play tip plate socket 14 and block steel reinforcement cage after fixing and strengthen binding round 5 with latch.
The rear end was placed on the swivel mount when described steel reinforcement cage hung aboard ship, front end adopts interim pad, steel reinforcement cage is when laying, should make steel reinforcement cage strengthen hoop 5 near beating tip plate 15 front ends, steel reinforcement cage is winched to when reaching plumbness soon rising, can tangle steel reinforcement cage and strengthen hoop, prevent that the steel reinforcement cage lower end breaks away from swivel mount suddenly or glides along swivel mount.
Described swivel mount undersetting 7 is welded on flat board and refutes 1 afterbody, and upper bracket 8 is fixing with undersetting 7 by roller pin 9, and upper and lower bearing should be able to rotate freely with the variation of steel reinforcement cage angle.
The arc surface of described swivel mount arc supporting beam 13 is consistent with the steel reinforcement cage external diameter, and the spacing that the spacing of two arc supporting beams 13 and steel reinforcement cage are strengthened hoop is consistent.
Described crane barge suspender reply steel reinforcement cage adopts many suspension centres lifting method, prevents that the steel reinforcement cage local pressure is excessive and is out of shape.
During enforcement: make one and connect the swivel mount of two arc supporting beams by shaped steel, swivel mount is fixed on the afterbody of dull and stereotyped barge, when steel reinforcement cage was placed aboard ship, rear fulcrum was placed on the swivel mount, and front end adopts interim pad; When steel reinforcement cage need be installed, crane barge tangled the steel reinforcement cage front end by suspender and slowly plays hook, and the steel reinforcement cage rear end and is raised and rotated with front fulcrum still on swivel mount, breaks away from swivel mount after reaching plumbness.
Concrete steps: according to steel casing diameter, strengthen hoop spacing design swivel mount → swivel mount undersetting 7 with dull and stereotyped refute 1 welding fixing → swivel mount framework installations → steel reinforcement cage hangs on flat board is refuted interim pad and swivel mount on 1 → crane barge 2 and suspender 3 preparation → steel reinforcement cages before suspension centre suspender installation → reinforcement cage hoisting (converting plumbness to) → steel reinforcement cage installation by horizontality.

Claims (5)

1, above-water large-scale reinforcement cage hoisting and overturning device is characterized in that comprising steel reinforcement cage and swivel mount two parts, and wherein the steel reinforcement cage rear end is placed on the swivel mount, and steel reinforcement cage is rotated with lifting, tangles steel reinforcement cage reinforcement hoop by breaking tip plate, bears safety precaution.
2, above-water large-scale reinforcement cage hoisting and overturning device according to claim 1, it is characterized in that described swivel mount forms the steel framework by longeron, end floor beam, center member, arc supporting beam, establish on 2 arc supporting beams and play tip plate socket, and will break tip plate with latch and fix; Swivel mount longeron middle part is welded with upper bracket, by roller pin be fixed on flat board and refute the undersetting of end and be connected.
3, above-water large-scale reinforcement cage hoisting and overturning device according to claim 1, it is characterized in that described swivel mount held an end of waiting to lift steel reinforcement cage by two arc tips support beams, play tip plate socket for 4 and be evenly distributed on the arc tips support beam, will break tip plate and play tip plate socket with latch and fix.
4, above-water large-scale reinforcement cage hoisting and overturning device according to claim 1, the rear end is placed on the swivel mount when it is characterized in that described steel reinforcement cage hangs aboard ship, front end adopts interim pad, steel reinforcement cage is when laying, should make steel reinforcement cage strengthen hoop near beating tip front edge of board, steel reinforcement cage is winched to when reaching plumbness soon rising, break tip plate and can tangle steel reinforcement cage and strengthen binding round, prevent that the steel reinforcement cage lower end breaks away from swivel mount suddenly or moves down along swivel mount.
5, above-water large-scale reinforcement cage hoisting and overturning device according to claim 1, it is characterized in that described swivel mount undersetting is welded on the afterbody that flat board is refuted, upper bracket is fixed by roller pin and undersetting, and upper and lower bearing should be able to rotate freely with the variation of steel reinforcement cage angle.
CNU2008202376669U 2008-12-30 2008-12-30 Aquatic large-sized reinforcing cage hoisting roll-over device Expired - Lifetime CN201362553Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008202376669U CN201362553Y (en) 2008-12-30 2008-12-30 Aquatic large-sized reinforcing cage hoisting roll-over device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008202376669U CN201362553Y (en) 2008-12-30 2008-12-30 Aquatic large-sized reinforcing cage hoisting roll-over device

Publications (1)

Publication Number Publication Date
CN201362553Y true CN201362553Y (en) 2009-12-16

Family

ID=41473214

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008202376669U Expired - Lifetime CN201362553Y (en) 2008-12-30 2008-12-30 Aquatic large-sized reinforcing cage hoisting roll-over device

Country Status (1)

Country Link
CN (1) CN201362553Y (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101891110A (en) * 2010-06-28 2010-11-24 中国第一重型机械股份公司 Workpiece turning and hanging universal process of large revolving body and tooling attachment thereof
CN102390795A (en) * 2010-12-27 2012-03-28 上海锅炉厂有限公司 Hoisting and turning-over device and method for large chemical container
CN105645248A (en) * 2016-03-24 2016-06-08 中交第四公路工程局有限公司 Reinforcement cage lifting device and method
CN106744266A (en) * 2016-12-29 2017-05-31 马鞍山万普实业发展有限公司 A kind of transport frock for transporting steel construction
CN109775565A (en) * 2019-02-25 2019-05-21 中交第三航务工程局有限公司 A kind of large-diameter pile single hook turns over piling method under water
CN111119169A (en) * 2019-12-23 2020-05-08 诚通凯胜生态建设有限公司 Construction method of drilled pile
CN113200439A (en) * 2021-04-02 2021-08-03 中国水电四局(酒泉)新能源装备有限公司 Conduit foundation tower turnover device for offshore wind power generation

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101891110A (en) * 2010-06-28 2010-11-24 中国第一重型机械股份公司 Workpiece turning and hanging universal process of large revolving body and tooling attachment thereof
CN102390795A (en) * 2010-12-27 2012-03-28 上海锅炉厂有限公司 Hoisting and turning-over device and method for large chemical container
CN102390795B (en) * 2010-12-27 2013-08-21 上海锅炉厂有限公司 Hoisting and turning-over device and method for large chemical container
CN105645248A (en) * 2016-03-24 2016-06-08 中交第四公路工程局有限公司 Reinforcement cage lifting device and method
CN105645248B (en) * 2016-03-24 2017-08-08 中交第四公路工程局有限公司 A kind of steel reinforcement cage lifting device and method
CN106744266A (en) * 2016-12-29 2017-05-31 马鞍山万普实业发展有限公司 A kind of transport frock for transporting steel construction
CN109775565A (en) * 2019-02-25 2019-05-21 中交第三航务工程局有限公司 A kind of large-diameter pile single hook turns over piling method under water
CN109775565B (en) * 2019-02-25 2020-03-20 中交第三航务工程局有限公司 Large-diameter single-pile single-hook underwater pile turning method
CN111119169A (en) * 2019-12-23 2020-05-08 诚通凯胜生态建设有限公司 Construction method of drilled pile
CN113200439A (en) * 2021-04-02 2021-08-03 中国水电四局(酒泉)新能源装备有限公司 Conduit foundation tower turnover device for offshore wind power generation

Similar Documents

Publication Publication Date Title
CN101445206A (en) Above-water large-scale reinforcement cage hoisting and overturning device
CN201362553Y (en) Aquatic large-sized reinforcing cage hoisting roll-over device
CN201756173U (en) Water surface hoisting construction ship with buoyant boxes
CN102701083A (en) Special equipment and method for replacing wind driven generator component
CN204644884U (en) High pier over-form construction reinforced bar installs mobile stock
CN208235560U (en) A kind of offshore wind turbine single-pile foundation being internally provided with floating drum
CN205443944U (en) A turning device for prefabricating hoist and mount of stand unit
CN113090470B (en) Installation method of offshore wind turbine
CN202390116U (en) High-intensity small-tonnage hoist
CN109626249B (en) Simple three-dimensional positioning installation and load bearing device and using method
CN218114848U (en) Installation device for seaworthy berthing component
CN102303812A (en) Large-scale wind turbine installation vessel crane and integral assembling method thereof
CN214780221U (en) Hoisting device for steel reinforcement cage
CN202643086U (en) Hoisting tool of hydroxylation reactor
CN101723240B (en) Special fixture for hoisting rectangular section steel column and hoisting method by using same
CN210122723U (en) Novel steel reinforcement cage gallows
CN207511719U (en) A kind of propeller for vessels boom hoisting
CN216918308U (en) Steel reinforcement cage hangs muscle device
CN216580913U (en) Large-gradient reverse-slope drainage tunnel water pump quick-moving installation device
CN202783700U (en) Vertical-rotation overlength fuel gas evacuating bracket of floating oil production platform
CN220078419U (en) Movable support hinge herringbone mast hoisting device
CN205077876U (en) Prestressed steel strand pulling machine and tensioning jack suspension device
CN216583828U (en) Combination turnover type vertical steel member mounting platform
CN214270021U (en) Operation radius lengthening device for tower crane
CN216476246U (en) Maintenance device for drilling platform and hoisting platform deep submersible pump

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20091216