CN201307159Y - Remote electric energy meter detection system - Google Patents

Remote electric energy meter detection system Download PDF

Info

Publication number
CN201307159Y
CN201307159Y CNU2008201664353U CN200820166435U CN201307159Y CN 201307159 Y CN201307159 Y CN 201307159Y CN U2008201664353 U CNU2008201664353 U CN U2008201664353U CN 200820166435 U CN200820166435 U CN 200820166435U CN 201307159 Y CN201307159 Y CN 201307159Y
Authority
CN
China
Prior art keywords
electric energy
energy meter
calibrating
computer
calibrating apparatus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008201664353U
Other languages
Chinese (zh)
Inventor
吴敏
吴坚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Electric Power Bureau
Original Assignee
Hangzhou Electric Power Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Electric Power Bureau filed Critical Hangzhou Electric Power Bureau
Priority to CNU2008201664353U priority Critical patent/CN201307159Y/en
Application granted granted Critical
Publication of CN201307159Y publication Critical patent/CN201307159Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The utility model relates to a detection device for an electric energy meter, and aims to provide the electric energy meter detection system, through which one computer can operate and control the detection devices of a plurality of electric energy meters for a long distance, and the detection device has the characteristics of high operating efficiency, high field use ratio and low running cost. The utility model adopts the technical scheme that the remote electric energy meter detection system comprises at least two electric energy meter detection devices and is characterized in that each electric energy meter detection device is equipped with an RS232 conversion module and performs the data transmission with the computer in the detection center after being switched in the Ethernet through the module, so that the computer can realize the remote control to each electric energy meter detection device.

Description

Remote power table verification system
Technical field
The utility model relates to a kind of calibrating installation of electric energy meter, the remote power table verification system of especially utilizing Ethernet to form as telecommunication media.
Background technology
The pattern that domestic present calibrating department carries out electric energy meter calibration work is that a computing machine is by calibrating installation of a RS232 connection control, by the calibrating of testing person's operating computer realization to electric energy meter, the proportionate relationship of testing person, computing machine and calibrating installation is 1:1:1.
There is following shortcoming in this kind pattern: (1) antijamming capability is relatively poor; External interference is superimposed on the signal ground easily, and causing receiving terminal to disturb increases; (2) transmission range is relatively short (not by MODEM distance<30m); For guaranteeing reliability of data communication, computing machine can not be away from calibrating installation; (3) communication speed is relatively slow
(115.2kbps); (4) computing machine carries the RS232 port and generally has only one, if Other Instruments equipment need use the RS232 port, must expand the computer motherboard function, increases the RS232 port, and the expansion limited amount.
Along with the increase year by year of electric energy meter calibration amount, calibrating installation is also corresponding to be increased, and require the electric energy meter calibration personnel can control many calibrating installations simultaneously at work, and the aforementioned techniques shortcoming has restricted this requirement.
The utility model content
Technical problem to be solved in the utility model is to overcome the shortcoming that exists in the above-mentioned background technology, a kind of electric energy meter detecting system is provided, this system should enough computer remote operations control many electric energy meter calibrating apparatus, have high efficiency, utilization of area rate height, reduce the characteristics of operating cost.
The utility model has adopted following technical scheme:
Remote power table verification system, comprise at least two electric energy meter calibrating apparatus, it is characterized in that every electric energy meter calibrating apparatus all disposes a RS232 modular converter, and by behind this module access network based on ethernet with the calibrating center computing machine carry out data transmission so that computer realization is to every electric energy meter calibrating apparatus Long-distance Control.
The computing machine that RS232 serial ports on described every electric energy meter calibrating apparatus is connected behind RS232 modular converter, Ethernet and the hub successively with the calibrating center carries out data transmission.
Described every electric energy meter calibrating apparatus also disposes a display terminal.
Use of the present utility model is: do relevant the setting earlier on computers, the electric energy meter calibrating apparatus of being connected is modeled as the network equipment; Then electric energy meter to be examined and determine is loaded onto calibrating installation, by computing machine successively by connecting the RS232 modular converter on the calibrating installation behind the hub, Ethernet, calibrating installation is directly controlled, carried out every performance calibrating, and carry out two-way data and transmit electric energy meter; Realized the long-range calibrating of electric energy meter thus.
The beneficial effects of the utility model: (1) electric energy meter calibration personnel uses a calculating function to control many calibrating installations simultaneously, calibration operation efficient is significantly improved, and need not to increase calibrating place and testing person, operating cost also is able to obvious reduction; (2) Ethernet is fit to telecommunication, the testing person can control remote calibration equipment by computer remote, perhaps can set up a central control room, master control computer of outfit just can be controlled all electric energy meter calibrating apparatus away from central control room in central control room, monitors all the electric energy meter calibration situations above the calibrating installation simultaneously.(3) owing to can fast, accurately carry computer commands and the every error information that receives electronic electric energy meter, and and electric energy meter calibrating apparatus has been realized control more reasonable, science.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Embodiment
Remote power table verification system, comprise at least two electric energy meter calibrating apparatus, it is characterized in that each electric energy meter calibrating apparatus 5 all disposes a RS232 modular converter 4, and carry out data transmission by the computing machines 1 at this module access network based on ethernet 3 backs and calibrating center, so that computer realization is to every electric energy meter calibrating apparatus Long-distance Control.
The computing machine that RS232 serial ports on described each electric energy meter calibrating apparatus is connected RS232 modular converter, Ethernet 3 and hub 2 backs and calibrating center successively carries out data transmission.
Described each electric energy meter calibrating apparatus also disposes a display terminal 6.
The utility model technology Network Based makes that the RS232 serial ports on every electric energy meter calibrating apparatus is examined and determine the computing machine at center by the long-range connection of Ethernet, thereby realizes the data transmission and the control of networking.Like this,, realize the electric energy meter calibrating apparatus more than 2 is controlled and operated by network, realize the telecommunication network centralized control with a computing machine by the function of access to netwoks.
Main control computer uses a unification control platform program, and each calibrating installation is all separate; Can start and stop the program of some calibrating installations arbitrarily, not influence the operation of other calibrating installation; Program is used unified calibrating control picture, shared scheme and database; An operator only needs just can control many electric energy meter calibrating apparatus to a main control computer operation; The field staff only need load and unload table, improves personnel and utilization of area efficient greatly, improves the work efficiency of system.
Can learn in the accompanying drawing that total system comprises many cover calibration equipments 7 (only showing 4 covers among the figure), every cover calibration equipment is made up of electric energy meter calibrating apparatus 5, display terminal 6 and RS232 modular converter 4; Wherein display terminal is a utility appliance.
1, computing machine also is provided with the page that a plurality of calibrating installations are monitored simultaneously when each calibrating installation being provided with a complete calibrating interface; In the verification process, the testing person can in time recognize the calibrating content that each calibrating installation is current by this interface.2, issue instructions to hub (HUB module) by computing machine earlier, hub is differentiated the RS232 modular converter that sends to each device to these instructions again, the RS232 modular converter is told device with instruction, allows device carry out calibration operation and the present duty of device also can occur at the interface of display terminal simultaneously.3, turn back on the control computer by same approach during from calibrating data that the electric energy meter of calibrating receives when calibrating installation.The testing person just can check the result of this project.
The equal buyable of above-described all components and parts.
The required software of the computer run of described controller and Surveillance center can be write by the common software technician.

Claims (3)

1, remote power table verification system, comprise at least two electric energy meter calibrating apparatus, it is characterized in that every electric energy meter calibrating apparatus (5) all disposes a RS232 modular converter (4), and by behind this module access network based on ethernet with the calibrating center computing machine (1) carry out data transmission so that computer realization is to every electric energy meter calibrating apparatus Long-distance Control.
2, remote power table verification system according to claim 1 is characterized in that RS232 serial ports on described every electric energy meter calibrating apparatus connects the computing machine at RS232 modular converter, Ethernet (3) and hub (2) back and calibrating center successively and carry out data transmission.
3, remote power table verification system according to claim 1 and 2 is characterized in that described every electric energy meter calibrating apparatus also disposes a display terminal (6).
CNU2008201664353U 2008-11-04 2008-11-04 Remote electric energy meter detection system Expired - Fee Related CN201307159Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008201664353U CN201307159Y (en) 2008-11-04 2008-11-04 Remote electric energy meter detection system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008201664353U CN201307159Y (en) 2008-11-04 2008-11-04 Remote electric energy meter detection system

Publications (1)

Publication Number Publication Date
CN201307159Y true CN201307159Y (en) 2009-09-09

Family

ID=41099626

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008201664353U Expired - Fee Related CN201307159Y (en) 2008-11-04 2008-11-04 Remote electric energy meter detection system

Country Status (1)

Country Link
CN (1) CN201307159Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102305922A (en) * 2011-05-25 2012-01-04 湖南省电力公司科学研究院 On-load detection method and device for intelligent optical fiber electric energy meter in substation
CN101776740B (en) * 2010-01-19 2012-12-26 云南电网公司 Electric energy metering automation simulation laboratory

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101776740B (en) * 2010-01-19 2012-12-26 云南电网公司 Electric energy metering automation simulation laboratory
CN102305922A (en) * 2011-05-25 2012-01-04 湖南省电力公司科学研究院 On-load detection method and device for intelligent optical fiber electric energy meter in substation
CN102305922B (en) * 2011-05-25 2013-09-04 湖南省电力公司科学研究院 On-load detection method and device for intelligent optical fiber electric energy meter in substation

Similar Documents

Publication Publication Date Title
CN101907694B (en) Device and method for testing low-voltage collecting meter reading system
CN103997079B (en) A kind of electric vehicle alternating-current charging pile and using method thereof
CN202794497U (en) On-site comprehensive detection equipment for electric energy information acquisition terminal
CN102184749A (en) Method for automatically testing DCS (Digital Control System) control cabinet
CN203688055U (en) Weighing instrument of dynamic rail weighter
CN105785099A (en) Multi-node electrical power quality real-time monitoring system based embedded wireless network
CN100470976C (en) Integrated automation converting station debugging apparatus
CN204156542U (en) A kind of electric vehicle alternating-current charging pile
CN201732472U (en) Automatic testing device of concentrated electric energy meter reading equipment
CN201307159Y (en) Remote electric energy meter detection system
CN102254414B (en) Embedded automatic meter reading system based on GPRS (Global System for Mobile Communications)
CN202872468U (en) Real-time data access interface devic of SCADA (Supervisory Control and Data Acquisition) system
CN204904026U (en) Environmental protection data acquisition device
CN203430525U (en) Shield distribution type PLC control system based on controller
CN202077160U (en) Intelligent switch cabinet display control device with remote wireless communication module
CN202661873U (en) Intelligent phone-based automobile diagnosing system
CN201821314U (en) Modularized microcomputer excitation regulator
CN104467668A (en) Multi-channel photovoltaic module generating capacity test data collection system
CN209927948U (en) Valve base electronic equipment's test device
CN107154675A (en) A kind of monobus communication system and its method applied to mesohigh SVG
CN203660662U (en) Single-space five-in-one device for intelligent transformer station
CN109951364B (en) Charging control management system and method for electric vehicle charging pile
CN202268901U (en) Distributed controller for simple communication
CN202931033U (en) Integrated measurement and control apparatus for intelligent transformer station
CN206283517U (en) The detection platform of intelligent MANET data terminal communication station

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090909

Termination date: 20171104