CN201292519Y - 土工模袋 - Google Patents

土工模袋 Download PDF

Info

Publication number
CN201292519Y
CN201292519Y CNU2008202181177U CN200820218117U CN201292519Y CN 201292519 Y CN201292519 Y CN 201292519Y CN U2008202181177 U CNU2008202181177 U CN U2008202181177U CN 200820218117 U CN200820218117 U CN 200820218117U CN 201292519 Y CN201292519 Y CN 201292519Y
Authority
CN
China
Prior art keywords
bag
concrete
hang
muscle
geotechnical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008202181177U
Other languages
English (en)
Inventor
刘明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN TIMEAST OFFSHORE ENGINEERING Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNU2008202181177U priority Critical patent/CN201292519Y/zh
Application granted granted Critical
Publication of CN201292519Y publication Critical patent/CN201292519Y/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

一种土工模袋,其属于土建工程的建材领域。这种土工模袋由长度相同的外吊筋袋和内吊筋袋组成,外吊筋袋和内吊筋袋形成的二个环状端部采用袋布料封闭,中间环状部设有吊筋绳把外吊筋袋和内吊筋袋等间距固定,在袋上设有一个向中间环状部注入填充物的袋口。土工模袋是通过用高压泵把混凝土或水泥砂浆灌入模袋中,混凝土或水泥砂浆固结后形成具有一定强度的能满足工程需要的结构。土工模袋施工采用一次喷灌成型,施工简便、速度快;可直接水下施工,机械化程度高,整体性强、稳定性好,使用寿命长;具有一定的透水性,在混凝土或水泥砂浆灌入以后,多余的水分通过织物空隙渗出,可以迅速降低水灰比,加快混凝土的凝固速度,增加混凝土的抗压强度。

Description

土工模袋
技术领域
本实用新型涉及一种土工模袋,其属于土建工程的建材领域。
背景技术
土工模袋是一种新的建筑材料,已广泛应用于水利、水电、公路、铁路、海港以及军工等各个领域。土工充泥袋应用于护岸工程时,保沙性能要求较高。因此,土工充泥袋外层用聚丙烯充泥袋布,内层用聚乙烯薄膜复合制成土工复合袋,然后,把袋体安装在抛枕架内,由人工把泥沙装入袋中,封住袋口后,扳动抛枕架,将袋体抛入加固堤段。土工复合袋人工装沙用于黄河大堤防冲加固取得了较好的效果。实践表明,在治河抢险等水利工程中用土工充泥袋代替石方具有施工进度快、造价低、又能就地取材和便于机械化施工等。土工充泥袋的保沙效果试验  用泥浆泵充填土工充泥袋,透水与保沙是相互矛盾的。从施工角度考虑,要求土工充泥袋布有较好的透水性,使充填的泥浆在袋体内排水快,泥沙固结时间短,从而达到加快施工进度的目的,但相应保沙效果也较差,尤其在水流湍急区域的永久性土建结构无法采用土工充泥袋。
发明内容
为了解决上述现有技术存在的问题,本实用新型提供一种土工模袋。该产品是通过用高压泵把混凝土或水泥砂浆灌入模袋中,混凝土或水泥砂浆的厚度是通过吊筋绳的长度来控制内、外吊筋袋间的距离,混凝土或水泥砂浆固结后形成具有一定强度的能满足工程需要的结构。
本发明解决其技术问题所采用的技术方案是:一种土工模袋主要由长度相同的外吊筋袋和内吊筋袋组成;由外吊筋袋和内吊筋袋形成的二个环状端部采用袋布料封闭,中间环状部设有定位结构;在袋上设有一个向中间环状部注入填充物的袋口。
所述外吊筋袋和内吊筋袋都采用矩形结构或圆形结构。
所述定位结构采用吊筋绳把外吊筋袋和内吊筋袋等间距固定。
所述填充物采用混凝土或泥沙。
土工模袋采用聚合化纤合成材料制成的高强度机织布,其主要技术指标:单位面积重量大于600g/m2,经向抗拉强度大于2200N/5cm,纬向抗拉强度大于2000N/5cm,延伸率大于30%,CBR顶破强度大于4000N,垂直渗透系数为0.014cm/s,等效孔径为0.08mm。
模袋用混凝土要求有良好的和易性和流动性,易于泵送。采用的混凝土配合比为:水泥1份、粉煤灰0.5份、砂3份、石4.5份。模袋混凝土设计抗压强度为32MPa。
本实用新型的有益效果是:这种土工模袋由长度相同的外吊筋袋和内吊筋袋组成,外吊筋袋和内吊筋袋形成的二个环状端部采用袋布料封闭,中间环状部设有吊筋绳把外吊筋袋和内吊筋袋等间距固定,在袋上设有一个向中间环状部注入填充物的袋口。土工模袋是通过用高压泵把混凝土或水泥砂浆灌入模袋中,混凝土或水泥砂浆固结后形成具有一定强度的能满足工程需要的结构。土工模袋施工采用一次喷灌成型,施工简便、速度快;可直接水下施工,机械化程度高,整体性强、稳定性好,使用寿命长;具有一定的透水性,在混凝土或水泥砂浆灌入以后,多余的水分通过织物空隙渗出,可以迅速降低水灰比,加快混凝土的凝固速度,增加混凝土的抗压强度。
附图说明
下面结合附图和实施例对本实用新型作进一步说明。
图1是一种方形土工模袋的结构图。
图2是在灌注混凝土后的方形土工模袋的结构图。
图3是一种圆形土工模袋的结构图。
图4是一种方形模袋混凝土在海底管系工程中的应用。
图中:1、方形外吊筋袋,1a、袋口,2、方形内吊筋袋,3、方形中心通孔,4、方形环状端部,5、吊筋绳,5a、外露吊筋绳,6、填充物,7、圆形外吊筋袋,7a、袋口,8、圆形内吊筋袋,9、圆形中心通孔,10、圆形环状端部,11、吊筋绳,11a、外露吊筋绳;a、方形模袋混凝土,b、通水孔,c、输油气管,d、海床。
具体实施方式
图1示出了一种方形土工模袋,图2是已充满混凝土的土工模袋。图中,方形外吊筋袋1套在方形内吊筋袋2上,两端缝上方形环状端部4,在方形外吊筋袋1上设有用于灌注混凝土的袋口1a,为了保持方形外吊筋袋1与方形内吊筋袋2之间等距,采用等间距缝制吊筋绳5,这样在灌注混凝土后可基本上保证混凝土的厚度均匀。该方形模袋混凝土具有方形中心通孔3,适用于需要支撑又能保持水流畅通的工程。
图3示出了一种圆形土工模袋。图中,圆形外吊筋袋7套在圆形内吊筋袋8上,两端缝上圆形环状端部10,在圆形外吊筋袋7上设有用于灌注混凝土的袋口7a,为了保持圆形外吊筋袋7与圆形内吊筋袋8之间等距,采用等间距缝制吊筋绳11,这样在灌注混凝土后可基本上保证混凝土的厚度均匀。该圆形模袋混凝土具有圆形中心通孔9,也适用于需要支撑又能保持水流畅通的工程。
图4示出了方形模袋混凝土在海底管系工程中的应用实例。由于海流的作用,某些海底存在湍急的水流,铺设在海床中的输油气管会在水流的作用下被冲走泥沙而造成局部悬空,当输油气管难以支撑自重时造成断裂等事故时常发生,除影响生产外,还会污染海洋。图中,在海床d上已被水流冲出沟的输油气管c的下部填满方形模袋混凝土a,方形模袋混凝土a既能可靠地支撑住输油气管c,又能让海流经通水孔b流过。此所以要采用中空模袋混凝土,是因为其可以在水下施工,容易保证施工质量,使输油气管c得到可靠支撑。

Claims (4)

1、一种土工模袋,其特征在于:它主要由长度相同的外吊筋袋和内吊筋袋组成;由外吊筋袋和内吊筋袋形成的二个环状端部采用袋布料封闭,中间环状部设有定位结构;在袋上设有一个向中间环状部注入填充物的袋口。
2、据权利要求1所述的土工模袋,其特征在于:所述外吊筋袋和内吊筋袋都采用矩形结构或圆形结构。
3、据权利要求1所述的土工模袋,其特征在于:所述定位结构采用吊筋绳把外吊筋袋和内吊筋袋等间距固定。
4、据权利要求1所述的土工模袋,其特征在于:所述填充物采用混凝土或泥沙。
CNU2008202181177U 2008-09-18 2008-09-18 土工模袋 Expired - Fee Related CN201292519Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008202181177U CN201292519Y (zh) 2008-09-18 2008-09-18 土工模袋

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008202181177U CN201292519Y (zh) 2008-09-18 2008-09-18 土工模袋

Publications (1)

Publication Number Publication Date
CN201292519Y true CN201292519Y (zh) 2009-08-19

Family

ID=41005989

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008202181177U Expired - Fee Related CN201292519Y (zh) 2008-09-18 2008-09-18 土工模袋

Country Status (1)

Country Link
CN (1) CN201292519Y (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102733844A (zh) * 2012-04-27 2012-10-17 徐州中矿安达矿山科技有限公司 一种封孔结构及封孔方法及封孔用膨胀水泥
CN107524470A (zh) * 2017-08-21 2017-12-29 长沙有色冶金设计研究院有限公司 一种土工模袋及快速构建人工矿柱的方法

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102733844A (zh) * 2012-04-27 2012-10-17 徐州中矿安达矿山科技有限公司 一种封孔结构及封孔方法及封孔用膨胀水泥
CN102733844B (zh) * 2012-04-27 2016-05-04 中国矿业大学 一种封孔结构及封孔方法及封孔用膨胀水泥
CN107524470A (zh) * 2017-08-21 2017-12-29 长沙有色冶金设计研究院有限公司 一种土工模袋及快速构建人工矿柱的方法
CN107524470B (zh) * 2017-08-21 2020-02-11 长沙有色冶金设计研究院有限公司 一种土工模袋及快速构建人工矿柱的方法

Similar Documents

Publication Publication Date Title
CN102051896B (zh) 堤坝管涌抢险高聚物封闭注浆方法
CN105507335B (zh) 钢板桩围堰基坑封底结构及施工方法
CN107859145A (zh) 一种排水管水下接驳施工方法
JP4920057B2 (ja) 水域構造物基礎の強化方法
CN103233444B (zh) 水下抛石基床和边坡防冲刷结构及其施工方法
CN101694100A (zh) 一种地下室底板防水构造及施工方法
CN110258452B (zh) 一种用于水利水电工程上的防渗止水结构
CN205475107U (zh) 一种新型多功能水库坝体结构
CN201292519Y (zh) 土工模袋
CN215289911U (zh) 一种可快速修复漏砂的重力式码头结构
TW201028510A (en) An assembling and fixing structure for linking waste tires as one bunch
CN201495521U (zh) 河流抢险、防洪用铰链式大土工包
JP2000045247A (ja) 二重矢板式港湾土木構造物
Abdelgader et al. State-of-the-Art Report on fabric formwork
CN106284204A (zh) 一种抗洪救灾、护筑堤堆的快捷装置及工艺
CN105839653A (zh) 一种沉管隧道重建围堰防渗体系的施工方法
WO2018196495A1 (zh) 一种三维水泥基土工复合材料防水垫
CN202064318U (zh) 笼体
CN112832199A (zh) 一种水利工程建设中堤防溃口快速封堵装置
CN210507492U (zh) 一种围堰结构
CN208701605U (zh) 一种基于胶结化堆石的透水防波堤
CN106120958A (zh) 组合式钢箱基座取水头结构
CN106544986B (zh) 珊瑚礁岛机场护岸的高聚物注浆、柔性护岸的加固方法
JP2012180669A (ja) 防波堤の補強方法及び補強防波堤
Hawkswood Fabric formwork systems used in marine construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: TIANJIN TIANYI OFFSHORE ENGINEERING CO., LTD.

Free format text: FORMER OWNER: LIU MING

Effective date: 20090925

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20090925

Address after: Block B, six floor, No. 2 Dongting Road, Tianjin Development Zone, postcode: 300457

Patentee after: TIANJIN TIMEAST OFFSHORE ENGINEERING CO., LTD.

Address before: No. 10, No. 9-2, Haidong Road, Xigang District, Liaoning, Dalian Province: 116011

Patentee before: Liu Ming

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090819

Termination date: 20170918

CF01 Termination of patent right due to non-payment of annual fee