CN201265018Y - Combined type blast furnace cooling wall mounting auxiliary device - Google Patents

Combined type blast furnace cooling wall mounting auxiliary device Download PDF

Info

Publication number
CN201265018Y
CN201265018Y CNU2008201423573U CN200820142357U CN201265018Y CN 201265018 Y CN201265018 Y CN 201265018Y CN U2008201423573 U CNU2008201423573 U CN U2008201423573U CN 200820142357 U CN200820142357 U CN 200820142357U CN 201265018 Y CN201265018 Y CN 201265018Y
Authority
CN
China
Prior art keywords
blast furnace
crossbeam
furnace cooling
cooling stave
auxiliary device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008201423573U
Other languages
Chinese (zh)
Inventor
常喜
王雪
侯尔祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin MCC20 Construction Co Ltd
Original Assignee
Tianjin MCC20 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin MCC20 Construction Co Ltd filed Critical Tianjin MCC20 Construction Co Ltd
Priority to CNU2008201423573U priority Critical patent/CN201265018Y/en
Application granted granted Critical
Publication of CN201265018Y publication Critical patent/CN201265018Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Blast Furnaces (AREA)
  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The utility model discloses a combination-typed large blast furnace cooling wall installation auxiliary device, comprising a fixed bracket and a hoisting mechanism; the fixed bracket consists of an inverted T-shaped crossbeam (3), and an upper column (4) and two lower columns (10) which are connected with the crossbeam (3); the crossbeam (3) is provided with the hoisting device (6); an inclined supporting bar (7) is arranged between the two inverted T-shaped crossbeams (3); an inclined supporting bar (12) is arranged between the upper column and the crossbeam; the hoisting device (6) is mainly a guide chain; and the end of the guide chain is provided with an expansion bolt (8). The combination-typed large blast furnace cooling wall installation auxiliary device has simple structure, convenient operation, safety and reliability, and excellently improves the construction efficiency and construction quality; the material used for preparing the device can sufficiently utilize scraps and the preparation cost is low.

Description

Built-up type blast furnace cooling stave installation auxiliary device
Technical field
The utility model relates to a kind of combined large blast furnace cooling stave installation auxiliary device, relates in particular to a kind of large blast furnace cooling stave that is applicable to the drawing device that hangs of the outer little job space of stove is installed.
Background technology
At present, for the large blast furnace equipment installation project all have the duration short, workload is big, working face is little, safety and specification of quality be than characteristics such as height; For guaranteeing both quality and quantity to finish smoothly each task, press for and improve existing mounting process, improve work efficiency.It is working procedure comparatively crucial in the blast-furnace equipment installation work that blast furnace cooling stave is installed, and its installation quality and speed directly affect the quality and the duration of engineering.The installation of blast furnace cooling stave mainly comprises: lifting, in place and adjustment.
In place and adjust at cooling stave, generally be to utilize crane in the blast furnace, lead chain and the people pushes away in place pickaback by existing traditional construction technology.It has the following disadvantages: (1) take a lot of work, dangerous; General large blast furnace cooling stave is of a size of 1000*500*3000 (the thick * height of wide *), and weight heavier (its weight is generally in 3T to 5T scope), therefore needs to drop into more man power and material in the installation process of cooling stave; In the construction, operation on the service platform in blast furnace, the workmen will prevent that not only cooling stave from wounding, and will prevent also that simultaneously the underfooting object from mixing down, and also will concentrate strength on making cooling stave in place, this has brought inconvenience also to bring very big potential safety hazard simultaneously to construction.(2) be unfavorable for the protection of finished product, all will carry out the pressure testing experiment before and after blast furnace cooling stave is installed, its apparatus body and water pipe are all forbidden to collide energetically; Therefore in the stove many people operation strength unstable etc. very easily with equipment and furnace shell damaged in collision.(3) the construction operation face is little, and general blast furnace diameter is about 8-12 rice, and blast furnace cooling stave is installed on the platform of all setting up in blast furnace and carried out, it is very narrow that the monolithic cooling stave is installed its scope of operation, is not suitable for operation in many people stove, is subjected to the restriction of construction operation face, easily cause the work holdup, delay the construction period.(4) operating efficiency, quality can not guarantee; Because large blast furnace cooling stave quality is all very heavy, in stove, utilize manpower to install, not only inefficiency is dangerous, and cooling stave is also wayward with the furnace shell gap, is difficult to the assurance construction quality.
According to the characteristics of cooling stave constructional method, also once outside blast furnace, used and lead chain and hang on the platform, chain passes the method that the water pipe eyelet welding is connected on the water pipe and installs, but not being every layer of cooling stave, the platform sling point do not have, and highly also not parallel, chain is welded on hell to pay on the water pipe in addition, and program is loaded down with trivial details.Therefore, at the mounting condition of present large blast furnace cooling stave, need exploitation to be adapted to the blast furnace cooling stave installation auxiliary device of the outer little job space of stove.
The utility model content
The purpose of this utility model is in order to overcome existing drawback in the above-mentioned prior art, and a kind of easy to operate, high efficiency, high safety, built-up type blast furnace cooling stave installation auxiliary device with low cost are provided.
In order to solve the problems of the technologies described above, the technical scheme that the utility model built-up type blast furnace cooling stave installation auxiliary device is achieved is, a kind of combined large blast furnace cooling stave installation auxiliary device, comprise lifting appliance and hang to draw and use fixed support, described fixed support is made of an inverse-T-shaped crossbeam and a top column and two lower pole of being connected on the described crossbeam, and described inverse-T-shaped crossbeam is provided with lifting appliance.
Described top column is a retractor device, can be the setting of a bolt or other adjustable lengths.Described top column is fixedlyed connected with described crossbeam.Described lower pole and described crossbeam are slidingly connected for the bolt indentation formula.Be provided with two inclined support bars between described inverse-T-shaped two crossbeams, also be provided with inclined support bar between top column and crossbeam.Described lifting appliance is led chain end and is provided with expansion bolt for leading chain.
The utility model compared with prior art its beneficial effect is: the utility model hangs to draw with fixed support and lifting appliance combination and is provided with, wherein, support bracket fastened lower prop adopts slidably and connects, and can adjust the pillar distance and insert in the water pipe fixedly entire bracket according to lower floor's cooling stave water pipe spacing; The top column can utilize bolt to regulate its length setting, so that along with the support angle is adjusted at the last furnace shell angle of inclination, is convenient to workmen's operation, need not many people operation, and the safety coefficient height; Lifting appliance is led chain end and is provided with expansion bolt, can be good at being connected with water pipe, and conveniently adorns, tears open; The utility model is simple in structure, and is easy to operate, safe and reliable, higher to the protectiveness of product; Make material of the present utility model and can make full use of scrap stock, cost of manufacture is cheap.
Description of drawings
Fig. 1 is the main TV structure sketch of the utility model built-up type blast furnace cooling stave installation auxiliary device.
Fig. 2 is the right view of Fig. 1 built-up type blast furnace cooling stave installation auxiliary device.
Fig. 3 is the application sketch of the utility model built-up type blast furnace cooling stave installation auxiliary device.
Embodiment
Below in conjunction with the drawings and specific embodiments the utility model is described in further detail.
The utility model combined large blast furnace cooling stave installation auxiliary device, comprise hanging and draw with fixed support and lifting appliance, as shown in Figure 1 and Figure 2, the utility model combined large blast furnace cooling stave is installed and is hung drawing device, fixed support mainly by a crossbeam of falling the T-shape 3 and be connected the top vertical rod 4 on the described crossbeam, two bottom vertical rods 10 are formed, its top vertical rod 4 is a bolt arrangement, can telescopic adjustment length, adjust flexibly the crossbeam angle and with the furnace shell distance.Between top vertical rod 4 and the crossbeam 3 can be that welding, riveted joint etc. are fixedlyed connected.Its underpart vertical rod 10 is provided with two, and fixed plate 9 is set, the distance that guarantees bottom vertical rod insertion water pipe suits the requirements, bottom vertical rod 10 and crossbeam 3 can be that welding etc. is fixedlyed connected, preferred bottom vertical rod 10 is adopted with crossbeam 3 and is slidingly connected, and can be the bolt indentation formula and is slidingly connected, and crossbeam 3 is provided with chute 11, can adjust vertical pole ' s span according to cooling stave water pipe spacing like this, guarantee support bracket fastened resistance to overturning; 3 on inverse-T-shaped two crossbeams are provided with two inclined support bars 7, and 3 on top column 4 and crossbeam also are provided with inclined support bar 12, to guarantee the steadiness of general frame.Hoisting ring 5 is set on crossbeam 3, and in order to hang up device for hoisting 6, lifting appliance 6 adopts leads chain, hangs expansion bolt 8 in lifting appliance 6 ends, and expansion bolt 8 closely is connected with the cooling stave water pipe when work, can play fixed action.
As shown in Figure 3, described built-up type blast furnace cooling stave installation auxiliary device with cooling stave 2 hang draw in place, at first fixed support bottom vertical rod 10 is inserted in the cooling stave water pipe during work, its top vertical rod 4 withstands on the furnace shell 1 and adjusts flexible to the optimum position, pierce in the stove by the water pipe hole leading the chain chain subsequently, be connected with cooling stave 2 water pipes with expansion bolt 8, chain is led in pulling at last makes cooling stave 2 in place.Whole cooling stave installation is hung drawing device and can be changed structure formation according to field condition, its material therefor is also unrestricted, firm available getting final product, such as: its crossbeam 3 can be used joist steel, channel-section steel, its column 4,10 can be with square tube or pipe etc., but must consider its overall weight, be fit to singlely to move, handled easily is benefit.Lifting appliance 6 adopts leads chain, leads chain and selects and can generally can select 2 tons and lead chain according to the weight of cooling stave 2, can increase and hang the security of drawing.Supplementary unit is made main consider levels cooling stave water pipe distance, furnace shell angle of inclination, cooling stave weight etc.
Although in conjunction with the accompanying drawings the utility model has been carried out foregoing description; but the utility model is not limited to above-mentioned embodiment; above-mentioned embodiment only is schematic; rather than it is restrictive; those of ordinary skill in the art is under enlightenment of the present utility model; under the situation that does not break away from the utility model aim and claim institute protection domain, can also make a lot of distortion, these all belong to the row of protection of the present utility model.

Claims (6)

1. combined large blast furnace cooling stave installation auxiliary device, comprise lifting appliance (6), it is characterized in that, also comprise fixed support, described fixed support is by an inverse-T-shaped crossbeam (3) and be connected a top column (4) on the described crossbeam (3) and two lower pole (10) constitute, and described crossbeam (3) is provided with lifting appliance (6).
2. according to the described combined large blast furnace cooling stave of claim 1 installation auxiliary device, it is characterized in that described top column (4) is a retractor device.
3. according to claim 1 or 2 described combined large blast furnace cooling stave installation auxiliary devices, it is characterized in that described top column (4) is fixedlyed connected with described crossbeam (3).
4. according to the described combined large blast furnace cooling stave of claim 1 installation auxiliary device, it is characterized in that described lower pole (10) is slidingly connected for the bolt indentation formula with described crossbeam (3).
5. according to the described combined large blast furnace cooling stave of claim 1 installation auxiliary device, it is characterized in that, be provided with inclined support bar (7) between described inverse-T-shaped crossbeam (3), be provided with inclined support bar (12) between top column (4) and crossbeam (3).
6. according to the described combined large blast furnace cooling stave of claim 1 installation auxiliary device, it is characterized in that described lifting appliance (6) is led chain end and is provided with expansion bolt (8) for leading chain.
CNU2008201423573U 2008-10-10 2008-10-10 Combined type blast furnace cooling wall mounting auxiliary device Expired - Fee Related CN201265018Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008201423573U CN201265018Y (en) 2008-10-10 2008-10-10 Combined type blast furnace cooling wall mounting auxiliary device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008201423573U CN201265018Y (en) 2008-10-10 2008-10-10 Combined type blast furnace cooling wall mounting auxiliary device

Publications (1)

Publication Number Publication Date
CN201265018Y true CN201265018Y (en) 2009-07-01

Family

ID=40831383

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008201423573U Expired - Fee Related CN201265018Y (en) 2008-10-10 2008-10-10 Combined type blast furnace cooling wall mounting auxiliary device

Country Status (1)

Country Link
CN (1) CN201265018Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110684875A (en) * 2019-11-08 2020-01-14 莱芜钢铁集团有限公司 Large square hole cover installation auxiliary device
CN112304203A (en) * 2020-10-19 2021-02-02 中国一冶集团有限公司 Cooling wall connecting pipe measuring die and size determining method of cooling wall connecting pipe

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110684875A (en) * 2019-11-08 2020-01-14 莱芜钢铁集团有限公司 Large square hole cover installation auxiliary device
CN110684875B (en) * 2019-11-08 2023-12-19 莱芜钢铁集团有限公司 Auxiliary device for installing large square hole cover
CN112304203A (en) * 2020-10-19 2021-02-02 中国一冶集团有限公司 Cooling wall connecting pipe measuring die and size determining method of cooling wall connecting pipe

Similar Documents

Publication Publication Date Title
CN204899180U (en) Steel construction jar body aerial working platform simply sets up device
CN109973112B (en) Super-large-dip-angle narrow-space tunnel anchor cable saddle gantry system and installation method thereof
CN111764629A (en) Method for mounting and dismounting inclined roof hanging basket without counterweight
CN207245138U (en) Boat scaffold adjustable in pitch
CN201265018Y (en) Combined type blast furnace cooling wall mounting auxiliary device
CN217028004U (en) Annular hanging basket suspension device for curtain wall construction of super high-rise building
CN210105267U (en) Hanging basket suspension structure
CN111827648A (en) Construction device and method for down-supporting type overhanging scaffold
CN110939261B (en) Double outer scaffold of dish knot formula structure of encorbelmenting
CN105110205B (en) A kind of reverse method for dismounting of derrick crane
CN202767547U (en) Nuclear plant construction safety rope fixing clamping rod
CN201027135Y (en) Hanging tool mechanism for swinging 55mPHC pipe pile
CN203582282U (en) Automatic tripping device
CN206799012U (en) A kind of concrete batten transport of small space and installation tool group
CN203200719U (en) Hanging type slope pouring template device
CN202000649U (en) Movable strengthening device for bottom of upright stenshion of construction cantilevered frame
CN205134921U (en) Building outer wall concrete constructional column hangs construction platform
CN211285604U (en) Manual tube drawing machine
CN204456891U (en) Mortar hopper is adopted mortar concrete to be transported to the device of floor
CN204609267U (en) A kind of suspension bracket for tank inside construction
CN202322137U (en) Telescopic hanger
CN201924585U (en) Fixed device for reinforcing bottom of upright rod of suspension scaffold for building
CN214836452U (en) Advanced roof control device for anchor net cable of coal roadway
CN220055952U (en) Antitheft device for main cable matched with construction lifting equipment
CN109987501A (en) A kind of device threaded off in Quick air in steel structure hoisting and tripping method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090701

Termination date: 20131010