CN201176366Y - Hook structure for suspensing transportation device added in buildings - Google Patents

Hook structure for suspensing transportation device added in buildings Download PDF

Info

Publication number
CN201176366Y
CN201176366Y CNU2007202016550U CN200720201655U CN201176366Y CN 201176366 Y CN201176366 Y CN 201176366Y CN U2007202016550 U CNU2007202016550 U CN U2007202016550U CN 200720201655 U CN200720201655 U CN 200720201655U CN 201176366 Y CN201176366 Y CN 201176366Y
Authority
CN
China
Prior art keywords
transportation device
model
steel plate
plate
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007202016550U
Other languages
Chinese (zh)
Inventor
李黎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CNU2007202016550U priority Critical patent/CN201176366Y/en
Application granted granted Critical
Publication of CN201176366Y publication Critical patent/CN201176366Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a steeliness lifting point structure of a hanging transportation device, which is characterized by arranging two holes (3) on floorslabs (2) which are arranged on both sides of an existing armored concrete beam (1) of a building, box type steel supports which are made by top boards (4) and side plates (5) are inserted into holes (3) and are fixed through being screwed by screw bolts (6), wherein a steel plate (7) is welded with the side plates (5), a bottom board (8) is welded with the steel plate (7) and the side plates (5), and the bottom plate (8) is connected with a hanging transportation orbit (9) through the screw bolt (10). The lifting point structure avoids the defects that the construction of the traditional structure has big difficulties, the appearance is not beautiful, the maintaining time is long and the requirements of the lifting height are difficultly satisfied, and the unity model has the advantages that the construction of the traditional structure is simple, and the utility model has the advantages that the appearance is light, the cost is low, and the lifting point structure is easy to carry out and satisfy the requirements of the lifting height, and the lifting point structure can be immediately put into use.

Description

The suspension transportation device suspension centre structure of setting up in the building
Technical field
The utility model relates to a kind of suspension transportation device suspension centre structure of setting up in the existing building thing.
Background technology
In industrial premises,, therefore need set up suspension centre in the building of having constructed for this equipment because the needs on using usually need increase and hang transportation device.The suspension transportation device here is meant electric single-beam or electric block, and its purposes is hanging device or goods.
Fig. 1, Fig. 2 are that adopt orthodox method to set up at the bottom of floor beam of having constructed or roof girder to hang the transportation device suspension centre be the scheme drawing of track, 1 is reinforcing bar in the existing reinforced beam among the figure, 2 for increasing the steel bar stress of the necessity that is provided with in the beams of concrete newly, 3 is the beams of concrete of newly building, 4 for being cut bolt, 5,6 is back welding steel plate, and 7 for hanging transporting facility track, and 8 for connecting the tension bolt that hangs transporting facility track.As can be seen, adopt this structure not only to need the surperficial cement concrete at the bottom of original beam destroyed and expose original beam steel, so that with newly add reinforcing bar welding, and the beams of concrete of newly building combines not tight with original beam, also very difficult at high-altitude formwork casting concrete, bring great difficulty to construction, and also need after the concreting it is carried out the maintenance of long period, place in operation at once, therefore adopting conventional confguration to seem wastes time and energy.
The utility model content
The technical matters that the utility model originally will solve is: the suspension transporting facility track of setting up in a kind of building structure is provided, with overcome constructional difficulties that conventional confguration exists, weak point such as waste time and energy.
In order to solve the problems of the technologies described above, the utility model has been taked following technical scheme: open two holes on the reinforced beam both sides floor that the existing building thing has been constructed, make a box steelframe, insert perforate then and tighten fixing by bolt, weld side plate, base plate and stiffener again, hang transporting facility track by bolted connection, with cement concrete that the floor hole envelope is real at last.
Obviously, newly-increased steel suspension transportation device suspension centre build is light and handy, simple in structure, and it is convenient to construct, and can save the time of concrete curing, satisfies the requirement of hoisting height easily, and its advantage is very outstanding.
The beneficial effects of the utility model are: avoided adopting the shortcoming that the conventional confguration difficulty of construction is big, profile is not attractive in appearance, curing time is long, steel hangs that the construction of transportation device suspension centre is convenient, profile is light and handy, and place in operation at once.
Description of drawings
Fig. 1 is that transportation device suspension centre structural representation is hung in traditional increase;
Fig. 2 is the A-A cutaway view among Fig. 1;
Fig. 3 is a perforate plan sketch of the present utility model;
Fig. 4 is a box steelframe scheme drawing of the present utility model;
Fig. 5 is a scheme drawing of the present utility model, is the scheme drawing when 100mm≤h<200mm;
Fig. 6 is the B-B cutaway view among Fig. 5;
Fig. 7 is the C-C cutaway view among Fig. 5;
Fig. 8 is a scheme drawing of the present utility model, is the scheme drawing when 200mm≤h≤600mm;
Fig. 9 is the D-D cutaway view among Fig. 8.
Concrete real-time mode
Embodiment of the present utility model: when adopting the utility model on the existing building reinforced beam, to set up steel suspension transportation device suspension centre, can carry out as follows:
The first, set up the mounting hole 3 of respectively offering a 100mm * 250mm on existing reinforced beam 1 biside plate 2 that hangs transportation device suspension centre place at needs, symmetrical perforate, Fig. 3 is seen in its plane signal;
The second, adopt steel plate to make box steelframe, use a top board 4 and two blocks of side plates 5, the specification of top board 4 is the thick steel plate of 10mm, and width is deck-siding+45mm, and length is 200mm; The specification of two blocks of side plates 5 is the thick steel plate of 8mm, and width is 200mm, highly is deck-molding+100mm, reserves 2 bolts hole on every block of side plate, and aperture 18mm is welded on the top board 4, and scheme drawing is seen Fig. 4;
The 3rd, in the box steelframe patchhole of making 3, penetrate bolt 6 and tight a bolt, make box steelframe clamp fitting on beams of concrete, bolt 6 is two M16.Scheme drawing is seen Fig. 5;
The 4th, welding steel 7 and base plate 8, and by tension bolt 10 with the suspension transporting facility track 9 be connected.The distance on the h plane that is existing reinforced beam 1 bottom surface to the back of half bearing shell 8.According to the value size of h, this step is divided into following two kinds of situations and carries out:
1. when 100mm≤h<200mm, the specification of steel plate 7 is the thick steel plate of 8mm, and width is 100mm, highly is h+150mm; The specification of back of half bearing shell 8 is the thick steel plate of 14mm, and width is 130mm, and length is 200mm, reserves 2 bolts hole, aperture 18mm on the every base plate; Tension bolt 10 is four M16; The specification that hangs transporting facility track 9 is I25a.Scheme drawing is seen Fig. 5, Fig. 6, Fig. 7;
2. when 200mm≤h≤600mm, increase stiffener 11, the specification of steel plate 7 is the thick steel plate of 8mm, and width is 100mm, highly is h+150mm; The specification of back of half bearing shell 8 is the thick steel plate of 14mm, and width is deck-siding+200mm, and length is 200mm; Reserve 4 bolts hole, aperture 18mm on the every base plate; The specification of stiffener 11 is the thick steel plate of 8mm, and width is a deck-siding, highly is h-80mm; Tension bolt 10 is four M16; The specification that hangs transporting facility track 9 is I25a.Scheme drawing is seen Fig. 8, Fig. 9;
The 5th, with slightly expanded concrete that perforate 3 envelopes on the plate 2 are real.
By above steps, promptly finished and on beam, set up the work that steel hangs the transportation device suspension centre, as can be seen, whole process is very simple and direct, and it is lightly attractive in appearance that the steel of newly establishing hangs the transportation device suspension centre, place in operation at once, stressed effect is also fine.

Claims (2)

1. the suspension transportation device suspension centre structure of setting up in the building, it is characterized in that: on reinforced beam (1) the both sides floors (2) of existing building thing, two mounting holes (3) are arranged, the interior bolt of making of top board (4), side plate (5) (6) that also passes through of box steelframe insertion mounting hole (3) connects, steel plate (7) is connected with side plate (5), base plate (8) is connected with steel plate (7), side plate (5), and base plate (8) connects suspension transporting facility track (9) by bolt (10).
2. the suspension transportation device suspension centre structure of setting up in the building according to claim 1 is characterized in that: on the base plate (8) between the biside plate (5) stiffener (11) is arranged.
CNU2007202016550U 2007-12-17 2007-12-17 Hook structure for suspensing transportation device added in buildings Expired - Fee Related CN201176366Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007202016550U CN201176366Y (en) 2007-12-17 2007-12-17 Hook structure for suspensing transportation device added in buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007202016550U CN201176366Y (en) 2007-12-17 2007-12-17 Hook structure for suspensing transportation device added in buildings

Publications (1)

Publication Number Publication Date
CN201176366Y true CN201176366Y (en) 2009-01-07

Family

ID=40216381

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007202016550U Expired - Fee Related CN201176366Y (en) 2007-12-17 2007-12-17 Hook structure for suspensing transportation device added in buildings

Country Status (1)

Country Link
CN (1) CN201176366Y (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103696582A (en) * 2012-09-27 2014-04-02 贵阳铝镁设计研究院有限公司 Method and structure for improving rigidity of reinforced concrete beam
CN106006436A (en) * 2016-07-01 2016-10-12 广东省工业设备安装有限公司 Beam embracing hoisting device
CN106049883A (en) * 2016-05-23 2016-10-26 中交第航务工程局有限公司 Novel lifting point construction process for concrete components
CN109779289A (en) * 2019-03-23 2019-05-21 中国二十二冶集团有限公司 The mounting structure and construction method of single track beam orbit
CN112027903A (en) * 2020-08-27 2020-12-04 中铁二十局集团有限公司 Portal crane walking rail fixing device and portal crane

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103696582A (en) * 2012-09-27 2014-04-02 贵阳铝镁设计研究院有限公司 Method and structure for improving rigidity of reinforced concrete beam
CN106049883A (en) * 2016-05-23 2016-10-26 中交第航务工程局有限公司 Novel lifting point construction process for concrete components
CN106006436A (en) * 2016-07-01 2016-10-12 广东省工业设备安装有限公司 Beam embracing hoisting device
CN106006436B (en) * 2016-07-01 2019-03-05 广东省工业设备安装有限公司 One kind embracing beam hoisting apparatus
CN109779289A (en) * 2019-03-23 2019-05-21 中国二十二冶集团有限公司 The mounting structure and construction method of single track beam orbit
CN112027903A (en) * 2020-08-27 2020-12-04 中铁二十局集团有限公司 Portal crane walking rail fixing device and portal crane
CN112027903B (en) * 2020-08-27 2022-07-12 中铁二十局集团有限公司 Portal crane walking rail fixing device and portal crane

Similar Documents

Publication Publication Date Title
CN206053131U (en) Precast floor slab steel reinforcement cage component and floor
CN201176366Y (en) Hook structure for suspensing transportation device added in buildings
CN110607867A (en) Non-dismantling mold laminated slab
CN112832368A (en) Quick construction process for cantilever beam at ultrahigh position
CN113585075A (en) Cast-in-place bridge deck formwork for steel-concrete composite beam
CN202125104U (en) Residential building system formed by cast-in-place beam columns and prefabricated sandwich concrete wall slabs
CN114482375A (en) Integral joint type reinforced concrete laminated slab and construction method
CN219773324U (en) Concrete beam plate structure
CN211143440U (en) Assembled bidirectional steel bar truss floor
CN111851827A (en) Assembly type prefabricated steel bar truss disassembly-free template system and manufacturing method thereof
CN206646634U (en) Assemble prefabricated components formula house
CN112962847B (en) Construction method of assembled laminated slab
CN214402368U (en) Detachment-free truss plate
CN213926975U (en) Concrete wall and prefabricated profiled steel sheet combined plate connecting structure
CN212802189U (en) Assembly type disassembly-free template
CN211499312U (en) Bolt type connection structure of partially-coated concrete combined shear wall
CN211949131U (en) Combined upper-chord corrugated web ribbed secondary beam floor system
WO2021109181A1 (en) High-strength lightweight composite floor slab and floor slab layer system thereof
CN111535581A (en) Convenient and fast mounting and dismounting type combined prefabricated formwork applicable to building floor lowering position
CN111851830A (en) Assembly type disassembly-free template and manufacturing method thereof
CN111663695A (en) Assembly type template-free box-type floor system and construction process thereof
CN206846097U (en) A kind of Men Gangyu frameworks separately-loaded pipeline support structure
CN216552527U (en) Heat preservation and decoration integrated module wall and house based on heat preservation and decoration integrated module wall
CN109881834A (en) Grid beams add the floor construction and construction method of composite plate
CN220318499U (en) Prefabricated underground continuous wall with three-hole structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: GUIYANG ALUMINUM AND MAGNESIUM DESIGN INSTITUTE CO

Free format text: FORMER NAME: GUIYANG ALUMINIUM AND MAGNESIUM DESIGN INST.

CP03 Change of name, title or address

Address after: 550081 Guiyang Province, Jinyang New District, Zhu Zhu Road, No. 2

Patentee after: Guiyang Aluminum & Magnesium Design Institute Co., Ltd.

Address before: 550004 No. 208, Beijing Road, Guiyang, Guizhou

Patentee before: Guiyang Aluminium and Magnesium Design Inst.

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee