CN201162214Y - 根式抗拔桩 - Google Patents

根式抗拔桩 Download PDF

Info

Publication number
CN201162214Y
CN201162214Y CNU2007202014540U CN200720201454U CN201162214Y CN 201162214 Y CN201162214 Y CN 201162214Y CN U2007202014540 U CNU2007202014540 U CN U2007202014540U CN 200720201454 U CN200720201454 U CN 200720201454U CN 201162214 Y CN201162214 Y CN 201162214Y
Authority
CN
China
Prior art keywords
pile
uplift pile
bar
uplift
melt pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007202014540U
Other languages
English (en)
Inventor
常建华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CNU2007202014540U priority Critical patent/CN201162214Y/zh
Application granted granted Critical
Publication of CN201162214Y publication Critical patent/CN201162214Y/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本实用新型公开了一种建筑物/构筑物下部基础用根式抗拔桩,该桩位于地坑的下面成群布置,为根式钢筋砼现浇结构。其中,抗拔桩长度H≥5m,桩顶锚入地坑的底部尺寸h≥200mm;抗拔桩含有横向钢筋(4)和桩箍筋(6),钢筋(4)为4根,其直径不小于14mm,桩箍筋(6)的直径为6~8mm,间距为200~400mm,抗拔桩中钢筋砼的细石砼等级≥C25。本实用新型通过将传统的大直径钢筋砼桩改为小直径根式桩后,可使成桩工艺变得简单,不需使用大型成孔机械设备,仅需采用简单钻孔小机械即可,同时消除了人工开挖成孔时对施工者人身安全所潜在威胁。同时,更加经济而有效。

Description

根式抗拔桩
技术领域
本实用新型涉及一种建筑物/构筑物下部基础用抗拔桩。
背景技术
桩基础是一种常见的基础型式,目前已广泛采用,采用桩基往往是由于浅层地基力学指标较差,而下部符合要求的岩土埋置又较深,此时,就需要采用桩基作为基础型式,以便有效而安全地传递荷载。桩基不仅可以传递向下的压力荷载,而且也常作为抗拔构件使用。如一个地坑式构筑物,当地下水位埋深较浅,那么待地坑施工完毕后,其受力状态如图1所示,地坑自重为G,水的上浮力为F,若上浮力F大于其自重G时,地坑将发生上浮,并且当各部位的上浮速度不一致时,还会导致地坑发生开裂甚至破坏。为解决这一问题,传统的处理方法一般有两种:一种是简单的增加结构自重,即G值,但这样势必造成材料的浪费;另一种就是在地坑底部配置抗拔桩,通过桩侧的摩擦力及桩底的锚拉力抵抗上浮力。而传统的抗拔桩往往为直径600mm以上的大直径预制或人工挖孔现浇桩,如图2所示,采用这种结构需要大型机械或人工开挖成孔,材料用量较大,施工人员易出现人身安全问题,而且往往还需在桩顶设置桩顶梁,耗时费材,施工中的节点构造也较为复杂。
实用新型内容
本实用新型要解决的技术问题是:针对传统大直径桩型在解决抗拔时的不足之处,提出一种新的抗拔桩,该抗拔桩成桩工艺简单,不需使用大型成孔设备,且避免了人工开挖成孔时对施工者人身安全所潜在的威胁,以克服现有技术的不足。
为了解决上述技术问题,本实用新型采用如下技术方案:
设计时应先分别计算出地坑的自重G及所受的上浮力F值,若G<F,或G/F值小于规范规定的安全值,则可按本实用新型在地坑底设置根式桩(该桩截面小,使用时又以群桩型式使用,形似于植物的根部,因此可将其称为根式桩),构筑物(地坑)的抗浮力不足部分由根式抗拔桩提供,在确定桩长、桩径后即可根据地勘报告中的相关参数计算出需要配置的根式桩的根数。当然,在地勘阶段,还应首先通过地勘判定构筑物底部无淤泥土层的存在。本实用新型应用于拟建的建筑物/构筑物下部土层无淤泥质土的地基情况。
本实用新型的有益效果是:通过将传统的大直径钢筋砼桩改为本实用新型的小直径根式桩后,可以使成桩工艺变得十分简单,避免了大型成孔机械设备的使用,仅需采用简单钻孔小机械即可,同时也消除了人工开挖成孔时对施工者人身安全所潜在威胁。同时,与传
统大直径抗拔桩型相比,在相同材料用量的情况下,显而易见,改用本实用新型的根式小直径桩后,由于桩侧面积大幅增加,其抗拔能力可大大提高。可见,采用结构后可更加经济而有效。
附图说明
图1为不设抗拔桩的地坑受力状态示意图,图中G为地坑自重,F为水的上浮力,7为地面标高,8为地下水位标高;
图2为传统的大直径钢筋砼桩及地坑示意图;图中1为地坑,2为坑底布置的传统大直径钢筋砼抗拔桩,3为桩顶梁;
图3为本实用新型的结构示意图;图中1为地坑,5为根式抗拔桩;
图4为图3中的A朅剖视图,4为竖向钢筋,6为桩箍筋。
具体实施方式
本实用新型的实施例:采用本实用新型的地坑时,可按如下步骤进行:
通过对建筑物/构筑物的受荷计算,可分别得出G及F值,当G/F<1.3时,表明其抗浮力不满足要求,需要配置抗拔桩;
通过地勘确定建筑物/构筑物底部各土层分布情况,包括各土层的力学指标,并判断其底部是否有淤泥质土层的存在,若无,则可采用本结构进行设计;
在第一步中抗浮承载力不足部分即为根式抗拔桩所承担的荷载,根式抗拔桩应满足下述构造要求:
根式抗拔桩的桩径d为80~200mm,桩间距B≥5d,
②根式抗拔桩的桩长H≥5m,
③根式抗拔桩的竖向受力筋不小于4根,直径φ14,箍筋为φ6~φ8,间距200~400mm,细石砼等级≥C25,
④桩顶锚入地坑底部尺寸h≥200mm,
确定了桩长及桩径后,再通过地勘相关资料即可计算出单根桩所能提供的抗拔力,从而确定所需布置的根式抗拔桩数量;
第四,施工时先用小型钻孔设备钻孔,到达设计标高后放入预先制作好的钢筋笼,再注入细石砼振捣成桩。

Claims (6)

1.一种根式抗拔桩,位于地坑(1)的下面成群布置,其特征在于:抗拔桩(5)为根式钢筋砼现浇结构,抗拔桩(5)含有竖向钢筋(4)和桩箍筋(6)。
2.根据权利要求1所述的抗浮地坑结构,其特征在于:抗拔桩(5)长度H≥5m。
3.根据权利要求1所述的抗浮地坑结构,其特征在于:抗拔桩(5)桩顶锚入地坑(1)的底部尺寸h≥200mm。
4.根据权利要求1所述的抗浮地坑结构,其特征在于:钢筋(4)最小构造配筋为4根,其直径不小于14mm。
5.根据权利要求1所述的抗浮地坑结构,其特征在于:桩箍筋(6)的直径为6~8mm,间距为200~400mm。
6.根据权利要求1所述的抗浮地坑结构,其特征在于:抗拔桩(5)中钢筋砼的细石砼等级≥C25。
CNU2007202014540U 2007-11-27 2007-11-27 根式抗拔桩 Expired - Fee Related CN201162214Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007202014540U CN201162214Y (zh) 2007-11-27 2007-11-27 根式抗拔桩

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007202014540U CN201162214Y (zh) 2007-11-27 2007-11-27 根式抗拔桩

Publications (1)

Publication Number Publication Date
CN201162214Y true CN201162214Y (zh) 2008-12-10

Family

ID=40183152

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007202014540U Expired - Fee Related CN201162214Y (zh) 2007-11-27 2007-11-27 根式抗拔桩

Country Status (1)

Country Link
CN (1) CN201162214Y (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105256833A (zh) * 2014-03-21 2016-01-20 刘献刚 一种地下空间建筑结构
CN105256826A (zh) * 2014-01-24 2016-01-20 刘献刚 地下空间建筑结构
CN111005410A (zh) * 2019-11-07 2020-04-14 航天建筑设计研究院有限公司 一种建筑物抗浮结构及其绿色施工方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105256826A (zh) * 2014-01-24 2016-01-20 刘献刚 地下空间建筑结构
CN105256833A (zh) * 2014-03-21 2016-01-20 刘献刚 一种地下空间建筑结构
CN105256834A (zh) * 2014-03-21 2016-01-20 刘献刚 一种地下空间建筑结构
CN105256835A (zh) * 2014-03-21 2016-01-20 刘献刚 一种地下空间建筑结构
CN111005410A (zh) * 2019-11-07 2020-04-14 航天建筑设计研究院有限公司 一种建筑物抗浮结构及其绿色施工方法
CN111005410B (zh) * 2019-11-07 2024-06-11 航天建筑设计研究院有限公司 一种建筑物抗浮结构及其绿色施工方法

Similar Documents

Publication Publication Date Title
CN100501011C (zh) 钻孔压浆桩施工方法
CN103233473B (zh) 高聚物多棱桩注浆方法
CN108517861B (zh) 一种抵抗地基隆起的复合加筋桩构造及施工方法
CN101446088A (zh) 一种用于戈壁滩碎石土地区的杆塔基础施工方法
CN105421445A (zh) 非预应力离心高强混凝土桩植桩施工方法
CN106948340A (zh) 一种高聚物注浆防护的人工挖孔桩结构的施工方法
CN201151920Y (zh) 抗浮地坑结构
CN201162214Y (zh) 根式抗拔桩
CN102561377A (zh) 带扩底的抗震柱岩石锚杆基础及其施工方法
CN202187340U (zh) 钢管混凝土芯柱嵌岩桩
CN107587511B (zh) 用于预防和治理基坑坑底隆起的长短桩加固结构及加固方法
CN104196013B (zh) 一种复合y形桩及其施工方法
CN201459749U (zh) 一种深水钢管桩施工平台稳定结构
CN201502065U (zh) 一种锚杆联合开挖类复合基础
CN201162229Y (zh) 抗浮地坑结构
CN205576957U (zh) 桩底桩结构
CN104895078B (zh) 一种以端承受力为主的预制桩的施工方法
CN102286971A (zh) 钢管混凝土芯柱嵌岩桩
CN202672161U (zh) 一种带有土钉的水泥土搅拌筒板联桩护坡结构
CN201588222U (zh) 叠合式掏嵌基础
CN110939161B (zh) 一种大直径嵌岩抗浮锚杆的施工方法及用于该方法中的钻具
CN208472721U (zh) 一种在松散体地层中采用手风钻施工的锚杆
CN206844129U (zh) 一种新型斜撑复合支护装置
CN202247856U (zh) 地基处理用取土圆环桩及地下基础
CN201495554U (zh) 一种锚杆联合掏挖复合基础

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: GUIYANG ALUMINUM AND MAGNESIUM DESIGN INSTITUTE CO

Free format text: FORMER NAME: GUIYANG ALUMINIUM AND MAGNESIUM DESIGN INST.

CP03 Change of name, title or address

Address after: 550081 Guiyang Province, Jinyang New District, Zhu Zhu Road, No. 2

Patentee after: Guiyang Aluminum & Magnesium Design Institute Co., Ltd.

Address before: 550004 No. 208, Beijing Road, Guiyang, Guizhou

Patentee before: Guiyang Aluminium and Magnesium Design Inst.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081210

Termination date: 20141127

EXPY Termination of patent right or utility model