CN201144393Y CNU200820065240XU CN200820065240U CN201144393Y CN 201144393 Y CN201144393 Y CN 201144393Y CN U200820065240X U CNU200820065240X U CN U200820065240XU CN 200820065240 U CN200820065240 U CN 200820065240U CN 201144393 Y CN201144393 Y CN 201144393Y
Authority
CN
China
Prior art keywords
anchor
pipe
steel
plate
honeycomb fashion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU200820065240XU
Other languages
Chinese (zh)
Inventor
彭元诚
廖朝华
陈杨明
朱玉
陈毅明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Highway Consultants Co Ltd
Original Assignee
CCCC Second Highway Consultants Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Highway Consultants Co Ltd filed Critical CCCC Second Highway Consultants Co Ltd
Priority to CNU200820065240XU priority Critical patent/CN201144393Y/en
Application granted granted Critical
Publication of CN201144393Y publication Critical patent/CN201144393Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a replaceable prestressing device for the anchorage of a suspension bridge, which comprises a honeycomb type embedded pipe, a prestressed reinforcement, a spiral reinforcement under an anchor, a hexagon steel bushing, a leakproof end plate, an outer hexagon steel pipe and a circular steel bushing. The honeycomb type embedded pipe is embedded in the anchorage concrete. The prestressed reinforcement is inserted into the steel pipe of the honeycomb type embedded pipe. The honeycomb type embedded pipes are connected with the hexagon steel bushing, the plug welding, the leakproof end plate and the outer hexagon steel pipe via an intermediate joint. The two ends of the honeycomb type embedded pipe are connected with an anchorage plate via the plug welding of the end joint, the leakproof end plate and the circular steel bushing. An anti-loosening baffle is positioned at the end of the clips and tightly pushed against. A shield is connected with a front anchor facet connector or a back anchor facet anchor base plate and is airtight. The anticorrosion oil is filled into the gap of the honeycomb type embedded pipe and the shield. The replaceable prestressing device for the anchorage of the suspension bridge has the advantages of simple method, convenient replacement, good safety, simple structure, stable and reliable operation, powerfully achieving the maintenance of the entire bundle of the prestressed reinforcement and promoting the security and the reliability of the bridge.

Description

The prestressed device of suspension bridge anchoring changeable formula
Technical field
The utility model relates to a kind of prestressing technique field that is used for the suspension bridge anchorage, more specifically relate to the prestressed device of a kind of suspension bridge anchoring changeable formula, keeping with the effective anchoring of main rope of suspension bridge strand, guaranteeing under the prerequisite of bridge safety, replace constituting the prestressed multiply presstressed reinforcing steel of whole bundle, thereby the prestressing without bondn of realizing bridge later stage maintainability is constructed.
Background technology
Anchorage is that suspension bridge is stressed, the key structure of carrying, and it plays a part to transmit tension of main cable to the basis.Generally be divided into gravity anchor and tunnel-type anchorage two classes from the mode of transfer force between anchorage and the foundation.Gravity anchor relies on the huge pulling force of the dead-weight balanced main push-towing rope of anchorage, and tunnel-type anchorage utilizes the acting in conjunction of anchorage and its surrounding rock body, the anchoring main push-towing rope.
The main rope of suspension bridge pulling force is huge, and anchorage is generally large volume concrete structural, under the tension of main cable effect, anchorage can produce very big tensile stress and cause concrete cracking, so need apply prestressing force to anchorage,, guarantee the safety of structure with the tensile stress that the opposing tension of main cable produces.
The modern suspension anchorage adopts prestress system more, and existing anchorage prestress system has two kinds: bonding system and no bonding system are arranged.
Anchorage bonded prestress system, to common post-stressed similar: when cast anchor body concrete, adopt steel pipe, or metal bellows, or plastic film capicitor reserves the pipeline that prestressed strand is walked in concrete, the pre-buried backing plate that can transmit immense pressure in the anchor surface concrete of front and back, after concrete reaches certain intensity, prestressed strand (presstressed reinforcing steel) is passed the pipeline of reservation, adopt fluid pressure type jack tension prestressed strand to certain tonnage, stress level, by ground tackle fluid pressure type jack tension power is changeed being added on the backing plate pre-buried in the anchor surface concrete of front and back at last, thereby the anchor body concrete has been applied precompression.By being connected of ground tackle and main push-towing rope bundle thigh, main push-towing rope power is delivered to the anchor body.Be characterized in, after prestressed stretch-draw is finished, to prestress pipe, anchor head cement injection mortar or epoxy mortar, mortar and prestressed strand form permanent adhesive, make prestressed strand and anchor body become integral body, mortar and the bonding, airtight of prestressed strand play antisepsis to prestressed strand simultaneously.
The main deficiency of the bonded prestress system of perfusion mortar is: (1) detection, difficult in maintenance is difficult to the actual corrosion situation of prestressed strand is made judgement accurately; (2) because mortar solidifies the influence of after-contraction, microcrack appears unavoidably, and anticorrosion unreliable; (3) prestressed strand and anchoring intermediate plate bond together by mortar curing, can't under the prerequisite that guarantees structural integrity, change and safeguard, and be the prestress system of " disposable ".
At bonded prestress mode anti-corrosive properties, the shortcoming that detection property is not good, people have proposed not have bonding prestressing force mode, conventional no bonding prestressed 26S Proteasome Structure and Function main points are: when cast anchor body concrete the employing tightness preferably steel pipe in concrete, reserve the pipeline that prestressed strand is walked, the pre-buried backing plate that can transmit immense pressure in the anchor surface concrete of front and back, after concrete reaches certain intensity, prestressed strand (high-tensile steel wires or presstressed reinforcing steel) is passed the pipeline of reservation, adopt fluid pressure type jack tension prestressed strand to certain tonnage, stress level, by ground tackle fluid pressure type jack tension power is changeed at last and be added on the backing plate pre-buried in the anchor surface concrete of front and back, thereby the anchor body concrete has been applied precompression, by being connected of ground tackle and main push-towing rope bundle thigh, main push-towing rope power is delivered to the anchor body.Be characterized in, after prestressed stretch-draw is finished, prestress pipe, anchor head poured into anticorrosion grease, protect by anticorrosion grease, prestressed strand and surrounding concrete do not have bonding.
The main deficiency of the conventional prestressing without bondn system of suspension bridge anchorage is: because it is many to form the bundle thigh of prestressed strand, easily beat strand when lashing, stretch-draw, and the mutual jam-packed of curved section, therefore can not partly substitute, can not carry out safe replacing operation, maintainability is not compared not improvement with bonding system is arranged.
Generally speaking, traditional anchorage prestress system, the main deficiency that exists is: detection, difficult in maintenance, can not under the prerequisite that guarantees bridge safety, realize the replacing attended operation of steel bundle, intermediate plate, in case prestressed strand and intermediate plate generation corrosion and damage, the safety of whole bridge and durability will be had a strong impact on.
Summary of the invention
The purpose of this utility model is to be to provide a kind of suspension bridge anchoring changeable formula prestressed device, simple in structure, it is convenient to change, the pre-buried pipeline of honeycomb fashion that each strand of steel bundle can pass through respectively in pipeline separately realizes that safety changes rope, under the prerequisite that guarantees bridge safety, realize the prestressed replaceable operation of suspension bridge anchorage, improved the maintainability of anchorage and main push-towing rope anchor system, finally improved the safety and the reliability of bridge.
To achieve these goals, the utility model adopts following technical measures:
A kind of suspension bridge anchoring changeable formula prestressing apparatus comprises: the pre-pipe laying of honeycomb fashion, presstressed reinforcing steel, anchor plate, connect with six (many) limits shape steel sleeve, leakproof end plate, shape steel pipe limit, outsourcing six (many) limit shape steel sleeve, connection circular steel sleeve pipe spiral reinforcement under anchor slab, intermediate plate, locking baffle plate, protective cover, the anchor, anticorrosion grease.
Its annexation is: the pre-pipe laying of honeycomb fashion is embedded in the anchorage concrete, and presstressed reinforcing steel is through in the little steel pipe of the pre-pipe laying of honeycomb fashion, and by the transition joint spreading, the pre-pipe laying of honeycomb fashion two ends are connected with anchor plate by end joint between the pre-pipe laying of honeycomb fashion; Tensioned prestressing bar tightens intermediate plate and forms the self-locking anchoring to the stress of design code, anchor face and back anchor face before the pulling force of presstressed reinforcing steel passes to by intermediate plate, anchor slab; Locking baffle plate is installed in the intermediate plate end and holds out against; Protective cover is connected with preceding anchor face connector or back anchor face anchor plate and is airtight, and anticorrosion grease is poured in the space of pre-pipe laying of honeycomb fashion and protective cover.
1, anchor system is connected with main push-towing rope bundle thigh
The monitoring of anchorage prestress system, maintainability is the key factor that influences suspension bridge structural safety and life-span.Suspension bridge anchorage prestressing force is connected with main push-towing rope bundle thigh by anchor system, thereby transmits tension of main cable because main push-towing rope bundle thigh pulling force is huge, can not loose power at Cheng Qiaohou, the prestressed replacing of anchorage with not loose corresponding main push-towing rope bundle thigh, not influence bridge safety be prerequisite.
The prestressed crucial thinking of changeable type is the prestressing force strand with the anchoring of whole bundle, the minimum unit of pressing stretch-draw, anchoring is (for presstressed reinforcing steel intermediate plate anchor, for one/the root presstressed reinforcing steel), independently current pipeline is set, when satisfying maintenance under the prerequisite of (the bridge design standard is referred to as transient situation) structural safety, adopt single mode of substituting, realize replacing whole bundle prestressed cable.
Suspension bridge anchoring changeable formula prestressed constructions as shown in Figure 1, the independently current pipeline of each strand press the honeycomb fashion setting, for instance, 19 strands of corresponding 19 pipe honeycomb ducts of presstressed reinforcing steels, 37 strands of presstressed reinforcing steels corresponding 37 are managed honeycomb ducts, the rest may be inferred for other.
2, the pre-pipe laying structure of honeycomb fashion
The pre-pipe laying of prestressed strand honeycomb fashion adopts minor diameter seamless steel tube usually, press regular hexagon or intend regular hexagon and form bundle, as shown in Figure 2, the internal diameter of minor diameter seamless steel tube is determined by 2 times of the presstressed reinforcing steel area that wherein will pass through, for φ 15.24 presstressed reinforcing steels, internal diameter is got 28mm.The wall thickness of minor diameter seamless steel tube wants to satisfy the intensity needs of concrete pouring, for being positioned at the curved section part, and the radial force requirement in the time of also will satisfying steel Shu Zhangla, thickness is 3~5mm.
Adopt the plug welding welding every 2m between the seamless steel pipe, and then form cellular tube bundle assembly, for the ease of transportation and installation, tube bundle assembly length can be 9~12m, connect by transition joint again after transporting the scene to,, adopt welding manner to connect for guaranteeing seal.
The pre-buried tube end of honeycomb fashion is connected with the interface of anchor plate by end joint.For guaranteeing seal, can adopt welding manner to connect or the employing epoxy sealing.
The pre-pipe laying of honeycomb fashion has been for the per share presstressed reinforcing steel of forming the steel bundle provides an independent passage, makes that each strand presstressed reinforcing steel can not pass separately intrusively, stretch-draw separately, anchoring and attended operation separately separately.
3, honeycomb duct joint construction
Because prestressed strand is longer, the honeycomb duct segmentation is made, and on-the-spot the installation adopts joint to connect.It is accurate, airtight that the contraposition of honeycomb duct joint requires, and transition joint is constructed as Fig. 3.Six (many) limits shape steel sleeve is inserted in plug welding or the cellular steel pipe that is bundled into six (many) limits shape, docks by steel sleeve, the plug welding of honeycomb duct end and with the steel sleeve full weld, with the seal of assurance honeycomb duct to steel sleeve.
The joint bit errors will form faulting of slab ends between honeycomb duct, for avoiding faulting of slab ends the steel bundle (thigh) that navigates within is wherein caused friction or damage, the honeycomb duct of butt joint place to carry out chamfered edge.
Be connected between honeycomb duct and the anchor plate, need be converted to circle earlier, connect (weldering) with anchor plate again and connect, joint such as Fig. 4 will guarantee the seal that connects equally.
The utility model compared with prior art, have the following advantages and effect: 1) owing to form each strand presstressed reinforcing steel of steel bundle and run in the guide separately independently in the minor diameter seamless steel tube, do not disturb mutually, do not push, make that steel Shu Shouli is even, thereby improved the reliability of steel bundle; 2) by the honeycomb fashion pipeline, make the later stage to carry out stretch-draw, to change operation, thereby realized the safeguarding of whole bundle presstressed reinforcing steel, convertibility safety the sub-thread presstressed reinforcing steel, reliable and stable.
Description of drawings
Fig. 1 is a kind of suspension bridge anchoring changeable formula prestressing apparatus structure collectivity schematic diagram;
Fig. 2 cooperates schematic diagram for Fig. 1;
Fig. 3 is a honeycomb fashion embedded steel tube structural representation;
Fig. 4 is a honeycomb fashion prestress pipe transition joint structural representation;
Fig. 5 cooperates schematic diagram for Fig. 4;
Fig. 6 is honeycomb fashion prestress pipe and anchor plate end joint structural representation;
Fig. 7 is the cooperation schematic diagram of Fig. 6;
Fig. 8 is a honeycomb fashion prestress pipe joint leakproof end plate schematic diagram;
Wherein: the pre-pipe laying of 1-honeycomb fashion, 2-presstressed reinforcing steel, 3-anchor plate, 4-anchor slab, the 5-intermediate plate, the locking baffle plate of 6-, 7-protective cover, spiral reinforcement under the 8-anchor, 9-connector (forged steel), 10-connecting rod, 11-nut, anchor face (anchorage concrete) before the 12-spheric washer, 13-, anchor face behind the 14-(anchorage concrete), the anticorrosion grease of 15-, 16-connect with six (many) limits shape steel sleeve, 17-plug welding, 18-leakproof end plate, shape steel pipe limit, 19-outsourcing six (many) limit shape steel sleeve, 20-connect uses the circular steel sleeve pipe.
The specific embodiment
Below in conjunction with accompanying drawing the utility model is described in further detail:
According to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5 as can be known, a kind of suspension bridge anchoring changeable formula prestressing apparatus comprises: the pre-pipe laying 1 of honeycomb fashion, presstressed reinforcing steel 2, anchor plate 3, connect with six (many) limits shape steel sleeve 16, leakproof end plate 18, shape steel pipe limit, outsourcing six (many) limit shape steel sleeve 19, connection usefulness circular steel sleeve pipe 20 spiral reinforcement 8 under anchor slab 4, intermediate plate 5, locking baffle plate 6, protective cover 7, the anchor, anticorrosion grease 15.
Its annexation is: the pre-pipe laying 1 of honeycomb fashion is embedded in the anchorage concrete, presstressed reinforcing steel 2 is through in the little steel pipe of the pre-pipe laying 1 of honeycomb fashion, be connected with hexagon steel sleeve 16, plug welding 17, leakproof end plate 18, outsourcing hexagon steel pipe 19 by transition joint between the pre-pipe laying 1 of honeycomb fashion, the pre-pipe laying of honeycomb fashion 1 two ends are connected with anchor plate 3 by the plug welding on the end joint 17, leakproof end plate 18, circular steel sleeve pipe 20; Tensioned prestressing bar 2 tightens intermediate plate 5 and forms the self-locking anchoring to the stress of design code, anchor face 13 and back anchor face 14 before the pulling force of presstressed reinforcing steel passes to by intermediate plate 5, anchor slab 4; Locking baffle plate 6 is installed in intermediate plate 5 ends and holds out against; Protective cover 7 is connected with preceding anchor face connector 9 or back anchor face anchor plate 3 and is airtight, and anticorrosion grease 15 is poured in the space of pre-pipe laying 1 of honeycomb fashion and protective cover 7.
Anchor face 13 and back anchor face 14 before anchor plate 3 is placed in, mounted connector 9, anchor slab 4, tensioned prestressing bar 2 in the steel pipe.Plug welding 17 or be bundled into hexagonal cellular steel pipe and insert polygonal steel pipe 19 connects by steel sleeve, cellular tube end plug welding 17 and steel sleeve full weld, and honeycomb duct is connected with anchor plate 3, is converted to circle and is connected with anchor plate 3.The pre-pipe laying 1 of described prestressed strand honeycomb fashion adopts seamless steel pipe, press regular hexagon or intend regular hexagon composition bundle, seamless steel pipe adopts plug welding 17 welding, form cellular tube bundle assembly, the honeycomb duct end is connected by the interface of end joint with anchor plate 3, connects or the employing epoxy sealing with welding manner.
First mounting method: the pre-pipe laying 1 of honeycomb fashion that little steel pipe is formed is before cast anchorage concrete, set in advance in design named pipe position, anchor face 13 and back anchor face 14 before anchor plate 3 is placed in, cast anchorage concrete, detect the seal of the pre-pipe laying 1 of honeycomb fashion, after qualified presstressed reinforcing steel 2 is through in the little steel pipe of the pre-pipe laying 1 of honeycomb fashion, mounted connector 9, anchor slab 4, tensioned prestressing bar 2 is to the stress of design code, tighten intermediate plate and form the self-locking anchoring, finish the stretch-draw and the anchoring of all presstressed reinforcing steels 2 successively, baffle plate is loosened in installation, protective cover is installed, is adopted the anticorrosion grease 15 of oil pump pressure injection to be full of all spaces of pre-pipe laying of honeycomb fashion and protective cover, promptly finish prestressed installation and construction.

Claims (4)

1, the prestressed device of a kind of suspension bridge anchoring changeable formula, comprise the pre-pipe laying of honeycomb fashion (1), presstressed reinforcing steel (2), anchor plate (3), anchor slab (4), intermediate plate (5), locking baffle plate (6), protective cover (7), spiral reinforcement under the anchor (8), anticorrosion grease (15), connect with hexagon steel sleeve (16), leakproof end plate (18), outsourcing hexagon steel pipe limit shape steel sleeve (19), connect with circular steel sleeve pipe (20), it is characterized in that: the pre-pipe laying of honeycomb fashion (1) is embedded in the anchorage concrete, presstressed reinforcing steel (2) is through in the steel pipe of the pre-pipe laying of honeycomb fashion (1), between the pre-pipe laying of honeycomb fashion (1) by transition joint and hexagon steel sleeve (16), plug welding (17), leakproof end plate (18), outsourcing hexagon steel pipe (19) connects, and the pre-pipe laying of honeycomb fashion (1) two ends are by the plug welding on the end joint (17), leakproof end plate (18), circular steel sleeve pipe (20) is connected with anchor plate (3); Tighten intermediate plate (5) and form the self-locking anchoring, locking baffle plate (6) is installed in intermediate plate (5) end and holds out against; Protective cover (7) is connected with preceding anchor face (13) connector (9) or back anchor face (14) anchor plate (3) and is airtight, and anticorrosion grease (17) is poured in the space of pre-pipe laying of honeycomb fashion (1) and protective cover (7).
2, the prestressed device of a kind of suspension bridge anchoring changeable formula according to claim 1 is characterized in that: anchor face (13) and back anchor face (14) before anchor plate (3) is placed in, mounted connector in the steel pipe (9), anchor slab (4), presstressed reinforcing steel (2).
3, the prestressed device of a kind of suspension bridge anchoring changeable formula according to claim 1, it is characterized in that: plug welding (17) or be bundled into hexagonal cellular steel pipe and insert polygonal steel pipe (19), connect by steel sleeve, cellular tube end plug welding (17) and steel sleeve full weld, honeycomb duct is connected with anchor plate (3), is converted to circle and is connected with anchor plate (3).
4, the prestressed device of a kind of suspension bridge anchoring changeable formula according to claim 1 is characterized in that:
The described pre-pipe laying of steel bundle honeycomb fashion (1) adopts seamless steel pipe, press regular hexagon or intend regular hexagon composition bundle, seamless steel pipe adopts plug welding (17) welding, form cellular tube bundle assembly, the honeycomb duct end is connected by the interface of end joint with anchor plate (3), connects or the employing epoxy sealing with welding manner.
CNU200820065240XU 2008-01-08 2008-01-08 Replaceable prestressed device for suspension bridge anchor Expired - Lifetime CN201144393Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU200820065240XU CN201144393Y (en) 2008-01-08 2008-01-08 Replaceable prestressed device for suspension bridge anchor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU200820065240XU CN201144393Y (en) 2008-01-08 2008-01-08 Replaceable prestressed device for suspension bridge anchor

Publications (1)

Publication Number Publication Date
CN201144393Y true CN201144393Y (en) 2008-11-05

Family

ID=40081265

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU200820065240XU Expired - Lifetime CN201144393Y (en) 2008-01-08 2008-01-08 Replaceable prestressed device for suspension bridge anchor

Country Status (1)

Country Link
CN (1) CN201144393Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820523A (en) * 2019-11-22 2020-02-21 柳州欧维姆机械股份有限公司 Cable strand connecting structure for replacing main cable of suspension bridge, anchorage structure and construction method
CN111041984A (en) * 2019-12-01 2020-04-21 中铁二院工程集团有限责任公司 Rear anchor surface anchoring system for anchoring main cable of suspension bridge

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820523A (en) * 2019-11-22 2020-02-21 柳州欧维姆机械股份有限公司 Cable strand connecting structure for replacing main cable of suspension bridge, anchorage structure and construction method
CN111041984A (en) * 2019-12-01 2020-04-21 中铁二院工程集团有限责任公司 Rear anchor surface anchoring system for anchoring main cable of suspension bridge

Similar Documents

Publication Publication Date Title
CN100570067C (en) Prestressed method of suspension bridge anchoring changeable formula and device
CN107575257B (en) The anchoring process of anchor tool system for fibre-reinforced high molecular material bar
CN205877455U (en) Prestressing force steel cylinder concrete pipe
CN207537886U (en) It is a kind of can the compound sealing type suspension cable substituted of single steel strand
CN104514572A (en) Rod body connecting device, anchor rod and manufacturing method thereof
CN102359672A (en) Prestressed steel cylinder concrete push pipe
CN104060535A (en) Prestress high-strength twisted steel anchoring system and construction method
CN102493660A (en) Anchoring method and anchoring tool for carbon fiber reinforced composite material prestressed bar
CN202031027U (en) Whole replaceable anchorage system
CN204040209U (en) A kind of syndeton of replaceable steel coupling beam
CN106838463B (en) The fastener inserts and usage of longitudinal overall stiffness after raising rectangular top plumber
CN202099801U (en) Threaded carbon fiber anchor cable anchoring device
CN201144393Y (en) Replaceable prestressed device for suspension bridge anchor
CN108221666A (en) A kind of compound anchorage of FRP tendons
CN104234325B (en) The installation method of FRP rib tape screw plug bond type anchorage
CN202031026U (en) Finished cable type anchorage anchoring system
CN108643454A (en) A kind of the prestressed group anchorage system and its construction method of internal single beam sealing
CN209604089U (en) A kind of external hanging type preburied component and shield duct piece
CN204728585U (en) The reinforcing bar grouting branch sleeve of precast assembly
CN110952994A (en) Bent bolt combined joint for secondary lining of mine method construction tunnel and reinforcing method
CN110630030A (en) P-UHPC reinforcing device for reinforced concrete structure and construction method thereof
CN201865104U (en) Anchor device of extrusion type carbon fiber anchor cable
CN212641447U (en) Prestress tension-compression composite anti-floating anchor rod
CN2389176Y (en) Sealed anchorage cable
CN210072422U (en) Underground high-pressure gas storage reinforcing device capable of carrying out intelligent monitoring

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20081105