CN201121407Y - Template-turning device of climbing scaffold for chimney construction - Google Patents

Template-turning device of climbing scaffold for chimney construction Download PDF

Info

Publication number
CN201121407Y
CN201121407Y CNU2007200434932U CN200720043493U CN201121407Y CN 201121407 Y CN201121407 Y CN 201121407Y CN U2007200434932 U CNU2007200434932 U CN U2007200434932U CN 200720043493 U CN200720043493 U CN 200720043493U CN 201121407 Y CN201121407 Y CN 201121407Y
Authority
CN
China
Prior art keywords
base
chimney
movable
movable disk
rotary disk
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2007200434932U
Other languages
Chinese (zh)
Inventor
徐竹林
张慎忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Nantong three construction group Limited by Share Ltd
Original Assignee
Jiangsu Nantong No3 Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Nantong No3 Construction Group Co Ltd filed Critical Jiangsu Nantong No3 Construction Group Co Ltd
Priority to CNU2007200434932U priority Critical patent/CN201121407Y/en
Application granted granted Critical
Publication of CN201121407Y publication Critical patent/CN201121407Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to a formwork turning device of a climbing scaffold used for chimney construction. A support bracket and a telescopic joint are fixed on the inner wall of a chimney, and are stayed in cross direction at the inner diameter of the chimney. A base is fixed on the support bracket, a round hole is arranged on the base, and a movable rotary disk is arranged at the upper part of the base. A plane bearing is installed between the movable rotary disk and the base, and the movable rotary disk is provided with a shaft which extends into the round hole of the base to cause the movable rotary disk to rotate. A guide sleeve is fixed on the movable rotary disk, the upper end of the guide sleeve is connected with a beam, and a hydraulic jack is installed at the upper part of the beam. A support steel bar is installed on the ground, and penetrates through the base, the movable rotary disk, the guide sleeve, the beam and the hydraulic jack. Two lifting frames are respectively installed at each side of the beam, and are provided with movable outriggers. The movable outriggers are respectively connected with an inner formwork and an outer formwork of the chimney. The hydraulic jack climbs on the support steel bar to drive the lifting frames to lift upwards. The formwork turning device of the utility model has the advantages of compact scaffold and formwork turning device, convenient operation, rapid work efficiency and quality assurance.

Description

The rollover board equipment of the climbing scaffold of chimney construction
Affiliated technical field
The utility model relates to the rollover board equipment of the climbing scaffold of chimney construction.
Background technology
The rollover board of existing chimney construction is to adopt to set up scaffold along the chimney body of wall, and fixed form carries out concrete pouring again.Its weak point is: scaffold and rollover board equipment are numerous and diverse, the operation effort, and work efficiency is slow again, and quality can not get guaranteeing.
The utility model content
The purpose of this utility model is the rollover board equipment that the climbing scaffold of chimney construction is provided in order to overcome above-mentioned weak point, scaffold and rollover board facility compact, and easy to operate, work efficiency is fast again, and quality is guaranteed.
The technical scheme that its technical problem that solves the utility model adopts is: the rollover board equipment of the climbing scaffold of chimney construction, at interior wall the bolt bearing support and the expansion coupling of chimney building, stull is at the internal diameter of chimney.Be fixed with cup dolly on bearing support, a circular hole is arranged on base, there is movable disk the base top, between movable disk and the base plane bearing is housed, and has shaft extension in the circular hole of base it to be rotated on the movable disk.There is latch at the position of keeping to the side between movable disk and base, when movable disk does not require rotation, latch is plugged.On movable disk, be fixed with guide pin bushing.The upper end of guide pin bushing is connected with crossbeam, and hydraulic jack is equipped with in the crossbeam top.The supporting steel pole is installed on the ground, and the supporting steel pole passes base, movable disk, guide pin bushing, crossbeam, hydraulic jack.On the crossbeam both sides two hoisting frames are installed respectively, movable supporting legs is housed on hoisting frame, movable supporting legs is connected with inner formword, the exterior sheathing of chimney respectively.After template installs, placing of concrete, behind the concrete coagulation, stripping, hydraulic jack withstand on the support steel bar and climb, and drive hoisting frame and upwards promote, and continue mounting template.
Effective effect of the present utility model is, uses the rollover board equipment of the climbing scaffold of chimney construction of the present utility model, scaffold and rollover board facility compact, and easy to operate, work efficiency is fast again, and quality is guaranteed.
Description of drawings
Figure is the structural representation of rollover board equipment of the climbing scaffold of chimney construction of the present utility model.1-hound among the figure, 2-chimney body of wall, the 3-expansion coupling, the 4-bolt, the 5-hoisting frame, the 6-template, the 7-movable supporting legs, the 8-crossbeam, the 9-hydraulic jack, 10-supports steel pole, 11-guide pin bushing, 12-movable disk, 13-plane bearing, 14-base, 15-bearing support.
Specific implementation method
The rollover board equipment of the climbing scaffold of chimney construction, at interior wall the bolt bearing support (15) and the expansion coupling (3) of chimney building, stull is at the internal diameter of chimney.On bearing support (15), be fixed with cup dolly (14), on base (14), a circular hole is arranged, there is movable disk (12) base (14) top, between movable disk (12) and the base (14) plane bearing (13) is housed, has shaft extension in the circular hole of base (14), it to be rotated on the movable disk (12).There is latch at the position of keeping to the side between movable disk (12) and base (14), when movable disk (12) does not require rotation, latch is plugged.On movable disk (12), be fixed with guide pin bushing (11).The upper end of guide pin bushing (11) is connected with crossbeam (8), and hydraulic jack (9) is equipped with in crossbeam (8) top.Supporting steel pole (10) is installed on the ground, and supporting steel pole (10) passes base (14), movable disk (12), guide pin bushing (11), crossbeam (8), hydraulic jack (9).On crossbeam (8) both sides two hoisting frames (5) are installed respectively, movable supporting legs (7) is housed on hoisting frame (5), movable supporting legs (7) is connected with inner formword, the exterior sheathing of chimney respectively.After template (6) installs, placing of concrete, behind the concrete coagulation, stripping (6), hydraulic jack (9) is climbed on supporting steel pole (10), drives hoisting frame (5) and upwards promotes, and continues mounting template.

Claims (2)

1, the rollover board equipment of the climbing scaffold of chimney construction, it is characterized in that: at interior wall the bolt bearing support and the expansion coupling of chimney building, stull is at the internal diameter of chimney, on bearing support, be fixed with cup dolly, one circular hole is arranged on base, there is movable disk the base top, between movable disk and the base plane bearing is housed, shaft extension is arranged on the movable disk in the circular hole of base, on movable disk, be fixed with guide pin bushing, the upper end of guide pin bushing is connected with crossbeam, and hydraulic jack is equipped with in the crossbeam top, and the supporting steel pole is installed on the ground, the supporting steel pole passes base, movable disk, guide pin bushing, crossbeam, hydraulic jack, on the crossbeam both sides two hoisting frames are installed respectively, movable supporting legs are housed on hoisting frame, movable supporting legs respectively with the inner formword of chimney, exterior sheathing is connected.
2, the rollover board equipment of the climbing scaffold of chimney construction according to claim 1 is characterized in that: there is latch at the position of keeping to the side between movable disk and base.
CNU2007200434932U 2007-11-05 2007-11-05 Template-turning device of climbing scaffold for chimney construction Expired - Lifetime CN201121407Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200434932U CN201121407Y (en) 2007-11-05 2007-11-05 Template-turning device of climbing scaffold for chimney construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200434932U CN201121407Y (en) 2007-11-05 2007-11-05 Template-turning device of climbing scaffold for chimney construction

Publications (1)

Publication Number Publication Date
CN201121407Y true CN201121407Y (en) 2008-09-24

Family

ID=40008632

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200434932U Expired - Lifetime CN201121407Y (en) 2007-11-05 2007-11-05 Template-turning device of climbing scaffold for chimney construction

Country Status (1)

Country Link
CN (1) CN201121407Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105113794A (en) * 2015-08-17 2015-12-02 中建五局第三建设有限公司 Tripod turnover construction method of cambered-surface and thin-walled structure
CN112343330A (en) * 2020-11-11 2021-02-09 广西建工集团冶金建设有限公司 Cylinder wall construction method and cylinder wall template structure of large-diameter reinforced concrete cylinder

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105113794A (en) * 2015-08-17 2015-12-02 中建五局第三建设有限公司 Tripod turnover construction method of cambered-surface and thin-walled structure
CN112343330A (en) * 2020-11-11 2021-02-09 广西建工集团冶金建设有限公司 Cylinder wall construction method and cylinder wall template structure of large-diameter reinforced concrete cylinder

Similar Documents

Publication Publication Date Title
CN201231532Y (en) Mobile boring device for building top board
CN201121407Y (en) Template-turning device of climbing scaffold for chimney construction
CN202850484U (en) Safety mechanism for building construction climbing template
CN206972169U (en) Drilling equipment
CN110304593B (en) PC column vertical lifting auxiliary device
CN111319011A (en) Operation device for concrete structure bar planting and bar planting drilling method
CN104389525A (en) Liftable working platform at front end of pile frame and operation method thereof
CN204590555U (en) Assembling elevator hoistway construction platform
CN110552346A (en) Double-spraying double-shaft oblique cement-soil stirring and profile steel inserting integrated construction method and equipment
CN203238967U (en) Large steel structure frame whole lifting device
CN202689498U (en) Liftable scaffold for simple and easy building outer wall
KR100475544B1 (en) Wall form climbing system for constructing concrete wall of high-rise buldings
CN202023353U (en) Integral lifting scaffold for building operations
CN210975799U (en) Double-spraying double-shaft oblique cement-soil stirring and profile steel inserting integrated equipment
CN201109996Y (en) Fluid pressure climbing template apparatus
CN212688948U (en) Drilling mechanism for screw threaded pile and anchor pile
CN210997324U (en) Tower crane sleeve welding frock
CN208996055U (en) A kind of bracing members axle power application jack fixing device
CN201027490Y (en) Vane wheel lift type floor drilling machine
CN203109295U (en) Auxiliary frame for upward drilling of electric drill
CN201428378Y (en) Drill for recycling tower crane foundation screws
CN205996261U (en) Foot-operated drilling equipment
CN201065636Y (en) High chimney construction device
CN219472110U (en) Shaft formwork sliding formwork
CN212471370U (en) Construction machinery equipment maintenance platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 226100 Jiangsu city of Nantong Province Haimen Shishan Road No. 131

Patentee after: Jiangsu Nantong three construction group Limited by Share Ltd

Address before: 226100 Haimen Road, Haimen, Jiangsu, No. 131

Patentee before: Jiangsu Nantong No.3 Construction Group Co., Ltd.

CX01 Expiry of patent term

Granted publication date: 20080924