CN201105957Y - Tower crane engineering special-purpose gin pole hoist - Google Patents

Tower crane engineering special-purpose gin pole hoist Download PDF

Info

Publication number
CN201105957Y
CN201105957Y CNU2007200452697U CN200720045269U CN201105957Y CN 201105957 Y CN201105957 Y CN 201105957Y CN U2007200452697 U CNU2007200452697 U CN U2007200452697U CN 200720045269 U CN200720045269 U CN 200720045269U CN 201105957 Y CN201105957 Y CN 201105957Y
Authority
CN
China
Prior art keywords
arm
tower crane
crane
special
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007200452697U
Other languages
Chinese (zh)
Inventor
胡华兵
朱涛
戴苏敏
王觅
刘柳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huajian Construction Co Ltd
Original Assignee
Jiangsu Huajian Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Huajian Construction Co Ltd filed Critical Jiangsu Huajian Construction Co Ltd
Priority to CNU2007200452697U priority Critical patent/CN201105957Y/en
Application granted granted Critical
Publication of CN201105957Y publication Critical patent/CN201105957Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a special button pole crane used in a tower crane method and pertains to the technical field of lifting hoisting. The button pole crane of the utility model comprises a base. The upper part of the base fixedly supports the lower end of a vertical tower body column and the lower end of an oblique boom. A side of the base is fixedly connected with one end of a balancing arm. The upper end of the tower body column is connected with the other end of the balancing arm through a pull rod of the balancing arm and is connected with the upper end of the boom through a pull rod of the boom. The upper end of the boom is provided with an ascending and descending hook through pulleys. With simple structure, the special button pole crane can be conveniently installed on the spot and is applicable to being used as a transitional hoisting device for disintegration part swinging of an inner-climbing style crane, thereby practically ensuring the implementation of ultra high-rise roofing disintegration engineering method of the inner-climbing style crane.

Description

The special-purpose dead man of tower crane worker method hangs
Technical field
The utility model relates to a kind of lifting appliance, and especially a kind of lifting dead man belongs to the hoisting and hanging technical field.
Background technology
Along with the rise of high-rise building, the vertical transport in the work progress faces the challenge.Because common attached tower crane setting height(from bottom) is limited, implement the first-selection that internal-climbing tower crane becomes superelevation layer unit in charge of construction.For this reason, applicant creates the superelevation layer roofing disintegration construction method of internal-climbing tower crane---be called for short tower crane worker method.This worker method is effective through the engineering practice proof, is characterized in whole decline of internal-climbing tower crane set aside on the roofing fully until crane arm and equilibrium arm, and then carries out the disintegration of tower machine and the handling operation of parts.With traditional with tower crane remove internal-climbing tower crane, remove with helicopter method such as internal-climbing tower crane compare have easy construction, technology is simple, cost is low, be convenient to operation, advantage such as safe and reliable.
Yet the enforcement of this worker's method must be by the auxiliary lifting appliance of special use.
The utility model content
The purpose of this utility model is: propose the special-purpose dead man of a kind of tower crane worker method and hang, thereby lay the foundation for the enforcement of internal-climbing tower crane superelevation layer roofing disintegration construction method.
In order to reach above purpose, the special-purpose dead man bull ladle of tower crane worker method of the present utility model is drawn together base, described base upper fixed supports the lower end of vertical body of the tower column, support the lower end of inclination arm simultaneously, one side of described base is captiveed joint with an end of equilibrium arm, the upper end of described body of the tower column is connected with the other end of equilibrium arm by the equilibrium arm pull bar, is connected with the upper end of described arm by the arm pull bar simultaneously, and the liftable suspension hook is equipped with by pulley in the upper end of described arm.
This special-purpose dead man hangs simple in structure, and on-site installation is convenient, very is suitable as the transition lifting appliance that internal-climbing tower crane is separated the body component handling, thereby guarantees the enforcement of internal-climbing tower crane superelevation layer roofing disintegration construction method conscientiously.
Description of drawings
Below in conjunction with accompanying drawing the utility model is further described.
Fig. 1 is the structural representation of an embodiment of the utility model.
The specific embodiment
Embodiment one
The special-purpose dead man of the tower crane worker method of present embodiment hangs as shown in Figure 1, and base 2 upper fixed support the lower end of vertical body of the tower column 3, support the lower end of inclination arm 4 simultaneously.The rear side of base 2 is captiveed joint with an end of equilibrium arm 1.The upper end of body of the tower column 3 is connected with the other end of equilibrium arm 1 by equilibrium arm pull bar 6, is connected with the upper end of arm 4 by arm pull bar 5 simultaneously, and the liftable suspension hook 7 of steel rope 8 tractives is installed in the upper end of this arm by pulley.
Body of the tower column 3 is made by steel pipe, and equilibrium arm 2 is made by I-beam section, and arm 4 is a truss structure.Body of the tower column, arm, equilibrium arm and pull bar all adopt the segmentation package assembly.
During use, equilibrium arm and the logical high strength bolt of flooring Vierendeel girder are connected and fixed, install dead man and hang.Just can implement the superelevation layer roofing disintegration construction method of internal-climbing tower crane afterwards: tower machine integral body is dropped to crane arm and equilibrium arm is held on the building roof, disintegrate at roofing then; On the prior design-calculated route of roofing, lay steel pipe in employing aspect the parallel motion of parts and do guide rail, draw mobile with auxiliary winch; Lift up into capable handling then adopting dead man aspect the vertical transport of parts.After treating that tower machine parts are transported ground back, again accessory equipment is separated body and function and transport back, thereby finish whole tower machine dismounting task.
In a word, the special-purpose dead man of present embodiment hangs simple and reasonable, installation and removal are all very convenient, separate the transition lifting appliance of body component handling as internal-climbing tower crane after, can make being applied conscientiously of internal-climbing tower crane superelevation layer roofing disintegration construction method.

Claims (5)

1. the special-purpose dead man of tower crane worker method hangs, and comprises base, and it is characterized in that: described base upper fixed supports the lower end of vertical body of the tower column, supports the lower end of inclination arm simultaneously; One side of described base is captiveed joint with an end of equilibrium arm; The upper end of described body of the tower column is connected with the other end of equilibrium arm by the equilibrium arm pull bar, is connected with the upper end of described arm by the arm pull bar simultaneously; The liftable suspension hook is equipped with by pulley in the upper end of described arm.
2. hang according to the special-purpose dead man of the described tower crane worker of claim 1 method, it is characterized in that: described body of the tower column is made by steel pipe.
3. hang according to the special-purpose dead man of the described tower crane worker of claim 2 method, it is characterized in that: described equilibrium arm is made by I-beam section.
4. hang according to the special-purpose dead man of the described tower crane worker of claim 3 method, it is characterized in that: described arm is a truss structure.
5. hang according to the special-purpose dead man of the arbitrary described tower crane worker method of claim 1 to 4, it is characterized in that: described body of the tower column, arm, equilibrium arm and pull bar all adopt the segmentation package assembly.
CNU2007200452697U 2007-08-24 2007-08-24 Tower crane engineering special-purpose gin pole hoist Expired - Fee Related CN201105957Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200452697U CN201105957Y (en) 2007-08-24 2007-08-24 Tower crane engineering special-purpose gin pole hoist

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200452697U CN201105957Y (en) 2007-08-24 2007-08-24 Tower crane engineering special-purpose gin pole hoist

Publications (1)

Publication Number Publication Date
CN201105957Y true CN201105957Y (en) 2008-08-27

Family

ID=39957754

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200452697U Expired - Fee Related CN201105957Y (en) 2007-08-24 2007-08-24 Tower crane engineering special-purpose gin pole hoist

Country Status (1)

Country Link
CN (1) CN201105957Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106429880A (en) * 2016-11-11 2017-02-22 沈阳建筑大学 Compound movable arm type roof crane
CN107720569A (en) * 2017-11-08 2018-02-23 中国三冶集团有限公司 One kind is removed inner climbing crane tower and hung with masts type roofing
CN110371840A (en) * 2019-08-06 2019-10-25 庄俊 A kind of lifting supporting beam of adjustable in length

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106429880A (en) * 2016-11-11 2017-02-22 沈阳建筑大学 Compound movable arm type roof crane
CN107720569A (en) * 2017-11-08 2018-02-23 中国三冶集团有限公司 One kind is removed inner climbing crane tower and hung with masts type roofing
CN107720569B (en) * 2017-11-08 2019-11-15 中国三冶集团有限公司 A kind of dismounting inner climbing crane tower is hung with masts type roofing
CN110371840A (en) * 2019-08-06 2019-10-25 庄俊 A kind of lifting supporting beam of adjustable in length
CN110371840B (en) * 2019-08-06 2020-06-02 庄俊 Lifting supporting beam with adjustable length

Similar Documents

Publication Publication Date Title
CN103086279B (en) Vertical transportation construction method for building construction
CN101177959A (en) Curtain wall unit hanging equipment and construction method thereof
CN201276399Y (en) Apparatus hoisting mechanism for tall building floor non-steel platform
CN201105957Y (en) Tower crane engineering special-purpose gin pole hoist
CN205387439U (en) Mast hoisting accessory
CN205367454U (en) Large -size formwork hoisting machine constructs
CN101649684B (en) Installing method of roof mast
CN201952153U (en) Portable detachable hoisting equipment
CN206799012U (en) A kind of concrete batten transport of small space and installation tool group
CN201762053U (en) Simple automatic derrick
CN217028004U (en) Annular hanging basket suspension device for curtain wall construction of super high-rise building
CN206680096U (en) One kind is used for restricted clearance hanging apparatus
CN108483212A (en) Cladding glass installation self-control electric hoist hanger system and its hanging method
CN212249126U (en) Sliding platform for large-size cornice aluminum plate construction
CN109279522A (en) Movable units body glass curtain wall cantilevered hanging device
CN205873594U (en) Special construction elevator of cooling tower section of thick bamboo wall
CN202000647U (en) Base device for lifting scaffold in elevator shaft
CN105819352B (en) Lifting device for detachable door type mast building and construction method thereof
CN215291554U (en) Slant traction guide rope lock device
CN205527413U (en) Hang cantilever crane
CN209367692U (en) It is a kind of to rise gantry type two-way lifter device certainly
CN210193239U (en) Supplementary portal frame device of dismantling construction tower crane counterweight
CN204198306U (en) A kind of device for purlin lifting in building operation
CN209780257U (en) Steel structure high altitude construction device
CN208648517U (en) Cladding glass installation self-control electric hoist hanger system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080827

Termination date: 20160824