CN201095721Y - Soft soil foundation porous double suspension arms arched bridge structure - Google Patents

Soft soil foundation porous double suspension arms arched bridge structure Download PDF

Info

Publication number
CN201095721Y
CN201095721Y CNU2007201141712U CN200720114171U CN201095721Y CN 201095721 Y CN201095721 Y CN 201095721Y CN U2007201141712 U CNU2007201141712 U CN U2007201141712U CN 200720114171 U CN200720114171 U CN 200720114171U CN 201095721 Y CN201095721 Y CN 201095721Y
Authority
CN
China
Prior art keywords
arch
cantilever
arched
sheet
group
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007201141712U
Other languages
Chinese (zh)
Inventor
林长川
敖鹏
唐振兴
金存芳
吴刘槐
蒋生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHANGYE CONSTRUCTION GROUP Co Ltd
Original Assignee
CHANGYE CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHANGYE CONSTRUCTION GROUP Co Ltd filed Critical CHANGYE CONSTRUCTION GROUP Co Ltd
Priority to CNU2007201141712U priority Critical patent/CN201095721Y/en
Application granted granted Critical
Publication of CN201095721Y publication Critical patent/CN201095721Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a soft-ground multi-hole double-cantilever arched bridge structure, which belongs to the field of arched bridge construction technology. The utility model consists of two arched springing abutments, two edge hole cantilever arched girders arranged between the two arched springing abutments and multiple groups of double-cantilever arched girders, which are connected between the two edge hole cantilever arched girders and connected with each other. Each group of double-cantilever arched girder is arranged in two groups of pile foundations, foundation struts and pillar-typed piers that are arranged from bottom to top in sequence. The double-cantilever arched girder consists of a beam arranged on each group of pillar-typed piers, an arched strap arranged on both sides of each group of pillar-typed piers with an arched strap tie-in arranged between the arched straps on the adjacent side of the two groups of pillar-typed piers, an arched slab arranged below the arched strap and a bridge deck arranged above the beam and the arched strap. The two arched springing abutments are respectively connected with the corresponding edge hole cantilever arched girder through a butt strap. The soft-ground multi-hoe double-cantilever arched bridge structure has short construction period and economical cost, and can prevent the arched springing abutment from a side shift or settlement.

Description

Soft-ground multi-cell twin-cantilever arched bridge structure
Technical field
The utility model discloses a kind of soft-ground multi-cell twin-cantilever arched bridge structure, belong to the technical field of arch bridge construction.
Background technology
Arch bridge is the most frequently used a kind of bridge pattern of China.More than its style, quantity is big, is the hat of various bridge types.Arch bridge beautiful design, mellow and full, the rich dynamically sense of curve.The porous arch bridge generally is the mesopore maximum, successively decreases successively in proportion in the aperture, both sides, and full-bridge is coordinated well-balanced, and the slope that falls naturally both had been convenient to be beneficial to the shipping of all kinds of ships again about the pedestrian.When the main arch load-bearing of certain hole, can load other hole main arch that is delivered to from the close-by examples to those far off be got on by the distortion of bridge pier or the effect of spandrel structure, finally be delivered on the arch springing abutment, thereby the arch springing abutment to bear bigger horizontal thrust.For the soft foundation arch bridge, make arch springing abutment generation sidesway or sedimentation under the bigger horizontal thrust effect easily, thereby have influence on the safety of whole arch bridge.For this reason, the arch springing abutment foundation must carry out that the arch springing ground is anti-to push away processing, cost increases, anti-to push away processing be a technological difficulties always for duration lengthening and soft foundation arch springing, throughout the year current dynamic vehicle load makes soft foundation, and anti-to push away effect not ideal enough, and the arch bridge of many soft clay area phenomenons such as bridge floor sedimentation or cracking often occur with the passing in age.Also have the part arch bridge arch end to increase girt makes the arch springing abutment not produce horizontal thrust for this reason, that has so just avoided the arch springing ground anti-ly pushes away processing, but the girt that increases had both reduced headway, had also destroyed that graceful curve modeling of arch bridge, still was difficult to satisfactory.
The utility model content
In order to solve above-mentioned problems of the prior art, the utility model provides a kind of duration weak point, cost to economize, can prevent the soft-ground multi-cell twin-cantilever arched bridge structure of arch springing abutment generation sidesway or sedimentation.
To achieve these goals, the technical scheme that the utility model adopted is: a kind of soft-ground multi-cell twin-cantilever arched bridge structure, comprise two arch springing abutments, two lateral opening cantilever arch ellbeams between these two arch springing abutments, and being connected between these two the lateral opening cantilever arch ellbeams and the two cantilever arch ellbeams of interconnective many groups, described every group of two cantilever arch ellbeams are arranged on two groups of pile foundations that are provided with from the bottom to top successively, foundation connection beam, the columnar pier; The described pair of cantilever arch ellbeam comprises between the arch sheet of the crossbeam that is arranged on every group of columnar pier, the arch sheet that is arranged on every group of columnar pier both sides and these two groups of columnar pier sides adjacent and is provided with the arch strip terminal, is arranged on the arch bar of arch sheet below and is arranged on crossbeam and the bridge deck of arch sheet top; Described these two arch springing abutments interconnect by attachment strap respectively with between the corresponding lateral opening cantilever arch ellbeam.
As the further setting of such scheme, described lateral opening cantilever arch ellbeam comprises the arch sheet, is arranged on the arch bar of arch sheet below and the bridge deck that are arranged on arch sheet top; Described pair of cantilever arch ellbeam has two groups of A, B; Side arch sheet in the two cantilever arch ellbeams of A group encircles between the sheet with a side in the two cantilever arch ellbeams of B group and is connected by attachment strap crossbeam and attachment strap; Another side arch sheet in the two cantilever arch ellbeams of A group is connected by the arch strip terminal with the arch sheet of a lateral opening cantilever arch ellbeam; Another side arch sheet in the two cantilever arch ellbeams of B group is connected by the arch strip terminal with the arch sheet of another lateral opening cantilever arch ellbeam.
The utility model soft-ground multi-cell twin-cantilever arched bridge structure, by two cantilever arch ellbeams self moment of flexure balance, the bridge floor load is passed to columnar pier with the axial force form, be connected by attachment strap between lateral opening cantilever arch ellbeam and the arch springing abutment, so the arch springing abutment is not subjected to horizontal thrust.Simultaneously double cantilever beam arch section form exactly meets the mechanical characteristic of cantilever again, the double cantilever beam bearing place moment of flexure maximum of encorbelmenting, and sagitta is also maximum herein, so just greatly reduces the amount of deflection of semi girder arrangement of reinforcement and end.The two cantilever arch ellbeams of each group form a multispan static determinacy force structure by attachment strap again, and the structure power transmission is direct, and system is simple.
Specifically, the utlity model has following characteristics:
1. keep the graceful profile of porous arch bridge, and given full play to the advantage of arched girder cantilever force, satisfied the headway requirement of river course shipping simultaneously.
2. a series of problems of having avoided thrust at springer to produce.Need not carry out that the soft foundation arch springing is anti-to push away processing, save cost, shorten the duration, also eliminate because thrust at springer causes the bridge floor structure hidden danger such as cracking of sinking.
3. adopt the precast arch piece assembling and construction method, reduce soft foundation, improve the quality of arch sheet, made things convenient for construction and shortened the duration the adverse effect in the work progress.
4. because this structure is no thrust arch bridge, more be applicable to soil property difference area and the bigger arch bridge of bridge floor load, as the arch shelter bridge.
Description of drawings
Below in conjunction with the drawings and specific embodiments the utility model is described in further detail.
Fig. 1 is a structural representation of the present utility model;
Fig. 2 is the vertical view of Fig. 1.
The specific embodiment
As shown in Figure 1, 2, the utility model soft-ground multi-cell twin-cantilever arched bridge structure, comprise two arch springing abutment 3a, 3b, two lateral opening cantilever arch ellbeams between arch springing abutment 3a, 3b, and be connected between these two the lateral opening cantilever arch ellbeams and two groups of two cantilever arch ellbeams of interconnective A, B.Every group of two cantilever arch ellbeams all are arranged on two groups of pile foundations 7 that are provided with from the bottom to top successively, foundation connection beam 2, the columnar pier 4. Arch springing abutment 3a, 3b interconnect by attachment strap 5 respectively with between the corresponding lateral opening cantilever arch ellbeam.
Two cantilever arch ellbeams comprise and are provided with arch strip terminal 6 between the arch sheet 1 of the crossbeam 9 that is arranged on every group of columnar pier 4, the arch sheet 1 that is arranged on every group of columnar pier 4 both sides and these two groups of columnar pier 4 sides adjacent, are arranged on the arch bar 10 of arch sheet 1 below and are arranged on crossbeam 9 and the bridge deck 8 of arch sheet 1 top.
Lateral opening cantilever arch ellbeam comprises arch sheet 11, is arranged on the arch bar 10 of arch sheet 11 belows and the bridge deck 8 that are arranged on arch sheet 11 tops.
Side arch sheet 1 in the two cantilever arch ellbeams of A group encircles between the sheet 1 with a side in the two cantilever arch ellbeams of B group and is connected by attachment strap crossbeam 12 and attachment strap 5; Another side arch sheet 1 in the two cantilever arch ellbeams of A group is connected by arch strip terminal 6 with the arch sheet 11 of a lateral opening cantilever arch ellbeam; Another side arch sheet 1 in the two cantilever arch ellbeams of B group is connected by arch strip terminal 6 with the arch sheet 11 of another lateral opening cantilever arch ellbeam.
The utility model soft-ground multi-cell twin-cantilever arched bridge structure is to adopt the following steps construction to form:
1. the cofferdam of building a dam: wherein adopt the timber supporting;
2. construction stake basis 7, foundation connection beam 2, columnar pier 4: wherein pile foundation 7 adopts bored piles; The drill-pouring pile concrete is built earlier to foundation connection beam 2 tops, cuts foundation connection beam 2 deck-molding part concrete again, with bored pile and columnar pier 4 reinforcing bar spreadings and colligation foundation connection beam 2 reinforcing bars, carries out concrete secondary and builds;
3. construction arch springing abutment 3a, 3b: wherein the ground in arch springing abutment 3a, 5 meters scopes of 3b substrate periphery is carried out grouting reinforcement, handle the degree of depth and be not less than 10 meters, and arch springing abutment 3a, 3b earth material select the sand compaction in layers for use;
4. precast arch piece 1,11: adopt platform prefabricated building, per four stacked building;
5. sheet 1,11 is encircleed in lifting: it is vertical that sheet 1,11 will be encircleed in edge arch sheet 1,11 long limits earlier; To encircle sheet 1,11 with mobile crane according to focus point again winches under the bridge; Arch sheet 1,11 is provided with steel work earlier in foundation connection beam 2 positions and supports temporarily, and regulates the discrepancy in elevation with two timber wedges; Arch sheet 1,11 is provided with the steel pipe bracing frame earlier in the span centre position, and the support body substrate cuts out 1 meter of weak soil, spread 0.5 meter thick particulate pool slag and tamps, on build 0.2 meter C20 concrete; Steel pipe supports end face wood beam in length and breadth is set, and forms arch curve, two timber wedges is set between upper berth bamboo hectograph and wooden frame regulates the discrepancy in elevation and be convenient in demoulding;
6. strip terminal 6 and attachment strap crossbeam 12 are respectively encircleed in construction: wherein template is inside and outside horizontal stupefied with the bolt tension, every 2 meters the concrete spouting mouth is set highly; Template is supported on foundation connection beam 2 or the support; Select slightly expanded concrete for use;
7. construction arch bar 10 and crossbeam 9: wherein backform is all established greater than 20 degree in arch bar 10 angle of slope, and the top soffit formwork is provided with bolt draw bar, in establish hard plastic tube; Arch bar 10 is built order and is built from lower to upper; Arch sheet in the crossbeam 91,11 reinforcing bars are welded to connect; Crossbeam 9 concretings are spent placement layer by layer by gradient less than 20 in proper order;
The construction bridge deck 8: wherein soffit formwork is supported on the precast arch piece 1,11; The concrete order of building is: spanning span centre about 1/2 is striden wide part concrete in the middle of watering earlier, and symmetry is advanced to the centre by the end bay both sides again, builds the intermediate support part at last;
9. unloading: unload again after bridge construction cast-in-situ concrete intensity reaches designing requirement, and adopt symmetry unloading manner synchronously;
10. each attachment strap 5 of constructing: wherein clog with 1: 1 pitch sawdust in the slit between attachment strap 5 and the bridge deck 8.

Claims (2)

1. soft-ground multi-cell twin-cantilever arched bridge structure, comprise two arch springing abutments (3a, 3b), be positioned at two lateral opening cantilever arch ellbeams between the arch springing abutment (3a, 3b), and be connected between these two the lateral opening cantilever arch ellbeams and the two cantilever arch ellbeams of interconnective many groups, it is characterized in that: described every group of two cantilever arch ellbeams are arranged on two groups of pile foundations (7) that are provided with from the bottom to top successively, foundation connection beam (2), the columnar pier (4); The described pair of cantilever arch ellbeam comprise be provided with arch strip terminal (6), be arranged on the arch bar (10) of arch sheet (1) below and be arranged on crossbeam (9) between the arch sheet (1) of the crossbeam (9) that is arranged on every group of columnar pier (4), the arch sheet (1) that is arranged on every group of columnar pier (4) both sides and this two groups of columnar piers (4) sides adjacent and arch sheet (1) above bridge deck (8); Described arch springing abutment (3a, 3b) interconnects by attachment strap (5) respectively with between the corresponding lateral opening cantilever arch ellbeam.
2. according to the described soft-ground multi-cell twin-cantilever arched bridge structure of claim 1, it is characterized in that: described lateral opening cantilever arch ellbeam comprises arch sheet (11), is arranged on the arch bar (10) of arch sheet (11) below and the bridge deck (8) that are arranged on arch sheet (11) top; Described pair of cantilever arch ellbeam has two groups of A, B; Side arch sheet (1) in the two cantilever arch ellbeams of A group encircles between the sheet (1) with a side in the two cantilever arch ellbeams of B group and is connected by attachment strap crossbeam (12) and attachment strap (5); Another side arch sheet (1) in the two cantilever arch ellbeams of A group is connected by arch strip terminal (6) with the arch sheet (11) of a lateral opening cantilever arch ellbeam; Another side arch sheet (1) in the two cantilever arch ellbeams of B group is connected by arch strip terminal (6) with the arch sheet (11) of another lateral opening cantilever arch ellbeam.
CNU2007201141712U 2007-09-06 2007-09-06 Soft soil foundation porous double suspension arms arched bridge structure Expired - Fee Related CN201095721Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007201141712U CN201095721Y (en) 2007-09-06 2007-09-06 Soft soil foundation porous double suspension arms arched bridge structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007201141712U CN201095721Y (en) 2007-09-06 2007-09-06 Soft soil foundation porous double suspension arms arched bridge structure

Publications (1)

Publication Number Publication Date
CN201095721Y true CN201095721Y (en) 2008-08-06

Family

ID=39922772

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007201141712U Expired - Fee Related CN201095721Y (en) 2007-09-06 2007-09-06 Soft soil foundation porous double suspension arms arched bridge structure

Country Status (1)

Country Link
CN (1) CN201095721Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102828619A (en) * 2011-12-31 2012-12-19 常熟古建园林建设集团有限公司 Construction method of connection of archaizing granite bracket system and concrete pillar
CN104674645A (en) * 2015-02-02 2015-06-03 淮海工学院 Integral plate type small bridge and culvert combination applicable to soft soil foundations

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102828619A (en) * 2011-12-31 2012-12-19 常熟古建园林建设集团有限公司 Construction method of connection of archaizing granite bracket system and concrete pillar
CN104674645A (en) * 2015-02-02 2015-06-03 淮海工学院 Integral plate type small bridge and culvert combination applicable to soft soil foundations

Similar Documents

Publication Publication Date Title
CN100447338C (en) Soft-ground multi-cell twin-cantilever arched bridge structure and its construction method
CN101538831B (en) Post-poured hidden coping construction method for converting simply supported beams into continuous beams
CN106894326B (en) The construction method of assembled pretensioned prestressing corrugated steel web plate composite box girder
CN101824800B (en) Method for construction of bridge cast-in-situ pre-stressed concrete continuous beam
CN205205635U (en) Stride footpath bailey frame steel suspension bridge structure greatly
CN201155080Y (en) Large-span V-shaped continuous rigid frame bridge
CN104404869A (en) Pile column type concrete hollow pile pier structure
CN204282199U (en) Pile-column concrete hollow pile bridge pier structure
CN101349061A (en) Construction method for controlling operation station structure floating in reconstruction and extension of subway junction center station
CN201581409U (en) Combined tower crane foundation of cross beam supported by steel latticework columns in deep foundation pit
CN106012960A (en) Assembly type long piled wharf upper structure system and construction method thereof
CN112095495A (en) Bridge underpinning support structure and construction method
CN103510458B (en) Pile type continuous rigid frame bridge and construction method thereof
CN201648978U (en) Tied arch support of bridge location cast-in-situ prestressed concrete continuous beam
CN201095721Y (en) Soft soil foundation porous double suspension arms arched bridge structure
CN203475289U (en) Pile type continuous rigid frame bridge
CN210395119U (en) Face novel bridge beam supports frame that combines forever
CN203765790U (en) Pedestal for prestress small box girder of highway in soft-foundation geological condition
US20220325492A1 (en) Prefabricated, modular hydropower foundation system for soil conditions
CN213571600U (en) Bridge underpins bearing structure
CN112095659B (en) Recyclable single-side formwork system and construction method
CN205296206U (en) Tower cane foundation
CN110836023A (en) Reinforcing construction method of concrete beam
CN209780081U (en) Light assembling stairway with steel concrete combined flat bottom plate and filler
CN210117724U (en) Garage foundation structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080806

Termination date: 20150906

EXPY Termination of patent right or utility model