CN201082948Y - Over electrified railway overpass construction protecting canopy - Google Patents
Over electrified railway overpass construction protecting canopy Download PDFInfo
- Publication number
- CN201082948Y CN201082948Y CNU2007200912243U CN200720091224U CN201082948Y CN 201082948 Y CN201082948 Y CN 201082948Y CN U2007200912243 U CNU2007200912243 U CN U2007200912243U CN 200720091224 U CN200720091224 U CN 200720091224U CN 201082948 Y CN201082948 Y CN 201082948Y
- Authority
- CN
- China
- Prior art keywords
- suspension rod
- fixed
- insulated plate
- electric
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model discloses a protective shed used in construction of an overpass stepping across an electrified railway, and comprises an upright post, a beam (7), a roof board (9) and an electricity preventing device, wherein, a plurality of upright posts (6) are arranged on both sides except a railroad clearance (1) and an electric pole; two opposite upright posts (6) are provided with a beam (7) which is provided with a plurality of lengthwise purlines (8) on which the roof board (9) is arranged; an electricity preventing board (10) is arranged on the upper side of each contact network electrified body (2) and is fixed on each purlines (8) through a telescopic boom; the rear side of each electric pole is provided with an electricity preventing stick (18) fixed on each upright post, the lower end of which is fixed in a reinforced concrete filling pile (4) and is provided with an antistatic earth wire (5). The protective shed can resist the attack of an object falling accidentally in the construction of the overpass, ensure smooth construction of the overpass and personnel safety, guarantee traffic of transportation of railways, and improve construction efficiency.
Description
Technical field
The utility model relates to the technical field of railway overpass construction protection, strides electric railway overpass bridge construction protection canopy on a kind of.
Background technology
At present, continuous increase along with China's electric railway, the construction of crossing over the overpass bridge of electric railway will get more and more, when guaranteeing to cross over the electric railway bridge construction, the volt voltages up to ten thousand of electric railway are to falling to the safety of train operation object accidentally in constructor's health safety and the construction.For the construction of the overpass bridge of crossing over electric railway, often adopt steel pipe to fight, the slow time of installation rate is long, and the anti-shock device of installing on it can't be resisted in the construction of electric railway overpass bridge, and because of the impact of accidentally general purpose tool material tool being fallen, security reliability is poor; The suspension suspension rod of all-insulated plate is non-telescoping, can not adjust length, makes that the installation rate of all-insulated plate is slow, and the time that taking has a power failure blocks is long, and is big to the interference of railway transportation.
Summary of the invention
At the problem defective that prior art exists, the purpose of this utility model provides strides electric railway overpass bridge construction protection canopy on a kind of; Can guarantee to cross over the smooth construction that overpass bridge is built in electric railway, guarantee personal safety and traffic safety, it is simple in structure, construction is easy to make, and little, high efficiency is disturbed in transportation to train.
In order to realize the foregoing invention purpose, the utility model adopts following technical scheme:
Stride electric railway overpass bridge construction protection canopy on described, comprising: column, crossbeam, roof panel and insulating slab; Some columns of both sides are arranged on beyond railway clearance and the electric pole, and two relative columns are provided with crossbeam, and crossbeam is provided with some vertical purlins, is equipped with roof panel on the purlin; Every contact net electrical body top is provided with the all-insulated plate insulating slab, and all-insulated plate is fixed on the purlin by flexible suspension rod; The anti-electric prod of the rear side setting of each electric pole is fixed on the column, and the lower end of column is fixed in the deposited reinforced concrete pile, and is provided with the grounding wire of antistatic.
Stride electric railway overpass bridge construction protection canopy on described, flexible suspension rod comprises: upper hanger, following suspension rod and hoisting rope; The upper end of upper hanger is fixed with hoisting rope, hangs on it on purlin, and the hook cover is built-in with down suspension rod on the lower end of upper hanger; The lower draw-bar cover of following suspension rod is built-in with upper hanger, and upper and lower suspension rod middle part is equipped with some adjustment holes, and adjustment hole is built-in with steady pin; The lower draw-bar of following suspension rod is built-in with vertical slide bar of all-insulated plate.
Stride electric railway overpass bridge construction protection canopy on described, all-insulated plate is that insulating slab is rectangular, and its cross section is curved; All-insulated plate is provided with vertical slide bar.
Stride electric railway overpass bridge construction protection canopy on described, anti-electric prod is fixed on the column for the insulation rod.
Owing to adopt aforesaid technical scheme, the utlity model has following superiority:
Stride electric railway overpass bridge construction protection canopy on being somebody's turn to do, reasonable in design, can resist the impact of accidentally general purpose tool material tool being fallen in the construction of electric railway overpass bridge, the security reliability height; The suspension of all-insulated plate scalable, the adjustable length of suspension rod that stretches makes that the installation rate of all-insulated plate is fast, and the time that taking has a power failure blocks is short, and is little to the interference of transportation, personal safety and traffic safety in the time of can guaranteeing the bridge crossing construction.
Description of drawings
Fig. 1 on stride the elevation of electric railway overpass bridge construction protection canopy,
When Fig. 2 hangs for all-insulated plate, the view of flexible hook elongation,
Fig. 3 is the view of the flexible hook of the all-insulated plate that regulates.
Among the figure: 1-railway clearance; The 2-electrical body; The 3-overpass bridge; The 4-castinplace pile; The 5-grounding wire; The 6-column; The 7-crossbeam; The 8-purlin; The 9-roof panel; The 10-all-insulated plate; The 11-slide bar; The 12-lower draw-bar; 13-lower draw-bar cover; The last hook of 14-; The last hook cover of 15-; The 16-pin; The 17-hoisting rope; 18-prevents electric prod.
The specific embodiment
As shown in Figure 1, 2, 3, stride electric railway overpass bridge construction protection canopy on this, comprising: column (6), crossbeam (7), roof panel (9) and anti-shock device; Some columns (6) of both sides are arranged on beyond railway clearance (1) and the electric pole, and two relative columns (6) are provided with crossbeam (7), and crossbeam is provided with some vertical purlins (8), is equipped with roof panel (9) on the purlin; Every contact net electrical body (2) top is provided with all-insulated plate (10), and all-insulated plate is fixed on the purlin (8) by flexible suspension rod; The anti-electric prod (18) that the rear side of each electric pole is provided with is fixed on the column, and the lower end of column (6) is fixed in the deposited reinforced concrete pile (4), and is provided with the grounding wire (5) of antistatic.Its flexible suspension rod comprises: upper hanger, following suspension rod and hoisting rope (17); The upper end of upper hanger is fixed with hoisting rope (17), and hook (14) hangs on the purlin on it, and hook cover (15) is built-in with down suspension rod on the lower end of upper hanger; The lower draw-bar cover (13) of following suspension rod is built-in with upper hanger, and upper and lower suspension rod middle part is equipped with some adjustment holes, and adjustment hole is built-in with steady pin (16); The lower draw-bar of following suspension rod (12) is built-in with vertical slide bar (11) of all-insulated plate.Its all-insulated plate (10) is that insulating slab is rectangular, and its cross section is curved; All-insulated plate is provided with vertical slide bar (11).Its anti-electric prod (18) is fixed on column (6) top for the insulation rod.
When striding the construction of electric railway overpass bridge construction protection canopy on being somebody's turn to do, earlier in addition at railway clearance (1) and contact net electrical body (2), deposited reinforced concrete pile (4) is done in the below of overpass bridge (3), go up installation column (6) at deposited reinforced concrete pile (4), go up at column (6) grounding wire (5) is installed.Under the condition of blocking circuit, contact net power failure, crossbeam (7) is lifted on the top of column (6), vertical purlin (8) is installed in the top of crossbeam (7).
On ground with all-insulated plate (10) with by lower draw-bar (12), lower draw-bar cover (13), go up hook (14), go up hook cover (15), flexible suspension rod that pin (16) and hoisting rope (17) are formed is assembled into and prevents electric assembly, flexible suspension rod is in elongation state, installation personnel will prevent that by hoisting rope (17) electric assembly mentions the top of contact net electrical body (2), to go up hook (14) hangs on vertical purlin (8), the suspension rod that will stretch again shortens, and puts on pin (16) and makes all-insulated plate (10) hang the jail, be locked on vertical purlin (8).Remove hoisting rope (17), install roof panel (9) afterwards, can resist the impact of accidentally general purpose tool material tool being fallen in the construction of electric railway overpass bridge; At this moment, stride the construction of electric railway overpass bridge on just can carrying out normally.
Claims (4)
1. stride electric railway overpass bridge construction protection canopy on one kind, it is characterized in that: described protection canopy comprises: column (6), crossbeam (7), roof panel (9) and anti-shock device; Some columns (6) of both sides are arranged on beyond railway clearance (1) and the electric pole, and two relative columns (6) are provided with crossbeam (7), and crossbeam is provided with some vertical purlins (8), is equipped with roof panel (9) on the purlin; Every contact net electrical body (2) top is provided with all-insulated plate (10), and all-insulated plate is fixed on the purlin (8) by flexible suspension rod; The anti-electric prod (18) that the rear side of each electric pole is provided with is fixed on the column, and the lower end of column (6) is fixed in the deposited reinforced concrete pile (4), and is provided with the grounding wire (5) of antistatic.
2. stride electric railway overpass bridge construction protection canopy on according to claim 1, it is characterized in that: flexible suspension rod comprises: upper hanger, following suspension rod and hoisting rope (17); The upper end of upper hanger is fixed with hoisting rope (17), and hook (14) hangs on the purlin on it, and hook cover (15) is built-in with down suspension rod on the lower end of upper hanger; The lower draw-bar cover (13) of following suspension rod is built-in with upper hanger, and upper and lower suspension rod middle part is equipped with some adjustment holes, and adjustment hole is built-in with steady pin (16); The lower draw-bar of following suspension rod (12) is built-in with vertical slide bar (11) of all-insulated plate.
3. stride electric railway overpass bridge construction protection canopy on according to claim 1, it is characterized in that: all-insulated plate (10) is rectangular for insulating slab, and its cross section is curved; All-insulated plate is provided with vertical slide bar (11).
4. stride electric railway overpass bridge construction protection canopy on according to claim 1, it is characterized in that: anti-electric prod (18) is the insulation rod, and is fixed on column (6) top.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2007200912243U CN201082948Y (en) | 2007-07-17 | 2007-07-17 | Over electrified railway overpass construction protecting canopy |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2007200912243U CN201082948Y (en) | 2007-07-17 | 2007-07-17 | Over electrified railway overpass construction protecting canopy |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201082948Y true CN201082948Y (en) | 2008-07-09 |
Family
ID=39625412
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU2007200912243U Expired - Fee Related CN201082948Y (en) | 2007-07-17 | 2007-07-17 | Over electrified railway overpass construction protecting canopy |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201082948Y (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101806150A (en) * | 2010-03-13 | 2010-08-18 | 中铁西北科学研究院有限公司 | Effective and safe anti-slide pile construction method |
WO2011029340A1 (en) * | 2009-09-11 | 2011-03-17 | 长春轨道客车股份有限公司 | Top operation safety protection device for vehicle body assembly |
CN101624024B (en) * | 2009-08-12 | 2011-04-27 | 株洲柒星实业有限责任公司 | Manufacture method of electricity-resistant isolating shed by precast beam of electric railroad-crossing contact net |
CN102444082A (en) * | 2010-10-15 | 2012-05-09 | 中铁五局(集团)有限公司 | Light shelf protection structure for over crossing electrified railway bridge |
CN107620259A (en) * | 2017-09-30 | 2018-01-23 | 中铁二局第四工程有限公司 | Construction protection method for bridge under a kind of high-voltage line |
CN108277994A (en) * | 2018-03-20 | 2018-07-13 | 中铁三局集团有限公司 | On across the high ferro safe guarding shed quick method for dismounting of operation line |
CN111364366A (en) * | 2020-03-24 | 2020-07-03 | 浙江大学宁波理工学院 | Hinged protective shed frame for construction of viaduct spanning railway and erection method |
-
2007
- 2007-07-17 CN CNU2007200912243U patent/CN201082948Y/en not_active Expired - Fee Related
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101624024B (en) * | 2009-08-12 | 2011-04-27 | 株洲柒星实业有限责任公司 | Manufacture method of electricity-resistant isolating shed by precast beam of electric railroad-crossing contact net |
WO2011029340A1 (en) * | 2009-09-11 | 2011-03-17 | 长春轨道客车股份有限公司 | Top operation safety protection device for vehicle body assembly |
US8544602B2 (en) | 2009-09-11 | 2013-10-01 | Changchun Railway Vechicles Co., Ltd. | Safety protection device for roof construction of train body assembly |
CN101806150A (en) * | 2010-03-13 | 2010-08-18 | 中铁西北科学研究院有限公司 | Effective and safe anti-slide pile construction method |
CN102444082A (en) * | 2010-10-15 | 2012-05-09 | 中铁五局(集团)有限公司 | Light shelf protection structure for over crossing electrified railway bridge |
CN107620259A (en) * | 2017-09-30 | 2018-01-23 | 中铁二局第四工程有限公司 | Construction protection method for bridge under a kind of high-voltage line |
CN108277994A (en) * | 2018-03-20 | 2018-07-13 | 中铁三局集团有限公司 | On across the high ferro safe guarding shed quick method for dismounting of operation line |
CN111364366A (en) * | 2020-03-24 | 2020-07-03 | 浙江大学宁波理工学院 | Hinged protective shed frame for construction of viaduct spanning railway and erection method |
CN111364366B (en) * | 2020-03-24 | 2021-10-22 | 浙江大学宁波理工学院 | Hinged protective shed frame for construction of viaduct spanning railway and erection method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201082948Y (en) | Over electrified railway overpass construction protecting canopy | |
CN201315444Y (en) | Suspended cable basket blocking net charged crossing support | |
JPS63501229A (en) | Improved elastic guard fence structure | |
CN105186378A (en) | Power transmission line channel crossing protection mechanism | |
CN105178206B (en) | Spliced-type shed tunnel | |
CN207377264U (en) | A kind of spliced foundation pit protective fence | |
CN204738243U (en) | Novel flexible protection grating net | |
CN205954489U (en) | Stride cast -in -place space of business line steel structure construction protection on bridge and move movable support | |
CN109853408B (en) | Double-grading flexible protection system for high-steep side slope adjacent cliff road and design method thereof | |
CN208293455U (en) | A kind of three anti-fall stone structures of suspension cable rope net | |
CN207314176U (en) | A kind of cantilever shed tunnel applied to Bang Shan highways | |
CN101875473A (en) | Fence device on escalator or moving pavement | |
JP2017002515A (en) | Guard fence | |
CN205024700U (en) | Follow -on flexible passive protection net | |
CN202282576U (en) | Moso bamboo crossing frame | |
CN111719469A (en) | Anti-collision isolation guardrail device in highway center | |
CN201627154U (en) | Foreign material invasion rigid protective screen for high-speed railways | |
CN214301267U (en) | Pedestrian cableway bridge with partial glass bridge deck | |
CN103225411A (en) | Existing line protective shed | |
CN112448350A (en) | Drilling and crossing tower capable of preventing wire jumping and wind deflection | |
CN207277214U (en) | A kind of upstroke movable framework rain and snow canopy | |
CN207619814U (en) | Steel suspension bridge | |
CN202012226U (en) | Narrow base tower | |
CN210621511U (en) | Open type tension overhanging type recoverable flexible protection shed tunnel | |
CN205141514U (en) | Protection mechanism's unwrapping wire coaster is strideed across to transmission line passageway |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20080709 |