CN201057038Y - Novel separate-layer fracturing process pipe column for sand-blocking-prevention gas well - Google Patents

Novel separate-layer fracturing process pipe column for sand-blocking-prevention gas well Download PDF

Info

Publication number
CN201057038Y
CN201057038Y CNU2007201696383U CN200720169638U CN201057038Y CN 201057038 Y CN201057038 Y CN 201057038Y CN U2007201696383 U CNU2007201696383 U CN U2007201696383U CN 200720169638 U CN200720169638 U CN 200720169638U CN 201057038 Y CN201057038 Y CN 201057038Y
Authority
CN
China
Prior art keywords
oil pipe
packer
hydraulic anchor
sand
tubing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2007201696383U
Other languages
Chinese (zh)
Inventor
付钢旦
桂捷
赵粉霞
张华光
赵广民
巨亚锋
张文星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Original Assignee
Petrochina Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd filed Critical Petrochina Co Ltd
Priority to CNU2007201696383U priority Critical patent/CN201057038Y/en
Application granted granted Critical
Publication of CN201057038Y publication Critical patent/CN201057038Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a novel sand control card gas well layered fracturing technology tubular column, including hydraulic anchor (1), packer (2), oil pipe nipple joint (3), sandblast sliding sleeve (4), hydraulic anchor (5), packer (6), oil pipe (7), sit and seal ball seat (8), oil pipe shoes (10), hydraulic anchor (1), packer (2) cup joint on oil pipe (7), hydraulic anchor (5) cup joint on oil pipe (7), sandblast sliding sleeve (4) is connected in oil pipe nipple joint (3), packer (6), sit and seal ball seat (8) at the sub-unit connection of packer (6), the bottom of oil pipe (7) is connected with oil pipe shoes (10), both guaranteed the reliable implementation of layered fracturing technology, solved again because of the easy sand card of fracturing upper strata hydraulic anchor and arouse the difficult problem of tubular column after the pressure, effectively solved because of the difficult play tubular column problem of hydraulic anchor sand card.

Description

New type of sand prevention treibgas well separate stratum fracfturing process pipe string
Technical field
The utility model is after carrying out separate stratum fracfturing at a plurality of gas-bearing formation sections of the natural gas well, because of hydraulic anchor sand card is difficult for tripping out a kind of new type of sand prevention treibgas well separate stratum fracfturing process pipe string that tubing string designs.
Background technology
In recent years, the separate stratum fracfturing process pipe string based on different packers such as retrievable, permanent types is developed in succession at the separate stratum fracfturing transformation of multilayer gas well in domestic oil field.Though based on the separate stratum fracfturing tubing string of retrievable packer problem at the beginning of design with regard to lift pipe string after considering separate stratum fracfturing, but push up on the tubing string when preventing pressure break lower floor, cause tubing bending, fracture or the inefficacy of packer wriggling, often on packer, increase a hydraulic anchor, can guarantee the reliability of high pressure separate stratum fracfturing construction like this.But owing to increased hydraulic anchor, when carrying out the upper strata pressure break, inevitably on packer, increased the sand setting amount, after causing finishing whole pressing crack constructions, when needing lift pipe string, because of hydraulic anchor sand card, make that the difficulty of lift pipe string increases after the pressure break, to the well workover in gas well later stage, repeat retrofit work and exert a certain influence.For adopting permanent packer is main separate stratum fracfturing tubing string, and the later stage, its construction was more complicated, technical requirements is higher, difficulty is bigger, expense also can be higher if will move tubing string.
Summary of the invention
The purpose of this utility model is to provide a kind of new type of sand prevention treibgas well separate stratum fracfturing process pipe string, in the technological requirement that satisfies natural gas well separate stratum fracfturing, has also guaranteed after the separate stratum fracfturing or trips out tubing string during the later stage well workover.
The purpose of this utility model is achieved in that
Tubing string structure composition from top to bottom is: comprise hydraulic anchor 1, packer 2, tubing nipple 3, sandblast sliding sleeve 4, hydraulic anchor 5, packer 6, oil pipe 7, setting ball seat 8, tubing shoe 10, this process pipe string is socketed on the oil pipe 7 at the top of top gas-bearing formation hydraulic anchor 1 and packer 2, hydraulic anchor 5 is socketed on the oil pipe 7, tubing nipple 3 connects sandblast sliding sleeve 4, packer 6, bottom at packer 6 connects setting ball seat 8, and the bottom of oil pipe 7 is connected with tubing shoe 10.
Described connection all is that tubing round thread links and connects.
Advantage of the present utility model is:
Compare with traditional packer separate stratum fracfturing mode, both guaranteed the reliable enforcement of separate stratum fracfturing technology, solved again, efficiently solve because of hydraulic anchor sand card and be difficult for tripping out the tubing string problem because of hydraulic anchor easy sand card in pressure break upper strata causes the problem of pressing back lift pipe string difficulty.
Description of drawings
Accompanying drawing is a structural representation of the present utility model.
The specific embodiment
As shown in drawings, this process pipe string is that oil pipe connects hydraulic anchor 1 and packer 2, hydraulic anchor 5 on the top of top gas-bearing formation.Between top gas-bearing formation and the bottom gas-bearing formation is that tubing nipple 3 is connected sandblast sliding sleeve 4, packer 6, and connecting setting ball seat 8,7 in the bottom of packer 6 is oil pipe, the 10th, and tubing shoe.
In natural gas well sleeve pipe, be lowered to natural gas well separate stratum fracfturing sand control clipping technique tubing string:
1, at first, following perforating gun is once penetrated out two gas-bearing formation sections in the natural gas well;
2, the utility model natural gas well separate stratum fracfturing sand control clipping technique tubing string is lowered in the gas well;
3, by the pressurization of oil pipe infusion fracturing fluid, packer, hydraulic anchor etc. enters duty, packer sealing packing element packing target zone and oil sets annular space;
4, carry out the pressure break of bottom gas-bearing formation, at this moment, hydraulic anchor 1,5 is tubing string fixedly, prevents that tubing string is subjected to top power, causes tubing bending, fractures or the inefficacy of packer wriggling.
5, drop into steel ball from oil pipe after the bottom gas-bearing formation pressure break, treat that steel ball falls into sandblast sliding sleeve 4 backs and opens sandblast sliding sleeve 4 from oil pipe 7 pressurizations, oil pipe 7 and top gas-bearing formation are linked up, simultaneously, steel ball and sandblast sliding sleeve 4 fall to sleeve base 8 places shutoff bottom gas-bearing formation together;
6, by oil pipe infusion fracturing fluid, fracturing fluid enters the top gas-bearing formation by sandblast sliding sleeve 4 seating nipple openings, carries out the pressing crack construction of top gas-bearing formation.At this moment, hydraulic anchor 1 prevents that tubing string is subjected to top power, and the slips of packer 6 prevents that then tubing string is subjected to downward power.
7, after gas-bearing formation pressing crack construction in top is finished, as not tripping out tubing string, directly completion, discharge opeing, operation.When having needed fracturing string, the anti-kill-job that circulates, at this moment, hydraulic anchor 1,5 anchor flukes are recoverable, because of the sand setting amount between last gas-bearing formation and the packer 6 seldom, tubing string is easier to be tripped out.

Claims (2)

1. new type of sand prevention treibgas well separate stratum fracfturing process pipe string, comprise hydraulic anchor (1), packer (2), tubing nipple (3), sandblast sliding sleeve (4), hydraulic anchor (5), packer (6), oil pipe (7), setting ball seat (8), tubing shoe (10), it is characterized in that: hydraulic anchor (1), packer (2) are socketed on the oil pipe (7), hydraulic anchor (5) is socketed on the oil pipe (7), tubing nipple (3) connects sandblast sliding sleeve (4), packer (6), bottom at packer (6) connects setting ball seat (8), and the bottom of oil pipe (7) is connected with tubing shoe (10).
2. new type of sand prevention treibgas well separate stratum fracfturing process pipe string according to claim 1 is characterized in that: above-mentioned each parts connect and are tubing round thread and link and connect.
CNU2007201696383U 2007-07-10 2007-07-10 Novel separate-layer fracturing process pipe column for sand-blocking-prevention gas well Expired - Lifetime CN201057038Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007201696383U CN201057038Y (en) 2007-07-10 2007-07-10 Novel separate-layer fracturing process pipe column for sand-blocking-prevention gas well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007201696383U CN201057038Y (en) 2007-07-10 2007-07-10 Novel separate-layer fracturing process pipe column for sand-blocking-prevention gas well

Publications (1)

Publication Number Publication Date
CN201057038Y true CN201057038Y (en) 2008-05-07

Family

ID=39425879

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007201696383U Expired - Lifetime CN201057038Y (en) 2007-07-10 2007-07-10 Novel separate-layer fracturing process pipe column for sand-blocking-prevention gas well

Country Status (1)

Country Link
CN (1) CN201057038Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102268972A (en) * 2011-08-04 2011-12-07 荆州市翔龙石油科技有限公司 Method for preventing setting failure of packer resulted from creeping of pipe string
CN102839920A (en) * 2012-08-07 2012-12-26 中国石油化工股份有限公司 Multi-segment transforming tubular column for horizontal well and use method for same
CN103321626A (en) * 2013-07-11 2013-09-25 中国海洋石油总公司 Fracture and sand prevention integrated completion pipe string and application method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102268972A (en) * 2011-08-04 2011-12-07 荆州市翔龙石油科技有限公司 Method for preventing setting failure of packer resulted from creeping of pipe string
CN102839920A (en) * 2012-08-07 2012-12-26 中国石油化工股份有限公司 Multi-segment transforming tubular column for horizontal well and use method for same
CN102839920B (en) * 2012-08-07 2015-04-22 中国石油化工股份有限公司 Multi-segment transforming tubular column for horizontal well and use method for same
CN103321626A (en) * 2013-07-11 2013-09-25 中国海洋石油总公司 Fracture and sand prevention integrated completion pipe string and application method thereof
CN103321626B (en) * 2013-07-11 2016-01-13 中国海洋石油总公司 A kind of fracturing sand control integration completion tubular column and application process thereof

Similar Documents

Publication Publication Date Title
CN104929603B (en) Infinite stage sectional fracturing method for casing
CN103015955B (en) Open-hole horizontal well multi-cluster sliding sleeve staged fracturing string and fracturing method thereof
CN102022104B (en) Open-hole packer for open-hole horizontal well and preset connector fracturing well completion method
CN101638982B (en) Multi-formation fracturing device and process of release tubular column
CN201902202U (en) Staged fracturing string of oil-gas horizontal well
CN202900205U (en) Multifunctional oil testing and well completion integrated pipe column
CN201593405U (en) Integrated tubular column for horizontal well completion and fracturing production
CN107387050A (en) A kind of ball-throwing type full-bore fracturing sliding bush
CN102518419A (en) High-efficiency fracturing combined device for multi-stage horizontal well
CN102979495A (en) Multi-cluster current limiting fracturing string of open hole horizontal well and fracturing method thereof
CN207048760U (en) A kind of ball-throwing type full-bore fracturing sliding bush
CN2866812Y (en) Natural gas well separate layer fracturing and combined layer mining integrated pipe column
CN201057038Y (en) Novel separate-layer fracturing process pipe column for sand-blocking-prevention gas well
CN105888639A (en) Feeding-controlling full-bore sliding sleeve sectional fracturing tube column
CN101105121A (en) Horizontal well machinery staged fracturing tool string
CN109138880A (en) Bidirectionally anchoring device
CN104563997A (en) Hydraulic jet and bridge plug combined process pipe column and working method thereof
CN209040783U (en) Bidirectionally anchoring device
CN104213893A (en) Perforation and fracturing integrated tubular column for selectively and repeatedly reforming old well of oil field and working method thereof
CN202500541U (en) Multistage layered fracturing process pipe column for gas well vertical well
CN208734311U (en) A kind of permanent type well completion packer that mechanical can be given up
CN1752404A (en) Gas well separate layer fracturing and producing integrated well completing pipe string and technique
CN201031679Y (en) Deep layer gas well multiple fracturing tools string
CN107724995A (en) A kind of mechanical-set half dissolving bridging device and its fracturing process
CN200975248Y (en) Fracturing of separate layers technique pipe column

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20080507

CX01 Expiry of patent term