CN201027548Y - Gateway wireline material-carrying device on fully mechanized mining face - Google Patents

Gateway wireline material-carrying device on fully mechanized mining face Download PDF

Info

Publication number
CN201027548Y
CN201027548Y CNU2007200196578U CN200720019657U CN201027548Y CN 201027548 Y CN201027548 Y CN 201027548Y CN U2007200196578 U CNU2007200196578 U CN U2007200196578U CN 200720019657 U CN200720019657 U CN 200720019657U CN 201027548 Y CN201027548 Y CN 201027548Y
Authority
CN
China
Prior art keywords
terminal
wire rope
wirerope
steel cable
haul
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007200196578U
Other languages
Chinese (zh)
Inventor
贾民
刘健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yanzhou Coal Mining Co Ltd
Yanzhou Coal Industry Co Ltd
Original Assignee
Yanzhou Coal Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yanzhou Coal Industry Co Ltd filed Critical Yanzhou Coal Industry Co Ltd
Priority to CNU2007200196578U priority Critical patent/CN201027548Y/en
Application granted granted Critical
Publication of CN201027548Y publication Critical patent/CN201027548Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

A fully mechanized coal face gateway wirerope material transporting device consisting of upright posts (9), metal top beams (10), post shoes (8) which are arranged on a material transporting start end and a material transporting terminal, wirerope (1) and a tensioning mechanisms thereof, material transporting pulleys (5) and height regulating mechanisms arranged on the wirerope start end and the wirerope terminal. The wirerope (1) is arranged between the metal top beams (10) on the start end and the terminal; one end of the wirerope is connected with the wirerope tensioning mechanism. A plurality of material transporting pulleys (5) are arranged on the wirerope and slide along the wirerope; hanging hooks of the pulleys hang materials to be transported. The height regulating mechanisms on the wirerope start end and on the wirerope terminal for adjusting the heights of two ends of wirerope are respectively arranged between one side of the wirerope start end and a fixed shackles (12) arranged on the post shoes of the start end and between the one side of the wirerope terminal and a fixed shackles (12) arranged on the post shoes of the terminal. The utility model is used for material transportation of leading maintenance section of fully mechanized coal face gateway in coal mines, greatly lightens labor intensity, improves efficiency and operates safely, in particular in coal faces with an obvious pressure appearance and complex geological condition.

Description

Fully-mechanized mining working crossheading wire rope haul device
Technical field
The utility model relates to coal mine fully-mechanized mining working transport of materials apparatus, the leading service section of particularly a kind of fully-mechanized mining working crossheading, utilizes the fully-mechanized mining working crossheading wire rope haul device of wire rope transported material.
Background technology
In fully-mechanized mining working, because the needs of coal winning technology, two ends all need have leading service section, and supporting is carried out by hydraulic prop and metal hinge top beam in this zone, narrow space, and can't lay normal orbit, therefore a large amount of materials need artificial transportation.The work plane that particularly pressure is obvious, geological conditions is complicated has increased labor strength and unsafe factor greatly.
Summary of the invention
In order to overcome big, the unsafe deficiency of the artificial transported material labour intensity of the leading service section of fully-mechanized mining working crossheading, the utility model provides a kind of and can reduce labor intensity greatly, raises the efficiency, the fully-mechanized mining working crossheading wire rope haul device of job safety.
The technical scheme that its technical problem that solves the utility model adopts is:
Fully-mechanized mining working crossheading wire rope haul device is by column, metal roof bar, the post footwear of haul top and terminal, wire rope and steel cable strainer, and haul coaster and steel cable top and terminal height-regulating mechanism are formed.
The column of top and terminal, metal roof bar, post footwear are erected at the top and the terminal of fully-mechanized mining working crossheading haul respectively, have the ring that is fixedly connected on the post footwear.Between the metal roof bar of beginning, terminal, connect wire rope.Between the wherein end and metal roof bar of wire rope, string has the steel cable strainer.The haul coaster is several, is installed in wire rope upper edge wire rope and slides, and the suspension hook of haul coaster is hung the as ready material.
Regulate steel cable top height-regulating mechanism, terminal height-regulating mechanism that wire rope two ends height is used, on top one side that is separately positioned on wire rope and the top post footwear be fixedly connected between the ring, between being fixedly connected on terminal one side of wire rope and the terminal pillar footwear encircle.
The technical scheme that its technical problem that solves the utility model adopts can also be:
Difference clamping rings chain on the top of fully-mechanized mining working crossheading wire rope haul device, the terminal metal back timber, the wire rope two ends are connected to gib head.The steel cable strainer adopts bottle gouard moved by hands.Steel cable top height-regulating mechanism, steel cable terminal height-regulating mechanism all by coaster with heighten bottle gouard moved by hands and connect to form.
The beneficial effects of the utility model are:
1. this wire rope haul device can reduce labor intensity greatly, raise the efficiency and safety factor, particularly manifests obviously at pressure, the complicated work plane of geological conditions, and effect is more obvious.
2. wire rope has good flexibility and intensity, easily tensioning and bear bigger load.Compliance is strong, can regulate according to space requirement to take root a little and angle.Pulley transit rub resistance is little, and is convenient and swift.
3. simple in structure, be easy to processing, install, remove, transport, safeguard.
Description of drawings
Accompanying drawing is a fully-mechanized mining working crossheading wire rope haul Unit Installation schematic diagram.
Among the figure: 1-wire rope, 2-steel cable tensioning bottle gouard moved by hands, 3-terminal coaster, 4-steel cable terminal are heightened bottle gouard moved by hands, 5-haul coaster, 6-top coaster, 7-steel cable top and are heightened bottle gouard moved by hands, 8-post footwear, 9-column, 10-metal roof bar, 11-round-link chain, the 12-ring that is fixedly connected.
The specific embodiment
Below in conjunction with drawings and Examples the utility model is further specified.
The composition of the utility model fully-mechanized mining working crossheading wire rope haul device shown in the drawings.Column 9 by haul top and terminal is formed with heighten bottle gouard moved by hands 7 and 4 etc. of metal roof bar 10 and post footwear 8, wire rope 1, steel cable tensioning bottle gouard moved by hands 2, haul coaster 5, steel cable top and terminal.
In top, the terminal of fully-mechanized mining working crossheading, the leading service section in stope termination, set up column 9 and metal roof bar 10 respectively, strutting footwear 8 are wanted in column 9 bottoms, and ring 12 will be fixedly connected on the post footwear 8.Difference clamping rings chain 11 on the metal roof bar 10 of top, terminal, between two round-link chains 11 of top, terminal, long distance is set up wire rope 1.The two ends of wire rope 1 are connected to gib head; Wire rope 1 one ends are connected with round-link chain 11 two ends of top metal roof bar 10 by gib head, and the other end is connected with round-link chain 11 two ends on the terminal metal back timber 10 by steel cable tensioning bottle gouard moved by hands 2.Several haul coasters 5 are installed on the wire rope 1, and coaster 5 slides along wire rope 1, hangs the as ready material with the suspension hook of coaster 5.
For the height of regulating wire rope 1 top and terminal, made it the discrepancy in elevation, between wire rope 1 top, one side and the top column post footwear 8 and between wire rope 1 terminal, one side and the terminal column post footwear 8, respectively coaster is set and steel cable is heightened bottle gouard moved by hands.The suspension hook that is located at the coaster 6 on wire rope 1 top one side is connected with the chain that bottle gouard moved by hands 7 is heightened at steel cable top, and the ring 12 that is fixedly connected on the suspension hook of bottle gouard moved by hands 7 and the top post footwear connects.Coaster 3 suspension hooks that are located on wire rope 1 terminal one side are connected with the chain that the steel cable terminal is heightened bottle gouard moved by hands 4, and the ring 12 that is fixedly connected on the suspension hook of bottle gouard moved by hands 4 and the terminal pillar footwear 8 connects.Coaster 6 and 3 or claim later to take turns 6 and 3.Column is a hydraulic prop, and round-link chain adopts Φ 16X84 high-tensile round-link chain.
Operating principle:
The round-link chain 11 of top, terminal is taken root respectively on the metal roof bar 10 of haul beginning, terminal, is connected in the wire rope 1 between two round-link chains 11, by 2 tensionings of tensioning bottle gouard moved by hands.Utilization is taken root in the bottle gouard moved by hands 7 of post footwear 8, coaster 6 and bottle gouard moved by hands 4, coaster 3, regulates the height of wire rope beginning, terminal, makes it to form the discrepancy in elevation.Haul coaster 5 slides on wire rope 1, and material is hung on the suspension hook of coaster 5, promotes to hang material on coaster 5 by manpower, transports along wire rope 1.
Except such scheme, also can adopt following measure change:
Steel cable tensioning bottle gouard moved by hands 2, steel cable that wire rope 1 connects are heightened bottle gouard moved by hands 7 and 4, can use open type wire tensioner, electric block equivalent it.The coaster 6 of wire rope 1 top and terminal and 3 can use steel cable cutting ferrule, rig thimbler equivalent it.Round-link chain 11 can be with the wire rope of two ends band rig thimbler for it.

Claims (3)

1. fully-mechanized mining working crossheading wire rope haul device, it is characterized in that: the column (9), metal roof bar (10), the post footwear (8) that comprise haul top and terminal, wire rope (1) and steel cable strainer, haul coaster (5), and steel cable top height-regulating mechanism and terminal height-regulating mechanism;
The column of haul top and terminal (9), metal roof bar (10), post footwear (8) are erected at the top and the terminal of fully-mechanized mining working crossheading haul respectively, have the ring (12) that is fixedly connected on the post footwear (8); Between the metal roof bar (10) of beginning, terminal, be connected with wire rope (1); A wherein end of wire rope (1), and metal roof bar (10) between, string has a steel cable strainer; Haul coaster (5) is several, is installed on the wire rope (1), slides along wire rope (1), and the suspension hook of coaster (5) is hung the as ready material;
Regulate steel cable top height-regulating mechanism, the terminal height-regulating mechanism of wire rope (1) two ends height, be separately positioned on wire rope (1) top one side and the top post footwear be fixedly connected between the ring (12), being fixedly connected between the ring (12) on wire rope (1) terminal one side and the terminal pillar footwear.
2. fully-mechanized mining working crossheading wire rope haul device according to claim 1 is characterized in that: the metal roof bar of said top, terminal (10) is gone up clamping rings chain (11) respectively; The two ends of wire rope (1) are connected to gib head; Wire rope (1) one end is connected with round-link chain (11) two ends on the top metal roof bar (10) by gib head, the other end is by said steel cable strainer---and steel cable tensioning bottle gouard moved by hands (2) is connected with round-link chain (11) two ends on the terminal metal back timber (10).
3. fully-mechanized mining working crossheading wire rope haul device according to claim 1, it is characterized in that: said steel cable top height-regulating mechanism is heightened bottle gouard moved by hands (7) by coaster (6) on one side of top on the wire rope and top steel cable and is formed, the suspension hook of coaster (6) is connected with the chain of bottle gouard moved by hands (7), and the suspension hook of bottle gouard moved by hands (7) connects with the ring (12) that is fixedly connected on the post footwear; Steel cable terminal height-regulating mechanism is heightened bottle gouard moved by hands (4) by the coaster (3) on one side of terminal on the wire rope and terminal steel cable and is formed, and connected mode is identical with top.
CNU2007200196578U 2007-03-21 2007-03-21 Gateway wireline material-carrying device on fully mechanized mining face Expired - Fee Related CN201027548Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200196578U CN201027548Y (en) 2007-03-21 2007-03-21 Gateway wireline material-carrying device on fully mechanized mining face

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200196578U CN201027548Y (en) 2007-03-21 2007-03-21 Gateway wireline material-carrying device on fully mechanized mining face

Publications (1)

Publication Number Publication Date
CN201027548Y true CN201027548Y (en) 2008-02-27

Family

ID=39131752

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200196578U Expired - Fee Related CN201027548Y (en) 2007-03-21 2007-03-21 Gateway wireline material-carrying device on fully mechanized mining face

Country Status (1)

Country Link
CN (1) CN201027548Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105736043A (en) * 2016-04-22 2016-07-06 华北科技学院 Carrying device of single hydraulic pillar of advanced support for fully mechanized coal mining face of coal mine
CN106744352A (en) * 2016-12-29 2017-05-31 安徽芜湖海螺建筑安装工程有限责任公司 A kind of hoisting structure being useful in tertiary-air pipe construction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105736043A (en) * 2016-04-22 2016-07-06 华北科技学院 Carrying device of single hydraulic pillar of advanced support for fully mechanized coal mining face of coal mine
CN105736043B (en) * 2016-04-22 2018-06-19 华北科技学院 A kind of coal mine fully-mechanized mining working advance support hydraulic prop handling device
CN106744352A (en) * 2016-12-29 2017-05-31 安徽芜湖海螺建筑安装工程有限责任公司 A kind of hoisting structure being useful in tertiary-air pipe construction
CN106744352B (en) * 2016-12-29 2018-01-12 安徽芜湖海螺建筑安装工程有限责任公司 A kind of hoisting structure being useful in tertiary-air pipe construction

Similar Documents

Publication Publication Date Title
CN103452574B (en) Auxiliary bracket moving device of circular self-moving advance support
CN103742138B (en) One fells and transports coal all-in-one
RU2595227C2 (en) Method and device to prevent deviation of guiding cable
CN201027548Y (en) Gateway wireline material-carrying device on fully mechanized mining face
CN102874691B (en) Coal mine fully-mechanized mining the middle pan of scraper conveyor hanging apparatus
CN107387139B (en) Downward dismantling process for large-inclination-angle retracting working surface support
CN202991085U (en) Comprehensive hydraulic support for driving working face
CN201009889Y (en) Cableway tackle
CN103016039A (en) Tunneling working surface comprehensive hydraulic support
CN207551862U (en) A kind of belt rolls up discharge mechanism
CN202147997U (en) Device for tensioning chain of scraper conveyor
CN204326981U (en) A kind of linear guide rail type speed apparatus for feeding for vehicle-mounted drilling machine for coal bed gas
CN104481417B (en) Linear guide rail type speed apparatus for feeding for vehicle-mounted drilling machine for coal bed gas
CN202897867U (en) Middle trough hoisting device of fully-mechanized coal mining scraper conveyer in coal mine
CN203729994U (en) Coal mining/conveying integrated machine
CN202626985U (en) Hoist traction anchor cable penetration device
CN102704477B (en) Cable threading device and method of chain hoist traction anchor cable
RU2333880C1 (en) Method of slinging loads in mine working
CN112217172A (en) Towing cable telescoping device for fully-mechanized excavating machine
CN218261549U (en) Pillar conveyer
CN205532330U (en) Tunnel well drilling impels support
CN205370623U (en) Goaf filling hydraulic support
CN217917916U (en) Mining cableway material transporting device
CN217029004U (en) Light-duty material transporting device
CN204980977U (en) A promote hoist for colliery underground transportation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080227

Termination date: 20120321