CN200962133Y - Transformer station electrical test vehicle - Google Patents

Transformer station electrical test vehicle Download PDF

Info

Publication number
CN200962133Y
CN200962133Y CN 200620063964 CN200620063964U CN200962133Y CN 200962133 Y CN200962133 Y CN 200962133Y CN 200620063964 CN200620063964 CN 200620063964 CN 200620063964 U CN200620063964 U CN 200620063964U CN 200962133 Y CN200962133 Y CN 200962133Y
Authority
CN
China
Prior art keywords
tester
master control
testing
transformer station
car
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 200620063964
Other languages
Chinese (zh)
Inventor
王富荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHUHAI NANZI ELECTRIC SYSTEM ENGINEERING Co Ltd
Original Assignee
ZHUHAI NANZI ELECTRIC SYSTEM ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHUHAI NANZI ELECTRIC SYSTEM ENGINEERING Co Ltd filed Critical ZHUHAI NANZI ELECTRIC SYSTEM ENGINEERING Co Ltd
Priority to CN 200620063964 priority Critical patent/CN200962133Y/en
Application granted granted Critical
Publication of CN200962133Y publication Critical patent/CN200962133Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Testing Electric Properties And Detecting Electric Faults (AREA)

Abstract

An electric test car in the converting station comprises a driver and passenger section, a partition, a testing facility and a main control section. The testing facility and the main control section are provided with a plurality of independent frames for placing the testing facility and accessories. Each testing facility is connected with the computer through the communication interface. The system has high conformity and convenient use. The car is provided with the air conditioner system which ensures that the test controllers work in the comfortable environment even under rough weather conditions.

Description

Transformer station's electric testing car
Technical field
The utility model relates to a kind of high-voltage electrical apparatus test unit that is suitable for mobile operating, specifically, is a kind of transformer station electric testing car.
Background technology
For newly-built and operating high voltage substation, need carry out engineering commissioning test or operating preventive trial to high voltage electric equipment.When high voltage electric equipment is carried out various tests and test, existing method is that many high-precision instruments are transported to respectively near the transformer station by vehicle etc., then these instruments being transported to suitable place measures, and the data that will at every turn measure note respectively, import computing machine afterwards again and integrate; Yet, because high voltage electric equipment is of a great variety, test wiring complexity, the personnel that test needs strong working experience operate, and when using instrument separately, instrument only shows current test result, can't carry out effective discriminatory analysis, the time that delays to pinpoint the problems immediately to the result; The processing of test figure lacks special conversion, analysis, statistical software, also fails to include in the department information automated system, and the degree of integration of system is very low.
In addition, because the volume and the quality of various testing tools all differ greatly, if spuious arrangement in the transportation is easy to because extruding or jolting of haulage vehicle are caused damage; Measuring and test site, get off if each testing tool all carried, move back on the transport vehicle again after test finishes, because equipment is numerous and jumbled, handling process will be very loaded down with trivial details, use very inconveniently, especially under comparatively abominable natural conditions (for example period in severe winter of China the Northeast), carrying work is easy to cause the damage of instrument; On the other hand, all tests are all carried out outdoor, consider that high voltage substation generally all is in the remote point, and when weather was comparatively abominable, the working environment of tester and instrument necessity can not be protected, and the precision of test data is difficult to guarantee.
In sum, the present invention aims to provide a kind of system combination degree height, easy to use and can guarantee transformer station's electric testing car of tester's working environment.
Summary of the invention
The purpose of this utility model is that design provides a kind of system combination degree height, easy to use and can guarantee transformer station's electric testing car of tester's working environment.
For achieving the above object, transformer station's electric testing car that the utility model provides comprises driving and occupant area, partition wall and testing equipment and master control district, partition wall separates driving and occupant area with testing equipment and master control differentiation, the independent rack that several settle test apparatus and annex is set in testing equipment and the master control district, each test apparatus and computing machine link, and form complete test and test macro.
The utility model provide electric testing car with orderly being installed in the car body of various instrument and equipments, each test cell links by communication interface and computing machine, constitutes multi-functional automatization test system.In the process of test and test, can pilot system and tested equipment be linked by outside lead, finish experiment work automatically by computer control; Also test cell can be separated (especially under the Hi-pot test environment) with system, as independently instrument use, finish experiment work by panel operation, test result can be input in the computing machine and handle, store, system combination degree height, purpose easy to use have been reached, and,, also can guarantee tester's working environment even under the atrocious weather condition owing to be provided with air-conditioning system in the car.
Description of drawings
Fig. 1 is the overall layout chart of transformer station described in the utility model electric testing car;
Fig. 2 is the instrument distribution plan among the electric testing car rack A of transformer station described in the utility model;
Fig. 3 is the instrument distribution plan among the electric testing car rack B of transformer station described in the utility model;
Fig. 4 is the instrument distribution plan among the electric testing car rack C of transformer station described in the utility model;
Fig. 5 is the instrument distribution plan among the electric testing car rack D of transformer station described in the utility model;
Below in conjunction with the diagram and embodiment the utility model is described in further detail.
Embodiment
Referring to shown in Figure 1, transformer station described in the utility model electric testing car comprises to be driven and occupant area 1, partition wall 2 and testing equipment and master control district 3, and partition wall 2 will be driven and occupant area 1 is separated with testing equipment and master control district 3.
Driving and occupant area 1 comprise operator seat 10 and two member seats 12,13, wherein the inverter 14 of 12,13 belows, member seat fixed installation 1.7kW.Inverter 14 can provide emergency power pack for transformer station's electric testing car under the situation of no external power supply.
Partition wall 2 is arranged on the rear portion of driving and occupant area 1, and the middle part of partition wall 2 can be provided with view window (figure does not show), so that in the driving process of vehicle situation behind testing equipment and master control district 3 and the car is observed.The bottom of view window also can be provided with conversation hole (figure does not show), converses with staff in convenient driving and the occupant area 1 and the staff in testing equipment and the master control district 3.The both sides of view window are provided with access door (figure does not show), with maintenance and the loading and unloading that make things convenient for testing equipment.
Below in conjunction with Fig. 2, Fig. 3, Fig. 4 and Fig. 5 the concrete structure in testing equipment and the master control district 3 is described in detail.
Rack and operating platform are installed for each unit in the pilot system provides by testing equipment and master control district 3, be provided with four independent racks of settling main test apparatus in testing equipment and the master control district 3: rack A, rack B, rack C and rack D, and air-conditioner outdoor unit cabinet E, marshalling cabinet F.
In conjunction with shown in Figure 2, two post cabinets about rack A divides, sub-connecting switch of transformer tester A1,60kV high direct voltage controller A2,300kV high direct voltage controller A3, dielectric loss and capacitance tester A4 are installed among the wherein right post cabinet A31, among the post cabinet A32 of a left side deformation of transformer winding tester A5, no-load voltage ratio group tester A6, instrument for measuring DC resistance A7, series resonance variable-frequency power sources A8 are installed, above-mentioned A1-A8 is all can be by the directly actuated fixed equipment of computing machine, in addition, ups power A9 also is arranged among the right post cabinet A31.Between right post cabinet A31 and left post cabinet A32,, main control computer 33 is set on this operating platform, a file cabinet A10 is set under the operating platform for controlling platform.Between right post cabinet A31 and the left post cabinet A32 reactor grading shield 34 is set.Ups power A9 is a standby power supply, can guarantee that external power source power failure back computing machine 33 can normally move 30 minutes.
In conjunction with shown in Figure 3, Insulation Resistance Tester B1, circuit resistance tester B2,60kV high direct voltage multiplication of voltage tower B3, capacitance bridge B4, exciting transformer B5 be installed among the rack B, do not have dizzy hi-line B6, the humorous device fitting B7 of string and distribution console panel B8.
In conjunction with shown in Figure 4, place resonance reactor C1, C2, C3, C4 among the rack C, fix a printer 35 on the cabinet face of rack C.
In conjunction with shown in Figure 5, place reactor base D1, assist with cable aid D2 and other annex (not mark) etc. among the rack D.300kV high direct voltage multiplication of voltage tower D3 is installed on the table top of rack D, multiplication of voltage tower grading shield D4 is installed on sidewall.
Fixed installation voltage divider E1, E2 on the cabinet face of air-conditioner outdoor unit cabinet E, the sidewall fixed installation voltage divider grading shield E3 of air-conditioner outdoor unit cabinet E.
Marshalling cabinet F be used for each rack p-wire draw and power supply inserts, marshalling cabinet F also provides the system earth point simultaneously.
The following of indoor apparatus of air conditioner G in testing equipment and the master control district 3 can be provided with two passenger seats 36,37, and wherein 36 belows, member seat are provided with the super isolating transformer H of a 5kVA.
In sum, the utility model transformer station electric testing car is by cordwood indoor arrangement, and with orderly being installed in the car body of various instrument and equipments, each test cell links by communication interface and computing machine 33, constitutes multi-functional automatization test system.In the process of test and test, can pilot system and tested equipment be linked by outside lead, finish experiment work automatically by computer control; Also test cell can be separated (especially under the Hi-pot test environment) with system, as independently instrument use, finish experiment work by panel operation, test result can be input in the computing machine 33 and handle, stores, system combination degree height, purpose easy to use have been reached, and,, also can guarantee tester's working environment even under the atrocious weather condition owing to be provided with air-conditioning system in the car.
Except above-mentioned structure, the utility model can also have other ameliorative measure, for example, can increase other dependence test instrument according to the test needs in testing equipment and master control district 3, to increase the test function of electric testing car.Other suchlike minor alteration and equivalent transformation all should be included within the described scope of claim.

Claims (3)

1, transformer station's electric testing car comprises:
Driving and occupant area, testing equipment and master control district;
The partition wall that separates is distinguished in driving and occupant area and testing equipment and master control;
It is characterized in that:
Be provided with in testing equipment and the master control district: Insulation Resistance Tester, instrument for measuring DC resistance, no-load voltage ratio group tester, dielectric loss and capacitance tester, circuit resistance tester, 60kV high direct voltage controller and 300kV high direct voltage controller, series resonance variable-frequency power sources and sub-connecting switch of transformer tester, above-mentioned testing tool all links with main control computer.
2, transformer station according to claim 1 electric testing car is characterized in that:
Further comprise four independent racks in testing equipment and the master control district, wherein instrument for measuring DC resistance, no-load voltage ratio group tester, dielectric loss and capacitance tester, 60kV high direct voltage controller and 300kV high direct voltage controller, series resonance variable-frequency power sources and sub-connecting switch of transformer tester all are arranged in the first independent rack, and Insulation Resistance Tester and circuit resistance tester are arranged in the second independent rack.
3, transformer station according to claim 1 electric testing car is characterized in that: in testing equipment and the master control district air-conditioning system is set further.
CN 200620063964 2006-08-31 2006-08-31 Transformer station electrical test vehicle Expired - Lifetime CN200962133Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200620063964 CN200962133Y (en) 2006-08-31 2006-08-31 Transformer station electrical test vehicle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200620063964 CN200962133Y (en) 2006-08-31 2006-08-31 Transformer station electrical test vehicle

Publications (1)

Publication Number Publication Date
CN200962133Y true CN200962133Y (en) 2007-10-17

Family

ID=38798650

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200620063964 Expired - Lifetime CN200962133Y (en) 2006-08-31 2006-08-31 Transformer station electrical test vehicle

Country Status (1)

Country Link
CN (1) CN200962133Y (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101986166A (en) * 2010-08-23 2011-03-16 中国电力科学研究院 Test vehicle for partial discharge of power equipment on site
CN101986163A (en) * 2010-08-23 2011-03-16 上海思创电器设备有限公司 Field high-voltage dielectric-loss test vehicle for power equipment
CN102452347A (en) * 2010-11-03 2012-05-16 上海市电力公司 External power comprehensive tester
CN102582495A (en) * 2012-01-20 2012-07-18 安徽省电力公司合肥供电公司 Vehicle-mounted comprehensive test system used for condition based maintenance for electrical equipment
CN102937678A (en) * 2012-10-30 2013-02-20 苏州华电电气股份有限公司 Moving test station for large power transformer scene characteristic testing
CN103057456A (en) * 2012-12-29 2013-04-24 苏州华电电气股份有限公司 Electromagnetic environment inspection vehicle
CN104118346A (en) * 2014-08-05 2014-10-29 国家电网公司 Intelligent high-voltage test vehicle
CN105823962A (en) * 2016-05-16 2016-08-03 龙岩市海德馨汽车有限公司 Cable fault location car
CN107621576A (en) * 2017-09-20 2018-01-23 国家电网公司 Portable dielectric dissipation factor and capacitance test platform

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101986166A (en) * 2010-08-23 2011-03-16 中国电力科学研究院 Test vehicle for partial discharge of power equipment on site
CN101986163A (en) * 2010-08-23 2011-03-16 上海思创电器设备有限公司 Field high-voltage dielectric-loss test vehicle for power equipment
CN101986163B (en) * 2010-08-23 2013-06-19 上海思创电器设备有限公司 Field high-voltage dielectric-loss test vehicle for power equipment
CN101986166B (en) * 2010-08-23 2013-11-27 中国电力科学研究院 Test vehicle for partial discharge of power equipment on site
CN102452347A (en) * 2010-11-03 2012-05-16 上海市电力公司 External power comprehensive tester
CN102582495A (en) * 2012-01-20 2012-07-18 安徽省电力公司合肥供电公司 Vehicle-mounted comprehensive test system used for condition based maintenance for electrical equipment
CN102937678A (en) * 2012-10-30 2013-02-20 苏州华电电气股份有限公司 Moving test station for large power transformer scene characteristic testing
CN103057456A (en) * 2012-12-29 2013-04-24 苏州华电电气股份有限公司 Electromagnetic environment inspection vehicle
CN104118346A (en) * 2014-08-05 2014-10-29 国家电网公司 Intelligent high-voltage test vehicle
CN105823962A (en) * 2016-05-16 2016-08-03 龙岩市海德馨汽车有限公司 Cable fault location car
CN107621576A (en) * 2017-09-20 2018-01-23 国家电网公司 Portable dielectric dissipation factor and capacitance test platform

Similar Documents

Publication Publication Date Title
CN200962133Y (en) Transformer station electrical test vehicle
CN101515012B (en) External mounted electric combined test car
KR102596181B1 (en) Field test method and system for no-load and load loss of vehicle-mounted power transformer
CN103257286B (en) A kind of charging electric vehicle facility automatic test approach and system
CN101986163B (en) Field high-voltage dielectric-loss test vehicle for power equipment
CN201383629Y (en) Comprehensive power test vehicle
CN107329063A (en) A kind of electric-power safe instruments nigration car
CN109188071A (en) Vehicular power transformer sky, load loss on-site test system and method
CN202144220U (en) Check vehicle for ultrahigh voltage power transformer
CN103381996B (en) HGIS self-adaption emergency first-aid repair device and applications thereof
CN201382983Y (en) Outside-fitted type comprehensive power test vehicle
CN103950404A (en) Loading vehicle for high-voltage cable maintenance equipment
CN102582495A (en) Vehicle-mounted comprehensive test system used for condition based maintenance for electrical equipment
CN201413390Y (en) Electric power transformer field calibration vehicle
CN203032515U (en) On-site measurement verification vehicle for transformer
CN103592614B (en) A kind of van-type electric power mutual-inductor nigration platform
CN201800614U (en) On-site partial discharge test vehicle for power equipment
CN207875481U (en) A kind of electric engineering car
CN204488603U (en) A kind of combined power inspection vehicle of height integrated modular
CN203854554U (en) High-voltage cable maintenance equipment loading car
CN201345511Y (en) Distribution network emergency repair equipment vehicle
CN201355380Y (en) Intelligent field high-pressure test vehicle
CN103630783A (en) Mobile detection device of transformer equipment
CN203601100U (en) Alternating current voltage-withstanding vehicle-mounted test platform for 750kv supervoltage equipment
CN203037821U (en) Three-phase asynchronous motor dummy load testing analyzer

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20071017

EXPY Termination of patent right or utility model