CN1994940A - Circulated backfilling and artificial wetland combined leachate processing method and its facility - Google Patents

Circulated backfilling and artificial wetland combined leachate processing method and its facility Download PDF

Info

Publication number
CN1994940A
CN1994940A CN 200610136773 CN200610136773A CN1994940A CN 1994940 A CN1994940 A CN 1994940A CN 200610136773 CN200610136773 CN 200610136773 CN 200610136773 A CN200610136773 A CN 200610136773A CN 1994940 A CN1994940 A CN 1994940A
Authority
CN
China
Prior art keywords
leachate
landfill
lattice
layer
percolate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200610136773
Other languages
Chinese (zh)
Other versions
CN100491275C (en
Inventor
徐峥勇
杨朝晖
曾光明
王荣娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University
Original Assignee
Hunan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University filed Critical Hunan University
Priority to CNB2006101367738A priority Critical patent/CN100491275C/en
Publication of CN1994940A publication Critical patent/CN1994940A/en
Application granted granted Critical
Publication of CN100491275C publication Critical patent/CN100491275C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Of Solid Wastes (AREA)
  • Purification Treatments By Anaerobic Or Anaerobic And Aerobic Bacteria Or Animals (AREA)

Abstract

一种循环回灌与人工湿地联用的渗滤液处理方法,包括以下步骤:使垃圾渗滤液经格栅井去除部分粒径较大的悬浮物和杂物;然后集中于调节池第一格中去除一部分沙粒和悬浮物;使上述调节池第一格中一部分垃圾渗滤液通过渗滤液回灌系统回灌至垃圾填埋场,另一部分经过调节池第二格和调节池第三格的预处理后灌入人工湿地系统进行处理,出水达标后排放,污水在调节池中的总停留时间为15~30天。一种实现上述方法的渗滤液处理设施,包括格栅井、调节池、循环回灌系统和人工湿地系统,调节池被功能优化成三格,格栅井内设回转式格栅一台,格栅井出水口直接与调节池的第一格相连。本发明成本投入低,适应于各种填埋龄的渗滤液,且具景观修复功能。

Figure 200610136773

A leachate treatment method combined with recirculation and artificial wetlands, comprising the following steps: making the landfill leachate pass through a grid well to remove some suspended solids and impurities with larger particle sizes; Remove a part of sand and suspended matter; let part of the landfill leachate in the first grid of the above-mentioned regulating tank be recharged to the landfill through the leachate recharge system, and the other part pass through the pre-treatment of the second grid of the regulating tank and the third grid of the regulating tank. After treatment, it is poured into the artificial wetland system for treatment, and the effluent is discharged after reaching the standard. The total residence time of the sewage in the regulating tank is 15 to 30 days. A leachate treatment facility for realizing the above method, including a grid well, a regulating tank, a circulation recharge system and a constructed wetland system, the regulating tank is optimized into three grids, a rotary grid is arranged in the grid well, and the grid The grid well outlet is directly connected with the first grid of the regulating tank. The invention has low cost input, is suitable for leachate of various landfill ages, and has the function of landscape restoration.

Figure 200610136773

Description

一种循环回灌与人工湿地联用的渗滤液处理方法及其设施A leachate treatment method and its facilities for combined use of circulating irrigation and constructed wetlands

技术领域technical field

本发明属于环境保护、污水处理技术领域,具体涉及一种生活垃圾填埋场渗滤液处理方法及其设施。The invention belongs to the technical fields of environmental protection and sewage treatment, and in particular relates to a leachate treatment method and facilities of domestic waste landfill.

背景技术Background technique

垃圾渗滤液是垃圾填埋过程产生的二次污染,是一种成分复杂的高浓度有机废水,主要来源于降水和填埋废物本身的内含水,其对环境的污染是填埋场最主要的环境问题之一。它可以污染水体、土壤、大气等,使地面水体缺氧、水质恶化、富营养化,威胁饮用水和工农业用水水源,使地下水丧失利用价值,有机污染物进入食物链将直接威胁人类健康。Landfill leachate is the secondary pollution produced in the landfill process. It is a kind of high-concentration organic wastewater with complex components. It mainly comes from precipitation and the embedded water of the landfill waste itself. one of the environmental problems. It can pollute water bodies, soil, atmosphere, etc., make surface water bodies hypoxic, deteriorate water quality, and become eutrophic, threaten drinking water and industrial and agricultural water sources, and make groundwater lose its use value. Organic pollutants entering the food chain will directly threaten human health.

随着人们对填埋场渗滤液问题的逐渐重视,各种渗滤液处理方法得到广泛的发展。常用的渗滤液处理方法一般包括物化法、生化法和土地法。As people pay more and more attention to the problem of landfill leachate, various leachate treatment methods have been widely developed. Commonly used leachate treatment methods generally include physical and chemical methods, biochemical methods and land methods.

物化法一般作为预处理或深度处理而为渗滤液的达标排放和生物处理系统有效运行创造良好的条件。物化处理一般不受渗滤液水质水量的影响,出水水质比较稳定,尤其是对BOD/COD比值较低(0.07~0.20),难以生化处理的渗滤液,有较好的处理效果,当COD浓度为2000~4000mgL-1时,物化法的COD去除率一般可达到50%~80%。但物化处理技术针对性太强,处理效果单一,且成本高,不适于大量渗滤液的处理。Physical and chemical methods are generally used as pretreatment or advanced treatment to create good conditions for the discharge of leachate up to the standard and the effective operation of the biological treatment system. Physicochemical treatment is generally not affected by the water quality and quantity of leachate, and the effluent water quality is relatively stable, especially for leachate with a low BOD/COD ratio (0.07-0.20), which is difficult to biochemically treat, and has a good treatment effect. When the COD concentration is 2000 ~ 4000mgL -1 , the COD removal rate of physicochemical method can generally reach 50% ~ 80%. However, the physical and chemical treatment technology is too targeted, the treatment effect is single, and the cost is high, so it is not suitable for the treatment of large amounts of leachate.

生化法包括好氧处理、厌氧处理及两者结合处理的方法,它具有处理效果好、操作简单、投资及运行成本低等优点,适合于处理生化性较好的渗滤液。但生化法很难去除那些已降解的较小相对分子质量的有机成分,其出水COD很难降低到国家标准以下。而其生化法在处理渗滤液的过程中最严重的缺陷在于,对于BOD/COD比值较小的“老”龄渗滤液几乎没有处理效果。The biochemical method includes aerobic treatment, anaerobic treatment and a combination of the two. It has the advantages of good treatment effect, simple operation, low investment and operation costs, and is suitable for treating leachate with good biochemical properties. However, it is difficult to remove the degraded organic components with relatively small molecular weight by biochemical method, and it is difficult to reduce the COD of the effluent to below the national standard. The most serious defect of the biochemical method in the process of treating leachate is that it has almost no treatment effect on the "old" leachate with a small BOD/COD ratio.

土地法主要通过土壤颗粒的过滤、离子交换、吸附和沉淀等作用去除滤液中悬浮固体,并将可溶解成分固定在颗粒上。同时通过土壤中的微生物使渗滤液中的有机物和氮进行转化和稳定,通过蒸腾作用减少渗滤液的量。目前用于垃圾渗滤液处理的土地法主要有回灌法和人工湿地法。但土地法一般占地面积较大。The land method mainly removes the suspended solids in the filtrate through the filtration of soil particles, ion exchange, adsorption and precipitation, and fixes the soluble components on the particles. At the same time, the organic matter and nitrogen in the leachate are transformed and stabilized by microorganisms in the soil, and the amount of leachate is reduced through transpiration. At present, the land methods used for landfill leachate treatment mainly include recharge method and constructed wetland method. However, land law generally covers a larger area.

垃圾渗滤液水质水量变化大、营养元素比例失调、氨氮含量等特点造成其处理难度大,实现其经济有效处理是仍然是垃圾填埋处理技术中一个研究的热点和难点。Large changes in water quality and quantity of landfill leachate, imbalanced proportion of nutrient elements, ammonia nitrogen content and other characteristics make its treatment difficult. Realizing its economical and effective treatment is still a research hotspot and difficulty in landfill treatment technology.

发明内容Contents of the invention

本发明的目地在于克服上述现有技术的不足,提供一种成本投入低,处理效果好,操作简单,运行维护费用低,适应于各种填埋龄的渗滤液,且具景观修复功能的垃圾渗滤液处理方法及其设施。The purpose of the present invention is to overcome the deficiencies of the above-mentioned prior art, and provide a kind of garbage with low cost input, good treatment effect, simple operation, low operation and maintenance cost, suitable for leachate of various landfill ages, and with landscape restoration function Leachate treatment method and its facilities.

为解决上述问题,本发明采用以下技术方案:In order to solve the above problems, the present invention adopts the following technical solutions:

一种循环回灌与人工湿地联用的渗滤液处理方法,包括以下步骤:A leachate treatment method combined with recirculation and artificial wetland, comprising the following steps:

a.使垃圾渗滤液经格栅井去除部分粒径较大的悬浮物和杂物;a. Let the landfill leachate pass through the grid well to remove some suspended solids and sundries with larger particle sizes;

b.将上述经处理过的垃圾渗滤液集中于调节池第一格中去除一部分沙粒和悬浮物;b. Concentrate the above-mentioned treated landfill leachate in the first compartment of the adjustment tank to remove part of the sand and suspended matter;

c.使上述调节池第一格中一部分垃圾渗滤液通过渗滤液回灌系统回灌至垃圾填埋场,另一部分经过调节池第二格和调节池第三格的预处理后灌入人工湿地系统进行处理,出水达标后排放。污水在调节池中的总停留时间为15~30天。c. Recharge part of the landfill leachate in the first compartment of the above-mentioned regulating pool to the landfill through the leachate recharge system, and pour the other part into the constructed wetland after pretreatment in the second compartment of the regulating pool and the third compartment of the regulating pool The system conducts treatment, and the effluent is discharged after reaching the standard. The total residence time of sewage in the regulating tank is 15 to 30 days.

所述垃圾渗滤液通过渗滤液回灌系统回灌至垃圾填埋场的具体步骤为:1)用渗滤液回灌提升泵将调节池第一格中的垃圾渗滤液提升至布水泵房;2)通过高密度聚乙烯(HDPE)管将上述布水泵房中的垃圾渗滤液输入回灌井中并由回灌井两侧的回灌沟将其回灌至垃圾填埋场中;3)通过填埋场底部的渗滤液收集管道将上述垃圾填埋场的垃圾渗滤液集中至调节池,回灌频率为1~2次/d,回灌水力负荷为0.01~0.1m3/m2.d。The specific steps for recharging the landfill leachate to the landfill through the leachate recharge system are: 1) using the leachate recharge lift pump to lift the landfill leachate in the first grid of the regulating tank to the water distribution pump room; 2) ) input the landfill leachate in the above-mentioned water distribution pump room into the reinjection well through high-density polyethylene (HDPE) pipes, and reinfuse it into the landfill through the reinjection ditch on both sides of the reinjection well; 3) through the filling The leachate collection pipeline at the bottom of the landfill collects the leachate from the above-mentioned landfill to the adjustment tank, the refilling frequency is 1-2 times/d, and the refilling hydraulic load is 0.01-0.1m 3 /m 2 .d.

所述调节池第二格池底潜水型曝气机进行不间断曝气,单台作用范围4~8m;第三格池底设置的污泥泵定期排泥,第三格池底提升泵将垃圾渗滤液输送至人工湿地系统的配水井。所述人工湿地系统单元水力停留时间6~12小时;平均气温高于15℃时,水力负荷10~15L/m2.d;平均气温4~15℃时,水力负荷5~10L/m2.d;平均气温低于4℃时或当日降雨量为4~15mm时,水力负荷3~5L/m2.d;当日降雨量大于15mm时,停止进水。The submersible aerator at the bottom of the second grid of the adjustment tank performs uninterrupted aeration, and the range of action of a single unit is 4-8m; the sludge pump installed at the bottom of the third grid regularly discharges sludge, and the lifting pump at the bottom of the third grid will The landfill leachate is transported to the distribution well of the constructed wetland system. The hydraulic retention time of the constructed wetland system unit is 6-12 hours; when the average temperature is higher than 15°C, the hydraulic load is 10-15L/m 2 .d; when the average temperature is 4-15°C, the hydraulic load is 5-10L/m 2 . d; When the average temperature is lower than 4°C or when the daily rainfall is 4-15mm, the hydraulic load is 3-5L/m 2 .d; when the daily rainfall is greater than 15mm, stop water intake.

一种实现上述渗滤液处理方法的渗滤液处理设施,包括格栅井、置于格栅井之后的调节池、循环回灌系统和人工湿地系统,调节池被功能优化成三格,形成缺氧—好氧—缺氧的功能模式。格栅井内设回转式格栅一台,格栅井出水口直接与调节池的第一格相连。A leachate treatment facility that implements the above leachate treatment method, including a grid well, a regulating tank placed behind the grid well, a circulation recharge system and a constructed wetland system. The regulating tank is optimized into three grids to form anoxic - Aerobic-hypoxic functional model. A rotary grille is installed in the grill well, and the water outlet of the grill well is directly connected with the first grid of the regulating tank.

所述调节池第一格有效容积为调节池总有效容积的60%~80%,第二格和第三格有效容积相同,第一格内设置渗滤液回灌提升泵一台,在第二格池底设置1~4台潜水型曝气机,在第三格池底设置污泥泵和提升泵一台。所述循环回灌系统依次包括布水泵房、通过HDPE管与布水泵房相连的回灌井和回灌井两侧的回灌沟。每隔40~50m设置回灌井,回灌井左右各设计一条回灌沟,回灌沟结构为:中间是穿孔配水管,四周填充级配碎石,上覆一层压实粘土层。The effective volume of the first compartment of the regulating tank is 60% to 80% of the total effective volume of the regulating tank, the effective volume of the second compartment and the third compartment are the same, and a leachate recharge lift pump is installed in the first compartment, and a leachate recharge pump is installed in the second compartment Set 1 to 4 submersible aerators at the bottom of the grid, and set a sludge pump and a lift pump at the bottom of the third grid. The circulation and recharge system sequentially includes a water distribution pump house, a recharge well connected to the water distribution pump house through HDPE pipes, and recharge ditches on both sides of the recharge well. Recharge wells are set every 40-50m, and a recharge ditch is designed on the left and right sides of the recharge well. The structure of the recharge ditch is: a perforated water distribution pipe in the middle, filled with graded gravel around, and covered with a layer of compacted clay.

所述人工湿地系统根据地形将其划分为不同形状和面积的人工湿地单元,单元与单元之间根据实际需要进行串联和并联,人工湿地单元长度为20~50m,长∶宽=1~3∶1,配水井出水口与人工湿地单元的布水管相连,冬季当湿地植物枯萎后在人工湿地单元表面覆盖0.1~0.5mm厚的聚乙烯薄膜,所述湿地植物为挺水植物。当人工湿地单元位于填埋场最终覆盖层时,直接利用填埋场最终覆盖层的场地构建人工湿地单元,在垃圾层以上自下而上分别布置:粘土层、HDPE防渗膜密封层、合成材料导流层、填土层、植被层,在人工湿地单元前端设置穿孔布水管;当人工湿地单元位于填埋区域以外时,首先对地面进行平整,然后铺设砂石导流层,该层内铺设有穿孔导流管,砂石导流层上覆粘土层,平整后覆盖HDPE防渗膜密封层,膜上依次为砂石层、填土层和植被层,在人工湿地单元前端设置穿孔布水管,布水管高出植被层。The constructed wetland system is divided into constructed wetland units of different shapes and areas according to the terrain, and the units are connected in series and parallel according to actual needs. The length of the constructed wetland unit is 20-50m, and the length:width=1-3: 1. The water outlet of the water distribution well is connected to the water distribution pipe of the constructed wetland unit. In winter, when the wetland plants wither, the surface of the constructed wetland unit is covered with a 0.1-0.5mm thick polyethylene film. The wetland plants are emergent plants. When the constructed wetland unit is located in the final cover layer of the landfill, the site of the final cover layer of the landfill site is directly used to construct the constructed wetland unit, and the constructed wetland unit is arranged above the garbage layer from bottom to top: clay layer, HDPE anti-seepage membrane sealing layer, synthetic Material diversion layer, filling layer, and vegetation layer, and perforated water distribution pipes are set at the front end of the constructed wetland unit; The perforated diversion pipe is laid, and the sand and gravel diversion layer is covered with a clay layer. After leveling, it is covered with an HDPE anti-seepage membrane sealing layer. Water pipes, water pipes are higher than the vegetation layer.

所述人工湿地单元位于填埋场最终覆盖层时,粘土层厚度为0.2~0.3m、HDPE防渗膜密封层厚≥1mm、合成材料导流层厚度为0.2~0.3m、填土层厚度≥0.3m、植被层厚度≥0.3m,穿孔布水管长3~5m,布水管高出植被层0.3~0.6m;所述人工湿地单元位于填埋区域以外时,地面平整坡度为1%~2%,砂石导流层厚度为0.2m,砂石直径≤1cm,砂石导流层内间隔10m铺设一条穿孔布水管,砂石导流层上粘土层厚0.2m,HDPE防渗膜密封层厚1mm,防渗膜上砂石层厚0.2m,填土层和植被层厚度均不小于0.3m,穿孔布水管长约3~5m,布水管高出植被层0.3~0.6m。When the constructed wetland unit is located in the final cover layer of the landfill, the thickness of the clay layer is 0.2-0.3m, the thickness of the HDPE anti-seepage membrane sealing layer is ≥1mm, the thickness of the synthetic material diversion layer is 0.2-0.3m, and the thickness of the filling layer is ≥ 0.3m, vegetation layer thickness ≥ 0.3m, perforated water distribution pipe 3-5m long, water distribution pipe 0.3-0.6m higher than the vegetation layer; when the constructed wetland unit is located outside the landfill area, the ground slope is 1%-2% , the thickness of the sand and gravel diversion layer is 0.2m, the diameter of the sand and gravel is ≤1cm, and a perforated water pipe is laid at an interval of 10m in the sand and gravel diversion layer. The thickness of the sandstone layer on the anti-seepage membrane is 0.2m, the thickness of the filling layer and the vegetation layer are not less than 0.3m, the perforated water distribution pipe is about 3-5m long, and the water distribution pipe is 0.3-0.6m higher than the vegetation layer.

所述的人工湿地单元植被层所种植的植物主要为芦苇、茭草、旱伞竹、香蒲、美人蕉、黄竹草、水葱、水莎草及灯芯草等挺水植物。同一单元内栽种同种植物,但不同的单元内需根据景观需要和污水特征栽种不同植物,并定期对植物进行收割。The plants planted in the unit vegetation layer of the constructed wetland are mainly emergent plants such as reed, water sedge, bamboo, cattail, canna, yellow bamboo grass, water onion, water sedge and rush grass. The same plant is planted in the same unit, but different plants need to be planted in different units according to the landscape needs and sewage characteristics, and the plants are harvested regularly.

本发明的优点是:The advantages of the present invention are:

1.本发明将污水处理技术与景观修复技术有机的结合,在将渗滤液处理达到国家一级排放标准(GB16889-1997)的同时,对垃圾填埋场进行了景观修复。1. The present invention organically combines the sewage treatment technology with the landscape restoration technology, and while the leachate treatment reaches the national first-class discharge standard (GB16889-1997), the landfill has been landscape restored.

2.本发明具有减少渗滤液排放量的作用,渗滤液回灌系统及人工湿地系统都能以截留和蒸发作用的方式较大幅度的减少渗滤液的总量。2. The present invention has the effect of reducing the amount of leachate discharge, and both the leachate recharge system and the constructed wetland system can greatly reduce the total amount of leachate by means of interception and evaporation.

3.本发明的调节池经过功能优化,在积蓄渗滤液的同时能够对渗滤液进行初步处理,减轻了人工湿地系统的负荷压力。3. The regulating pool of the present invention has been optimized in function, and can initially treat the leachate while accumulating the leachate, reducing the load pressure of the constructed wetland system.

4.本发明适应于任何填埋龄的渗滤液处理,并且随着填埋场使用年限的增长,所获得的人工湿地的建设面积也就越大,渗滤液的处理能力也随之逐渐提高。4. The present invention is suitable for leachate treatment of any landfill age, and with the increase of the service life of the landfill, the construction area of the obtained constructed wetland will be larger, and the leachate treatment capacity will gradually increase accordingly.

5.本发明的实施成本低,尤其是填埋场进行分区填埋及分区最终覆盖时,人工湿地的构建直接利用最终覆盖层的结构,仅需对湿地单元进行分隔并增加相应的输水和布水设施。5. The implementation cost of the present invention is low, especially when the landfill is subdivided and finally covered, the construction of the constructed wetland directly uses the structure of the final covering layer, and only needs to separate the wetland units and increase the corresponding water delivery and distribution. water facilities.

6.本发明能加速垃圾分解,加快垃圾稳定化过程,提高垃圾的产甲烷速率和产甲烷量。6. The present invention can accelerate the decomposition of garbage, accelerate the stabilization process of garbage, and increase the rate and amount of methane production of garbage.

7.本发明不但不需要外加物质和能源进行水质调节,而且使得渗滤液中的水分、氮素及有机物质为植物所利用,转化为具有可再资源化的生物材料。7. The present invention not only does not require external substances and energy sources to regulate water quality, but also enables plants to utilize water, nitrogen and organic substances in the leachate and convert them into recyclable biological materials.

附图说明Description of drawings

图1为本发明的工艺流程图;Fig. 1 is a process flow diagram of the present invention;

图2为本发明的调节池示意图;Fig. 2 is the schematic diagram of the regulating pool of the present invention;

图3为本发明的循环回灌系统示意图;Fig. 3 is the schematic diagram of the circulating refilling system of the present invention;

图4为本发明的回灌沟剖面示意图;Fig. 4 is a schematic cross-sectional view of a refill ditch of the present invention;

图5为本发明的位于填埋场最终覆盖层的人工湿地单元剖面示意图;Fig. 5 is the schematic cross-sectional view of the constructed wetland unit located in the final cover layer of the landfill according to the present invention;

图6为本发明的位于填埋场区域以外的人工湿地单元剖面示意图。Fig. 6 is a schematic cross-sectional view of a constructed wetland unit located outside the landfill area of the present invention.

附图中的标号说明如下:The labels in the accompanying drawings are explained as follows:

1、调节池第一格            2、调节池第二格         3、调节池第三格1. The first grid of the adjustment pool 2. The second grid of the adjustment pool 3. The third grid of the adjustment pool

4、渗滤液回灌提升泵        5、潜水型曝气机         6、污泥泵4. Leachate recharge lift pump 5. Submersible aerator 6. Sludge pump

7、提升泵                  8、格栅井               9、渗滤液收集管道7. Lift pump 8. Grid well 9. Leachate collection pipe

10、回灌井                 11、固体垃圾            12、布水泵房10. Reinjection well 11. Solid waste 12. Water distribution pump room

13、压实粘土               14、级配碎石            15、穿孔配水管13. Compacted clay 14. Graded crushed stone 15. Perforated water distribution pipe

16、穿孔布水管             17、植被层              18、填土层16. Perforated water pipes 17. Vegetation layer 18. Filling soil layer

19、合成材料导流层         20、HDPE防渗膜密封层    21、粘土层19. Synthetic material diversion layer 20. HDPE anti-seepage membrane sealing layer 21. Clay layer

22、垃圾层                 23、出水管              24、砂石层22. Garbage layer 23. Outlet pipe 24. Sand and gravel layer

25、砂石导流层上粘土层     26、砂石导流层          27、穿孔导流管25. Clay layer on sand and gravel diversion layer 26. Sand and gravel diversion layer 27. Perforated diversion pipe

具体实施方式Detailed ways

本发明实施例工艺流程如图1所示。The process flow of the embodiment of the present invention is shown in Fig. 1 .

实施例1Example 1

某新建填埋场,格栅井8(如图3所示)设置于调节池北侧西北角,尺寸为长×宽=2000mm×700mm,有效水深1.95m。内设回转式机械格栅1台,有效栅宽0.7m,配电机功率1.2kW,格栅井南端开孔300mm×300mm与调节池相连。In a newly built landfill site, the grid well 8 (as shown in Figure 3) is set in the northwest corner of the north side of the adjustment pool, the size is length × width = 2000mm × 700mm, and the effective water depth is 1.95m. There is one rotary mechanical grille with an effective grille width of 0.7m and a power distribution motor of 1.2kW. The south end of the grille well has a hole of 300mm×300mm connected to the regulating pool.

如图2所示,调节池有效容积3600m3,有效水深3m。调节池第一格1尺寸长×宽=36m×25m,调节池第二格2与第三格3尺寸均为长×宽=12m×25m,调节池总水力停留时间为20天。在第二格内设置潜水型曝气机5两台进行不间断曝气,单台作用范围5m,配电机功率3.7kW。在第三格池底设置污泥泵6一台(流量12.5m3/h,扬程9m,配电机功率0.75kW),定期排泥,并设置提升泵7一台(流量12.5m3/h,扬程20m,配电机功率2kW),将渗滤液输送至人工湿地系统的配水井,配水井出水口连接人工湿地单元的穿孔布水管16(如图5所示)。As shown in Figure 2, the effective volume of the regulating pool is 3600m 3 and the effective water depth is 3m. The size of the first grid 1 of the regulating tank is length×width=36m×25m, the dimensions of the second grid 2 and the third grid 3 of the regulating tank are both length×width=12m×25m, and the total hydraulic retention time of the regulating tank is 20 days. Two submersible aerators are installed in the second cell for uninterrupted aeration, with a range of 5m and a motor power of 3.7kW. Set up 6 sets of sludge pumps (flow rate 12.5m 3 /h, head 9m, distribution motor power 0.75kW) at the bottom of the third tank to discharge sludge regularly, and install 7 sets of lift pumps (flow rate 12.5m 3 /h , head 20m, distribution motor power 2kW), the leachate is transported to the water distribution well of the constructed wetland system, and the outlet of the water distribution well is connected to the perforated water distribution pipe 16 of the constructed wetland unit (as shown in Figure 5).

调节池第一格中的渗滤液经循环回灌系统回灌至垃圾填埋场,如图3所示,循环回灌系统实现的具体途径是:首先渗滤液回灌提升泵4将调节池第一格中的渗滤液提升至布水泵房12,然后HDPE管将布水泵房中的垃圾渗滤液输入回灌井10中,并由回灌井两侧的回灌沟将其回灌至垃圾填埋场中,通过填埋场底部的渗滤液收集管道9将上述垃圾填埋场的垃圾渗滤液集中至调节池。每隔50m设置回灌井,回灌井左右各设计一条50m×2m×0.5m回灌沟,其结构如图4所示,中间是Ф100mm的穿孔配水管15,四周填充级配碎石14,上覆一层压实粘土13。回灌频率为2次/d,回灌水力负荷为0.5m3/m2.d。The leachate in the first cell of the regulating tank is recharged to the landfill through the circulating recharge system, as shown in Figure 3, the specific way to realize the recirculating recharge system is: firstly, the leachate is recharged by the lift pump 4 to the second cell of the regulating tank. The leachate in one grid is lifted to the water distribution pump room 12, and then the HDPE pipe transfers the landfill leachate in the water distribution pump room into the reinjection well 10, and it is recharged to the landfill by the recharge ditch on both sides of the reinjection well. In the landfill, the leachate from the above-mentioned landfill is collected into the adjustment pool through the leachate collection pipeline 9 at the bottom of the landfill. Reinjection wells are set every 50m, and a 50m×2m×0.5m recharge ditch is designed on the left and right sides of the reinjection well. Cover with a layer of compacted clay 13 . The recharge frequency is 2 times/d, and the recharge hydraulic load is 0.5m 3 /m 2 .d.

经过多次循环回灌,填埋场内土壤的吸附作用和微生物的分解作用使得渗滤液内的总污染物质浓度降低,并且回灌过程中蒸发作用和固体垃圾11(如图3所示)的截流作用使渗滤液的体积大幅度减少。而调节池第二、三格的曝气和厌氧过程可以使渗滤液中的污染物浓度进一步降低。After multiple cycles of recharge, the adsorption of soil in the landfill and the decomposition of microorganisms reduce the concentration of total pollutants in the leachate, and the evaporation and solid waste 11 (as shown in Figure 3) during the recharge process The interception effect greatly reduces the volume of leachate. The aeration and anaerobic process of the second and third compartments of the regulating tank can further reduce the concentration of pollutants in the leachate.

本实施例的运行初期,没有最终覆盖场地可以使用,因此早期的人工湿地单元建于填埋场区域以外。如图6所示,首先对地面进行平整(坡度为2%),然后铺设0.2m厚的砂石导流层26,砂石直径≤1cm,该层内间隔10m铺设一条穿孔导流管27以引出地下水径流;砂石导流层26上覆0.2m厚的粘土层25,平整后覆盖1mm厚的HDPE防渗膜密封层20。膜上依次为0.2m厚度的砂石层24及厚度均不小于0.3m填土层18和植被层17,砂石层24中设有出水管23。在人工湿地单元前端设置长约5m的穿孔布水管16,布水管高出植被层0.5m。Early in the operation of this example, no final cover site was available, so early constructed wetland units were built outside the landfill area. As shown in Figure 6, at first the ground is leveled (the slope is 2%), then a 0.2m thick sand diversion layer 26 is laid, and the diameter of the sand is less than or equal to 1cm, and a perforated diversion pipe 27 is laid at intervals of 10m in this layer. Lead out groundwater runoff; the sand diversion layer 26 is overlaid with a 0.2m thick clay layer 25, and is covered with a 1mm thick HDPE anti-seepage membrane sealing layer 20 after leveling. On the membrane are a sandstone layer 24 with a thickness of 0.2m, a filling soil layer 18 and a vegetation layer 17 with a thickness not less than 0.3m, and an outlet pipe 23 is arranged in the sandstone layer 24 . A perforated water distribution pipe 16 about 5m long is arranged at the front end of the constructed wetland unit, and the water distribution pipe is 0.5m higher than the vegetation layer.

本实施例运行一定时间后,部分填埋区域逐渐进行最终覆盖,直接利用填埋场最终覆盖层的场地构建人工湿地单元,如图5所示,在垃圾层22以上自下而上分别布置:粘土层21(1m)、HDPE防渗膜密封层20(2mm)、合成材料导流层19(0.3m)、填土层18(厚度≥0.3m)和植被层17(厚度≥0.3m),合成材料导流层19中设有出水管23。在人工湿地单元前端设置长约5m的穿孔布水管16,布水管高出植被层0.5m。After running for a certain period of time in this embodiment, part of the landfill area will be finally covered gradually, and the site of the final cover layer of the landfill site will be directly used to construct the artificial wetland unit. As shown in Figure 5, they are respectively arranged above the garbage layer 22 from bottom to top: Clay layer 21 (1m), HDPE anti-seepage membrane sealing layer 20 (2mm), synthetic material diversion layer 19 (0.3m), fill layer 18 (thickness ≥ 0.3m) and vegetation layer 17 (thickness ≥ 0.3m), A water outlet pipe 23 is provided in the synthetic material guide layer 19 . A perforated water distribution pipe 16 about 5m long is arranged at the front end of the constructed wetland unit, and the water distribution pipe is 0.5m higher than the vegetation layer.

本实施例中的人工湿地单元尺寸长×宽=30m×15m,人工湿地单元水力停留时间6小时,平均气温高于15℃时,水力负荷10L/m2.d,平均气温4~15℃时,水力负荷5L/m2.d,平均气温低于4℃时或当日降雨量为4~15mm时,水力负荷3L/m2.d,当日降雨量大于15mm时,停止进水。冬季当湿地植物枯萎后在人工湿地单元表面覆盖0.2mm厚的聚乙烯薄膜。The size of the constructed wetland unit in this example is length×width=30m×15m, the hydraulic retention time of the constructed wetland unit is 6 hours, when the average temperature is higher than 15°C, the hydraulic load is 10L/m 2 .d, and the average temperature is 4-15°C , the hydraulic load is 5L/m 2 .d, when the average temperature is lower than 4°C or the daily rainfall is 4-15mm, the hydraulic load is 3L/m 2 .d, and when the daily rainfall is greater than 15mm, stop watering. In winter, when the wetland plants wither, cover the surface of the constructed wetland unit with a 0.2mm thick polyethylene film.

本实施例中的工湿地单元植被层所种植的植物主要为芦苇、茭草、美人蕉、黄竹草、水葱及灯芯草等挺水植物。同一单元内栽种同种植物,但不同的单元内需根据景观需要和污水特征栽种不同植物,并定期对植物进行收割。Plants planted in the vegetation layer of the construction wetland unit in this embodiment are mainly emergent plants such as reeds, water lilies, cannas, yellow bamboo grasses, water onions and rushes. The same plant is planted in the same unit, but different plants need to be planted in different units according to the landscape needs and sewage characteristics, and the plants are harvested regularly.

本实施例人工湿地最终出水水质指标达到国家《生活垃圾填埋场污染控制标准》(GB16889-1997)一级排放标准。The water quality index of the final effluent from the constructed wetland in this embodiment has reached the first-level discharge standard of the national "Standards for Pollution Control of Domestic Garbage Landfill Sites" (GB16889-1997).

实施例2Example 2

某垃圾填埋场,调节池有效容积3600m3,其尺寸为长×宽=60m×25m,有效水深3m。原建有4座序批式活性污泥反应器(SBR),初步处理达到《生活垃圾填埋场污染控制标准》(GB16889-1997)三级排放标准后并入市政污水管网。现因污水管网改线,并入市政管网的代价过大,应用本发明在填埋场内单独处理达标后排放。In a landfill site, the effective volume of the regulating pool is 3600m 3 , its size is length×width=60m×25m, and the effective water depth is 3m. Originally, there were 4 Sequencing Batch Activated Sludge Reactors (SBR), which were incorporated into the municipal sewage pipe network after the preliminary treatment reached the third-level discharge standard of the "Pollution Control Standards for Domestic Waste Landfill Sites" (GB16889-1997). Now because the sewage pipe network is rerouted and the cost of merging into the municipal pipe network is too high, the invention is applied to the landfill for separate treatment and discharge after reaching the standard.

本实施例首先对调节池进行功能优化改造,将其隔分成三格,并通过增加相应的曝气设备而使其形成缺氧—好氧—缺氧的功能模式。第一格尺寸长×宽=36m×25m,调节池第二、三格尺寸长×宽=12m×25m。在第二格内设置潜水型曝气机2台进行不间断曝气,单台作用范围5m,配电机功率3.7kW。在第三格池底设置污泥泵1台(流量12.5m3/h,扬程9m,配电机功率0.75kW),定期排泥,并设置提升泵1台(流量12.5m3/h,扬程20m,配电机功率2kW),将渗滤液输送至SBR反应器。In this embodiment, firstly, the adjustment tank is functionally optimized, divided into three compartments, and a function mode of anoxic-aerobic-anoxic is formed by adding corresponding aeration equipment. The first grid size length * width = 36m * 25m, the second and third grid dimensions of the adjustment pool are length * width = 12m * 25m. In the second cell, two submersible aerators are installed for uninterrupted aeration, with a range of 5m and a motor power of 3.7kW. Set up one sludge pump (flow rate: 12.5m 3 /h, lift: 9m, power distribution motor: 0.75kW) at the bottom of the third cell for regular sludge discharge, and set up a lift pump (flow rate: 12.5m3 /h, lift: 20m, distribution motor power 2kW), the leachate is transported to the SBR reactor.

本实施例在新建填埋区增设渗滤液回灌系统,构建方式及回灌方式同实施例1。In this embodiment, a leachate recharge system is added to the newly built landfill area, and the construction method and recharge method are the same as those in Embodiment 1.

本实施例已经进行最终覆盖的填埋场面积大约为20000m2,直接利用填埋场最终覆盖层的场地构建人工湿地,构建方式同实施例1。SBR反应器的出水作为人工湿地系统的进水。In this embodiment, the area of the landfill that has been finally covered is about 20,000 m 2 , and the site of the final covering layer of the landfill is directly used to construct the artificial wetland, and the construction method is the same as in Embodiment 1. The effluent of the SBR reactor is used as the influent of the constructed wetland system.

本实施例人工湿地最终出水水质指标达到国家《生活垃圾填埋场污染控制标准》(GB16889-1997)一级排放标准。The water quality index of the final effluent from the constructed wetland in this embodiment has reached the first-level discharge standard of the national "Standards for Pollution Control of Domestic Garbage Landfill Sites" (GB16889-1997).

Claims (10)

1, the leachate processing method of a kind of circulated backfilling and artificial swamp coupling is characterized in that may further comprise the steps:
A. make percolate remove bigger suspended substance and the foreign material of part particle diameter through grille well;
B. the percolate with above-mentioned treated mistake concentrates on a part of grains of sand of removal and suspended substance in equalizing tank first lattice;
C. make that a part of percolate recharges to refuse landfill by the leachate recirculation system in above-mentioned equalizing tank first lattice, pouring into artificial wet land system after the pre-treatment of another part through equalizing tank second lattice and equalizing tank the 3rd lattice handles, water outlet back up to standard discharging, the total residence time of sewage in equalizing tank is 15~30 days.
2,, it is characterized in that described percolate recharges to the concrete steps of refuse landfill by the leachate recirculation system and be according to the leachate processing method of described a kind of circulated backfilling of claim 1 and artificial swamp coupling:
1) with the leachate recirculation lift pump percolate in equalizing tank first lattice is promoted to the cloth water plant;
2) will in the percolate in the above-mentioned cloth water plant input inverted well and by the ditch that recharges of inverted well both sides it be recharged to refuse landfill by high density polyethylene pipe;
3) the leachate collection pipeline bottom landfill yard is concentrated to equalizing tank with the percolate of above-mentioned refuse landfill, and recharging frequency is 1~2 time/d, and recharging hydraulic load is 0.01~0.1m 3/ m 2.d.
3, according to the leachate processing method of claim 1 or 2 described a kind of circulated backfillings and artificial swamp coupling, it is characterized in that the described equalizing tank second lattice pond at the bottom of the submerged type aerator carry out uninterrupted aeration, separate unit sphere of action 4~8m; The regular spoil disposal of sludge pump that is provided with at the bottom of the 3rd lattice pond, lift pump is delivered to percolate the distributing well of artificial wet land system at the bottom of the 3rd lattice pond.
4, according to the leachate processing method of claim 1 or 2 described a kind of circulated backfillings and artificial swamp coupling, it is characterized in that described artificial wet land system unit hydraulic detention time 6~12 hours; When temperature on average is higher than 15 ℃, hydraulic load 10~15L/m 2.d; During 4~15 ℃ of temperature on average, hydraulic load 5~10L/m 2.d; When temperature on average is lower than 4 ℃ or when daily rainfall is 4~15mm, hydraulic load 3~5L/m 2.d; When daily rainfall during, stop into water greater than 15mm.
5, a kind of percolate treatment facility of realizing the described method of claim 1, it is characterized in that comprising grille well, place grille well equalizing tank, circulated backfilling system and artificial wet land system afterwards, equalizing tank is become three lattice by function optimization, form anoxic-aerobic-anoxybiotic functional mode, establish one of rotary type grid in the grille well, the grille well water outlet directly links to each other with first lattice of equalizing tank.
6, percolate treatment facility according to claim 5, it is characterized in that, the described equalizing tank first lattice useful volume is 60%~80% of the total useful volume of equalizing tank, second lattice are identical with the 3rd lattice useful volume, one of leachate recirculation lift pump is set in first lattice, 1~4 submerged type aerator is set at the bottom of the second lattice pond, one of sludge pump and lift pump is set at the bottom of the 3rd lattice pond.
7, according to claim 5 or 6 described percolate treatment facilities, it is characterized in that, inverted well that described circulated backfilling system comprises the cloth water plant successively, link to each other with the cloth water plant by high density polyethylene pipe and inverted well both sides recharge ditch, every 40~50m inverted well is set, respectively establish one about inverted well and recharge ditch, its structure is: the centre be the perforation water distributing pipe, fill graded broken stone all around, on cover one deck compacting clay.
8, according to claim 5 or 6 described percolate treatment facilities, it is characterized in that, described artificial wet land system is divided into the artificial swamp unit of different shapes and area according to landform with it, connect according to actual needs between unit and the unit and in parallel, the artificial swamp element length is 20~50m, long: wide=1~3: 1, the distributing well water outlet links to each other with the unitary water distributor of artificial swamp, cover the thick polyethylene film of 0.1~0.5mm at the artificial swamp cell surface winter after wetland plant is withered, described wetland plant is an emergent.
9, percolate treatment facility according to claim 8, it is characterized in that, when the artificial swamp unit is positioned at the final tectum of landfill yard, directly utilize the final tectal place of landfill yard to make up the artificial swamp unit, more than waste layer, arrange respectively from bottom to top: clay seam, high density polyethylene(HDPE) anti seepage membrane sealing ply, synthetic materials water conservancy diversion layer, fill stratum, vegetable layer, front end is provided with the perforation water distributor in the artificial swamp unit; When the artificial swamp unit is positioned at beyond the landfill zone, at first carry out smooth to ground, lay sandstone water conservancy diversion layer then, be equipped with the perforation thrust-augmenting nozzle in this layer, cover clay seam on the sandstone water conservancy diversion layer, smooth back covers high density polyethylene(HDPE) anti seepage membrane sealing ply, is followed successively by sand stone layer, fill stratum and vegetable layer on the film, front end is provided with the perforation water distributor in the artificial swamp unit, and the perforation water distributor exceeds vegetable layer.
10, percolate treatment facility according to claim 9, when it is characterized in that described artificial swamp unit is positioned at the final tectum of landfill yard, thickness of clay soil is that 0.2~0.3m, high density polyethylene(HDPE) sealing ply thickness 〉=1mm, synthetic materials water conservancy diversion layer thickness are 0.2~0.3m, fill stratum thickness 〉=0.3m, vegetable layer thickness 〉=0.3m, perforation water distribution pipe range 3~5m, the perforation water distributor exceeds vegetable layer 0.3~0.6m; When described artificial swamp unit is positioned at beyond the landfill zone, the smooth gradient in ground is 1%~2%, sandstone water conservancy diversion layer thickness is 0.2m, and interval 10m lays a perforation water distributor in the sandstone diameter≤1cm, sandstone water conservancy diversion layer, clay bed thickness 0.2m on the sandstone water conservancy diversion layer, high density polyethylene(HDPE) anti seepage membrane sealing bed thickness 1mm, sandstone bed thickness 0.2m on the anti seepage membrane, fill stratum and vegetable layer thickness all are not less than 0.3m, the perforation water distributor is about 3~5m, and the perforation water distributor exceeds vegetable layer 0.3~0.6m.
CNB2006101367738A 2006-11-30 2006-11-30 A leachate treatment method and its facilities for combined use of circulating irrigation and constructed wetlands Expired - Fee Related CN100491275C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006101367738A CN100491275C (en) 2006-11-30 2006-11-30 A leachate treatment method and its facilities for combined use of circulating irrigation and constructed wetlands

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006101367738A CN100491275C (en) 2006-11-30 2006-11-30 A leachate treatment method and its facilities for combined use of circulating irrigation and constructed wetlands

Publications (2)

Publication Number Publication Date
CN1994940A true CN1994940A (en) 2007-07-11
CN100491275C CN100491275C (en) 2009-05-27

Family

ID=38250162

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006101367738A Expired - Fee Related CN100491275C (en) 2006-11-30 2006-11-30 A leachate treatment method and its facilities for combined use of circulating irrigation and constructed wetlands

Country Status (1)

Country Link
CN (1) CN100491275C (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101829674A (en) * 2010-05-19 2010-09-15 中南大学 Method and device for biochemically recharging and restoring polluted soils in chromium slag yard
CN101767877B (en) * 2010-01-13 2012-05-30 广西大学 Micro-aerobic recharge treatment method of landfill leachate membrane separation concentrate
CN104722562A (en) * 2015-03-13 2015-06-24 西南交通大学 Control process of aerobiotic bioreactor landfill site
CN109111056A (en) * 2018-10-12 2019-01-01 上海溪昌环境工程有限公司 A kind of innoxious terminal processing method of mature landfill leachate

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101767877B (en) * 2010-01-13 2012-05-30 广西大学 Micro-aerobic recharge treatment method of landfill leachate membrane separation concentrate
CN101829674A (en) * 2010-05-19 2010-09-15 中南大学 Method and device for biochemically recharging and restoring polluted soils in chromium slag yard
CN101829674B (en) * 2010-05-19 2011-08-10 中南大学 Method and device for biochemically recharging and restoring polluted soils in chromium slag yard
CN104722562A (en) * 2015-03-13 2015-06-24 西南交通大学 Control process of aerobiotic bioreactor landfill site
CN109111056A (en) * 2018-10-12 2019-01-01 上海溪昌环境工程有限公司 A kind of innoxious terminal processing method of mature landfill leachate

Also Published As

Publication number Publication date
CN100491275C (en) 2009-05-27

Similar Documents

Publication Publication Date Title
CN104773929B (en) Zero-valent iron/microorganism composite filtration wall purification system for domestic sewage in irrigation areas
CN101397178B (en) Livestock and poultry raising sewage disposal process and disposal system thereof
CN101973637B (en) River channel purification system for processing rural domestic sewage
CN100551850C (en) Composite ecological treatment method of sewage for artificial wet land and system thereof
CN203451288U (en) Compound ecological ditch for treating surface source sewage in village
CN103395930A (en) Ecological slope protection type sewage land infiltration system and ecological slope protection type sewage land infiltration method
CN100595169C (en) Ecological system for water purification and recover
CN202576154U (en) Complex ecological system for treating domestic wastewater of rural community
CN106830506A (en) A kind of intensified denitrification and dephosphorization biology delaying basin for being applied to sponge urban construction
CN104016542B (en) A kind of staged combined artificial wetland device for low-pollution water process
CN101955297A (en) Landscape-type composite artificial wetland treatment device for eutrophication water body and application thereof
CN101880105A (en) Composite flow manual-rapid infiltration ecological field
CN200974793Y (en) Sewage composite artificial marshland ecological treatment system
CN104058545A (en) A method for treating aquaculture sewage by combining biological carrier and ecological restoration technology
CN1935700A (en) Nutrient-rich river-lake water body and initial rainwater composite artificial wet land treating system
CN107487969A (en) One kind is early declined rainwater purification system
CN112142258B (en) Resource and standard treatment method for domestic sewage of villages and towns
CN102690013A (en) Vertical ecological greenhouse technology for decentralized domestic wastewater treatment and resource recovery
CN201770585U (en) Landscape type composite artificial wet land treatment device for eutrophication water bodies
CN104563266B (en) A kind of domestic sewage in rural areas by using high ridge irrigation of paddy fields regulator control system and method for construction thereof
CN108821510A (en) A kind of sponge wet land system
CN101585647A (en) Capillary tube compound sewage treatment device
CN100491275C (en) A leachate treatment method and its facilities for combined use of circulating irrigation and constructed wetlands
CN202148222U (en) Processing device for denitrification and phosphorous removal of high-load reciprocating type undercurrent artificial wetland
CN102605853B (en) Facility for ecologically treating and recycling rainwater in central business district and method therefor

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Hunan Well-Point Environmental Protection Technology Co., Ltd.

Assignor: Hunan University

Contract record no.: 2011430000030

Denomination of invention: Circulated backfilling and artificial wetland combined leachate processing method and its facility

Granted publication date: 20090527

License type: Exclusive License

Open date: 20070711

Record date: 20110401

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090527

Termination date: 20141130

EXPY Termination of patent right or utility model