CN1873168A - Technique for building biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site - Google Patents

Technique for building biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site Download PDF

Info

Publication number
CN1873168A
CN1873168A CNA2006100712247A CN200610071224A CN1873168A CN 1873168 A CN1873168 A CN 1873168A CN A2006100712247 A CNA2006100712247 A CN A2006100712247A CN 200610071224 A CN200610071224 A CN 200610071224A CN 1873168 A CN1873168 A CN 1873168A
Authority
CN
China
Prior art keywords
pond
concrete
top cover
casted
hydraulic pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2006100712247A
Other languages
Chinese (zh)
Other versions
CN100419065C (en
Inventor
孔德政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB2006100712247A priority Critical patent/CN100419065C/en
Publication of CN1873168A publication Critical patent/CN1873168A/en
Application granted granted Critical
Publication of CN100419065C publication Critical patent/CN100419065C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E50/00Technologies for the production of fuel of non-fossil origin
    • Y02E50/30Fuel from waste, e.g. synthetic alcohol or diesel

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Revetment (AREA)

Abstract

A process for preparing cast-in-place concrete methane pond of hydraulic type includes digging and forming soil model, depositing concrete to form pond wall and top cover, digging and removing off soil-model soil at material discharging-opening and pond core, depositing pond base concrete, carrying out pond internal sealing treatment with plastic film and erecting not water circulation pipe.

Description

The biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site build process
Technical field
The present invention relates to civil works, particularly relate to a kind of concrete marsh-gas pond build process.
Background technology
Biogas utilization is popularized gradually in the rural area, and the construction of biomass pool is similar, so builds and has but shown sizable difference in pond quality, cost input and application life: the brick mix structure of commonplace employing, build a 8m 3Biomass pool, generally cost 1500~1800 yuan, time-consuming taking a lot of work do not say, uses several Nian Houchang corrosion scaling and gas leak phenomenon to occur, has to build again; For the biomass pool building that adopts the whole concrete structure, though the problem of front brick mix structure has solved, but because the difference of construction technology, cost has increased substantially again, by dig pit usually, the traditional handicraft requirement of formwork, pouring, cover and maintenance, pond with top same volume is adjusted, and price cost has surpassed 2000 yuan, and the construction time is long.
Summary of the invention
At the problems referred to above, the present invention makes improvement from building pool process, has proposed some new processes, achieve the goal: ensure the quality of products with long prerequisite of life-span under, cost is descended significantly, and technology is simple, the time is also fast, practice shows, build a biomass pool with top same volume, expense drops to and is no more than 300 yuan, and the time can shift to an earlier date 3~5 days, the technical requirements of construction is low, and everybody can both operate.
Technology of the present invention is still followed the common practices of concrete constructions, include and fetch earth, formwork, water and put operation such as pipe, but mould therefor being native loose tool, is to take the ledge original soil after the fluting cast earlier to the sequence of construction of bay wall body, folder pad plastic sheeting in the groove of cast, cast back one-shot forming.Its concrete technical scheme is as follows:
(1) repair the shoveling loose tool: by the designing requirement unwrapping wire, this line is the surfaces externally and internally size of whole bay wall body, and sweathouse wherein is circular, and discharge room is square or circular; Soil in the sweathouse circle is taken peak position to bay wall downwards along object-line, stop backform and move back platform, dig the bottom, pond more always downwards; With the special-purpose shovel of strip spade, along the internal and external line of discharge room and the inside and outside radial line of sweathouse, do not contain the bonding surface at discharge room and sweathouse top, directly dig at the bottom of the design body of wall of discharge room dark; Repair groove and carry out the pad that native tire bed die is pushed up in the sphere pond, with all die face paving plastic sheetings.
(2) cast bay wall and top cover concrete:, prop up upright good auxiliary template by bay wall thickness at the bonding surface place of sweathouse and discharge room top cover; Wireway is fixed on the peak place of pond top cover,, places feed pipe over against discharge room; By the design proportion requirement, with cement, spun yarn with less than the blinding of 20mm diameter, blunge become reconciled after, closely knitly be poured into the combining in the face wall mould of sealing groove and discharging and sweathouse, then the pond top cover is watered one deck by bay wall thickness shop, note handling well top cover and body of wall bonding surface, repave next day and water one deck, add a cover plastic sheeting afterwards, the earthing maintenance.
(3) take the clay model of the discharging opening and the pond heart: treat that concrete setting can take this part soil on earth in 5~7 days, the fermentation vat bottom can be scraped out lower camber side, at the bottom of the compacting pond, carry out pond subsoil loose tool.
(4) cast pond base concrete: pre-buried three reinforcing bar hooks are poured into a mould the pond base concrete as fixedly adding the hot-water circulation pipe, and will suitably thicken with bay wall bonding surface place at the bottom of the pond.
(5) sealing in the pond: tear the inwall plastic sheeting off, brush several times with being mixed with a certain proportion of ferric trichloride cement paste.
(6) lay and add the hot-water circulation pipe: at the bottom of the plastic conduit dish is put in the pond, fix with the reinforcing bar hook, the two-port of pipe is thrown away by discharge room and connects circulating hot water.
Build process of the present invention, simple, the biomass pool that builds, cost is low, construction is fast, and profile is good, and the life-span is long, biomass pool than brick mix structure, can reduce investment outlay more than 60%, build the pond method than ordinary concrete and reduce investment outlay about 20%, and build pond speed fast 3~5 days, the metope one-shot forming does not have the decortication phenomenon.
Description of drawings
Accompanying drawing 1 is for repairing the signal of shoveling loose tool flow process;
Accompanying drawing 2 is bay wall and the signal of top cover concrete casting injection forming;
Accompanying drawing 3 builds up the back signal for biomass pool.
Among the figure, 1 for pressing the design unwrapping wire, and 2 for having taken Chi Ding and most of pond cubsoil, and 3 is the moulding soil loose tool after shovel digs bay wall soil, and 4 is the moulding bay wall of caping; 5 are the air guide tubule, and 6 is feed pipe, and 7 is the reinforcing bar hook, and 8 is the heat cycles pipe, and 9 is plastic sheeting.
The specific embodiment
The present invention is illustrated as example according to Fig. 3, specifically implements as follows:
The specification of biomass pool: fermentation vat is circular, diameter 240cm, and discharge room selects square, each 100cm of length and width, the total depth in pond is about 250cm, and bay wall thickness selects 8cm, the thick 15cm of top cover, at the bottom of the pond circular arc, suitably thicken with the bay wall junction at the bottom of the pond, the upper edge of bay wall is about 80cm far from ground, about the high 125cm of wall, wireway is contained in the centre of top cover, diameter 10mm, feed pipe be over against charging aperture, diameter 20~30cm, the straight cutting oblique cutting all can, make of sheet iron, the heat cycles pipe selects plastic conduit, and diameter is not limit, the length of spiraling 60~80m draws from discharging opening.
Construction technical requirement: carry out in proper order by foregoing concrete technical scheme requirement.Be filled into from 20cm place, top at the bay wall body, with the used concrete of top cover, need in concrete, to add a certain proportion of ferric trichloride, for guaranteeing the intensity of pond top cover, the top cover cast is carried out at twice, its final grouting needs to carry out after 24 hours in head time pouring, in addition also need be thicker at the charging aperture place, and the levelling press polish, cover one deck plastic foil, water seasoning, backfill after the initial set, the deposition of watering.Need join special-purpose stripe shape shovel spade during shoveling loose tool groove; All die faces are all wanted shaping and are attached plastic sheeting.

Claims (4)

1, a kind of biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site build process, include and fetch earth, formwork, water and put pipe, its essential characteristic is that mould therefor is native loose tool, sequence of construction is to take the ledge original soil after the fluting cast earlier, folder pad plastic sheeting in the groove of cast, pouring one-step forming, its concrete technical scheme is:
(1) repaiies the shoveling loose tool: by the designing requirement unwrapping wire, this line is the surfaces externally and internally size of whole bay wall body, soil in the sweathouse circle is taken peak position to bay wall downwards along object-line, stop backform and move back platform, dig the bottom, pond more always downwards, with the special-purpose shovel of strip spade, along the internal and external line of discharge room and the inside and outside radial line of sweathouse, directly dig downwards at the bottom of the design body of wall of discharge room deeply, finishing groove and carry out the pad that native tire bed die is pushed up in the sphere pond is with all die face paving plastic sheetings;
(2) cast bay wall and top cover concrete: at the bonding surface place of sweathouse and discharge room top cover, propped up auxiliary template by bay wall thickness, wireway is fixed on the peak place of pond top cover, over against discharge room, lay feed pipe, the concrete compaction that will become reconciled is poured into combining in the face wall mould of sealing groove and discharging and sweathouse;
(3) take the clay model of the discharging opening and the pond heart: treat to take after the concrete setting, and bottom, fermentation vat pond divided scrape out lower camber side, at the bottom of the compacting pond;
(4) cast pond base concrete: pre-buried three reinforcing bar hooks, cast pond base concrete, and will suitably thicken with bay wall bonding surface place at the bottom of the pond.
2, by the described biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site build process of claim 1, it is characterized in that described technology includes sealing in the pond, the inwall plastic sheeting is torn off, brush several times with being mixed with a certain proportion of ferric trichloride cement paste.
3, by the described biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site build process of claim 1, it is characterized in that described technology also comprises the placement heating pipe, at the bottom of the plastic conduit dish is put in the pond, fix with the reinforcing bar hook, the two-port of pipe is thrown away by discharge room and connects circulating hot water.
4, by the described biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site build process of claim 1, it is characterized in that described technology also comprises: the pond top cover reaches the used concrete of bay wall body with top cover junction, pond, need be added with a certain proportion of ferric trichloride.
CNB2006100712247A 2006-03-20 2006-03-20 Technique for building biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site Expired - Fee Related CN100419065C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006100712247A CN100419065C (en) 2006-03-20 2006-03-20 Technique for building biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006100712247A CN100419065C (en) 2006-03-20 2006-03-20 Technique for building biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site

Publications (2)

Publication Number Publication Date
CN1873168A true CN1873168A (en) 2006-12-06
CN100419065C CN100419065C (en) 2008-09-17

Family

ID=37483752

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006100712247A Expired - Fee Related CN100419065C (en) 2006-03-20 2006-03-20 Technique for building biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site

Country Status (1)

Country Link
CN (1) CN100419065C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100425787C (en) * 2007-06-29 2008-10-15 四川大学 Cement mortar free simple agricultural pond

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2217627Y (en) * 1994-10-05 1996-01-17 潘家俊 Water-pressure type methane-storage room of methane-generating pit and methane-generating pit thereof
CN2518855Y (en) * 2001-12-26 2002-10-30 吴世邦 Wood mould of concrete methane tank
CN1661003A (en) * 2005-01-04 2005-08-31 张金兰 Combination of triad materials in use for biomass pool for water and gas leak protection in pool body

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100425787C (en) * 2007-06-29 2008-10-15 四川大学 Cement mortar free simple agricultural pond

Also Published As

Publication number Publication date
CN100419065C (en) 2008-09-17

Similar Documents

Publication Publication Date Title
CN107130633A (en) A kind of steel tube concrete clay model bag stake is combined soil-baffling structure construction technology
CN208219694U (en) A kind of prefabricated barricade
CN202936768U (en) Prefabricated drainage ditch
CN108277777A (en) Wave wall substep pouring construction process
CN107191006A (en) A kind of guiding gutter refractory concrete soil layer removes restorative procedure
CN206189279U (en) Structure is assembled with bent cap to stand
CN105822068B (en) Ultralong thin walled concrete walls under hot environment pour and maintenance process
CN100419065C (en) Technique for building biomass pool in hydraulic pressure typed whole concrete with discharge port in bottom layer, casted on site
CN101949273A (en) Method for plugging spring opening in drilling
CN203741792U (en) Concrete tooth groove stilling basin
CN102953359B (en) Method for constructing covered channel through efficient water-saving cast-in-place irrigation and drainage
CN210066782U (en) Soil slope drainage structure
CN103171052B (en) The disposable prefabricated construction engineering method of twin columns wave-breaking body
CN109763399A (en) A kind of one body swimming ditch construction mould and construction method
CN107443548A (en) A kind of production method of water channel gool prefabricated component
CN107471424A (en) A kind of water channel engineering system and construction method
CN204875418U (en) Water permeability road surface structure
CN101550690B (en) Triangular concrete thin-wall folded plate pile and preparation method thereof
CN201411684Y (en) Triangular concrete thin-walled folded sheet pile
CN109235456A (en) A kind of foundation pit enclosure structure and construction method
CN111236170A (en) Quick construction method for buried rock concrete gravity dam
CN211472539U (en) Foundation pit drainage system combining waterproof sleeve with concealed conduit
CN2913450Y (en) U-shaped flume soil placenta dies
CN212670579U (en) Non-socketed wallboard bottom grouting device
CN110424439A (en) A kind of precast ceramsite concrete cored slab sizing fetal membrane and its construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080917