CN1847617A - Construction process of pushing in long and large box culvert under taxiway in airport - Google Patents

Construction process of pushing in long and large box culvert under taxiway in airport Download PDF

Info

Publication number
CN1847617A
CN1847617A CN 200610078375 CN200610078375A CN1847617A CN 1847617 A CN1847617 A CN 1847617A CN 200610078375 CN200610078375 CN 200610078375 CN 200610078375 A CN200610078375 A CN 200610078375A CN 1847617 A CN1847617 A CN 1847617A
Authority
CN
China
Prior art keywords
box culvert
taxiway
long
pushing
construction process
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200610078375
Other languages
Chinese (zh)
Other versions
CN100554643C (en
Inventor
陈佑新
张晓峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CNB2006100783755A priority Critical patent/CN100554643C/en
Publication of CN1847617A publication Critical patent/CN1847617A/en
Application granted granted Critical
Publication of CN100554643C publication Critical patent/CN100554643C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The construction process of pushing in long and large box culvert under taxiway in airport includes top supporting with steel pipes of 325 mm diameter and pushing in box culvert, and features that it also includes digging small guide holes below the box culvert and controlling the subsidence in taxiway. The present invention can ensure the normal taking off, landing and rolling of airplane during construction and has high engineering precision and low cost.

Description

Construction process of pushing in long and large box culvert under taxiway in airport
Technical field
The invention belongs to field of civil engineering, particularly relate to construction technology at underground jacking long and large box culvert.
Background technology
Beijing Capital International Airport west runway is the main runway of international flight landing; the L taxiway that connects western runway and No. four aprons and No. 2 terminal aprons is one of the busiest taxiway in airport; it is many to slide sortie; heavy traffic; it not only bears sliding of aircraft, also is that the slideway that transportation between goods yard, North Area and 1, No. 2 terminal must usual friendship be crossed is transferred in the shipping of South Area, airport CA.Because lorry comes and goes and all will give in to each other with the aircraft that slides, often cause a lot of flights to stop sliding, waiting in line.This situation not only influences normally taking off of flight and causes a large amount of goods to overstock, and brings enormous economic loss to the airport, and what is more important has a strong impact on the flight Normal Take-Off And Landing and slides safety, influences international image.
Present domestic underground construction circle, the pipe canopy of employing are propped up to expand and mostly are ф 159mm pipe, and length only about 60m, is applicable to the pure bored tunnel of little span.If use the above steel pipe of ф 325mm once to squeeze into, length does not have above 100 meters, and low precision." airport news " " airport grade separation acceptance on examination obtains good " that publish in June, 2004, introduced in the grade separation engineering of airport, Xiamen in 2003 jacking seat frame bridge once, but this frame bridge is not worn the aircraft slideway under not being, but wears Fu Shalu under the road of airport, is the part of Fuzhou-Xiamen road training works." transport science and techonologies " 2004 the 4th phases, to have introduced in " Jacking Technique of High-Aperture Pipe Shed Support research " under the lineman's journey of railway suburbs, Guangzhou-Shenzhen railway and worn Shenzhen-Guangzhou superhighway, the pipe shed support greater than 400mm caliber, long 78m has been adopted in the crest enters box culvert construction.Domestic still do not have under the condition of not suspending, and builds up the precedent in tunnel under runway.
Summary of the invention
The technical issues that need to address of the present invention are: a kind of construction process of pushing in long and large box culvert under taxiway in airport is provided, can guarantee that aircraft constructs under the condition of not suspending, ensure the flight Normal Take-Off And Landing and slide safety, prevent to prick head, fine solution butt joint problem, engineering precision height, cost are low.
Technical solution of the present invention is: construction process of pushing in long and large box culvert under taxiway in airport, comprise pre-timbering with tubular prop, crest enters box culvert, it is characterized in that: further comprising in the box culvert bottom and dug little pilot tunnel and road face settlement Control technology, described pre-timbering with tubular prop adopts the supporting of diameter ф 325mm steel pipe.
The present invention compared with prior art has following advantage: 1, little pilot tunnel builds up, at first verify the top and contained front of tunnel heading geology, the pre-supporting of face provides foundation during for jacking, next has reduced in the soil and has seeped water, behind the soil body discharging consolidation, intensity increases substantially, face stability strengthens, the most important thing is to contain the suitable chute surface in the end advances, thoroughly solved a problem of pricking, merging precision is far above code requirement, the discrepancy in elevation<20mm of the present invention, left-right deviation is within 50mm, and settlement Control does/one three.2, the pre-timbering with tubular prop technology of growing up adopts ф 325mm, L=148m, engineering precision 24cm.3, box culvert jacking in soil, total frictional resistance equals following 5 sums, promptly contains upper and lower, left and right face pressure and takes advantage of scholar's body friction factor to add the frontal drag of sword pin.This engineering is contained the top buried depth and is reached 6m, and the pressure of such 4 faces is just very big, more than 20,000 ton of total top power, more rare at home, box culvert top easily splits, and back also may push up race, the present invention selects a kind of daily output chemical grout for use, it is constant for a long time that its better performances, Main Feature are that viscosity can keep, and meets underground water and do not decompose, in the scholar, do not permeate, drying shrinkage knot is hard, and box culvert is not by locking when resetting more than 3 months stopping to tunnel more than several days total pushing tow time to have guaranteed box culvert.The mud resistance-reducing efficiency reaches 60%-80%, and two joint culverts one are pushed up simultaneously and needed more than 8000 ton top power, are kept to more than 2400 ton, for smooth jacking successfully provides prerequisite.4, the aircraft taxi load reaches 4000kN, much larger than railway or highway load, thereby the security protection requirement is higher, and box culvert shallow embedding (the tunneling buried depth is 2.7m only), the long 142m of top journey, the jacking of not suspending, pavement slab does not have faulting of slab ends, road face sedimentation curvature ≯ 1/3000, sedimentation ≯ 30mm, little to the influence of surface structures facilities such as airport, thoroughly solve freight and cross the L taxiway interference of aircraft Normal Take-Off And Landing and safety problem, increase substantially shipping efficient.5, cost is low, and method is simple, remarkable in economical benefits, and every cavitation rice is 90,000 yuan, and adopts tunneling to be about 120,000 yuan, every cavitation rice is saved 30,000 yuan, saves 4,400,000 yuan altogether.
Specific embodiments
Describe embodiments of the invention below in detail.
Empty side line road engineering, pushing in long and large box culvert under taxiway in airport engineering length is 148m, width is 13.7m, height is 6.45m, is designed to diplopore 6m rectangle box culvert, adopts relay well method jacking construction, the chemical mud pit body lubrication drag reduction of Japan, little pilot tunnel control is pricked head and is come back.
1, the bassoon canopy protects the top pre-supporting technology in advance.
During the box culvert jacking, the front edge pin is subjected to rigidity control and box culvert to prick head to be influenced, can not design oversizely, 2.5m only, and the high 6.5m of soil body face, press lam angle of friction 11 degree angles from containing the end, after calculating the soil body plane of fracture, ten meters thick soil body slump districts will be arranged at box culvert front end face and top, the pipe shed support that present domestic underground construction circle adopts mostly is ф 159mm pipe, and length only is about 60m, is applicable to the pure bored tunnel of little span, the long 148m of this engineering, the disposable ф 325mm pipe canopy beyond example still at home of getting through.
The present invention adopts wireless signal remote control to survey and receives and the emission instrument, record three-dimensional coordinate and the attitude angle of drill bit in soil of Directing Station, make the guiding sole at drill bit place to theory orientation deflection by rotation, thereafter give the drilling rod applied thrust, make it to advance, thereby finish the pilot hole of long 148m along the correction of guide strip bevel direction.
After utilizing the interior drill rod end of pilot hole to install the enlarged footing of band jetting cutting soil additional, pilot hole is extended to about 350mm, with the mud cover hole wall is protected simultaneously.After finishing reaming, draw with drilling rod, with ф 325mm diameter, the steel pipe of thick 10mm, after progressively weldering connected, being used as power with large-scale hauling pipe rig was dragged to the other end with steel pipe from Kong Yiduan.Afterwards measurement and positioning errorless after, in pipe, pump into the C25 concrete, form the beam on the elastic foundation in the soil, canopy is firmly contained the front end certain limit top soil body, effectively prevents landslide.
2, little pilot tunnel and glide path technology
Bundle in a box culvert jack-in process phenomenon is difficult to avoid, and domestic engineering circle is headache for this reason always, and so big box culvert on weak soil, is certain to prick head again, can't solve the butt joint problem in case prick head.The present invention adopts containing the end and digs a little pilot tunnel, and for the making slideway provides the space, little pilot tunnel is of a size of wide 1.3m * high 1.9m, periphery with linked network spray 10cm, thick C20 concrete is a supporting and protection structure, by a Pin bow member, to be that ф 50mm steel pipe is curved be welded into bow member every 0.5m.
At the bottom of little pilot tunnel, lay 3 I20 i iron, by the gradient mix up, leveling, fixing with the support welding, the slideway of pumping C20 concrete pouring bar shaped thereafter, size 1.0m is wide * 0.6m is thick, the i iron end face flushes with the concrete end face, thereby slideway formation.In the box culvert jack-in process, little pilot tunnel supporting and protection structure is abolished with excavator.
3, chemical slurry lubrication technology
Box culvert is jacking in soil, and total frictional resistance equals following 5 sums, promptly contains upper and lower, left and right face pressure and takes advantage of soil body friction factor to add the frontal drag of sword pin.Use daily output chemical grout better performances, it is constant for a long time that Main Feature is that viscosity can keep, and chance underground water does not decompose, in soil, do not permeate, drying shrinkage knot is hard, guarantee box culvert stop to tunnel more than several days, total pushing tow time, box culvert was not by locking when resetting more than 3 months.
Stirring pumping is pressed by mud lubrication of the present invention system, and pumping pressure 0.15-0.4Mpa, pipeline are by house steward, branch diameter ф 40mm, and the slip casting one way valve is formed.
By spacing 3m, case end distance 1.5m place's cloth pipeline and one way valve connect long ф 40 high-pressure rubber pipes of one section 5m at each relay well place of casing around the box culvert appearance, and branch road starting point end mounting ball valve is with flexible control slip casting position and grouting amount.
4, road face settlement Control technology
The road face is arranged net, and monitors sedimentation with precision level, monitors the tense sedimentation at each control point.The T-S curve is associated to putting distance L with containing end, draws T-S-L figure, to find out the position that needs slip casting, the contingent sedimentation value in prediction the place ahead.
The Comprehensive Control measure mainly contains in the hole: 1) native jacking, 2 are eaten in strictness) guarantee the two-edged pin side plate outside sky that do not collapse, 3) guarantee that face does not reveal the pipe canopy, reveals the landslip of sword pin, 4) contain the front end base plate and can not backbreak 5) slip casting pressure regulation and pressurize.
Pipe canopy stress, strain measurement, the anti-pipe canopy amount of deflection of asking.
Contain back of the body soil pressure measurement.
Local ground grouting and reinforcing anti-settling outside the road face.
5, tunneling of two-way jacking closure segment and joint treatment technology
A two-way position that closes up is chosen in beyond the taxiway, beyond the sliding limit vertical distance 10m of L, reduces like this slideway settlement influence, and is stressed also safer.
Sword pin spacing 3-5m is advisable, and mainly considers the influence of an end pushing tow to the other end, and when connecting soon, the other end face soil body can cave in, and is dangerous.
Sword pin steel plate is not dismantled, and still plays the effect of retaining soil.The vertical distribution reinforcement ф 16 of box culvert, ф 20 adopt boring bar planting technology to connect.Box culvert hoop steel bar stress, because its broken end will cut length 10d in oblique triangle sword pin concrete, about 30cm scope adopts overlap welding to connect.Waterproofing course will be attached to sword pin steel plate inboard, two ends, carries out and hands over circle, will glue the square chance freight of 50 * 50mm account sealing rod at culvert plate end face.
Principal rod colligation order: outer earlier, internal layer again, back envelope template.
Locate to irritate concrete from low to high, press lift-up method to build concrete with the bottom-up band of concrete pump line.Establish exhaust, plasma discharge mouth at highest point.
Select large fluidity for use, high-strength self-compacting concrete.Irritate when concrete seals arch at last and want slow, pump once stops, treats that air water arranged, and the concrete of emerging is starched to filling.Pre-buried madjack pipe, back ftercompction cement paste.
6, box culvert relay well and joint waterproofing
The every joint of the present invention is contained long 15m, and the place has established relay well and risen nest at every joint seam, and first joint must be established relay well, and other can establish one group of relay well by 2 joints, and to reduce seam, the culvert joint is long also to be adjustable to about 20m.
The internode waterproof: adopt the diameter at internode extruding ф 80mm, thick 1.5cm rubber tube is aided with joint filling cream grouting for water blocking later on again.

Claims (6)

1, construction process of pushing in long and large box culvert under taxiway in airport comprises pre-timbering with tubular prop, crest enters box culvert, it is characterized in that: further comprising in the box culvert bottom to have dug little pilot tunnel and road face settlement Control technology, and described pre-timbering with tubular prop adopts the supporting of diameter ф 325mm steel pipe.
2, construction process of pushing in long and large box culvert under taxiway in airport according to claim 1, it is characterized in that: at the bottom of little pilot tunnel, lay 3 No. 120 i iron, by the gradient mix up, leveling, fixing with the support welding, thereafter pumping C20 concrete pouring bar shaped slideway, the i iron end face flushes with the concrete end face.
3, construction process of pushing in long and large box culvert under taxiway in airport according to claim 1 and 2 it is characterized in that: further comprising mud and falls the resistance technology, adopts the daily output chemical grout.
4, construction process of pushing in long and large box culvert under taxiway in airport according to claim 3 is characterized in that: described road face settlement Control technology comprises:
The road face is arranged net, and monitors sedimentation with precision level, and the T-S curve is associated to putting distance L with containing end, draws T-S-L figure, finds out the position that needs slip casting, the contingent sedimentation value in prediction the place ahead;
The Comprehensive Control measure mainly contains in the hole: native jacking is eaten in strictness; Guarantee the two-edged pin side plate outside sky that do not collapse; Guarantee area and do not reveal the landslip of managing canopy, revealing the sword pin; Containing the front end base plate does not backbreak; Slip casting pressure regulation and pressurize;
Pipe canopy stress, strain measurement, the anti-pipe canopy amount of deflection of asking;
Contain back of the body soil pressure measurement;
Local ground grouting and reinforcing anti-settling outside the road face.
5, construction process of pushing in long and large box culvert under taxiway in airport according to claim 1 it is characterized in that: further comprising tunneling of two-way jacking closure segment and joint treatment technology:
A two-way position that closes up is chosen in beyond the taxiway, beyond the sliding limit vertical distance 10m of L;
Sword pin spacing 3-5m;
Sword pin steel plate is not dismantled, and the vertical distribution reinforcement ф 16 of box culvert, ф 20 adopt boring bar planting technology to connect, and box culvert hoop steel bar stress cuts length 10d, and about 30cm scope adopts overlap welding to connect;
Waterproofing course will be attached to sword pin steel plate inboard, two ends, carries out and hands over circle, will glue the square chance freight of 50 * 50mm account sealing rod at culvert plate end face;
Principal rod colligation order: outer earlier, internal layer again, back envelope template;
Locate to irritate concrete from low to high, press lift-up method to build concrete, establish exhaust, plasma discharge mouth at highest point with the bottom-up band of concrete pump line.
6, construction process of pushing in long and large box culvert under taxiway in airport according to claim 1 it is characterized in that: further comprising box culvert relay well and joint waterproofing:
Every joint is contained long 15m, and the place has established relay well and risen nest at every joint seam, and first joint must be established relay well, and other can establish one group of relay well by 2 joints, and the box culvert joint is long also to be adjustable to about 20m;
The internode waterproof: adopt the diameter at internode extruding ф 80mm, thick 1.5cm rubber tube is aided with joint filling cream grouting for water blocking later on again.
CNB2006100783755A 2006-05-17 2006-05-17 Construction process of pushing in long and large box culvert under taxiway in airport Expired - Fee Related CN100554643C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006100783755A CN100554643C (en) 2006-05-17 2006-05-17 Construction process of pushing in long and large box culvert under taxiway in airport

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006100783755A CN100554643C (en) 2006-05-17 2006-05-17 Construction process of pushing in long and large box culvert under taxiway in airport

Publications (2)

Publication Number Publication Date
CN1847617A true CN1847617A (en) 2006-10-18
CN100554643C CN100554643C (en) 2009-10-28

Family

ID=37077324

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006100783755A Expired - Fee Related CN100554643C (en) 2006-05-17 2006-05-17 Construction process of pushing in long and large box culvert under taxiway in airport

Country Status (1)

Country Link
CN (1) CN100554643C (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071945A (en) * 2010-12-29 2011-05-25 上海隧道工程股份有限公司 Method for driving-in and driving-out construction in built structure closed in three sides for shield
CN103015335A (en) * 2012-12-28 2013-04-03 中铁二十四局集团有限公司 Pre-penetrating limiting beam jacking method
CN106337373A (en) * 2015-07-13 2017-01-18 中铁第六勘察设计院集团有限公司 Construction method for oblique through existing line overhead jacking box culvert and pipe joint structure applying the same
CN107419741A (en) * 2017-07-04 2017-12-01 中铁上海设计院集团有限公司 A kind of slideway structure and its construction method for preventing jacking case body off normal

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071945A (en) * 2010-12-29 2011-05-25 上海隧道工程股份有限公司 Method for driving-in and driving-out construction in built structure closed in three sides for shield
CN102071945B (en) * 2010-12-29 2012-11-28 上海隧道工程股份有限公司 Method for driving-in and driving-out construction in built structure closed in three sides for shield
CN103015335A (en) * 2012-12-28 2013-04-03 中铁二十四局集团有限公司 Pre-penetrating limiting beam jacking method
CN103015335B (en) * 2012-12-28 2015-07-01 中铁二十四局集团有限公司 Pre-penetrating limiting beam jacking method
CN106337373A (en) * 2015-07-13 2017-01-18 中铁第六勘察设计院集团有限公司 Construction method for oblique through existing line overhead jacking box culvert and pipe joint structure applying the same
CN106337373B (en) * 2015-07-13 2021-03-30 中铁第六勘察设计院集团有限公司 Construction method for obliquely penetrating existing line overhead jacking box culvert
CN107419741A (en) * 2017-07-04 2017-12-01 中铁上海设计院集团有限公司 A kind of slideway structure and its construction method for preventing jacking case body off normal
CN107419741B (en) * 2017-07-04 2023-04-18 中铁上海设计院集团有限公司 Slideway structure for preventing jacking box body from deviating and construction method thereof

Also Published As

Publication number Publication date
CN100554643C (en) 2009-10-28

Similar Documents

Publication Publication Date Title
CN107060796B (en) It is a kind of to use Slurry Balanced Pipe Jacking Construction technique
CN102080548B (en) Construction method of tunnel to cross airport runway by shield method
CN109372532A (en) Jacking construction engineering method under multiplexed address environment
CN108868778A (en) A kind of Large Underground Structure no-dig technique construction method
CN105240019A (en) Pipe jacking construction method
CN109594990B (en) Large-section jacking pipe construction method for complex stratum
CN104265307A (en) Non-uniform-hardness stratum earth pressure balance shield tunnel underpassing railway existing line construction method
CN1215276C (en) Earth pressure balancing technology for laying rectangular top pipe
CN104343455A (en) Long-distance curved jacking pipe and pipe roof construction technique
CN209924998U (en) Shallow earthing shield tunnel is worn road reinforcement protection architecture down
CN103711492B (en) A kind of jacking-type cable sleeve channel construction method
CN102400694A (en) Reinforcement method for combined part of shield tunnel and mining-method tunnel
CN104847375B (en) A kind of small interval Four-Lane Road Shallow-buried Large-span Tunnel method for protecting support
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN109763828A (en) Push-bench tunneling construction method
CN104847365B (en) A kind of small interval Four-Lane Road Shallow-buried Large-span Tunnel construction method
CN100554643C (en) Construction process of pushing in long and large box culvert under taxiway in airport
CN105065037A (en) Double-layer arch center support construction method for highway soft rock tunnel
CN109667603A (en) A kind of super shallow-buried tunnel structure and construction method
CN109296371A (en) MJS method and horizontal freezing joint reinforcement pressure-bearing rich water arenaceous stratum overlap the system and its construction method that section is worn under station
CN109611103A (en) A method of for boulder group consolidation process outstanding on shield section
CN109555548A (en) A kind of supporting construction that high-ground stress Support System in Soft Rock Tunnels is formed using overlength enlarged footing anchor cable
CN103855650A (en) Special construction method by utilizing electricity jacking pipe
CN112983456A (en) Water-rich sand layer multi-row pipe jacking surface deformation control method
CN206888992U (en) A kind of water-bed mine shield tunnel combination docking structure form

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: BEIJING ENGINEERING COMPANY LIMITED OF CHINA RAILW

Effective date: 20150416

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150416

Address after: 100018 Beijing city Chaoyang District No. 2 North Pine dam Park

Patentee after: China Railway Construction Engineering Bureau No.16 Group Corp., Ltd.

Patentee after: BEIJING ENGINEERING COMPANY LIMITED OF CHINA RAILWAY URBAN CONSTRUCTION GROUP

Address before: 100018 Beijing city Chaoyang District No. 2 North Pine dam Park

Patentee before: China Railway Construction Engineering Bureau No.16 Group Corp., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091028

Termination date: 20210517

CF01 Termination of patent right due to non-payment of annual fee