CN100554643C - Construction process of pushing in long and large box culvert under taxiway in airport - Google Patents

Construction process of pushing in long and large box culvert under taxiway in airport Download PDF

Info

Publication number
CN100554643C
CN100554643C CNB2006100783755A CN200610078375A CN100554643C CN 100554643 C CN100554643 C CN 100554643C CN B2006100783755 A CNB2006100783755 A CN B2006100783755A CN 200610078375 A CN200610078375 A CN 200610078375A CN 100554643 C CN100554643 C CN 100554643C
Authority
CN
China
Prior art keywords
box culvert
face
soil
long
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2006100783755A
Other languages
Chinese (zh)
Other versions
CN1847617A (en
Inventor
陈佑新
张晓峰
马栋
郭秀琴
付梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CNB2006100783755A priority Critical patent/CN100554643C/en
Publication of CN1847617A publication Critical patent/CN1847617A/en
Application granted granted Critical
Publication of CN100554643C publication Critical patent/CN100554643C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Construction process of pushing in long and large box culvert under taxiway in airport, comprise little pilot tunnel laying, pre-timbering with tubular prop, crest enters box culvert and road face settlement Control technology, it is characterized in that: described little pilot tunnel is positioned at the box culvert bottom, by the gradient mix up, leveling, thereafter pumping C20 concrete pouring bar shaped slideway, in the top culvert process, little pilot tunnel is abolished with excavator; Described pre-timbering with tubular prop process using: wireless signal remote control is surveyed and is received and the emission instrument, record directed three-dimensional coordinate and the attitude angle of drill bit in soil of boring, finish the pilot hole of long 148m, after utilizing the interior drill rod end of pilot hole to install the enlarged footing of band jetting cutting soil additional, pilot hole is extended to about 350mm; Described road face settlement Control technology comprises: the road face is arranged net, the contingent sedimentation value in prediction the place ahead; Comprehensive Control measure in the hole.The present invention can guarantee that aircraft constructs under the condition of not suspending, ensure the flight Normal Take-Off And Landing and slide safety, prevents to prick head, fine solution butt joint problem, and engineering precision height, cost are low.

Description

Construction process of pushing in long and large box culvert under taxiway in airport
Technical field
The invention belongs to field of civil engineering, particularly relate to construction technology at underground jacking long and large box culvert.
Background technology
Beijing Capital International Airport west runway is the main runway of international flight landing; the L taxiway that connects western runway and No. four aprons and No. 2 terminal aprons is one of the busiest taxiway in airport; it is many to slide sortie; heavy traffic; it not only bears sliding of aircraft, also is that the slideway that transportation between goods yard, North Area and 1, No. 2 terminal must usual friendship be crossed is transferred in the shipping of South Area, airport CA.Because lorry comes and goes and all will give in to each other with the aircraft that slides, often cause a lot of flights to stop sliding, waiting in line.This situation not only influences normally taking off of flight and causes a large amount of goods to overstock, and brings enormous economic loss to the airport, and what is more important has a strong impact on the flight Normal Take-Off And Landing and slides safety, influences international image.
Present domestic underground construction circle, the pipe shed support of employing mostly are φ 159mm pipe, and length only about 60m, is applicable to the pure bored tunnel of little span.If use the above steel pipe of φ 325mm once to squeeze into, length does not have above 100 meters, and low precision." airport news " " airport grade separation acceptance on examination obtains good " that publish in June, 2004, introduced in the grade separation engineering of airport, Xiamen in 2003 jacking seat frame bridge once, but this frame bridge is not worn the aircraft slideway under not being, but wears Fu Shalu under the road of airport, is the part of Fuzhou-Xiamen road training works." transport science and techonologies " 2004 the 4th phases, to have introduced in " Jacking Technique of High-Aperture Pipe Shed Support research " under the lineman's journey of railway suburbs, Guangzhou-Shenzhen railway and worn Shenzhen-Guangzhou superhighway, the pipe shed support greater than 400mm caliber, long 78m has been adopted in the crest enters box culvert construction.Domestic still do not have under the condition of not suspending, and builds up the precedent in tunnel under runway.
Summary of the invention
The technical issues that need to address of the present invention are: a kind of construction process of pushing in long and large box culvert under taxiway in airport is provided, can guarantee that aircraft constructs under the condition of not suspending, ensure the flight Normal Take-Off And Landing and slide safety, prevent to prick head, fine solution butt joint problem, engineering precision height, cost are low.
Technical solution of the present invention is: construction process of pushing in long and large box culvert under taxiway in airport, comprise little pilot tunnel laying, pre-timbering with tubular prop, crest enters box culvert and road face settlement Control technology, it is characterized in that: described little pilot tunnel is positioned at the box culvert bottom, some I20 i iron are laid at the end of little pilot tunnel, by the gradient mix up, leveling, fixing with the support welding, thereafter pumping C20 concrete pouring bar shaped slideway, the i iron end face flushes with the concrete end face, in the box culvert jack-in process, with excavator little pilot tunnel is abolished; Described pre-timbering with tubular prop process using: wireless signal remote control is surveyed and is received and the emission instrument, record directed three-dimensional coordinate and the attitude angle of drill bit in soil of boring, make the guiding sole at drill bit place to theory orientation deflection by rotation, thereafter give the drilling rod applied thrust, make it to advance along the correction of guide strip bevel direction, thereby finish the pilot hole of long 148m, after utilizing the interior drill rod end of pilot hole to install the enlarged footing of band jetting cutting soil additional, pilot hole is extended to about 350mm, with the mud cover hole wall is protected simultaneously, finish reaming after, draw with drilling rod, with φ 325mm diameter, the steel pipe of thick 10mm is after progressively weldering connects, be used as power with large-scale hauling pipe rig steel pipe is dragged to the other end from Kong Yiduan, afterwards measurement and positioning errorless after, in pipe, pump into the C25 concrete, form the beam on the elastic foundation in the soil; Described road face settlement Control technology comprises: the road face is arranged net, and monitors sedimentation with precision level, and the T-S curve is associated to putting distance L with containing end, draws T-S-L figure, finds out the position that needs slip casting, the contingent sedimentation value in prediction the place ahead; The Comprehensive Control measure mainly contains in the hole: native jacking is eaten in strictness; Guarantee the two-edged pin side plate outside sky that do not collapse; Guarantee that face does not reveal the landslip of pipe canopy, dew sword pin; Containing the front end base plate does not backbreak; Slip casting pressure regulation and pressurize; Pipe canopy stress, strain measurement, the anti-pipe canopy amount of deflection of asking; Contain back of the body soil pressure measurement; Local ground grouting and reinforcing anti-settling outside the road face.
The present invention compared with prior art has following advantage: 1, little pilot tunnel builds up, at first verify the top and contained front of tunnel heading geology, the pre-supporting of face provides foundation during for jacking, next has reduced in the soil and has seeped water, behind the soil body discharging consolidation, intensity increases substantially, face stability strengthens, the most important thing is to contain the suitable chute surface in the end advances, thoroughly solved a problem of pricking, merging precision is far above code requirement, the discrepancy in elevation<20mm of the present invention, left-right deviation is within 50mm, and settlement Control is in three one thousandths.2, the pre-timbering with tubular prop technology of growing up adopts φ 325mm, L=148m, engineering precision 24cm.3, box culvert jacking in soil, total frictional resistance equals following 5 top sums, promptly contains upper and lower, left and right face pressure and takes advantage of soil body friction factor to add the frontal drag of sword pin.This engineering is contained the top buried depth and is reached 6m, and the pressure of such 4 faces is just very big, more than 20,000 ton of total top power, more rare at home, box culvert top easily splits, and back also may push up race, the present invention selects a kind of daily output chemical grout for use, it is constant for a long time that its better performances, Main Feature are that viscosity can keep, and meets underground water and do not decompose, in soil, do not permeate, drying shrinkage knot is hard, and box culvert is not by locking when resetting more than 3 months stopping to tunnel more than several days total pushing tow time to have guaranteed box culvert.The mud resistance-reducing efficiency reaches 60%-80%, and two joint culverts one are pushed up simultaneously and needed more than 8000 ton top power, are kept to more than 2400 ton, for smooth jacking successfully provides prerequisite.4, the aircraft taxi load reaches 4000kN, much larger than railway or highway load, thereby the security protection requirement is higher, and box culvert shallow embedding (the tunneling buried depth is 2.7m only), the long 142m of top journey, the jacking of not suspending, pavement slab does not have faulting of slab ends, road face sedimentation curvature ≯ 1/3000, sedimentation ≯ 30mm, little to the influence of surface structures facilities such as airport, thoroughly solve freight and cross the L taxiway interference of aircraft Normal Take-Off And Landing and safety problem, increase substantially shipping efficient.5, cost is low, and method is simple, remarkable in economical benefits, and every cavitation rice is 90,000 yuan, and adopts tunneling to be about 120,000 yuan, every cavitation rice is saved 30,000 yuan, saves 4,400,000 yuan altogether.
Specific embodiments
Describe embodiments of the invention below in detail.
Empty side line road engineering, pushing in long and large box culvert under taxiway in airport engineering length is 148m, width is 13.7m, height is 6.45m, is designed to diplopore 6m rectangle box culvert, adopts relay well method jacking construction, the chemical mud pit body lubrication drag reduction of Japan, little pilot tunnel control is pricked head and is come back.
1, the bassoon canopy protects the top in advance and pays nurse's skill in advance
During the box culvert jacking, the front edge pin is subjected to rigidity control and box culvert to prick head to be influenced, can not design oversizely, 2.5m only, and the high 6.5m of soil body face, press lam angle of friction 11 degree angles from containing the end, after calculating the soil body plane of fracture, ten meters thick soil body slump districts will be arranged at box culvert front end face and top, the pipe shed support that present domestic underground construction circle adopts mostly is φ 159mm pipe, and length only is about 60m, is applicable to the pure bored tunnel of little span, the long 148m of this engineering, the disposable φ 325mm pipe canopy beyond example still at home of getting through.
The present invention adopts wireless signal remote control to survey and receives and the emission instrument, record directed three-dimensional coordinate and the attitude angle of drill bit in soil of boring, make the guiding sole at drill bit place to theory orientation deflection by rotation, thereafter give the drilling rod applied thrust, make it to advance, thereby finish the pilot hole of long 148m along the correction of guide strip bevel direction.
After utilizing the interior drill rod end of pilot hole to install the enlarged footing of band jetting cutting soil additional, pilot hole is extended to about 350mm, with the mud cover hole wall is protected simultaneously.After finishing reaming, draw with drilling rod, with φ 325mm diameter, the steel pipe of thick 10mm, after progressively weldering connected, being used as power with large-scale hauling pipe rig was dragged to the other end with steel pipe from Kong Yiduan.Afterwards measurement and positioning errorless after, in pipe, pump into the C25 concrete, form the beam on the elastic foundation in the soil, canopy is firmly contained the front end certain limit top soil body, effectively prevents landslide.
2, little pilot tunnel and glide path technology
Bundle in a box culvert jack-in process phenomenon is difficult to avoid, and domestic engineering circle is headache for this reason always, and so big box culvert on weak soil, is certain to prick head again, can't solve the butt joint problem in case prick head.The present invention adopts containing the end and digs a little pilot tunnel, and for the making slideway provides the space, little pilot tunnel is of a size of wide 1.3m * high 1.9m, periphery with linked network spray 10cm, thick C20 concrete is a supporting and protection structure, by a Pin bow member, to be that φ 50mm steel pipe is curved be welded into bow member every 0.5m.
At the bottom of little pilot tunnel, lay 3 I20 i iron, by the gradient mix up, leveling, fixing with the support welding, the slideway of pumping C20 concrete pouring bar shaped thereafter, size 1.0m is wide * 0.6m is thick, the i iron end face flushes with the concrete end face, thereby slideway formation.In the box culvert jack-in process, little pilot tunnel supporting and protection structure is abolished with excavator.
3, chemical slurry lubricating process
Box culvert is jacking in soil, and total frictional resistance equals following 5 top sums, promptly contains upper and lower, left and right face pressure and takes advantage of soil body friction factor to add the frontal drag of sword pin.Use daily output chemical grout better performances, it is constant for a long time that Main Feature is that viscosity can keep, and chance underground water does not decompose, in soil, do not permeate, drying shrinkage knot is hard, guarantee box culvert stop to tunnel more than several days, total pushing tow time, box culvert was not by locking when resetting more than 3 months.
Stirring pumping is pressed by mud lubrication of the present invention system, and pumping pressure 0.15-0.4Mpa, pipeline are by house steward, branch diameter φ 40mm, and the slip casting one way valve is formed.
By spacing 3m, case end distance 1.5m place's cloth pipeline and one way valve connect long φ 40 high-pressure rubber pipes of one section 5m at each relay well place of casing around the box culvert appearance, and branch road starting point end mounting ball valve is with flexible control slip casting position and grouting amount.
4, road face settlement Control technology
The road face is arranged net, and monitors sedimentation with precision level, monitors the tense sedimentation at each control point.The T-S curve is associated to putting distance L with containing end, draws T-S-L figure, to find out the position that needs slip casting, the contingent sedimentation value in prediction the place ahead.
The Comprehensive Control measure mainly contains in the hole: 1) native jacking, 2 are eaten in strictness) guarantee the two-edged pin side plate outside sky that do not collapse, 3) guarantee that face does not reveal the pipe canopy, reveals the landslip of sword pin, 4) contain the front end base plate and can not backbreak 5) slip casting pressure regulation and pressurize.
Pipe canopy stress, strain measurement, the anti-pipe canopy amount of deflection of asking.
Contain back of the body soil pressure measurement.
Local ground grouting and reinforcing anti-settling outside the road face.
5, two-way jacking closure section tunneling and joint treatment process
Two-way closure point position is chosen in beyond the taxiway, reduces like this slideway settlement influence, and is stressed also safer.
Sword pin spacing 3-5m is advisable, and mainly considers the influence of an end pushing tow to the other end, and when connecting soon, the other end face soil body can cave in, and is dangerous.
Sword pin steel plate is not dismantled, and still plays the effect of retaining soil.The vertical distribution reinforcement φ 16 of box culvert, φ 20 adopt boring bar planting technology to connect.Box culvert hoop steel bar stress because its broken end will cut the about 30cm scope of length in oblique triangle sword pin concrete, adopts overlap welding to connect.Waterproofing course will be attached to sword pin steel plate inboard, two ends, carries out cushion rubber, will glue the bloated sealing rod of the square chance freight of 50 * 50mm at culvert plate end face.
Principal rod colligation order: outer earlier, internal layer again, back envelope template.
Locate to irritate concrete from low to high, press lift-up method to build concrete with the bottom-up band of concrete pump line.Establish exhaust, plasma discharge mouth at highest point.
Select large fluidity for use, high-strength self-compacting concrete.Irritate when concrete seals arch at last and want slow, pump once stops, treats that air water arranged, and the concrete of emerging is starched to filling.Pre-buried madjack pipe, back ftercompction cement paste.
6, box culvert relay well and joint waterproofing technology
The every joint of the present invention is contained long 15m, and the place has established relay well and risen nest at every joint seam, and first joint must be established relay well, and other can establish one group of relay well by 2 joints, and to reduce seam, the culvert joint is long also to be adjustable to about 20m.
The internode waterproof: adopt the diameter at internode extruding φ 80mm, thick 1.5cm rubber tube is aided with joint filling cream grouting for water blocking later on again.

Claims (2)

1, construction process of pushing in long and large box culvert under taxiway in airport, comprise little pilot tunnel laying, pre-timbering with tubular prop, crest enters box culvert and road face settlement Control technology, it is characterized in that: described little pilot tunnel is positioned at the box culvert bottom, some I20 i iron are laid at the end of little pilot tunnel, by the gradient mix up, leveling, fixing with the support welding, thereafter pumping C20 concrete pouring bar shaped slideway, the i iron end face flushes with the concrete end face, in the box culvert jack-in process, with excavator little pilot tunnel is abolished;
Described pre-timbering with tubular prop process using:
Wireless signal remote control is surveyed and is received and the emission instrument, record directed three-dimensional coordinate and the attitude angle of drill bit in soil of boring, make the guiding sole at drill bit place to theory orientation deflection by rotation, thereafter give the drilling rod applied thrust, make it to advance along the correction of guide strip bevel direction, thereby finish the pilot hole of long 148m, after utilizing the interior drill rod end of pilot hole to install the enlarged footing of band jetting cutting soil additional, pilot hole is extended to about 350mm, with the mud cover hole wall is protected simultaneously, finish reaming after, draw with drilling rod, with φ 325mm diameter, the steel pipe of thick 10mm is after progressively weldering connects, be used as power with large-scale hauling pipe rig steel pipe is dragged to the other end from Kong Yiduan, afterwards measurement and positioning errorless after, in pipe, pump into the C25 concrete, form the beam on the elastic foundation in the soil;
Described road face settlement Control technology comprises:
The road face is arranged net, and monitors sedimentation with precision level, and the T-S curve is associated to putting distance L with containing end, draws T-S-L figure, finds out the position that needs slip casting, the contingent sedimentation value in prediction the place ahead;
The Comprehensive Control measure mainly contains in the hole: native jacking is eaten in strictness; Guarantee the two-edged pin side plate outside sky that do not collapse; Guarantee that face does not reveal the landslip of pipe canopy, dew sword pin; Containing the front end base plate does not backbreak; Slip casting pressure regulation and pressurize;
Pipe canopy stress, strain measurement, the anti-pipe canopy amount of deflection of asking;
Contain back of the body soil pressure measurement;
Local ground grouting and reinforcing anti-settling outside the road face.
2, construction process of pushing in long and large box culvert under taxiway in airport according to claim 1 it is characterized in that: further comprising two-way jacking closure section tunneling and joint treatment process:
Two-way closure point position is chosen in beyond the taxiway;
Sword pin spacing 3-5m;
Sword pin steel plate is not dismantled, and the vertical distribution reinforcement φ 16 of box culvert, φ 20 adopt boring bar planting technology to connect, and box culvert hoop steel bar stress cuts the about 30cm scope of length, adopts overlap welding to connect;
Waterproofing course will be attached to sword pin steel plate inboard, two ends, carries out cushion rubber, will glue the bloated sealing rod of the square chance freight of 50 * 50mm at culvert plate end face;
Principal rod colligation order: outer earlier, internal layer again, back envelope template;
Locate to irritate concrete from low to high, press lift-up method to build concrete, establish exhaust, plasma discharge mouth at highest point with the bottom-up band of concrete pump line.
CNB2006100783755A 2006-05-17 2006-05-17 Construction process of pushing in long and large box culvert under taxiway in airport Expired - Fee Related CN100554643C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006100783755A CN100554643C (en) 2006-05-17 2006-05-17 Construction process of pushing in long and large box culvert under taxiway in airport

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006100783755A CN100554643C (en) 2006-05-17 2006-05-17 Construction process of pushing in long and large box culvert under taxiway in airport

Publications (2)

Publication Number Publication Date
CN1847617A CN1847617A (en) 2006-10-18
CN100554643C true CN100554643C (en) 2009-10-28

Family

ID=37077324

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006100783755A Expired - Fee Related CN100554643C (en) 2006-05-17 2006-05-17 Construction process of pushing in long and large box culvert under taxiway in airport

Country Status (1)

Country Link
CN (1) CN100554643C (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071945B (en) * 2010-12-29 2012-11-28 上海隧道工程股份有限公司 Method for driving-in and driving-out construction in built structure closed in three sides for shield
CN103015335B (en) * 2012-12-28 2015-07-01 中铁二十四局集团有限公司 Pre-penetrating limiting beam jacking method
CN106337373B (en) * 2015-07-13 2021-03-30 中铁第六勘察设计院集团有限公司 Construction method for obliquely penetrating existing line overhead jacking box culvert
CN107419741B (en) * 2017-07-04 2023-04-18 中铁上海设计院集团有限公司 Slideway structure for preventing jacking box body from deviating and construction method thereof

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
中继间法顶进箱涵施工技术. 王朝杰.山西建筑,第31卷第19期. 2005
中继间法顶进箱涵施工技术. 王朝杰.山西建筑,第31卷第19期. 2005 *
小湾水电站导流隧洞洞身开挖及支护施工. 朱宝凡.云南水力发电,第22卷第2期. 2006
小湾水电站导流隧洞洞身开挖及支护施工. 朱宝凡.云南水力发电,第22卷第2期. 2006 *
新型GB止水防水材料及其在水利工程中的应用. 鲁一晖,贾金生,于骁中,陈肖蕾,郝巨涛.防渗技术,第4卷第1期. 1998
新型GB止水防水材料及其在水利工程中的应用. 鲁一晖,贾金生,于骁中,陈肖蕾,郝巨涛.防渗技术,第4卷第1期. 1998 *
顶进法施工动态. 铁道建筑. 1974
顶进法施工动态. 铁道建筑. 1974 *

Also Published As

Publication number Publication date
CN1847617A (en) 2006-10-18

Similar Documents

Publication Publication Date Title
CN107060796B (en) It is a kind of to use Slurry Balanced Pipe Jacking Construction technique
CN102080548B (en) Construction method of tunnel to cross airport runway by shield method
CN209924998U (en) Shallow earthing shield tunnel is worn road reinforcement protection architecture down
CN104265307A (en) Non-uniform-hardness stratum earth pressure balance shield tunnel underpassing railway existing line construction method
CN109594990B (en) Large-section jacking pipe construction method for complex stratum
CN104343455A (en) Long-distance curved jacking pipe and pipe roof construction technique
CN104762978B (en) A kind of anchor pole Gravity Retaining Wall for high slope rockmass and manufacture method
CN106223963A (en) A kind of shield machine air pushing construction method by subsurface excavation method tunnel
CN102400694A (en) Reinforcement method for combined part of shield tunnel and mining-method tunnel
CN100554643C (en) Construction process of pushing in long and large box culvert under taxiway in airport
CN104847375B (en) A kind of small interval Four-Lane Road Shallow-buried Large-span Tunnel method for protecting support
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN103643961A (en) End-free reinforcing shield receiving structure and receiving method
CN105065037A (en) Double-layer arch center support construction method for highway soft rock tunnel
CN106246194A (en) The reinforcing Treatment Methods of tunnel roof fall wall caving
CN104847365B (en) A kind of small interval Four-Lane Road Shallow-buried Large-span Tunnel construction method
CN106522981B (en) Pass through the method for protecting support in goaf tunnel
CN112983456B (en) Water-rich sand layer multi-row pipe jacking ground surface deformation control method
CN103711492A (en) Pipe-jacking type cable sleeve passage construction method
CN109667603A (en) A kind of super shallow-buried tunnel structure and construction method
CN109611103A (en) A method of for boulder group consolidation process outstanding on shield section
CN203669876U (en) Non-end shield reinforcement arrival structure
CN206888992U (en) A kind of water-bed mine shield tunnel combination docking structure form
CN102797469A (en) Method for constructing inclined shaft by applying TBM (Tunnel Boring Machine) with earth pressure balancing function
CN106522248A (en) Method for reinforcing soil slope and slope reinforcing device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: BEIJING ENGINEERING COMPANY LIMITED OF CHINA RAILW

Effective date: 20150416

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150416

Address after: 100018 Beijing city Chaoyang District No. 2 North Pine dam Park

Patentee after: China Railway Construction Engineering Bureau No.16 Group Corp., Ltd.

Patentee after: BEIJING ENGINEERING COMPANY LIMITED OF CHINA RAILWAY URBAN CONSTRUCTION GROUP

Address before: 100018 Beijing city Chaoyang District No. 2 North Pine dam Park

Patentee before: China Railway Construction Engineering Bureau No.16 Group Corp., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091028

Termination date: 20210517