CN1740457A - 振动法cfg桩消除地基湿陷性处理方法 - Google Patents

振动法cfg桩消除地基湿陷性处理方法 Download PDF

Info

Publication number
CN1740457A
CN1740457A CN 200510200535 CN200510200535A CN1740457A CN 1740457 A CN1740457 A CN 1740457A CN 200510200535 CN200510200535 CN 200510200535 CN 200510200535 A CN200510200535 A CN 200510200535A CN 1740457 A CN1740457 A CN 1740457A
Authority
CN
China
Prior art keywords
foundation
pile
cfg
stake
falling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200510200535
Other languages
English (en)
Inventor
王绍华
王晶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN 200510200535 priority Critical patent/CN1740457A/zh
Publication of CN1740457A publication Critical patent/CN1740457A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

本发明公开了一种振动法CFG桩消除地基湿陷性处理技术,它是在具有湿陷性的黄土地基上,首先确定振动法CFG桩的位置,桩位按照正三角形即等边三角形布置,相邻的桩距离相等;其次确定桩距,桩距取3~5倍桩径;最后采用振动沉管灌注桩施工工艺进行施工。本发明能够提高地基承载力,消除土的湿陷性,缩短工期,节省费用。

Description

振动法CFG桩消除地基湿陷性处理方法
技术领域:
本发明涉及建筑工程,特别是涉及建筑物基础的施工方法。
背景技术:
CFG桩是水泥粉煤灰碎石桩的简称,当进行CFG桩复合地基设计时,如果地基为湿陷性黄土,以往施工就要分“两步走”:先采取强夯等方法消除或部分消除地基土的湿陷性,然后再进行水泥粉煤灰碎石桩的施工。第一步的强夯给第二步的桩施工增加了困难,以致地基工程工期长,费用高。
湿陷性黄土地基处理,还有一种“灰土挤密桩”的方法:先开挖桩孔,然后将3∶7的石灰和土拌匀倒入孔内,分层夯实成桩,在夯实灰土的同时挤密桩间土以消除地基土的湿陷性。灰土挤密桩有两个缺点,一是3∶7灰土的工料成本较高,单价比水泥粉煤灰碎石桩高约20%(粉煤灰是火力发电厂的废弃物,可便宜取用);二是其要求桩间距小,为2倍桩径,一个场地如果做灰土挤密桩,桩数将是CFG桩数的2.25倍,费用和工期都不经济。
发明内容:
本发明的目的在于:提供一种振动法CFG桩消除地基湿陷性处理技术,将以往的“两步走”改变为“一并处理”,既提高地基承载力,又消除土的湿陷性,缩短工期,节省费用。
本发明是这样实现的:在具有湿陷性的黄土地基(2)上,首先确定振动法CFG桩(1)的位置,桩位按照正三角形即等边三角形布置,相邻的桩距离相等;其次确定桩距,桩距取3~5倍桩径;最后采用振动沉管灌注桩施工工艺进行施工。
振动法CFG桩(1)的直径取值为350~600mm。
振动沉管灌注桩施工要点:成孔不是采取钻、挖将土取出成孔,而是采取沉入钢管将土排挤至管周围成孔;沉入钢管不是采取锤击,而是采取机械强烈振动使钢管边振边下。当沉管达到设计深度即提起钢管,向孔内灌注拌合物成桩。
通过对CFG桩的成桩方法深入研究,证实了振动沉管灌注成桩法对桩间土有很好的振密挤实作用;只要桩的布置合理,就能够全部消除桩深范围内地基土的湿陷性。本发明的原理:沉管成孔是将钢管所占体积的土挤入管周围土体中的孔隙,当做CFG桩复合地基时,也就是挤入桩间土使土挤实;在振动沉管的过程中,由于振动力大(离振源10m处都能使人感到地面振动),更使桩间土振密。而在灌注水泥粉煤灰碎石桩时,又是分层振实的,桩身压实系数达0.97(灰土的压实系数只能达到0.95)。湿陷性黄土又称大孔土,本方法对桩间土很好的振密挤实,使其改变“大孔隙”的性状,从而消除湿陷性。
本发明的有益效果是:能够提高地基承载力,消除土的湿陷性,缩短工期,节省费用。
附图说明:
图1:本发明的振动沉管灌注桩位布置示意图。
具体实施方式:
本发明的实施例:在29.45m×120m的湿陷性黄土地基2上,采用振动法CFG桩1制作复合地基。振动法CFG桩1的直径取值为400mm,桩位按正三角形布置,桩距为1.2m,采用振动沉管灌注桩施工工艺进行施工,桩端置于卵石层顶,桩身压实系数为0.97。施工完毕后制作的复合地基承载力达到设计值200Kpa,地基土的湿陷性全部消除。与以往“先强夯,后做桩”的方法相比,工期缩短35%,投资节约40%,经济效益显著。

Claims (2)

1.一种振动法CFG桩消除地基湿陷性处理方法,其特征在于:在具有湿陷性的黄土地基(2)上,首先确定振动法CFG桩(1)的位置,桩位按照正三角形即等边三角形布置,相邻的桩距离相等;其次确定桩距,桩距取3~5倍桩径;最后采用振动沉管灌注桩施工方法进行施工。
2.根据权利要求1所述的振动法CFG桩消除地基湿陷性处理技术,其特征在于:振动法CFG桩(1)的直径取值为350~600mm。
CN 200510200535 2005-09-15 2005-09-15 振动法cfg桩消除地基湿陷性处理方法 Pending CN1740457A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200510200535 CN1740457A (zh) 2005-09-15 2005-09-15 振动法cfg桩消除地基湿陷性处理方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200510200535 CN1740457A (zh) 2005-09-15 2005-09-15 振动法cfg桩消除地基湿陷性处理方法

Publications (1)

Publication Number Publication Date
CN1740457A true CN1740457A (zh) 2006-03-01

Family

ID=36092975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200510200535 Pending CN1740457A (zh) 2005-09-15 2005-09-15 振动法cfg桩消除地基湿陷性处理方法

Country Status (1)

Country Link
CN (1) CN1740457A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102359101A (zh) * 2011-07-28 2012-02-22 江苏建筑职业技术学院 一种湿陷性土的地基处理方法
CN101597897B (zh) * 2008-06-06 2012-04-25 贵阳铝镁设计研究院有限公司 一种湿陷性黄土地区地基的二次处理方法及复合地基结构
CN102477737A (zh) * 2010-11-29 2012-05-30 中冶天工集团有限公司 公路湿陷性黄土地基上水泥粉煤灰碎石桩施工方法
CN103643691A (zh) * 2013-12-24 2014-03-19 山东大学 一种烧结透水桩地基处理方法
CN104213576A (zh) * 2013-06-05 2014-12-17 中国石油天然气股份有限公司 一种湿陷性黄土场地上大型储罐地基制作方法

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101597897B (zh) * 2008-06-06 2012-04-25 贵阳铝镁设计研究院有限公司 一种湿陷性黄土地区地基的二次处理方法及复合地基结构
CN102477737A (zh) * 2010-11-29 2012-05-30 中冶天工集团有限公司 公路湿陷性黄土地基上水泥粉煤灰碎石桩施工方法
CN102359101A (zh) * 2011-07-28 2012-02-22 江苏建筑职业技术学院 一种湿陷性土的地基处理方法
CN104213576A (zh) * 2013-06-05 2014-12-17 中国石油天然气股份有限公司 一种湿陷性黄土场地上大型储罐地基制作方法
CN104213576B (zh) * 2013-06-05 2016-09-07 中国石油天然气股份有限公司 一种湿陷性黄土场地上大型储罐地基制作方法
CN103643691A (zh) * 2013-12-24 2014-03-19 山东大学 一种烧结透水桩地基处理方法
CN103643691B (zh) * 2013-12-24 2015-07-29 山东大学 一种烧结透水桩地基处理方法

Similar Documents

Publication Publication Date Title
CN102733377B (zh) 混凝土桩的施工方法
CN101718091B (zh) 液化土层与软土互层的地基处理方法
CN101736738B (zh) 一种抗压、抗拔两用型注浆碎石桩的制作工法
CN105625294A (zh) 一种复合地基及其施工方法
CN210288333U (zh) 深层地基处理结构
CN102392447B (zh) 予力变刚度散粒材料夯扩桩机及用途
CN1740457A (zh) 振动法cfg桩消除地基湿陷性处理方法
CN1191257A (zh) 混凝土桩的施工方法
CN105484230A (zh) 桩土混凝一体化复合桩及其施工方法
KR20090042393A (ko) 크레인에 말뚝 항타용 유압해머를 이용하여 지반을 다지는공법 및 장치
WO2017133373A1 (zh) 一种用于桩基的小直径桩簇及其施工方法
CN101736730A (zh) 高填方砂土地基混合加固法
CN1632236A (zh) 劲芯复合桩及施工方法
CN106337408A (zh) 一种碎石挤密桩复合地基的施工方法
CN1891913A (zh) 重锤冲扩置换法
CN1095517C (zh) 加固地基的施工方法
CN1137311C (zh) 干振挤密碎石抗拔防浮桩及其成型方法
RU2231596C2 (ru) Способ изготовления сваи в предварительно продавленной скважине
JP3794020B2 (ja) 土間コンクリートおよびその構築方法
CN1076064C (zh) 地基处理方法
CN206570799U (zh) 一种后注浆端锥式灌注桩
CN205712084U (zh) 一种钻孔回填端承桩基础
CN109577312A (zh) 一种粉土地质振冲碎石挤密桩施工方法
CN104153359B (zh) 预应力混凝土疏筋桩的施工方法
CN202577281U (zh) 一种多管围连水泥维护体的成型设备

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication