CN1704945A - Dangerous point safety precontrol method for power network dispatch - Google Patents

Dangerous point safety precontrol method for power network dispatch Download PDF

Info

Publication number
CN1704945A
CN1704945A CN 200410024819 CN200410024819A CN1704945A CN 1704945 A CN1704945 A CN 1704945A CN 200410024819 CN200410024819 CN 200410024819 CN 200410024819 A CN200410024819 A CN 200410024819A CN 1704945 A CN1704945 A CN 1704945A
Authority
CN
China
Prior art keywords
scheduling
servant
record
dispatching
day
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200410024819
Other languages
Chinese (zh)
Inventor
何维国
林红
张欣
陈东
奚增辉
邵靓
徐涛
王韧
丁毅
金玲丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
EASTERN POWER SUPPLY Co OF SHANGHAI MUNICIPAL ELECTRIC POWER Co
Original Assignee
EASTERN POWER SUPPLY Co OF SHANGHAI MUNICIPAL ELECTRIC POWER Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by EASTERN POWER SUPPLY Co OF SHANGHAI MUNICIPAL ELECTRIC POWER Co filed Critical EASTERN POWER SUPPLY Co OF SHANGHAI MUNICIPAL ELECTRIC POWER Co
Priority to CN 200410024819 priority Critical patent/CN1704945A/en
Publication of CN1704945A publication Critical patent/CN1704945A/en
Pending legal-status Critical Current

Links

Images

Abstract

This invention discloses a safety pre-control method to network controlled dangerous points including a dispatch step, an operation way and a relay protection, which automatically generate flow diaries with a flow monitor function and an effective prompt unit avoiding error dispatch to the network and error operation.

Description

Dispatching of power netwoks dangerous point safety precontrol method
Technical field
The present invention relates to the pre-control method of a kind of power grid security scheduling, particularly relate in a kind of dispatching of power netwoks safety precontrol method at dangerous point.
Background technology
Electrical network is the carrier of electricity market, will generate electricity and consumer link together, constitute an integral body.Power grid accident brings loss to electric power enterprise, more the life of broad masses of the people and entire society is caused to have a strong impact on, and is related to national economy, national security and social stability.
At present; urban distribution network load is concentrated, short-term in groups, relay protection setting cooperates difficulty, capacity of short circuit is big, power plant is tight must be like an integral body; the major network construction is difficult to satisfy fully the needs of load growth and assurance electric power netting safe running, also increases the possibility of large-area power-cuts in the time of power network development.The grid power blackout accident is to have potential hazards in the electrical network mostly, causes disintegrating or collapsing of electrical network (part) under certain inducement effect.From the trend of falling that increases of accident, the misoperation fault that can take technical measures to prevent reduces year by year, but not the misoperation fault that technical measures (disconnected as malfunction, erroneous judgement, mistuning degree etc.) can prevent increases.Under, the electricity consumption situation that the situation is tense very big at the current power breach, especially continuous overload operation makes equipment failure take place frequently during summer high temperature, the safety of electrical network is most important, key wherein is the sacurity dispatching of electrical network, and any one error of traffic department all can threaten the safe and stable operation of electrical network.Because dangerous point has objectivity, disguise, polytrope, but have the characteristics of knowability, preventing property simultaneously again; And dispatching of power netwoks working routine complexity, all departments' business relations is tight, and along with increasing in the development of electrical network and the factory station of administration, the dangerous point in the dispatching of power netwoks also increases severely thereupon.Most of electrical network mistuning degree, misoperation fault are relevant with the human operational error, because the restriction of people's physiology, psychological characteristic, the influence of social various factors, can not avoid error fully, therefore have can not pre-control for human factor, this just need be at the dangerous point that exists in the grid dispatching management, create the tight omnidistance dangerous point safety pre-control mechanism of dispatching of power netwoks, carry out careful workflow setting, carry out strict management, every workflow is adopted means such as effectively related monitoring, record.Yet existing management and running mechanism and pattern can not adapt to the fast-developing requirement of electrical network, exist in the dispatching of power netwoks and bring out the unsafe factor of accident potential's (being dangerous point), lack safe early warning and pre-control mechanism, add that all departments' information sharing is insufficient, restricted the safe and reliable of management and running work and efficiently carried out.
Summary of the invention
The technical problem to be solved in the present invention provides a kind of dispatching of power netwoks dangerous point safety precontrol method, and it can effectively prevent the generation of electrical network mistuning degree, misoperation fault, guarantees the safe operation of electrical network.
For solving the problems of the technologies described above, dispatching of power netwoks dangerous point safety precontrol method of the present invention, comprise scheduling step, method of operation step, relay protection step, communication steps, robotization step and integrated management step, and product process daily record automatically, flow monitoring function and notification mechanisms had;
The flow process closed loop pre-control of scheduling step standard dispatching of power netwoks related service, realization is write, examine, the computerized of dangerous point safety pre-control during the neutralization of executable operations ticket is relieved and scheduling day to day operation, comprise dispatching log, operation order, dispatcher training and daily report and day operation plan: dispatching log comprises scheduling groundwork record, its step is, according to the accident treatment situation, abnormal conditions are unplanned stops multiple labour, leading body at a higher level is to the indication of relevant production run, each responsible department is to requirement and subordinate's scheduling and factory's station operations staff's incident report of electrical network production run, the reference system time, carry out the dispatching log typing, according to significance level, generate prompting of different stage memorandum and color demonstration and self-defined memorandum and point out, carry out again finishing after other records generate selection automatically;
Operation order utilizes former SCADA (Supervisory Control And Data Acquisition promptly monitors control and data acquisition system (DAS)) ticket system import operation ticket, draws a bill, related work packing, review operations;
Dispatcher training and daily report comprise a day report, prediction failure, technology question and answer, anti-accident maneuver, and permission is listed and had prompt facility in the SCADA system;
Day operation plan mainly is the workflow management that stops using as a servant request slip, comprise that many are stopped the labour list, it is single that many Zhang Gongs do contact, many Notification of Changes lists, whole flow process is nested stops labour singly, working relation is single, three flow processs of Notification of Changes list, and with operation order between realize related and nested between multipaths, concrete steps are: at first by the constituent parts application, if the district transfers application, need to transfer to the reply of fortune side after the leader of the branch office audit, otherwise directly give an written reply by fortune side, giving an written reply the result (comprises and stops the labour list for returning constituent parts or sending a generation day operation plan, single and the Notification of Changes list of working relation), continue successively then and protect joint hearing, the side of fortune group leader audit, the approval of leading, the scheduling reply, the result in its each step is for returning operation plan or carrying out next step operation, dispatch packing after the scheduling reply, with operation order with stop using as a servant single related, carry out operation order and intend ticket, it is capable to examine laggard line operate ticket stubs at operation order, wherein after the scheduling packing, carry out the scheduled for executing step simultaneously, its result is for returning or carrying out, carry out in two kinds of situation, a kind of is that whether labour is single delays at stopping, if delay then need to regenerate day operation plan and examine through the side of fortune group leader, if do not delay then file, another kind is to carry out operation order and carry out at stopping single whether execution of labour;
Method of operation step comprises: (1) uses as a servant the application form record application time according to stopping of filling in of UHV (ultra-high voltage) company, each power supply station, each cable power transmission and distribution company, differentiates the application time, and whether the application of electric industry unit is less than 7 days, whether user applies is less than 10 days; (2) if step (1) is differentiated the result for being, jump to step (5), otherwise whether according to the equipment deficiency record, being differentiated by fortune side personnel is major defect; (3) if step (2) fortune side personnel differentiate the result for not, jump to step (5), otherwise generate record, solicit leader's suggestion then; (4) agree as if step (3) leader, jump to step (5), otherwise return original unit; (5) according to the prompting of application form key check points, whether the side's of fortune personnel inspection application form content is correct; (6) if step (5) erroneous results is write reason exactly, return original unit and generation record, otherwise given an written reply application form, generates record and carried out the application form filing according to cancelling of application form by fortune side personnel, whether differentiation arranges a day mode then; (7) if step (6) is differentiated the result for being, enter a day mode flow process, otherwise finish;
The relay protection step comprises: (1) determines the single applying unit of working relation, and implementing continues protects the responsible official and the guarantor person that continues, and whether differentiate working relation then single qualified; (2) if step (1) is differentiated the result for being whether need preserve, otherwise return as if step (1) if continuing to differentiate correlation parameter; (3) if step (2) is differentiated the result for being to change step (4) over to after the preservation parameter, otherwise directly change step (4) over to; (4) differentiate whether to call plug-in calculation procedure,, otherwise directly change step (5) over to if change step (5) over to after the result for being, moves plug-in calculation procedure; (5) differentiate whether need to develop the book of adjusting, if need execution in step (6), otherwise execution in step (7); (6) single numbering registration of adjusting, the inteilectual that adjusts who belongs to generaI investigation character becomes the findings of the survey record, and execution in step (7) changes step (8) then over to as required; (7) fill in the single feedback information of working relation,, return step (1) the single file of working relation; (8) single establishment of adjusting, whether differentiate is the list of formally adjusting, if not, return step (1), if, nuclear in organizing; (9),, carry out the leader of institute audit if correct if step (8) result for examining mistake in the group, returns step (8); (10) if step (9) auditing result of leading for not, is returned step (8), if the result is for being to submit the chief engineer of company and ratify; (11) if step (10) chief engineer of company gives an written reply the result for not, return step (8),, return step (1) and execution in step (12) as required if the result continues to protect and distributes the book of adjusting for being; (12) dispatch, the limit of adjusting, scheduled for executing is checked the back preservation simultaneously, and changes record generation relay protection configuration operation figure according to primary connection and relay protection temporarily;
Communication steps comprises sets up various types of communication distributing frame, demand pairs certificate, various types of communication equipment disposition, communication line ruuning situation database, communicate changing over to automatically and generation, equipment deficiency closed loop management and engineering process management of running log, all kinds of forms, and realize Work Process Management according to the characteristics of specialty own;
The robotization step comprises carries out changing over to automatically and generating of automatic operating daily record, all kinds of statistical report forms, and carries out Work Process Management according to the characteristics of specialty own;
The integrated management step covers all daily managements mission in the dispatching office comprehensively.
Adopt dispatching of power netwoks dangerous point safety precontrol method of the present invention, realize informationization, standardization and the networking of dangerous point safety pre-control.The present invention has tight pre-control mechanism, decision support tool, the function of dynamic pre-control and classification pre-control, for dispatching of power netwoks provides simple, unified, operable approach, the dangerous point of standard is searched, replenish, eliminate, the flow process of pre-control, generate pre-control means fast by computing machine, and provide the network inquiry of dangerous point statistical graph and pre-control implementation status, make things convenient for grid dispatching management work, dangerous point in the operation of power networks process is carried out dynamic pre-control and closed loop management, set up successive check, form the protected network of stereo safety, can guarantee to dispatch the standardization of every work, reduce the appearance of artificial potential safety hazard significantly.
Description of drawings
Below in conjunction with the drawings and specific embodiments the present invention is described in further detail:
Fig. 1 is that the present invention dispatches dispatching log schematic flow sheet in the step;
Fig. 2 is that the present invention dispatches the Sino-Japan operation plan schematic flow sheet of step;
Fig. 3 is a method of operation steps flow chart synoptic diagram of the present invention;
Fig. 4 is a relay protection steps flow chart synoptic diagram of the present invention.
Embodiment
A kind of dispatching of power netwoks dangerous point of the present invention safety precontrol method; comprise scheduling step, method of operation step, relay protection step, communication steps, robotization step and integrated management; and product process daily record automatically, have flow monitoring function and effective notification mechanisms.
1. scheduling step; it mainly is the flow process closed loop pre-control of standard dispatching of power netwoks related service; the dangerous point safety pre-control during realization is write, examined, the neutralization of executable operations ticket is relieved and the computerized of scheduling day to day operation comprise dispatching log, operation order, dispatcher training and daily report and day operation plan:
Described dispatching log comprises scheduling groundwork record, as the record of relieving, permissions records, continue protect that change, communication automation system are unusual, five unlocking preventions, draw ration the power supply, protect the electricity registration, by all off-loads, accident report etc., in relieving and permitting, report the work, realize the dangerous point pre-control, the in a single day formal typing of dispatching log must not be revised.Dispatching log possesses function of search, can search for according to contact unit, content and time on date.As shown in Figure 1, its operation steps is: according to the unplanned multiple labour, leading body at a higher level of stopping of accident treatment situation, abnormal conditions the indication of relevant production run, each responsible department are reported the requirement of electrical network production run and subordinate's scheduling and factory's station operations staff's incident, the reference system time, carry out the dispatching log typing, according to significance level, generate prompting of different stage memorandum and color demonstration and the prompting of self-defined memorandum, carry out other records again and generate selection automatically, the dispatching log typing finishes;
Described operation order utilizes former SCADA ticket system import operation ticket, realizes drawing a bill, related work packing, audit function, and writing, examining, realizing the dangerous point pre-control in the executable operations ticket, and in conjunction with relieving raising yardman's careful ticket rate.
Described dispatcher training and daily report comprise a day report, prediction failure, technology question and answer, anti-accident maneuver, and permission is listed and had prompt facility in the SCADA system;
Operation plan mainly was the workflow management that stops using as a servant request slip in described day; stop multiple labour work by the further standard of workflow management is daily; and built-in prompting and binding function; comprise that many are stopped the labour list; it is single that many Zhang Gongs do contact; many Notification of Changes lists; whole flow process is nested stops labour singly; working relation is single; three flow processs of Notification of Changes list; and with operation order between realize related and nested between multipaths; as shown in Figure 2; concrete steps are: at first by the constituent parts application; if the district transfers application; need to transfer to the reply of fortune side after the leader of the branch office audit; otherwise directly give an written reply by fortune side; giving an written reply the result (comprises and stops the labour list for returning constituent parts or sending a generation day operation plan; single and the Notification of Changes list of working relation); continue successively then and protect joint hearing; the side of fortune group leader audit; the approval of leading; the scheduling reply; the result in its each step is for returning operation plan or carrying out next step operation; dispatch packing after the scheduling reply; with operation order with stop using as a servant single related; carry out operation order and intend ticket; it is capable to examine laggard line operate ticket stubs at operation order; wherein after the scheduling packing, carry out the scheduled for executing step simultaneously; its result is for returning or carrying out; carry out in two kinds of situation; a kind of is that whether labour is single delays at stopping; if delay then need to regenerate day operation plan and examine through the side of fortune group leader; if do not delay then file, another kind is to carry out operation order and carry out at stopping single whether execution of labour.Wherein, protect joint hearing, fortune side group leader audit, institute and lead the approval node continuing, can only return whole day operation plan, can only return individual at scheduling reply, scheduled for executing node and stop using as a servant list, working relation list, Notification of Changes list; Each node of flow process carries out color differentiating according to the difference of state, for scheduling return or the side of fortune is newly-increased individual stop using as a servant that request slip, working relation are single, after Notification of Changes Dan Yunfang gives an written reply transmission again, see the content that day operation plan is all at the guarantor's joint hearing that continues, fortune side group leader audit, the approval node of leading, colour code is return or newly-increased record; Scheduling must be given an written reply one by one and stop using as a servant request slip, and the stopping using as a servant and just can send a day operation plan after the request slip reply is finished of scheduling reply node, stopping after the reply used as a servant the request slip colour code with all; Stop using as a servant request slip for what needs were changed the date, the record of changing the date is filled in scheduling, and system will stop to use as a servant the multiple labour operation filing of request slip to corresponding day operation plan automatically according to the up-to-date date of changing the date; Stopping after giving an written reply used as a servant request slip in scheduling and working relation is singly packed, request slip is used as a servant in relevant stopping and working relation is singly sorted out, automatically fill in relevant work permit record during scheduled for executing, current entry, termination packing record is return when the scheduled for executing node and to be stopped using as a servant request slip and working relation and should open automatically when single stop using as a servant request slip and working relation is single deletes from wrap; Using as a servant operation order again singly is all could carry out after the execution in the labour of stopping of association only;
2 method of operation steps realize the online circulation of fortune side's related service, set up complete primary equipment parameter database in the dispatching management scope, intelligent generation equipment Quota List; Realize computer management to stopping using as a servant request slip application, reply, statistics, examination etc.; Day mode module is concluded automatically to the request slip of having given an written reply, show the same day electrical network need stop labour equipment, stop labour equipment, protect all operation plan work such as electricity; To the SCADA data analysis, data such as maximum load, load factor, rate of growth are carried out tabulate statistics; Set up tight operation flow setting and effective notification mechanisms, realize the dangerous point safety pre-control in method of operation operation flow;
As shown in Figure 3, method of operation step is: (1) uses as a servant the application form record application time according to stopping of filling in of UHV (ultra-high voltage) company, each power supply station, each cable power transmission and distribution company, the side of fortune personnel differentiate the application time, and whether the application of electric industry unit is less than 7 days, whether user applies is less than 10 days; (2) if step (1) is differentiated the result for being, jump to step (5), otherwise whether according to the equipment deficiency record, being differentiated by fortune side personnel is major defect; (3) if step (2) fortune side personnel differentiate the result for not, jump to step (5), otherwise generate record, solicit leader's suggestion then; (4) agree as if step (3) leader, jump to step (5), otherwise return original unit; (5) according to the prompting of application form key check points, whether the side's of fortune personnel inspection application form content is correct; (6) if step (5) erroneous results is write reason exactly, return original unit and generation record, otherwise given an written reply application form, generates record and carried out the application form filing according to cancelling of application form by fortune side personnel, whether differentiation arranges a day mode then; (7) if step (6) is differentiated the result for being, enter a day mode flow process, otherwise finish;
3 relay protection steps; establishment continues and protects specialty relevant the continuing such as book and automatic generating software version management, setting program, anti-accident measures, operation notice of adjusting and protect professional management; carry out the daily evaluation works of guarantor that continue such as limit calculating, capacity of short circuit calculating, the calculating of adjusting, protect type in the book of selecting to adjust and on AUTOCAD figure, locate automatic generation protection drawing.Utilize the prompting function and the intelligence computation function of workflow, in the relay protection operation flow, realize the dangerous point safety pre-control;
As shown in Figure 4, the relay protection step is: (1) determines the single applying unit of working relation, and implementing continues protects the responsible official and the guarantor person that continues, and whether differentiate working relation then single qualified; (2) if step (1) is differentiated the result for being whether need preserve, otherwise return as if step (1) if continuing to differentiate correlation parameter; (3) if step (2) is differentiated the result for being to change step (4) over to after the preservation parameter, otherwise directly change step (4) over to; (4) differentiate whether to call plug-in calculation procedure,, otherwise directly change step (5) over to if change step (5) over to after the result for being, moves plug-in calculation procedure; (5) differentiate whether need to develop the book of adjusting, if need execution in step (6), otherwise execution in step (7); (6) single numbering registration of adjusting, the inteilectual that adjusts who belongs to generaI investigation character becomes the findings of the survey record, and execution in step (7) changes step (8) then over to as required; (7) fill in the single feedback information of working relation,, return step (1) the single file of working relation; (8) single establishment of adjusting, whether differentiate is the list of formally adjusting, if not, return step (1), if, nuclear in organizing; (9),, carry out the leader of institute audit if correct if step (8) result for examining mistake in the group, returns step (8); (10) if step (9) auditing result of leading for not, is returned step (8), if the result is for being to submit the chief engineer of company and ratify; (11) if step (10) chief engineer of company gives an written reply the result for not, return step (8),, return step (1) and execution in step (12) as required if the result continues to protect and distributes the book of adjusting for being; (12) dispatch, the limit of adjusting, scheduled for executing is checked the back preservation simultaneously, and changes record generation relay protection configuration operation figure according to primary connection and relay protection temporarily;
4 communication steps, foundation is about the database of various types of communication distributing frame, demand pairs certificate, various types of communication equipment disposition, communication line ruuning situation, realize changing over to automatically and generation, equipment deficiency closed loop management and engineering process management of communication running log, all kinds of forms, and realize Work Process Management according to the characteristics of specialty own;
5 robotization steps are carried out changing over to automatically and generating of automatic operating daily record, all kinds of statistical report forms, and realize Work Process Management according to the characteristics of specialty own;
6 integrated management steps, cover all daily managements mission in the dispatching office comprehensively, realize office automation, improve whole work efficiency, strengthen the management function between each specialty, the sharing of promptness, convenience, rationality and information that the practicality of realization function, work are finished.

Claims (7)

1. dispatching of power netwoks dangerous point safety precontrol method; it is characterized in that; it comprises scheduling step, method of operation step, relay protection step, communication steps, robotization step and integrated management step; and product process daily record automatically; have flow monitoring function and effective notification mechanisms, wherein:
(a) the flow process closed loop pre-control that the scheduling step can standard dispatching of power netwoks related service; the dangerous point safety pre-control during realization is write, examined, the neutralization of executable operations ticket is relieved and the computerized of scheduling day to day operation comprise dispatching log, operation order, dispatcher training and daily report and day operation plan:
Described dispatching log comprises scheduling groundwork record, the steps include: the indication of relevant production run, each responsible department to be reported the requirement of electrical network production run and subordinate's scheduling and factory's station operations staff's incident according to the unplanned multiple labour, leading body at a higher level of stopping of accident treatment situation, abnormal conditions, the reference system time, carry out the dispatching log typing, according to significance level, generate prompting of different stage memorandum and color demonstration and self-defined memorandum and point out, carry out again finishing after other records generate selection automatically;
Described operation order utilizes former SCADA ticket system import operation ticket, draws a bill, related work packing, review operations;
Described dispatcher training and daily report comprise a day report, prediction failure, technology question and answer, anti-accident maneuver, and permission is listed and had prompt facility in the SCADA system;
Operation plan mainly was the workflow management that stops using as a servant request slip in described day, comprise that many are stopped the labour list, it is single that many Zhang Gongs do contact, many Notification of Changes lists, whole flow process is nested stops labour singly, working relation is single, three flow processs of Notification of Changes list, and with operation order between realize related and nested between multipaths, concrete steps are: at first by the constituent parts application, if the district transfers application, need to transfer to the reply of fortune side after the leader of the branch office audit, otherwise directly give an written reply by fortune side, giving an written reply the result (comprises and stops the labour list for returning constituent parts or sending a generation day operation plan, single and the Notification of Changes list of working relation), continue successively then and protect joint hearing, the side of fortune group leader audit, the approval of leading, the scheduling reply, the result in its each step is for returning operation plan or carrying out next step operation, dispatch packing after the scheduling reply, with operation order with stop using as a servant single related, carry out operation order and intend ticket, it is capable to examine laggard line operate ticket stubs at operation order, wherein after the scheduling packing, carry out the scheduled for executing step simultaneously, its result is for returning or carrying out, carry out in two kinds of situation, a kind of is that whether labour is single delays at stopping, if delay then need to regenerate day operation plan and examine through the side of fortune group leader, if do not delay then file, another kind is to carry out operation order and carry out at stopping single whether execution of labour;
(b) method of operation step, comprise: (1) uses as a servant the application form record application time according to stopping of filling in of UHV (ultra-high voltage) company, each power supply station, each cable power transmission and distribution company, the side of fortune personnel differentiate the application time, and whether the application of electric industry unit is less than 7 days, whether user applies is less than 10 days; (2) if step (1) is differentiated the result for being, jump to step (5), otherwise whether according to the equipment deficiency record, being differentiated by fortune side personnel is major defect; (3) if step (2) fortune side personnel differentiate the result for not, jump to step (5), otherwise generate record, solicit leader's suggestion then; (4) agree as if step (3) leader, jump to step (5), otherwise return original unit; (5) according to the prompting of application form key check points, whether the side's of fortune personnel inspection application form content is correct; (6) if step (5) erroneous results is write reason exactly, return original unit and generation record, otherwise given an written reply application form, generates record and carried out the application form filing according to cancelling of application form by fortune side personnel, whether differentiation arranges a day mode then; (7) if step (6) is differentiated the result for being, enter a day mode flow process, otherwise finish;
(c) relay protection step comprises: (1) determines the single applying unit of working relation, and implementing continues protects the responsible official and the guarantor person that continues, and whether differentiate working relation then single qualified; (2) if step (1) is differentiated the result for being whether need preserve, otherwise return as if step (1) if continuing to differentiate correlation parameter; (3) if step (2) is differentiated the result for being to change step (4) over to after the preservation parameter, otherwise directly change step (4) over to; (4) differentiate whether to call plug-in calculation procedure,, otherwise directly change step (5) over to if change step (5) over to after the result for being, moves plug-in calculation procedure; (5) differentiate whether need to develop the book of adjusting, if need execution in step (6), otherwise execution in step (7); (6) single numbering registration of adjusting, the inteilectual that adjusts who belongs to generaI investigation character becomes the findings of the survey record, and execution in step (7) changes step (8) then over to as required; (7) fill in the single feedback information of working relation,, return step (1) the single file of working relation; (8) single establishment of adjusting, whether differentiate is the list of formally adjusting, if not, return step (1), if, nuclear in organizing; (9),, carry out the leader of institute audit if correct if step (8) result for examining mistake in the group, returns step (8); (10) if step (9) auditing result of leading for not, is returned step (8), if the result is for being to submit the chief engineer of company and ratify; (11) if step (10) chief engineer of company gives an written reply the result for not, return step (8),, return step (1) and execution in step (12) as required if the result continues to protect and distributes the book of adjusting for being; (12) dispatch, the limit of adjusting, scheduled for executing is checked the back preservation simultaneously, and changes record generation relay protection configuration operation figure according to primary connection and relay protection temporarily;
(d) communication steps, comprise and set up various types of communication distributing frame, demand pairs certificate, various types of communication equipment disposition, communication line ruuning situation database, communicate changing over to automatically and generation, equipment deficiency closed loop management and engineering process management of running log, all kinds of forms, and realize Work Process Management according to the characteristics of specialty own;
(e) robotization step comprises and carries out changing over to automatically and generating of automatic operating daily record, all kinds of statistical report forms, and carries out Work Process Management according to the characteristics of specialty own;
(f) the integrated management step covers all daily managements mission in the dispatching office comprehensively.
2. dispatching of power netwoks dangerous point safety precontrol method as claimed in claim 1; it is characterized in that; wherein in day operation plan; at the guarantor's joint hearing that continues, fortune side group leader audit, the approval node of leading; can only return whole day operation plan, can only return individual at scheduling reply, scheduled for executing node and stop labour list, single, the Notification of Changes list of working relation.
3. dispatching of power netwoks dangerous point safety precontrol method as claimed in claim 1; it is characterized in that; wherein in day operation plan; each node of flow process carries out color differentiating according to the difference of state; return or the side of fortune is newly-increased that individual stops using as a servant request slip, single, the Notification of Changes list of working relation for scheduling; after fortune side gives an written reply again and sends, see the content that day operation plan is all at the guarantor's joint hearing that continues, fortune side group leader audit, the approval node of leading, colour code is return or newly-increased record.
4. dispatching of power netwoks dangerous point safety precontrol method as claimed in claim 1, it is characterized in that, wherein in day operation plan, scheduling must be given an written reply one by one and stop using as a servant request slip, the stopping using as a servant and just can send a day operation plan after the request slip reply is finished of scheduling reply node, stopping after the reply used as a servant the request slip colour code with all.
5. dispatching of power netwoks dangerous point safety precontrol method as claimed in claim 1, it is characterized in that, wherein in day operation plan, stop using as a servant request slip for what needs were changed the date, the record of changing the date is filled in scheduling, and system will stop to use as a servant the multiple labour operation filing of request slip to corresponding day operation plan automatically according to the up-to-date date of changing the date.
6. dispatching of power netwoks dangerous point safety precontrol method as claimed in claim 1, it is characterized in that, wherein in day operation plan, stopping after giving an written reply used as a servant request slip in scheduling and working relation is singly packed, request slip is used as a servant in relevant stopping and working relation is singly sorted out, automatically fill in relevant work permit record during scheduled for executing, current entry, termination packing record.The scheduled for executing node is return should open automatically when stopping using as a servant request slip and working relation list and is stopped using as a servant request slip and the single deletion from bag of working relation.
7. dispatching of power netwoks dangerous point safety precontrol method as claimed in claim 1 is characterized in that, wherein in day operation plan, uses as a servant operation order again and only could carry out behind the stopping that labour is single and all carry out of association.
CN 200410024819 2004-06-01 2004-06-01 Dangerous point safety precontrol method for power network dispatch Pending CN1704945A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200410024819 CN1704945A (en) 2004-06-01 2004-06-01 Dangerous point safety precontrol method for power network dispatch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200410024819 CN1704945A (en) 2004-06-01 2004-06-01 Dangerous point safety precontrol method for power network dispatch

Publications (1)

Publication Number Publication Date
CN1704945A true CN1704945A (en) 2005-12-07

Family

ID=35577288

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200410024819 Pending CN1704945A (en) 2004-06-01 2004-06-01 Dangerous point safety precontrol method for power network dispatch

Country Status (1)

Country Link
CN (1) CN1704945A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101098069B (en) * 2007-06-13 2011-01-12 苏州工业园区慧思敦软件有限公司 Electric power scheduling simulation system electric network display process
CN101719690B (en) * 2009-11-30 2012-09-26 宁波市鄞州天灵信息科技有限公司 Dispatching method of electric network
CN103426055A (en) * 2013-07-17 2013-12-04 嘉兴市恒光电力建设有限责任公司华创分公司 Management system for dangerous points of power transmission
CN105629935A (en) * 2014-07-23 2016-06-01 国网山东省电力公司青岛供电公司 Dispatching voice reporting system for power plant
CN106655498A (en) * 2016-11-16 2017-05-10 合肥普望电子有限责任公司 Microgrid operation scheduling method
CN111680916A (en) * 2020-06-09 2020-09-18 南京及物智能技术有限公司 Electric power distribution virtual dispatcher device and method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101098069B (en) * 2007-06-13 2011-01-12 苏州工业园区慧思敦软件有限公司 Electric power scheduling simulation system electric network display process
CN101719690B (en) * 2009-11-30 2012-09-26 宁波市鄞州天灵信息科技有限公司 Dispatching method of electric network
CN103426055A (en) * 2013-07-17 2013-12-04 嘉兴市恒光电力建设有限责任公司华创分公司 Management system for dangerous points of power transmission
CN105629935A (en) * 2014-07-23 2016-06-01 国网山东省电力公司青岛供电公司 Dispatching voice reporting system for power plant
CN105629935B (en) * 2014-07-23 2018-03-30 国网山东省电力公司青岛供电公司 Power plant's schedule voice declaration system
CN106655498A (en) * 2016-11-16 2017-05-10 合肥普望电子有限责任公司 Microgrid operation scheduling method
CN111680916A (en) * 2020-06-09 2020-09-18 南京及物智能技术有限公司 Electric power distribution virtual dispatcher device and method

Similar Documents

Publication Publication Date Title
CN109740837B (en) Power grid province and land network command and safety error prevention method based on regulation and control integration
CN106157167B (en) Secondary equipment remote control operation ticket system and implementation method of secondary equipment remote control operation ticket
CN102361354B (en) The remote intensive managing and control system of unattended substation automated system
CN108038626A (en) A kind of cigarette machine Life cycle monitoring system and monitoring method
CN110633889A (en) Regional spot market technical support system
CN103578039B (en) A kind of power networks risk prewarning analysis system
CN110647567B (en) Power failure plan auxiliary decision system based on end data fusion
CN103761624A (en) Implementing method of integrated power grid dispatching operation intelligent mistaken-early-warning preventing system
CN111047143A (en) Power grid OMS-based regional and county team index management system
CN106651643A (en) Power security management and control method for whole process based on distribution and adjustment
CN106251237A (en) Various dimensions method for early warning in power marketing process management
CN112465167A (en) Intelligent decision management system and method for regional power grid equipment maintenance
CN105225176B (en) Warrant basic information system
CN103295164A (en) Power grid safety monitoring management information system and management method
CN107601187A (en) A kind of lift management system and method
CN1704945A (en) Dangerous point safety precontrol method for power network dispatch
CN108197907A (en) Ensure the multi-level collaborative regulation and administration method of power supply
CN112785279A (en) Block chain technology-based liability insurance application system and method
CN202795451U (en) Asset entire life-cycle management process control application system based on topic base
CN115271639A (en) New energy technology supervision and control system
CN107565579B (en) Multi-source cooperative management and control system and method for improving reactive voltage control level
CN112907003A (en) Renewable energy cross-region consumption system and method
CN108805428A (en) A kind of iron and steel enterprise's power scheduling flight deck system based on data-driven
CN110854848B (en) Control aid decision-making method for distribution network scheduling load
Zhang Research on the management information of scientific research institutes

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20051207