CN1701907A - Thin layer welding repair technology for forging die cavity - Google Patents

Thin layer welding repair technology for forging die cavity Download PDF

Info

Publication number
CN1701907A
CN1701907A CN 200510018789 CN200510018789A CN1701907A CN 1701907 A CN1701907 A CN 1701907A CN 200510018789 CN200510018789 CN 200510018789 CN 200510018789 A CN200510018789 A CN 200510018789A CN 1701907 A CN1701907 A CN 1701907A
Authority
CN
China
Prior art keywords
welding
mold cavity
mould
soldering
repair
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200510018789
Other languages
Chinese (zh)
Inventor
胡道财
张运军
曹世金
余国林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Tri Ring Forging Co Ltd
Original Assignee
Hubei Tri Ring Forging Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Tri Ring Forging Co Ltd filed Critical Hubei Tri Ring Forging Co Ltd
Priority to CN 200510018789 priority Critical patent/CN1701907A/en
Publication of CN1701907A publication Critical patent/CN1701907A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Forging (AREA)

Abstract

Thin layer repair welding technique for forging mould cavity overcomes the shortcomings in traditional method with much cost, great time consumption and less repair times, which uses series steps comprised integral heating welding, circle-to-mid turns and multiple layers welding of controlling layer thickness to cut repair time and cost obviously, reliable for quality, fit to repair more than ten times and prolong mould service life.

Description

Thin layer welding repair technology for forging die cavity
Technical field
The present invention uses mould about forging, particularly about forging the renovation technique with mould.
Background technology
Forging is one of common technology of engineering goods production, the mould that forges usefulness is the key of formed product, but repeat the brute force of mould is forged during owing to forging, behind the certain hour, the physical dimension that mold cavity all can occur in various degree enlarges, and cracks at some position, after this situation occurring, generally be to adopt the whole repair mode that falls, but the expense of this traditional approach and consuming time all bigger, and the reparation number of times of mould is generally less than 3-5 time.In recent years, the mould repair mode that a kind of direct employing soldering is arranged, be to adopt a kind of high rigidity welding rod that meets the mould requirement, directly be welded in the mold cavity, thereby recover the original size of mold cavity, but this recovery technique is still immature at present complete, be used for a spot of fine cracks etc. repair still can, be used for the reparation that mold cavity whole geometry size enlarges and do not see that complete technical matters is arranged.
Summary of the invention
The objective of the invention is to overcome the high length consuming time of traditional repair mode expense and can repair the few shortcoming of number of times, a kind of thin layer welding repair technology for forging die cavity that can be used for the whole complete maturation of technology of repairing of mold cavity is provided.
Technical scheme of the present invention is: earlier mold cavity is evenly enlarged 3-5mm, then mold integral is heated to 350-400 ℃ and keep this temperature to carry out soldering, welding rod is heated to 300-350 ℃ of maintenance 40-70 minute, naturally be used for soldering after reducing to normal temperature, during electric welding, from the circumferential edge of mold cavity along, in the middle of mold cavity, carry out gradually, finish in the centre at last, and adopt the mode of multilayer welding, every layer of soldering THICKNESS CONTROL is between 0.8-1.5mm, each the layer all from circumferential edge along, in the middle of mold cavity, finish,, then mould is carried out tempering until slightly surpassing the mold cavity original size, temperature 400-500 ℃, tempering insulation time is pressed 1 hour/2.5cm of mould maximum ga(u)ge and is determined that reduce to normal temperature after the tempering naturally, fine finishining mould die cavity is to using size again.
The present invention enlarges with the mode repairing mould die cavity of soldering is whole, makes mold cavity return to original size.Mold integral is heated and can be strengthened weld strength and the internal stress of organizing that reduces in the welding repair process; The welding rod oven dry effect of having heated, and the generation of pore, slag inclusion when avoiding welding; Elder generation's die cavity circumferential edge is carried out soldering gradually during electric welding in the middle of the back, can avoid the generation of undercut phenomenon, and can guarantee the globality and the quality of soldering; Adopt the mode of multilayer welding, can avoid pore, slag inclusion, guarantee the precision of the gross thickness of soldering; Soldering is to slightly surpassing the mold cavity original size, and processing leaves surplus to subsequent fine, guarantees the precision of mould repair; Tempering after the soldering can further be eliminated and organize internal stress.
Owing to adopt the soldering order of mold integral in the middle of heating behind welding, the first circumference, control a series of technical measures such as multilayer welding mode of bed thickness, shortened dramatically repair time of the present invention, expense reduces, repairing quality is reliable, and adopt repairing mould of the present invention, can repair repeatedly more than 10 times, obviously prolong the mould production cycle, reduce production cost.
Description of drawings
Fig. 1 is a soldering program generalized section of the present invention.
The specific embodiment
With reference to shown in Figure 1, earlier mold cavity is evenly enlarged 3-5mm, the general milling machine that adopts mills, then mold integral is heated to 350-400 ℃ and keep this temperature to carry out soldering, welding rod is heated to 300-350 ℃ of maintenance 40-70 minute, naturally be used for soldering after reducing to normal temperature, during electric welding, from the circumferential edge of mold cavity along 1, edge 1 whole circumference has been welded, again based on this circumference, carry out soldering to mold cavity middle 2 gradually, finish middle 2 at last, the similar concentric circles of its soldering track, and the mode of employing multilayer welding, as having welded ground floor 3 earlier among Fig. 1, weld the second layer 4 again, by that analogy, every layer of soldering THICKNESS CONTROL is between 0.8-1.5mm, and each layer is all from the edge 1,2 end in the middle of mold cavity, until slightly surpassing the mold cavity original size, be generally about 1mm, promptly mold cavity carries out tempering with mould then less than the original size of using after the soldering, temperature 400-500 ℃, tempering insulation time is pressed 1 hour/2.5cm of mold thickness and is determined that reduce to normal temperature after the tempering naturally, fine finishining mould die cavity is to the original size of using again.
Mould before the soldering is heated and should inside and outside integral body be reached the requirement temperature range, but not only the surface reaches the requirement temperature, therefore should be according to the volume size and the thickness of mould, guarantee enough warm-up times, in the welding repair process, should note mould is incubated, reduce to as temperature and to require below the temperature, should in time heat to requiring temperature, it should be noted that mould heats too low, be difficult to reach soldering requirement and quality, mould is heated too high, and energy consumption is big, also influences quality of welding repair.
Circumferential edge recited above along 1, edge 1 whole circumference, be meant the circle that the die joint of mould and the whole periphery that die cavity has a common boundary form, this circle is determined according to the product that forges, is not circle in general sense.The similar concentric circles of soldering track recited above also is meant this point.
Welding rod should adopt the high rigidity welding rod that meets the mould requirement, as models such as 545E, 9580E.In the soldering, should note the electric welding electric current, rule of thumb, the electric welding electric current should can make the surfacing of soldering like this than being advisable about the big 15-20A of common electric welding, is convenient to later stage fine finishining.
Tempering insulation time is looked concrete mould and difference, and generally according to the size at mould maximum ga(u)ge position, every 2.5cm calculated by insulation in 1 hour, determined total tempering insulation time.Fine finishining is mainly mills and the integer of polishing, if the size Control during soldering better, can only polish gets final product.

Claims (1)

1. thin layer welding repair technology for forging die cavity, earlier mold cavity is evenly enlarged 3-5mm, then mold integral is heated to 350-400 ℃ and keep this temperature to carry out soldering, welding rod is heated to 300-350 ℃ of maintenance 40-70 minute, naturally be used for soldering after reducing to normal temperature, it is characterized in that: during electric welding, circumferential edge edge (1) from mold cavity, carry out (2) in the middle of mold cavity gradually, finish in middle (2) at last, and the mode of employing multilayer welding, every layer of soldering THICKNESS CONTROL is between 0.8-1.5mm, and each layer is all from circumferential edge along (1), and finish (2) in the middle of mold cavity, until slightly surpassing the mold cavity original size, then mould is carried out tempering, temperature 400-500 ℃, tempering insulation time is pressed 1 hour/2.5cm of mould maximum ga(u)ge and is determined, naturally reduce to normal temperature after the tempering, fine finishining mould die cavity is to the original size of using again.
CN 200510018789 2005-05-25 2005-05-25 Thin layer welding repair technology for forging die cavity Pending CN1701907A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200510018789 CN1701907A (en) 2005-05-25 2005-05-25 Thin layer welding repair technology for forging die cavity

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200510018789 CN1701907A (en) 2005-05-25 2005-05-25 Thin layer welding repair technology for forging die cavity

Publications (1)

Publication Number Publication Date
CN1701907A true CN1701907A (en) 2005-11-30

Family

ID=35631948

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200510018789 Pending CN1701907A (en) 2005-05-25 2005-05-25 Thin layer welding repair technology for forging die cavity

Country Status (1)

Country Link
CN (1) CN1701907A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101767262B (en) * 2010-01-28 2012-05-02 重庆杰信模具有限公司 Reproducing method of forging mold by using composite build-up welding
CN102581543A (en) * 2012-03-01 2012-07-18 宁夏天地奔牛实业集团有限公司 Repair method for forging die
CN102728989A (en) * 2012-06-02 2012-10-17 安徽国通高新管业股份有限公司 Repairing process of pits on forming mold
CN102974993A (en) * 2012-12-04 2013-03-20 无锡透平叶片有限公司 Method for modifying 5CrNiMo hot-forging die
CN103008966A (en) * 2012-12-05 2013-04-03 中国海洋石油总公司 Repairing method of scrapped mud pump cylinder sleeve
CN105478764A (en) * 2015-12-11 2016-04-13 湖北三环锻造有限公司 Welding repair technology of forging die 3D printing material increase

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101767262B (en) * 2010-01-28 2012-05-02 重庆杰信模具有限公司 Reproducing method of forging mold by using composite build-up welding
CN102581543A (en) * 2012-03-01 2012-07-18 宁夏天地奔牛实业集团有限公司 Repair method for forging die
CN102728989A (en) * 2012-06-02 2012-10-17 安徽国通高新管业股份有限公司 Repairing process of pits on forming mold
CN102728989B (en) * 2012-06-02 2014-11-26 安徽国通高新管业股份有限公司 Repairing process of pits on forming mold
CN102974993A (en) * 2012-12-04 2013-03-20 无锡透平叶片有限公司 Method for modifying 5CrNiMo hot-forging die
CN103008966A (en) * 2012-12-05 2013-04-03 中国海洋石油总公司 Repairing method of scrapped mud pump cylinder sleeve
CN103008966B (en) * 2012-12-05 2015-07-01 中国海洋石油总公司 Repairing method of scrapped mud pump cylinder sleeve
CN105478764A (en) * 2015-12-11 2016-04-13 湖北三环锻造有限公司 Welding repair technology of forging die 3D printing material increase
CN105478764B (en) * 2015-12-11 2018-08-14 湖北三环锻造有限公司 Forging die 3D printing increases material welding and restoring process

Similar Documents

Publication Publication Date Title
CN1701907A (en) Thin layer welding repair technology for forging die cavity
CN103182618B (en) Roll forging die enabling surfacing manufacturing renovation technique
CN105478764A (en) Welding repair technology of forging die 3D printing material increase
CN101767262B (en) Reproducing method of forging mold by using composite build-up welding
CN101402163A (en) Bearing ferrule workblank triple external member smithing and molding process
CN105414444A (en) Forging process for integrated automobile traction support
CN110538914A (en) Plate sectional heating spinning forming method
CN103691813A (en) Special bending machine mould for special R-type plate and processing method of part thereof
CN102172734B (en) Rolling blank making method for automobile transmission gear ring
CN103252627A (en) Two-layer combined concave mould and machining method thereof
CN111992879A (en) Device for composite manufacturing based on laser shock peening and laser material increase and decrease
JP6162217B2 (en) Laser support tool production and repair method
CN103962801A (en) Forming process of petroleum drill rod joint
CN103357805B (en) The method for forging and molding of pin rail
CN105328109A (en) Local continuous loading forming method for large disc and shaft integrated parts
CN103121284A (en) Air valve alloyed forming die
CN101596572B (en) Technological method for producing axle case reinforcing ring
CN104723037A (en) Automotive transmission input shaft composite forming process and forging mold
CN105689612A (en) Near-net forming forging method for novel straight-tooth bevel gear tooth-profile die
CN102152070A (en) Method for manufacturing ring-shaped piece
CN204308054U (en) A kind of bender bending lower die tool
CN105855443A (en) Trimming concave die with combined-type cutting edge
CN109228041A (en) A kind of method for repairing tire mould and tire-mold
CN204545289U (en) Automotive transmission power shaft combined shaping forge die
CN103753157A (en) Process method and rolling machine for gear blank forming

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication